ID Task Task Name Duration Start Finish Mar 31, '19 Apr 7, '19 Apr 14, '19 Apr

Finish Mar 31, '19 Apr 7, '19 Apr 14, '19 Apr 21, '19 Apr 28, '19 May 5, '19 May 12, '19 May 19, '19 May 26, '19 Jun 2, '19 Jun 9, '19 Jun 16, '19 Jun 23, '19 Jun 30, '19 Jul 7, '19
Mode W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 Il Mercantele Project 62 days Sun 4/14/19 Tue 7/9/19
2 Submission/Presentation of 4 days Sun 4/14/19 Wed 4/17/19
documents, BOQ, schedules, etc

3 Excavation works 8 days Thu 4/18/19 Mon 4/29/19


4 Footing/foundation works 8 days Thu 4/25/19 Mon 5/6/19
5 Ground Beam installation/works 10 days Thu 4/25/19 Wed 5/8/19
6 Column installation 9 days Thu 5/9/19 Tue 5/21/19
7 Ground floor slab works 6 days Wed 5/15/19 Wed 5/22/19
8 Ground floor brickwall installation 8 days Thu 5/16/19 Mon 5/27/19

9 1st floor beam installation 8 days Wed 5/22/19 Fri 5/31/19


10 1st Floor slab installation/works 10 days Fri 5/31/19 Thu 6/13/19
11 1st floor column installation 8 days Thu 6/6/19 Mon 6/17/19
12 Roof installation works 10 days Sat 6/15/19 Thu 6/27/19
13 1st floor Brickwall works 8 days Thu 6/20/19 Mon 7/1/19
14 Ground Floor Glass works 8 days Mon 6/24/19 Wed 7/3/19
15 1st floor glass works 6 days Thu 6/27/19 Thu 7/4/19
16 Finishing touches/Cleaning 2 days Fri 7/5/19 Mon 7/8/19
17 Hand-over project 1 day Tue 7/9/19 Tue 7/9/19
18 MEP Schedule 4 days Sun 4/14/19 Thu 4/18/19
19 Electrical System
20 Conduiting & Wiring for Power 5 days
and Lighting

21 Installation of earthing cables 2 days


and rod

22 Installation of power sockets 2 days


23 installation of switches 2 days
24 Installation of lights 4 days
25 Installation of ventilation system 2 days
and accessories

26 Installation of MDB 1 day


27 Termination of cables and main 2 days
cable

28 Plumbing System
29 Installation of PPR pipes 2 days
30 Installation of PVC pipes 2 days
31 Installation of Sanitary wares 2 days
32 Conduct Leakage Test for 2 days
Drainage and Waste pipes

33 Conduct Pressure Test in Water 2 days


Supply System

34 Testing and commissiong of all 2 days


equipments

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Il Mercantel Project Sch
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 7/3/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress