Professional Documents
Culture Documents
WEEKLY REPORT
CONSTRUCTION OF NEW MASSEY CHILDREN’S
HOSPITAL AT ADENIJI ADELE, LAGOS FOR
LAGOS STATE GOVERNMENT.
(MAIN HOSPITAL BUILDING)
`
1
HK DESIGNS LIMITED
1ST JULY, 2023.
TABLE OF CONTENTS
EXECUTIVE SUMMARY 3
1.0 INTRODUCTION 4
3.0 CONCLUSION
LIST OF TABLES
LIST OF PLATES
2
HK DESIGNS LIMITED
1ST JULY, 2023.
EXECUTIVE SUMMARY
In the course of the week; fixing of pile cap reinforcements/formworks, casting of pile
cap, blinding of ground beam/ ground slab areas, fixing of ground slab reinforcements,
columns and fixing of first floor slab formworks were carried out.
3
HK DESIGNS LIMITED
1ST JULY, 2023.
1.0 INTRODUCTION
Piling Works: To ensure quality and suitable CFA piles capable of bearing the super
structure loadings of the Proposed New Massey Children Hospital (Main Hospital Building)
are installed to 38m depth using standard Engineering methodology/materials and ensure the
installed piles be found satisfactory when pile tests (PIT and PLT) are conducted.
The project site is located in the east of Lagos Island, along Adeniji Adele road. It shares
boundary with LAWMA building (to the right) and Dolphin Estate phase IV (to the left).
Perimeter fences made of block walls supported by columns at 3metres intervals surround the
site on two sides, while the other sides are surrounded by existing fence.
4
HK DESIGNS LIMITED
1ST JULY, 2023.
As built survey
Borehole installation
5
HK DESIGNS LIMITED
1ST JULY, 2023.
Fixing of Column
Reinforcements (A – P / 1-11)
MEP Works
Staircase works
6
HK DESIGNS LIMITED
1ST JULY, 2023.
3.0 CONCLUSION
As regards the foundation; the piles have been installed while the necessary piling tests
(PIT & PLT) have been conducted on the installed piles and found satisfactory.
As regards the other part of the sub – structure; pile caps works have been completed
areas, fixing of ground slab reinforcements/ formworks, casting of ground slabs, fixing of
the ground floor column reinforcements/formworks, casting of ground floor columns and
fixing of first floor slab formworks along construction zones 1,2&3 are simultaneously
ongoing.
7
HK DESIGNS LIMITED
1ST JULY, 2023.
8
HK DESIGNS LIMITED
1ST JULY, 2023.
9
HK DESIGNS LIMITED
1ST JULY, 2023.
10
HK DESIGNS LIMITED
1ST JULY, 2023.
11
HK DESIGNS LIMITED
1ST JULY, 2023.
12
HK DESIGNS LIMITED
1ST JULY, 2023.
13
HK DESIGNS LIMITED
1ST JULY, 2023.
14
HK DESIGNS LIMITED
1ST JULY, 2023.
15
HK DESIGNS LIMITED
1ST JULY, 2023.
16
HK DESIGNS LIMITED