WEEKLY PROJECT STATUS

REPORT

KRN Phase 3 (BPN)


2 x 25 MW POWER PLANT

12 Mar. 2021 ~ 18 Mar. 2021

1
EXECUTIVE SUMMARY
Key Achievement of the Last Period (12 Mar.- 19 March 2021) Risk Quality
Project Metrics Budget Schedule
Management Management
• 1. Main Bldg
- UG: Cable Trench (B-C/ 6-10) work and backfilling , Dewatering
- Deck Slab (EL+4.00 B-C/6-10): Installing Rebar & Wiremesh, Embedded Status O O R O
• 2. Coal Shed: Grouting
• 3. Coal Pit : Slab work, installing embedded plate, Dewatering Project Milestone Target Date Expected Status
• 4. Coal Handling : Trench work. dewatering Completion
• 5. WTH : Backfilling, Repairing
• 6. Oil pump FDN : Excavation
• 7. Diesel Generator :Trench, Slab work
• 8. Seawater inlet : Lean Con’c, dewatering Quality Management Issues
Key Planned for the Next Period - Inspection schedule for next week :
• 1. Main Bldg Drawing
- UG: Cable Trench (B-C/ 6-10) work and backfilling . No Date Building Description Remarks
- Deck Slab (EL+4.00 B-C/6-10): Embed, Formwork, Con’c. Number
• 2. Coal Shed: Grouting under base plate.
• 3. Coal Pit : Slab Con’c, Formwork for corridor 1 Monday, March 22, 2021 Oil Pump FDN T0703 Lean Con'c Concrete
• 4. Coal Handling : Trench work.
• 5. WTH : Backfilling and handover 2 Monday, March 22, 2021 Main Building T0205 Deckslab Elv +4 m Part I Concrete
• 6. Oil pump FDN : FDN work
• 7. Diesel Generator : Slab work 3 Monday, March 22, 2021 Coal Shed T0503 Grouting Concrete
• 8. Conveyor#1 : Excavation 4 Thursday, March 25, 2021 Main Building T0205 Cable Trench Wall Concrete
• 9. Seawater inlet : Excavation, Cutting Pile, Lean Con’c, Foundation,
Pedestal, Dewatering. 5 Wednesday, March 24, 2021 Main Building T0205 Short Column Pedestal Concrete
• 10. Outlet Trench : Excavation
Key Risks / Issues / Scope Changes
• 1. Floor Finishing to be confirmed
• 2. 16-area to be Hand Over for Civil construction
Main Transformer-1&2, Electrical House 20kv, Pipe rack at T/G , Workshop, Key Discussion Areas where Management Attention is required 
Sand Unit, Rack of Flu behind Boiler-1&2, Slag Transmission station,
Convert Room, Biomass and corridor, Coal Bulldozer house, Coal slurry pool - Progress Payment
Transfer Station, Coal Handling conveyor-1&2 10th (Feb 2021) : submitted for KRN’s confirmation 12 March 2021
- As the pandemic(COVID-19) is prolonged, it impact to delay progress so that Civil
work can not proceed in time.  
- There are the Road Cross(3 Points) for Sea-water-inlet. It is required the coordination with
the schedule of Piping installing. Excavation in the Road Cross has a very negative impact on
the operation of equipment in the field. =>> the sleeve of Steel Pipe(D1500mm) is required.
- The bedding material for FRP pipe of Sea water inlet is required.

Legend: R Major Issues O Some Issues G Satisfactory Internal Documents not for Distribution
2
WEEKLY PROGRESS STATUS
Main Work
CUM.
WEIGHT PLANNED CUM. DEV.
S.No. DESCRIPTION FACTOR for THIS ACTUAL JUSTIFICATION FOR PROGRESS VARIANCE
% WEEK % %
%

土方开挖 2,346 % 2,377% 0,031% • Chemical Water House, Coal Pit, Diesel
1 Earthwork 1,44% Generator House, Slag Silo, Oil Pump House,
38.000 m3 38.500 m3 500 m3 Limestone Silo
excavation
• Chemical Water House, Diesel Generator House
2 垫层 Cushion 1,14%
0,81 % 0,85 % 0,04%
Limestone Silo
layer 420 m3 439 m3 19 m3
• Pipe Rack-Sea Water Inlet

桩头填芯 0,43 % 0,37 % -0,06% • Chemical Water House, Diesel Generator House
3 Core filling in 1,20%
137 m3 116 m3 -21 m3 Limestone Silo, Slag Silo, Oil Pump House
head of pipe pile

基础、短柱及
• Air Compressor, I.D Fan, Chemical Water House
基础梁 11,53 % 11,43 % -0,10 % • Coal Crusher.
4 Foundation, 15,67%
3.850 m3 3.815 m3 -35 m3 • Oil Pump House
Short Col, • Pipe Rack-Sea Water Inlet
FDN &Beam

• Coal Crusher Top Slab, Column,


框架混凝土 2,40 % 2,25 % -0,15 % • Diesel Generator House Column
5 Reinforced 2,53 %
630 m3 590 m3 -40 m3 • T/G Top Deck
concrete frame • All Above Ground >+- 0.00
• Oil Pump House Top Deck

6 挡煤墙 coal 3,32%


2,94 % 2,72 % -0,22 % • Coal Shed Wall
retaining wall 680 m3 630 m3 -50 m3 • Coal Pit & Corridor

Total Progress for 3


Main Work
ATTACHMENTS
MANPOWER AND EQUIPMET STATISTICAL TABLE
(Cut off period 12 Mar. ~ 19 Mar. 2021)

Manpower Mobilization
Occupation 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Direct Manpower (M/D) 121 124 124 123 123 128 128

In-direct Manpower (M/D) 18 18 18 19 17 17 16

Total Manpower (M/D) 139 142 142 142 140 145 144

Equipment Status
Equipment Name 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Excavator PS-210 0,8 M3 4 4 4 4 5 5 4


Generator <60 KW 1 1 1 1 1 1 1
Dump Truck 8, 20ton 3 3 3 3 4 4 4
Crane 55 T 1 1 1 1 1 1 1
Total Day Heavy 9 9 9 9 11 11 10
Equipment

4
ATTACHMENTS
MANPOWER AND EQUIPMET STATISTICAL TABLE
(Cut off period 12 Mar. ~ 19 Mar. 2021)

Manpower Mobilization
Occupation 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Direct Manpower (M/D) 121 124 124 123 123 128

In-direct Manpower (M/D) 18 18 18 19 17 16

Total Manpower (M/D) 139 142 142 142 140 144

Equipment Status
Equipment Name 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Excavator PS-210 0,8 M3 4 4 4 4 5 4


Generator <60 KW 1 1 1 1 1 1
Dump Truck 8, 20ton 3 3 3 3 4 4
Crane 55 T 1 1 1 1 1 1
Total Day Heavy 9 9 9 9 11 10
Equipment

5
PHOTO IN SITE

SITE VIEW
6
PHOTO IN SITE

Main Bldg-Cable Trench work Main Bldg-Cable Trench work

Main Bldg-EL+4. Deck Slab WTH-repairing prior to Hand Over


7
PHOTO IN SITE

Coal Shed – Grouting Coal Pit& Corridor-Formwork for slab

Coal Handling– Cable Trench Disposal Soil


8
PROGRESS ON SITE

Progress Layout - Color Marked


HAND OVER

Hand Over Layout - Color Marked


PROGRESS ON SITE

Coal Pit & Corridor

11
PROGRESS ON SITE
Main

Main Bldg - Cable Trench

12
PROGRESS ON SITE

Main Bldg – Pedestal work

13
PROGRESS ON SITE

Coal Handling - Trench

14
PROGRESS ON SITE

Oil Pump House - FDN

15
PROGRESS ON SITE

Diesel Generator House – Column & FDN.

16
PROGRESS ON SITE

Sea Water Inlet Zone B

17
PROGRESS ON SITE

Sea Water Inlet Zone C

18
PROGRESS ON SITE

E.S.P, ID Fan, Racks of Flue FDN

19
PROGRESS ON SITE

Air Compressor House- Cable Trench & Foundation Equipment

20
PROGRESS ON SITE

Access Road

21
謝謝
(Thank You) !!