ID Task Name Duration Start Finish
12 Nov '23 19 Nov '23 26 Nov '23
F S S M T W T F S S
23 Internal and External Plastering 5 days Wed 06/12/23 Tue 12/12/23
24
25
26 COVERED WALKWAYS 15 days Mon 20/11/23 Fri 08/12/23
27 Substructure 31 days Mon 20/11/23 Mon 01/01/24
28 Setting out for disability ramps and ground beams and slabs 2 days Mon 20/11/23 Tue 21/11/23
Page 2
26 Nov '23 03 Dec '23 10 Dec '23 17 Dec '23 24 Dec '23 31 Dec '23
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Page 3
26 Nov '23 03 Dec '23 10 Dec '23 17 Dec '23 24 Dec '23 31 Dec '23
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Page 4