DOC NO: -KIA-B03- xxx -C_MC-L3-MDS-0004

METHOD STATEMENT FOR WATER PROOFING


KEMPEGOWDA INTERNATIONAL AIRPORT - TERMINAL 2

1 Name of the Concessionaire xxx


2 Location (Floor Level, Domestic / Level-3, DOM SHA
International)
3 Shop No xxx
4 Name of Concept xxx
5 Name of the Contractor xxx

Purpose
The intent of this document is to define the activities for various Civil & Interior Finishing.
Works of all kinds intended to be done at Level 3, Domestic of PTB of Terminal 2.

1. Detailed Scope of Works & Work Procedure


1-Scope of Work: Civil and Interior Finishing Works

 This method statement describes steps of waterproofing

2. Work Procedure:
A - Material Process and Signoff

Step 1: Unloading of material and proper stacking as per the area allotted by xxx

Step 2: Material Check – SE Team and xxx Team will signoff MIR

Step 3: Shifting of the part material at required location for the work– SE Team

B – EXECUTION OF WORKS
STEP 1: Cleaning of the area, to make it dry and dust free.
STEP 2: Application process
STEP 3: Final Signoff

DETAILS OF ALL THE STEPS:


STEP 1: Cleaning of the area, to make it dry and dust free for the water proofing to be done properly.

STEP 2: Application Process & Testing

 The chemical that will be used for waterproofing is FOSROC BRUSHBOND RFX AND NITOBOND
SBR
 The work will commence from the removal of the loose mortar from the mother slab
 Cleaning of the mother slab with hard metal brush for the removal of dirt and dust from the
surface with the air blowers.
 Application of the first coat of Fosroc RFX Brush Bond on the mother slab in clock wise
directions on all sides of walls to the height of 450mm.
 After drying of the 1st Coat of the Brush Bond Coating, 2nd coat will be applied in the anti-
clockwise directions.
 After complete of the drying of entire surface, we will fill water upto 6 inch levels for ponding
testing.
 Water will be kept for observations for 72 Hours and every 12 hours it will be checked for any
leakages or drop in level in the height of water level
 If there is no Leakage observed after 72 Hours, water will be drained out. If any leakage is
observed, the above process will be repeated.
 Protective screeding mixed with FOSROC NITOBOND SBR of average 25mm thickness mixed
with half inch concrete with cement and sand as per the methodology.
 Also coving will be done with NITOBOND SBR mixed with babychips cement and sand upto 150
mm
 The internal drainlines will be laid and tested.
 After this flooring will be raised by Light weight Siporex as per required height and doing a
protective screeding above the raised floor. Further Kota stone/ tiles will be laid as per the
drawings

STEP 3: Final Signoff

After the successful ponding test is completed, the Final Signoff on the IR will be done by xxx.

3. Equipment & Tools

SR NO DESCRIPTION QTY

1 Tar Brush 04
2 Normal Brush 04

3 Vacuum Machine 02
4. Health Safety and Environment:
 The entire works will be carried out with utmost safety of personnel and protection of
services.
 Briefing on the toolbox and its handling procedure will be carried out before commencing
the work.
 All person at site will be equipped with PPE’s.
 All required permits will be obtained from the authorities before commencement of works
 We will ensure proper and safe access for all workmen

5. Work responsibility:

Project Manager is responsible for coordination of resources, planning the required/ complete
activities, ensuring the product quality implementation and safety parameters related to the work
process.

Name- xxx
Contact no- xxx

Project Asst Manager is responsible for planning the required sequence of works, organising the
materials, executing and monitoring the daily work progress as scheduled.

Name- xxx
Contact no- 8 xxx
EHS Supervisor is responsible to monitor the compliance, identify the hazards and appraise the
concerned for immediate actions, examine the risk/ hazard for the activities and prepare the plan
to eliminate the risk.

Name- xxx
Contact no- 8 xxx