REPORT
1
EXECUTIVE SUMMARY
Key Achievement of the Last Period (12 Mar.- 19 March 2021) Risk Quality
Project Metrics Budget Schedule
Management Management
• 1. Main Bldg
- UG: Cable Trench (B-C/ 6-10) work and backfilling , Dewatering
- Deck Slab (EL+4.00 B-C/6-10): Installing Rebar & Wiremesh, Embedded Status O O R O
• 2. Coal Shed: Grouting
• 3. Coal Pit : Slab work, installing embedded plate, Dewatering Project Milestone Target Date Expected Status
• 4. Coal Handling : Trench work. dewatering Completion
• 5. WTH : Backfilling, Repairing
• 6. Oil pump FDN : Excavation
• 7. Diesel Generator :Trench, Slab work
• 8. Seawater inlet : Lean Con’c, dewatering Quality Management Issues
Key Planned for the Next Period - Inspection schedule for next week :
• 1. Main Bldg Drawing
- UG: Cable Trench (B-C/ 6-10) work and backfilling . No Date Building Description Remarks
- Deck Slab (EL+4.00 B-C/6-10): Embed, Formwork, Con’c. Number
• 2. Coal Shed: Grouting under base plate.
• 3. Coal Pit : Slab Con’c, Formwork for corridor 1 Monday, March 22, 2021 Oil Pump FDN T0703 Lean Con'c Concrete
• 4. Coal Handling : Trench work.
• 5. WTH : Backfilling and handover 2 Monday, March 22, 2021 Main Building T0205 Deckslab Elv +4 m Part I Concrete
• 6. Oil pump FDN : FDN work
• 7. Diesel Generator : Slab work 3 Monday, March 22, 2021 Coal Shed T0503 Grouting Concrete
• 8. Conveyor#1 : Excavation 4 Thursday, March 25, 2021 Main Building T0205 Cable Trench Wall Concrete
• 9. Seawater inlet : Excavation, Cutting Pile, Lean Con’c, Foundation,
Pedestal, Dewatering. 5 Wednesday, March 24, 2021 Main Building T0205 Short Column Pedestal Concrete
• 10. Outlet Trench : Excavation
Key Risks / Issues / Scope Changes
• 1. Floor Finishing to be confirmed
• 2. 16-area to be Hand Over for Civil construction
Main Transformer-1&2, Electrical House 20kv, Pipe rack at T/G , Workshop, Key Discussion Areas where Management Attention is required
Sand Unit, Rack of Flu behind Boiler-1&2, Slag Transmission station,
Convert Room, Biomass and corridor, Coal Bulldozer house, Coal slurry pool - Progress Payment
Transfer Station, Coal Handling conveyor-1&2 10th (Feb 2021) : submitted for KRN’s confirmation 12 March 2021
- As the pandemic(COVID-19) is prolonged, it impact to delay progress so that Civil
work can not proceed in time.
- There are the Road Cross(3 Points) for Sea-water-inlet. It is required the coordination with
the schedule of Piping installing. Excavation in the Road Cross has a very negative impact on
the operation of equipment in the field. =>> the sleeve of Steel Pipe(D1500mm) is required.
- The bedding material for FRP pipe of Sea water inlet is required.
Legend: R Major Issues O Some Issues G Satisfactory Internal Documents not for Distribution
2
WEEKLY PROGRESS STATUS
Main Work
CUM.
WEIGHT PLANNED CUM. DEV.
S.No. DESCRIPTION FACTOR for THIS ACTUAL JUSTIFICATION FOR PROGRESS VARIANCE
% WEEK % %
%
土方开挖 2,346 % 2,377% 0,031% • Chemical Water House, Coal Pit, Diesel
1 Earthwork 1,44% Generator House, Slag Silo, Oil Pump House,
38.000 m3 38.500 m3 500 m3 Limestone Silo
excavation
• Chemical Water House, Diesel Generator House
2 垫层 Cushion 1,14%
0,81 % 0,85 % 0,04%
Limestone Silo
layer 420 m3 439 m3 19 m3
• Pipe Rack-Sea Water Inlet
桩头填芯 0,43 % 0,37 % -0,06% • Chemical Water House, Diesel Generator House
3 Core filling in 1,20%
137 m3 116 m3 -21 m3 Limestone Silo, Slag Silo, Oil Pump House
head of pipe pile
基础、短柱及
• Air Compressor, I.D Fan, Chemical Water House
基础梁 11,53 % 11,43 % -0,10 % • Coal Crusher.
4 Foundation, 15,67%
3.850 m3 3.815 m3 -35 m3 • Oil Pump House
Short Col, • Pipe Rack-Sea Water Inlet
FDN &Beam
Manpower Mobilization
Occupation 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar
Direct Manpower (M/D) 121 124 124 123 123 128 128
Total Manpower (M/D) 139 142 142 142 140 145 144
Equipment Status
Equipment Name 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar
4
ATTACHMENTS
MANPOWER AND EQUIPMET STATISTICAL TABLE
(Cut off period 12 Mar. ~ 19 Mar. 2021)
Manpower Mobilization
Occupation 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar
Equipment Status
Equipment Name 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar
5
PHOTO IN SITE
SITE VIEW
6
PHOTO IN SITE
11
PROGRESS ON SITE
Main
12
PROGRESS ON SITE
13
PROGRESS ON SITE
14
PROGRESS ON SITE
15
PROGRESS ON SITE
16
PROGRESS ON SITE
17
PROGRESS ON SITE
18
PROGRESS ON SITE
19
PROGRESS ON SITE
20
PROGRESS ON SITE
Access Road
21