Excavation, Earthwork and Filling Method Statement


Date
February 6, 2014

Excavation, Earthwork and Filling Method Statement

WORK PROCEDURE

SUBJECT: BY:

https://planningengineer.net/excavation-earthwork-and-filling-method-statement-2/ 1/7
11/11/2020 Excavation, Earthwork and Filling Method Statement - Planning Engineer Est.

QA/QC ENGINEER

EXCAVATION, EARTHWORK AND FILLING APPROVED BY:

QEHS MANAGER

ACTION VERIFY

1. SCOPE Project Method


Manager Statement
This procedure provides a standardised framework for the
control of excavation, earthwork and filling to ensure Project
compliance with conditions of contract and contract Manager
specifications.

2. PROCEDURE

.1 All excavation, earthwork and filling will be carried out in


accordance with the specification detailed in the project
contract documentation. In any circumstances where
specifications are not provided or they are in any way
incomplete, the matter shall be referred back to consultant for
additional information.

.2 Method Statement

A method statement will be prepared and approved where


deemed necessary, and may include:

i) Site plan showing the location of spoil heaps for


temporary storage and if appropriate permanent storage
area.

ii) Type of plant and equipment to be used.

iii) Means for keeping excavations free of water.

iv) Method of trench supports.

v) Method and sequence of excavation to ensure that


no damage is caused to adjoining structures and
property. If there is potential for damage to adjoining
structures and property, the type of preventative
measures should be indicated.

https://planningengineer.net/excavation-earthwork-and-filling-method-statement-2/ 2/7
11/11/2020 Excavation, Earthwork and Filling Method Statement - Planning Engineer Est.

vi) Temporary support arrangement of adjacent


structures and services passing through the site.

vii) Method of compacting fill and testing procedure.

1. Health and Safety requirements.


2. Any other special requirements.

.3 Existing Utilities Project Drawing/


Manager
1. Liaise with all public utility companies e.g. water, N.O.C.
electricity, telephone sewerage and surface water etc. to Project
ensure that all the available information on the location Engineer Markings

of utilities and underground services through and


Project Trial Holes
adjacent to the site of the excavation is obtained.
Engineer
ii) Ensure that utilities and underground services are Survey
located on site using markings, which are clearly visible. Site Engr./
Approval to
Ensure those plant operators and operatives involved
Surveyor Tip
with the activity are fully aware of the location of the
various utilities and underground services and their
Project
respective depths.
Manager
iii) Where deemed necessary, excavate trial holes to
establish the precise location and depth of services.

iv) Plant operators must be aware of overhead cables.


Use height control indicators where necessary.

.4 Site Survey and Grid of Levels

Prior to commencement of any excavation work, a level survey


will be carried out to confirm the information included on the
contract drawings and to provide an accurate record of existing
ground levels for the calculation of quantities.

.5 Disposal of Surplus Excavated Material

Prior to any surplus excavated material being removed from the


site, documentary evidence of “approval to tip” must be
obtained beforehand from the relevant government/municipal

https://planningengineer.net/excavation-earthwork-and-filling-method-statement-2/ 3/7
11/11/2020 Excavation, Earthwork and Filling Method Statement - Planning Engineer Est.

departments and the owner of the land where the material is to


be tipped.

.6 Adjoining Structures and Property

Prior to the commencement of excavation work, a detailed


dilapidation survey will be undertaken to record the existing
condition of the adjoining structures and property. Where
necessary the survey may include photographic records.

This survey should be carried out in co-ordination with and Const. Dilapidation
involving the participation of the Consultant’s representative Manager
and the representative of the owners/occupiers of the adjacent Survey

property. Project
Engineer Survey

.7 Excavation Work
QA/QC Inspection

1. Excavation shall be allowed to progress to the designed Request

formation level less 50mm (unless specified otherwise). Project


Engineer/ Method
The remaining 50mm shall be carried out by further
Statement
careful excavation to avoid disturbing the formation
Site Safety
level.
Method
1. After reaching the designed formation level, Project Statement
Consultant’s representative shall be requested in writing Engineer/Site
Safety Inspection
to inspect and approve the formation prior to the
Request
commencement of any subsequent activities.
QA/QC
iii) Great care shall be taken to minimise noise, Source
vibration and dust pollution, which can cause nuisance Project Documents
and damage, particularly if the site is located in a built- Engineer
up area. Method
Project Statement
iv) Sides of all excavations should be properly Engineer
supported using an appropriate method as detailed in
the Method Statement.

.8 Filling

1. Prior to commencement of filling, the Consultant’s


representative shall be requested in writing to inspect
and approve the fill starting level.

https://planningengineer.net/excavation-earthwork-and-filling-method-statement-2/ 4/7
11/11/2020 Excavation, Earthwork and Filling Method Statement - Planning Engineer Est.

ii) Filling shall be carried out using approved materials


in accordance with the specification which can either be
selected from the material on site or imported from
selected and approved sources.

iii) Filling shall be carried out as per approved method


and as per the contract specification.

Download the Excavation, Earthwork and Filling Method Statement word document: EXCAVATION,
EARTHWORK AND FILLING

Download our Useful Planning Contents:

Name
Your Name

Email address: Your email address

DOWNLOAD

Tag: adjoining structures, Earthwork, Excavation, excavation earthwork, Filling, manager project,
method statement, project engineer, project manager, underground services

Share:    

Hany Ismail, MSC, PMP Hany Ismael is the founder and


CEO of Planning Engineer Est. in
Egypt. He has started his career
back in 2003 as a site engineer…

https://planningengineer.net/excavation-earthwork-and-filling-method-statement-2/ 5/7
11/11/2020 Excavation, Earthwork and Filling Method Statement - Planning Engineer Est.

Previous post Next post

HUMAN RESOURCE PLAN BORED PILING METHOD


February 6, 2014 STATEMENT
February 7, 2014

You may also like

How to perform Cost Control in Calculate Duration in P6 based We don’t know wh


Construction Projects on scope know! What Plan
29 September, 2020 14 August, 2020 Should Know?
6 February, 2020

Leave A Reply
You must be logged in to post a comment.

https://planningengineer.net/excavation-earthwork-and-filling-method-statement-2/ 6/7
11/11/2020 Excavation, Earthwork and Filling Method Statement - Planning Engineer Est.

FOLLOW US:

  

About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

Copyright ©2012- 2020 planningengineer.net | All materials, unless otherwise noted, were developed originally for

Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the

copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.