Professional Documents
Culture Documents
Purpose
The intent of this document is to define the activities for various Civil & Interior Finishing.
Works of all kinds intended to be done at Level 3, Domestic of PTB of Terminal 2.
2. Work Procedure:
A - Material Process and Signoff
Step 1: Unloading of material and proper stacking as per the area allotted by xxx
Step 2: Material Check – SE Team and xxx Team will signoff MIR
Step 3: Shifting of the part material at required location for the work– SE Team
B – EXECUTION OF WORKS
STEP 1: Cleaning of the area, to make it dry and dust free.
STEP 2: Application process
STEP 3: Final Signoff
The chemical that will be used for waterproofing is FOSROC BRUSHBOND RFX AND NITOBOND
SBR
The work will commence from the removal of the loose mortar from the mother slab
Cleaning of the mother slab with hard metal brush for the removal of dirt and dust from the
surface with the air blowers.
Application of the first coat of Fosroc RFX Brush Bond on the mother slab in clock wise
directions on all sides of walls to the height of 450mm.
After drying of the 1st Coat of the Brush Bond Coating, 2nd coat will be applied in the anti-
clockwise directions.
After complete of the drying of entire surface, we will fill water upto 6 inch levels for ponding
testing.
Water will be kept for observations for 72 Hours and every 12 hours it will be checked for any
leakages or drop in level in the height of water level
If there is no Leakage observed after 72 Hours, water will be drained out. If any leakage is
observed, the above process will be repeated.
Protective screeding mixed with FOSROC NITOBOND SBR of average 25mm thickness mixed
with half inch concrete with cement and sand as per the methodology.
Also coving will be done with NITOBOND SBR mixed with babychips cement and sand upto 150
mm
The internal drainlines will be laid and tested.
After this flooring will be raised by Light weight Siporex as per required height and doing a
protective screeding above the raised floor. Further Kota stone/ tiles will be laid as per the
drawings
After the successful ponding test is completed, the Final Signoff on the IR will be done by xxx.
SR NO DESCRIPTION QTY
1 Tar Brush 04
2 Normal Brush 04
3 Vacuum Machine 02
4. Health Safety and Environment:
The entire works will be carried out with utmost safety of personnel and protection of
services.
Briefing on the toolbox and its handling procedure will be carried out before commencing
the work.
All person at site will be equipped with PPE’s.
All required permits will be obtained from the authorities before commencement of works
We will ensure proper and safe access for all workmen
5. Work responsibility:
Project Manager is responsible for coordination of resources, planning the required/ complete
activities, ensuring the product quality implementation and safety parameters related to the work
process.
Name- xxx
Contact no- xxx
Project Asst Manager is responsible for planning the required sequence of works, organising the
materials, executing and monitoring the daily work progress as scheduled.
Name- xxx
Contact no- 8 xxx
EHS Supervisor is responsible to monitor the compliance, identify the hazards and appraise the
concerned for immediate actions, examine the risk/ hazard for the activities and prepare the plan
to eliminate the risk.
Name- xxx
Contact no- 8 xxx