May 2020 WEEK 01 WEEK 02 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Schedule No. 3 Design Services • Core Design •Civil Works/ Building •Civil / Structural Design Bases Final Revision/Review/Approval • Process • Tempfacil Design/Drawings (for permit) • Developed (Detailed) Design •Archi / Structural Design Drawings for Raw Water Intake •Archi / Structural Design Drawings for Treated Water Reservoir •Archi / Structural Design Drawings for Flowmeter Schedule No. 4.1a General Preliminaries • Geotechnical Survey • Mobilization for On-Shore Drilling • Set-up of Rig/Dismantling of Rig • Drilling of Borehole • Downhole Shear Test • Mobilization for Off-Shore Drilling • Set-up of Platform/Dismantling of Rig • Drilling of Borehole • Laboratory Testing • Site Clearing • Mobilization/Demobilization • Cleaning and Grubbing • Full Contractual Compliance (bonds and insurances, permits and clearances) • Regulatory, Implentation of Construction Safety, Health Programme, Quality and Environmental, Management Systems Schedule No. 4.2a Civil and Structural Works for 50 and 150 MLD • Earthworks • Excavation • Backfilling
Prepared by: Certified Correct by: Noted By:
Javier Ruiz/ Noel Villanueva NEPTHALIE CELES CHESTER BONGAY
AA-DMCI, Contractor ARUP, Project Management Consultant Maynilad Construction Manager