You are on page 1of 1

Project Title: Design and Build 150 MLD Laguna Lake Water Treatment Plant

Location: Poblacion, Muntinlupa City


Contract No.: WS-19-WTP-01
Contractor: AA-DMCI Consortium

2 Weeks Look-ahead Schedule


May 2020
WEEK 01 WEEK 02
11 12 13 14 15 16 17 18 19 20 21 22 23 24
Schedule No. 3 Design Services
• Core Design
•Civil Works/ Building
•Civil / Structural Design Bases Final Revision/Review/Approval
• Process
• Tempfacil Design/Drawings (for permit)
• Developed (Detailed) Design
•Archi / Structural Design Drawings for Raw Water Intake
•Archi / Structural Design Drawings for Treated Water Reservoir
•Archi / Structural Design Drawings for Flowmeter
Schedule No. 4.1a General Preliminaries
• Geotechnical Survey
• Mobilization for On-Shore Drilling
• Set-up of Rig/Dismantling of Rig
• Drilling of Borehole
• Downhole Shear Test
• Mobilization for Off-Shore Drilling
• Set-up of Platform/Dismantling of Rig
• Drilling of Borehole
• Laboratory Testing
• Site Clearing
• Mobilization/Demobilization
• Cleaning and Grubbing
• Full Contractual Compliance (bonds and insurances, permits and
clearances)
• Regulatory, Implentation of Construction Safety, Health Programme, Quality and
Environmental, Management Systems
Schedule No. 4.2a Civil and Structural Works for 50 and 150 MLD
• Earthworks
• Excavation
• Backfilling

Prepared by: Certified Correct by: Noted By:

Javier Ruiz/ Noel Villanueva NEPTHALIE CELES CHESTER BONGAY


AA-DMCI, Contractor ARUP, Project Management Consultant Maynilad Construction Manager