CONSTRUCTION SCHEDULE

COMMERCIAL BANK OF ETHIOPIA


TOP MANAGEMENT VILLA TWO BUILDING
ID Task Name Duration Start Finish Predece Sep '23 Oct '23
27 03 10 17 24 01 08 15 22 29
0 Top Management Villa 471 days? Mon 18/09/23 Tue 31/12/24
1 Top Management Villa 471 days? Mon 18/09/23 Tue 31/12/24
2 Construction Phase 471 days? Mon 18/09/23 Tue 31/12/24
3 Construction mobilization 27 days Mon 18/09/23 Sat 14/10/23 18/09 14/10
4 Demolishing works 27 days? Mon 16/10/23 Sat 11/11/23
5 Demolishing MEP 5 days Mon 16/10/23 Fri 20/10/23 16/10 20/10
6 Demolishing Structure 8 days Sat 21/10/23 Sat 28/10/23 5 21/10 28/
7 Demolishing Block 14 days Sun 29/10/23 Sat 11/11/23 6 29/10
8 Construction Work 414 days Mon 13/11/23 Mon 30/12/24 7
9 Structure Work 90 days Mon 13/11/23 Sat 10/02/24
10 Sub Structure 30 days Mon 13/11/23 Tue 12/12/23 8
11 Foundation Work 30 days Mon 13/11/23 Tue 12/12/23
12 Excavation Work 5 days Mon 13/11/23 Fri 17/11/23
13 Select Material Fill 3 days Sat 18/11/23 Mon 20/11/23 12
14 Rebar Work 3 days Tue 21/11/23 Thu 23/11/23 13
15 Form work Molding 3 days Fri 24/11/23 Sun 26/11/23 14
16 Concret Fill 2 days Mon 27/11/23 Tue 28/11/23 15
17 Curing Period 10 days Wed 29/11/23 Fri 08/12/23 16
18 Removal of Form work 2 days Sat 09/12/23 Sun 10/12/23 17
19 Selected Material Fill after Foundation is Laid 2 days Mon 11/12/23 Tue 12/12/23 18
20 Supper Structure 90 days Wed 13/12/23 Mon 11/03/24 19
21 Ground Floor 30 days Wed 13/12/23 Thu 11/01/24
22 Rebar Work 3 days Wed 13/12/23 Fri 15/12/23
23 Form work Molding 3 days Sat 16/12/23 Mon 18/12/23 22
24 Concret Fill 2 days Tue 19/12/23 Wed 20/12/23 23

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
ID Task Name Duration Start Finish Predece Sep '23 Oct '23
27 03 10 17 24 01 08 15 22 29
25 Curing Period 10 days Thu 21/12/23 Sat 30/12/23 24
26 Removal of Form work 2 days Sun 31/12/23 Mon 01/01/24 25
27 First Floor 30 days Tue 02/01/24 Wed 31/01/24 26
28 Rebar Work 3 days Tue 02/01/24 Thu 04/01/24
29 Form work Molding 3 days Fri 05/01/24 Sun 07/01/24 28
30 Concret Fill 2 days Mon 08/01/24 Tue 09/01/24 29
31 Curing Period 10 days Wed 10/01/24 Fri 19/01/24 30
32 Removal of Form work 2 days Sat 20/01/24 Sun 21/01/24 31
33 Second Floor 30 days Mon 22/01/24 Tue 20/02/24 32
34 Rebar Work 3 days Mon 22/01/24 Wed 24/01/24
35 Form work Molding 3 days Thu 25/01/24 Sat 27/01/24 34
36 Concret Fill 2 days Sun 28/01/24 Mon 29/01/24 35
37 Curing Period 10 days Tue 30/01/24 Thu 08/02/24 36
38 Removal of Form work 2 days Fri 09/02/24 Sat 10/02/24 37
39 Roof Working Design 30 days Mon 12/02/24 Tue 12/03/24
40 Roof Panal Work 10 days Mon 12/02/24 Wed 21/02/24
41 Roof flashing, vents and selant work 3 days Thu 22/02/24 Sat 24/02/24 40
42 Roof Works 16 days Mon 26/02/24 Tue 12/03/24 41
43 Finishing Works 290 days Wed 13/03/24 Fri 27/12/24
44 HCB work 60 days Wed 13/03/24 Sat 11/05/24
45 Partition Wall Construction 60 days Wed 13/03/24 Sat 11/05/24
46 HCB Exterior wall Construction 60 days Wed 13/03/24 Sat 11/05/24
47 HCB Partition wall Construction 60 days Wed 13/03/24 Sat 11/05/24
48 Wall Finishing 90 days Mon 13/05/24 Sat 10/08/24
49 Plastering 30 days Mon 13/05/24 Tue 11/06/24

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
ID Task Name Duration Start Finish Predece Sep '23 Oct '23
27 03 10 17 24 01 08 15 22 29
50 Gypsum chack 21 days Wed 12/06/24 Tue 02/07/24 49
51 painting 21 days Wed 03/07/24 Tue 23/07/24 50
52 Granite 25 days Wed 12/06/24 Sat 06/07/24 49
53 Wall Tiles 25 days Wed 12/06/24 Sat 06/07/24 49
54 Floor Finishing Works 50 days Mon 13/05/24 Mon 01/07/24
55 Carpet Tile 50 days Mon 13/05/24 Mon 01/07/24
56 Ceramic/Porcelin tile 50 days Mon 13/05/24 Mon 01/07/24
57 Granite 40 days Wed 29/05/24 Sun 07/07/24
58 Ceiling Works 30 days Mon 02/09/24 Tue 01/10/24
59 Suspended sound proof Ceiling 30 days Mon 02/09/24 Tue 01/10/24
60 Aluminum panel 30 days Mon 02/09/24 Tue 01/10/24
61 Gypsum board 30 days Mon 02/09/24 Tue 01/10/24
62 Metal works 21 days Mon 02/09/24 Sun 22/09/24
63 Handrail 21 days Mon 02/09/24 Sun 22/09/24
64 Carpentery and Joinery 60 days Mon 02/09/24 Thu 31/10/24
65 Wooden doors 30 days Mon 02/09/24 Tue 01/10/24
66 Built in furniture 25 days Mon 30/09/24 Thu 24/10/24
67 Interior Design works 30 days Mon 16/09/24 Tue 15/10/24
68 Interior design works 15 days Tue 01/10/24 Tue 15/10/24
69 Fixing Bed room Fixtures 15 days Mon 16/09/24 Mon 30/09/24
70 Fixing kitchen Fixtures 15 days Mon 16/09/24 Mon 30/09/24
71 Others Fixtures 5 days Tue 01/10/24 Sat 05/10/24 70
72 MEP WORKS 60 days Tue 01/10/24 Fri 29/11/24
73 SANITARY Works 30 days Tue 01/10/24 Wed 30/10/24
74 Sanitary Installation 30 days Tue 01/10/24 Wed 30/10/24

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
ID Task Name Duration Start Finish Predece Sep '23 Oct '23
27 03 10 17 24 01 08 15 22 29
75 DOMESTIC WATER PIPES & VALVES 15 days Tue 01/10/24 Tue 15/10/24
76 DRAINAGE PLUMBING SYSTEM 15 days Tue 01/10/24 Tue 15/10/24
77 Fixing of Sanitary fixtures and Water Tanks 10 days Wed 16/10/24 Fri 25/10/24 76
78 Mechanical works 7 days Tue 01/10/24 Mon 07/10/24
79 Mechanical Installation 7 days Tue 01/10/24 Mon 07/10/24
80 Fixing of Mechanical fixtures 7 days Tue 01/10/24 Mon 07/10/24
81 Electrical works 60 days Tue 01/10/24 Fri 29/11/24
82 Electrical Installation 60 days Tue 01/10/24 Fri 29/11/24
83 Conduit Installation 21 days Tue 01/10/24 Mon 21/10/24
84 Cable tray 21 days Tue 01/10/24 Mon 21/10/24
85 Cable ladder 21 days Tue 01/10/24 Mon 21/10/24
86 POWER SUPPLY AND DISTRBUTION 14 days Tue 22/10/24 Mon 04/11/24 83
87 LUMINAIRES 25 days Tue 05/11/24 Fri 29/11/24 86
88 WIRING DEVICES 25 days Tue 05/11/24 Fri 29/11/24 86
89 TELECOM 25 days Tue 22/10/24 Fri 15/11/24 83
90 LIGHTING PROTECTION AND EARTHING 7 days Tue 01/10/24 Mon 07/10/24

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
Nov '23 Dec '23 Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21

10
28/10
11/11

13/11 10/02

13/11 17/11
18/11 20/11
21/11 23/11
24/11 26/11
27/11 28/11
29/11 08/12
09/12 10/12
11/12 12/12

13/12 11/01
13/12 15/12
16/12 18/12
19/12 20/12

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
Nov '23 Dec '23 Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21
21/12 30/12
31/12 01/01
02/01 31/01
02/01 04/01
05/01 07/01
08/01 09/01
10/01 19/01
20/01 21/01
22/01 20/02
22/01 24/01
25/01 27/01
28/01 29/01
30/01 08/02
09/02 10/02

12/02 21/02
22/02 24/02
26/02 12/03

13/03 11/05

13/03 11/05
13/03 11/05

13/05 11/06

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
Nov '23 Dec '23 Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21
12/06 02/07
03/07 23/
12/06 06/07
12/06 06/07

13/05 01/07
13/05 01/07
29/05 07/07

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20

23/07

02/09 01/10
02/09 01/10
02/09 01/10

02/09 22/09

02/09 01/10
30/09 24/10

01/10 15/10
16/09 30/09
16/09 30/09
01/10 05/10

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by


CONSTRUCTION SCHEDULE
COMMERCIAL BANK OF ETHIOPIA
TOP MANAGEMENT VILLA TWO BUILDING
Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
28 04 11 18 25 01 08 15 22 29 0613 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20
01/10 15/10
01/10 15/10
16/10 25/10

01/10 07/10

01/10 21/10
01/10 21/10
01/10 21/10
22/10 04/11
05/11 29/11
05/11 29/11
22/10 15/11
01/10 07/10

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Progress Project Summary Start-only
Milestone Group By Summary Finish-only
Summary Deadline External Tasks
Rolled Up Task Inactive Milestone External Milestone
Rolled Up Critical Task Inactive Summary Manual Progress
Rolled Up Milestone Manual Task
Rolled Up Progress Duration-only

prepared by checked by . Approved by

You might also like