1ST JULY, 2023.

WEEKLY REPORT
CONSTRUCTION OF NEW MASSEY CHILDREN’S
HOSPITAL AT ADENIJI ADELE, LAGOS FOR
LAGOS STATE GOVERNMENT.
(MAIN HOSPITAL BUILDING)
`

1
HK DESIGNS LIMITED
1ST JULY, 2023.

TABLE OF CONTENTS

EXECUTIVE SUMMARY 3

1.0 INTRODUCTION 4

1.1 Aim and Objectives 4

1.2 Project Site Description 4

2.0 PROJECT PROGRESS REPORT 5

2.1 Progress Report (Piling Works) 5

2.2 Progress Report (Main Building Area) 6

3.0 CONCLUSION

LIST OF TABLES

Table 2.1 Progress Report (Piling Works) 5

Table 2.2 Progress Report (Main Building Area) 6

LIST OF PLATES

Plate 1 Fixing of Pile Cap Reinforcements 8

Plate 2 Fixing of Pile Cap Formworks 9

Plate 3 Excavation and Blinding of Ground Beam Area 10

Plate 4 Compaction of Ground Slab Areas 11

Plate 5 Fixing of Ground Slab Reinforcements 12

Plate 6 Fixing of Ground Floor Column Reinforcements/Formworks 13

Plate 7 Casting of Ground Floor Columns 1 14

Plate 8 Casting of Ground Floor Columns 2 15

Plate 9 Fixing of First Floor Slab Formworks 16

2
HK DESIGNS LIMITED
1ST JULY, 2023.

EXECUTIVE SUMMARY

In the course of the week; fixing of pile cap reinforcements/formworks, casting of pile

cap, blinding of ground beam/ ground slab areas, fixing of ground slab reinforcements,

fixing of ground floor column reinforcements/formworks, casting of ground floor

columns and fixing of first floor slab formworks were carried out.

3
HK DESIGNS LIMITED
1ST JULY, 2023.

1.0 INTRODUCTION

1.1 Aim and Objectives

Piling Works: To ensure quality and suitable CFA piles capable of bearing the super

structure loadings of the Proposed New Massey Children Hospital (Main Hospital Building)

are installed to 38m depth using standard Engineering methodology/materials and ensure the

installed piles be found satisfactory when pile tests (PIT and PLT) are conducted.

Main Hospital: To ensure that the Main Hospital is built to Architectural/Structural/MEP

details using standard methodology and materials.

1.2 Project Site Description

The project site is located in the east of Lagos Island, along Adeniji Adele road. It shares

boundary with LAWMA building (to the right) and Dolphin Estate phase IV (to the left).

Perimeter fences made of block walls supported by columns at 3metres intervals surround the

site on two sides, while the other sides are surrounded by existing fence.

4
HK DESIGNS LIMITED
1ST JULY, 2023.

2.0 PROJECT PROGRESS REPORT

Table 2.1 Progress Report (Piling Work)

ITEMS Completed Task Ongoing Task Task to be done

Pre-Piling Handling over of site


works
Confirmatory soil Investigation

Building Footprints setting out and


approval

Fabrication of 650mm pile rebar

Fabrication of 700mm pile rebar

Piling Main building (502/502)


works

Post Piling Pile Integrity Test


Works
Pile Load Test

As built survey

Other Perimeter Fencing (fence facing Perimeter fencing


Works highway, fence separating project’s
site from LNSC/IPP site and fence
at the left end of site)

Borehole installation

5
HK DESIGNS LIMITED
1ST JULY, 2023.

Table 2.2 Progress Report (Main Building)

ITEMS Completed Task Ongoing Task Task to be done

Post Contract Handling over of Site Earth Works


Works
Mobilization to Site Setting Out

Ground Pile Caps (110 of 110) Ground Walls Ramps


Floor
Ground Beam Works Block- walls

Ground Slabs (G – P / 1-6)

Fixing of Column
Reinforcements (A – P / 1-11)

Casting of Columns (G-P/ 1-6)

MEP Works

Staircase works

First Floor Floor Slab Formworks (G- P / 1-


4)

6
HK DESIGNS LIMITED
1ST JULY, 2023.

3.0 CONCLUSION

As regards the foundation; the piles have been installed while the necessary piling tests

(PIT & PLT) have been conducted on the installed piles and found satisfactory.

As regards the other part of the sub – structure; pile caps works have been completed

while other works; fixing of ground beam reinforcements/formworks, casting of ground

beams, backfilling/compaction of ground slab area/laying of DPM, blinding of ground slab

areas, fixing of ground slab reinforcements/ formworks, casting of ground slabs, fixing of

the ground floor column reinforcements/formworks, casting of ground floor columns and

fixing of first floor slab formworks along construction zones 1,2&3 are simultaneously

ongoing.

7
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 1: Fixing of Pile Cap Reinforcements

8
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 2: Fixing of Pile Cap Formworks

9
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 3: Excavation and Blinding of Ground Beam Area

10
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 4: Compaction of Ground Slab Areas

11
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 5: Fixing of Ground Slab Reinforcements

12
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 6: Fixing of Ground Floor Column Reinforcements/Formworks

13
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 7: Casting of Ground Floor Columns 1

14
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 8: Casting of Ground Floor Columns 2

15
HK DESIGNS LIMITED
1ST JULY, 2023.

Plate 9: Fixing of First Floor Slab Formworks

16