ID Task Mode Task Name Duration Start Finish May July September November

M B E M B E M B E M
1 Torino 852 days Mon 7/1/19 Fri 10/29/21

2 Design phase 85 days Mon 7/1/19 Mon 9/23/19

3 Setup design team 10 days Mon 7/1/19 Wed 7/10/19

4 Soil investigation 15 days Thu 7/11/19 Thu 7/25/19

5 Architectural design (review) 15 days Thu 7/11/19 Thu 7/25/19

6 Structural design 60 days Fri 7/26/19 Mon 9/23/19

7 MEP design 60 days Fri 7/26/19 Mon 9/23/19

8 EIA test 60 days Mon 7/1/19 Thu 8/29/19

9 Authority approvals 60 days Mon 7/1/19 Thu 8/29/19

10 Development phase 767 days Tue 9/24/19 Fri 10/29/21

11 Mobilization 70 days Tue 9/24/19 Mon 12/2/19

12 Personnel formation 15 days Tue 9/24/19 Tue 10/8/19

13 Entry of materials and machineries 10 days Wed 10/9/19 Fri 10/18/19

14 Preparing construction drawings 20 days Wed 10/9/19 Mon 10/28/19

15 power, water, road access and site clearing 15 days Sat 10/19/19 Sat 11/2/19

16 Febrication of living and construction 30 days Sun 11/3/19 Mon 12/2/19


temporary facilities
17 Febrication of temporary office space 15 days Sun 11/3/19 Sun 11/17/19

18 Survey & setting out 20 days Wed 10/9/19 Mon 10/28/19

19 Construction 697 days Tue 12/3/19 Fri 10/29/21

20 City hotel 499 days Tue 12/3/19 Wed 4/14/21

21 Structural works 359 days Tue 12/3/19 Wed 11/25/20

22 Substructure 203 days Tue 12/3/19 Mon 6/22/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
23 Pilling 80 days Tue 12/3/19 Thu 2/20/20

24 Shoring & excavation 30 days Fri 2/21/20 Sat 3/21/20

25 Pile hacking & testing 30 days Sat 3/7/20 Sun 4/5/20

26 Pile capping 45 days Tue 3/17/20 Thu 4/30/20

27 Water proofing 10 days Fri 4/24/20 Sun 5/3/20

28 Column footing upto DPC level 15 days Wed 4/29/20 Wed 5/13/20

29 Back filling upto capping beam 10 days Sat 5/9/20 Mon 5/18/20

30 Capping beam 25 days Tue 5/19/20 Fri 6/12/20

31 Back filling upto GF level 10 days Sat 6/13/20 Mon 6/22/20

32 Super structure 156 days Tue 6/23/20 Wed 11/25/20

33 Ground floor 15 days Tue 6/23/20 Tue 7/7/20

34 Formwork 5 days Tue 6/23/20 Sat 6/27/20

35 R/f work 10 days Fri 6/26/20 Sun 7/5/20

36 Concreting 2 days Mon 7/6/20 Tue 7/7/20

37 1st floor 46 days Thu 7/9/20 Sun 8/23/20

38 R/f for Colomns 15 days Thu 7/9/20 Thu 7/23/20

39 Formwork 25 days Thu 7/16/20 Sun 8/9/20

40 Slab r/f work 20 days Fri 7/31/20 Wed 8/19/20

41 Conduting & sleeves 10 days Wed 8/12/20 Fri 8/21/20

42 Concreting 2 days Sat 8/22/20 Sun 8/23/20

43 2nd floor 46 days Tue 8/25/20 Fri 10/9/20

44 R/f for Colomns 15 days Tue 8/25/20 Tue 9/8/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
45 Formwork 25 days Tue 9/1/20 Fri 9/25/20

46 Slab r/f work 20 days Wed 9/16/20 Mon 10/5/20

47 Conduting & sleeves 10 days Mon 9/28/20 Wed 10/7/20

48 Concreting 2 days Thu 10/8/20 Fri 10/9/20

49 Roof 46 days Sun 10/11/20 Wed 11/25/20

50 R/f for Colomns 15 days Sun 10/11/20 Sun 10/25/20

51 Formwork 25 days Sun 10/18/20 Wed 11/11/20

52 Slab r/f work 20 days Mon 11/2/20 Sat 11/21/20

53 Conduting & sleeves 10 days Sat 11/14/20 Mon 11/23/20

54 Concreting 2 days Tue 11/24/20 Wed 11/25/20

55 Architectural work 154 days Mon 9/28/20 Sun 2/28/21

56 Ground floor 60 days Mon 9/28/20 Thu 11/26/20

57 Masonry Work 25 days Mon 9/28/20 Thu 10/22/20

58 Internal Plastering 30 days Thu 10/8/20 Fri 11/6/20

59 Doors & Windows 30 days Fri 10/23/20 Sat 11/21/20

60 Floor Finishes 25 days Mon 11/2/20 Thu 11/26/20

61 Ceiling 25 days Fri 10/23/20 Mon 11/16/20

62 Internal painting 20 days Sat 11/7/20 Thu 11/26/20

63 Waterproofing 15 days Sat 11/7/20 Sat 11/21/20

64 External Plastering 20 days Fri 10/23/20 Wed 11/11/20

65 External Painting 10 days Thu 11/12/20 Sat 11/21/20

66 1st floor 60 days Sat 11/14/20 Tue 1/12/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
67 Masonry Work 25 days Sat 11/14/20 Tue 12/8/20

68 Internal Plastering 30 days Tue 11/24/20 Wed 12/23/20

69 Doors & Windows 30 days Wed 12/9/20 Thu 1/7/21

70 Floor Finishes 25 days Sat 12/19/20 Tue 1/12/21

71 Ceiling 25 days Fri 12/4/20 Mon 12/28/20

72 Internal painting 20 days Thu 12/24/20 Tue 1/12/21

73 Waterproofing 15 days Thu 12/24/20 Thu 1/7/21

74 External Plastering 20 days Wed 12/9/20 Mon 12/28/20

75 External Painting 10 days Tue 12/29/20 Thu 1/7/21

76 2nd floor 60 days Thu 12/31/20 Sun 2/28/21


77 Masonry Work 25 days Thu 12/31/20 Sun 1/24/21

78 Internal Plastering 30 days Sun 1/10/21 Mon 2/8/21

79 Doors & Windows 30 days Mon 1/25/21 Tue 2/23/21

80 Floor Finishes 25 days Thu 2/4/21 Sun 2/28/21

81 Ceiling 25 days Wed 1/20/21 Sat 2/13/21

82 Internal painting 20 days Tue 2/9/21 Sun 2/28/21

83 Waterproofing 15 days Tue 2/9/21 Tue 2/23/21

84 External Plastering 20 days Mon 1/25/21 Sat 2/13/21

85 External Painting 10 days Sun 2/14/21 Tue 2/23/21

86 MEP works 174 days Fri 10/23/20 Wed 4/14/21

87 Ground floor 75 days Fri 10/23/20 Tue 1/5/21

88 Elecrical System 45 days Fri 10/23/20 Sun 12/6/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
89 Plumbing Work 60 days Fri 10/23/20 Mon 12/21/20

90 Fire Protection & detection 45 days Fri 10/23/20 Sun 12/6/20

91 Fixing fittings 30 days Mon 12/7/20 Tue 1/5/21

92 1st floor 80 days Wed 12/9/20 Fri 2/26/21

93 Elecrical System 45 days Wed 12/9/20 Fri 1/22/21

94 Plumbing Work 60 days Wed 12/9/20 Sat 2/6/21

95 Fire Protection & detection 45 days Wed 12/9/20 Fri 1/22/21

96 Fixing fittings 30 days Thu 1/28/21 Fri 2/26/21

97 2nd floor 80 days Mon 1/25/21 Wed 4/14/21

98 Elecrical System 45 days Mon 1/25/21 Wed 3/10/21

99 Plumbing Work 60 days Mon 1/25/21 Thu 3/25/21

100 Fire Protection & detection 45 days Mon 1/25/21 Wed 3/10/21

101 Fixing fittings 30 days Tue 3/16/21 Wed 4/14/21

102 Elevetors installation 60 days Mon 1/25/21 Thu 3/25/21

103 Lighting protection 20 days Wed 2/24/21 Mon 3/15/21

104 Club house 334 days Tue 6/23/20 Sat 5/22/21

105 Structural works 184 days Tue 6/23/20 Wed 12/23/20

106 Substructure 75 days Tue 6/23/20 Sat 9/5/20

107 Shoring & excavation 20 days Tue 6/23/20 Sun 7/12/20

108 Foundation footing 30 days Fri 7/3/20 Sat 8/1/20

109 Tie beam 30 days Thu 7/23/20 Fri 8/21/20

110 Water proofing 15 days Fri 8/7/20 Fri 8/21/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
111 Back filling 15 days Sat 8/22/20 Sat 9/5/20

112 Super structure 109 days Sun 9/6/20 Wed 12/23/20

113 Ground floor 15 days Sun 9/6/20 Sun 9/20/20

114 Formwork 5 days Sun 9/6/20 Thu 9/10/20

115 R/f work 10 days Wed 9/9/20 Fri 9/18/20

116 Concreting 2 days Sat 9/19/20 Sun 9/20/20

117 1st floor 46 days Tue 9/22/20 Fri 11/6/20

118 R/f for Colomns 15 days Tue 9/22/20 Tue 10/6/20

119 Formwork 25 days Tue 9/29/20 Fri 10/23/20

120 Slab r/f work 20 days Wed 10/14/20 Mon 11/2/20

121 Conduting & sleeves 10 days Mon 10/26/20 Wed 11/4/20

122 Concreting 2 days Thu 11/5/20 Fri 11/6/20

123 Roof 46 days Sun 11/8/20 Wed 12/23/20

124 R/f for Colomns 15 days Sun 11/8/20 Sun 11/22/20

125 Formwork 25 days Sun 11/15/20 Wed 12/9/20

126 Slab r/f work 20 days Mon 11/30/20 Sat 12/19/20

127 Conduting & sleeves 10 days Sat 12/12/20 Mon 12/21/20

128 Concreting 2 days Tue 12/22/20 Wed 12/23/20

129 Architectural work 107 days Sat 12/12/20 Sun 3/28/21

130 Ground floor 60 days Sat 12/12/20 Tue 2/9/21

131 Masonry Work 25 days Sat 12/12/20 Tue 1/5/21

132 Internal Plastering 30 days Tue 12/22/20 Wed 1/20/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
133 Doors & Windows 30 days Wed 1/6/21 Thu 2/4/21

134 Floor Finishes 25 days Sat 1/16/21 Tue 2/9/21

135 Ceiling 25 days Fri 1/1/21 Mon 1/25/21

136 Internal painting 20 days Thu 1/21/21 Tue 2/9/21

137 Waterproofing 15 days Thu 1/21/21 Thu 2/4/21

138 External Plastering 20 days Wed 1/6/21 Mon 1/25/21

139 External Painting 10 days Tue 1/26/21 Thu 2/4/21

140 1st floor 60 days Thu 1/28/21 Sun 3/28/21

141 Masonry Work 25 days Thu 1/28/21 Sun 2/21/21

142 Internal Plastering 30 days Sun 2/7/21 Mon 3/8/21

143 Doors & Windows 30 days Mon 2/22/21 Tue 3/23/21

144 Floor Finishes 25 days Thu 3/4/21 Sun 3/28/21

145 Ceiling 25 days Wed 2/17/21 Sat 3/13/21

146 Internal painting 20 days Tue 3/9/21 Sun 3/28/21

147 Waterproofing 15 days Tue 3/9/21 Tue 3/23/21

148 External Plastering 20 days Mon 2/22/21 Sat 3/13/21

149 External Painting 10 days Sun 3/14/21 Tue 3/23/21

150 MEP works 137 days Wed 1/6/21 Sat 5/22/21

151 Ground floor 90 days Wed 1/6/21 Mon 4/5/21

152 Elecrical System 45 days Wed 1/6/21 Fri 2/19/21

153 Plumbing Work 60 days Wed 1/6/21 Sat 3/6/21

154 Fire Protection & detection 45 days Wed 1/6/21 Fri 2/19/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
155 Fixing fittings 30 days Sun 3/7/21 Mon 4/5/21

156 1st floor 90 days Mon 2/22/21 Sat 5/22/21

157 Elecrical System 45 days Mon 2/22/21 Wed 4/7/21

158 Plumbing Work 60 days Mon 2/22/21 Thu 4/22/21

159 Fire Protection & detection 45 days Mon 2/22/21 Wed 4/7/21

160 Fixing fittings 30 days Fri 4/23/21 Sat 5/22/21

161 Sports center 334 days Sun 9/6/20 Thu 8/5/21

162 Structural works 184 days Sun 9/6/20 Mon 3/8/21

163 Substructure 75 days Sun 9/6/20 Thu 11/19/20

164 Shoring & excavation 20 days Sun 9/6/20 Fri 9/25/20

165 Foundation footing 30 days Wed 9/16/20 Thu 10/15/20

166 Tie beam 30 days Tue 10/6/20 Wed 11/4/20

167 Water proofing 15 days Wed 10/21/20 Wed 11/4/20

168 Back filling 15 days Thu 11/5/20 Thu 11/19/20

169 Super structure 109 days Fri 11/20/20 Mon 3/8/21

170 Ground floor 15 days Fri 11/20/20 Fri 12/4/20

171 Formwork 5 days Fri 11/20/20 Tue 11/24/20

172 R/f work 10 days Mon 11/23/20 Wed 12/2/20

173 Concreting 2 days Thu 12/3/20 Fri 12/4/20

174 1st floor 46 days Sun 12/6/20 Wed 1/20/21

175 R/f for Colomns 15 days Sun 12/6/20 Sun 12/20/20

176 Formwork 25 days Sun 12/13/20 Wed 1/6/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
177 Slab r/f work 20 days Mon 12/28/20 Sat 1/16/21

178 Conduting & sleeves 10 days Sat 1/9/21 Mon 1/18/21

179 Concreting 2 days Tue 1/19/21 Wed 1/20/21

180 Roof 46 days Fri 1/22/21 Mon 3/8/21

181 R/f for Colomns 15 days Fri 1/22/21 Fri 2/5/21

182 Formwork 25 days Fri 1/29/21 Mon 2/22/21

183 Slab r/f work 20 days Sat 2/13/21 Thu 3/4/21

184 Conduting & sleeves 10 days Thu 2/25/21 Sat 3/6/21

185 Concreting 2 days Sun 3/7/21 Mon 3/8/21

186 Architectural work 107 days Thu 2/25/21 Fri 6/11/21

187 Ground floor 60 days Thu 2/25/21 Sun 4/25/21

188 Masonry Work 25 days Thu 2/25/21 Sun 3/21/21

189 Internal Plastering 30 days Sun 3/7/21 Mon 4/5/21

190 Doors & Windows 30 days Mon 3/22/21 Tue 4/20/21

191 Floor Finishes 25 days Thu 4/1/21 Sun 4/25/21

192 Ceiling 25 days Wed 3/17/21 Sat 4/10/21

193 Internal painting 20 days Tue 4/6/21 Sun 4/25/21

194 Waterproofing 15 days Tue 4/6/21 Tue 4/20/21

195 External Plastering 20 days Mon 3/22/21 Sat 4/10/21

196 External Painting 10 days Sun 4/11/21 Tue 4/20/21

197 1st floor 60 days Tue 4/13/21 Fri 6/11/21

198 Masonry Work 25 days Tue 4/13/21 Fri 5/7/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
199 Internal Plastering 30 days Fri 4/23/21 Sat 5/22/21

200 Doors & Windows 30 days Sat 5/8/21 Sun 6/6/21

201 Floor Finishes 25 days Tue 5/18/21 Fri 6/11/21

202 Ceiling 25 days Mon 5/3/21 Thu 5/27/21

203 Internal painting 20 days Sun 5/23/21 Fri 6/11/21

204 Waterproofing 15 days Sun 5/23/21 Sun 6/6/21

205 External Plastering 20 days Sat 5/8/21 Thu 5/27/21

206 External Painting 10 days Fri 5/28/21 Sun 6/6/21

207 MEP works 137 days Mon 3/22/21 Thu 8/5/21

208 Ground floor 90 days Mon 3/22/21 Sat 6/19/21

209 Elecrical System 45 days Mon 3/22/21 Wed 5/5/21

210 Plumbing Work 60 days Mon 3/22/21 Thu 5/20/21

211 Fire Protection & detection 45 days Mon 3/22/21 Wed 5/5/21

212 Fixing fittings 30 days Fri 5/21/21 Sat 6/19/21

213 1st floor 90 days Sat 5/8/21 Thu 8/5/21

214 Elecrical System 45 days Sat 5/8/21 Mon 6/21/21

215 Plumbing Work 60 days Sat 5/8/21 Tue 7/6/21

216 Fire Protection & detection 45 days Sat 5/8/21 Mon 6/21/21

217 Fixing fittings 30 days Wed 7/7/21 Thu 8/5/21

218 Outdoor works 115 days Sat 6/12/21 Mon 10/4/21

219 Excavation & filling 15 days Sat 6/12/21 Sat 6/26/21

220 Road network 45 days Sun 6/27/21 Tue 8/10/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
ID Task Mode Task Name Duration Start Finish May July September November
M B E M B E M B E M
221 Landscaping 45 days Mon 7/12/21 Wed 8/25/21

222 Boundry wall 30 days Sun 6/27/21 Mon 7/26/21

223 Water tank & sump 30 days Sun 6/27/21 Mon 7/26/21

224 Outdoor play area 30 days Wed 8/11/21 Thu 9/9/21

225 Electrical work 60 days Fri 8/6/21 Mon 10/4/21

226 Plumbing Work 60 days Fri 8/6/21 Mon 10/4/21

227 Testing & Commissioning 90 days Thu 5/6/21 Tue 8/3/21

228 Cleaning 30 days Fri 9/10/21 Sat 10/9/21

229 Handing over 30 days Thu 9/30/21 Fri 10/29/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 18
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 19
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 20
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 21
January March May July September November January March May July September
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 22
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 23
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 24
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 25
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 26
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 27
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 28
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 29
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 30
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 31
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 32
November January March May July September November January March May July
M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M B E M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Toriono
Summary Manual Summary Rollup Progress
Date: Wed 5/29/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only