You are on page 1of 4

ID Task Name Duration Start Finish

12 Nov '23 19 Nov '23 26 Nov '23


F S S M T W T F S S
1 GHANA PRIORITY HEALTH INFRASTRUCTURE 0 days Mon 20/11/23 Mon 20/11/23 20/11
PROJECT.AGENDA111-ATWIMA MPONUA DISTRICT
2 PROGRAMME OF WORKS 0 days Sat 18/11/23 Sat 18/11/23 18/11
3
4 SECURITYAND COMMENCE 16 days Mon 20/11/23 Mon 11/12/23
5 Substructure 6 days Mon 20/11/23 Mon 27/11/23
6 Backfilling 3 days Mon 20/11/23 Wed 22/11/23
7 Concrete in beams and slab apron 3 days Thu 23/11/23 Mon 27/11/23
8
9 Superstucture 16 days Mon 20/11/23 Mon 11/12/23
10 Installation of Roof trusses 2 days Mon 20/11/23 Tue 21/11/23
11 Installation of Roof covering 4 days Wed 22/11/23 Mon 27/11/23
12 Screeding and Water Proofing on roof gutters and upstands 4 days Tue 28/11/23 Fri 01/12/23
13 Internal block work 4 days Tue 28/11/23 Fri 01/12/23
14 External block work-CEB 6 days Mon 04/12/23 Mon 11/12/23
15
16
17 ADMINISTRATION BLOCK 31 days Mon 20/11/23 Mon 01/01/24
18 Superstructure 17 days Mon 20/11/23 Tue 12/12/23
19 External block work-CEB 3 days Mon 20/11/23 Wed 22/11/23
20 Screeding and Water Proofing on roof gutters and upstands 3 days Mon 20/11/23 Wed 22/11/23

21 Installation of Roof trusses 8 days Mon 20/11/23 Wed 29/11/23


22 Installation of Roof covering 4 days Thu 30/11/23 Tue 05/12/23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: WEEKLY WORK PROGR
Summary Manual Summary Rollup Progress
Date: Sun 19/11/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start Finish
12 Nov '23 19 Nov '23 26 Nov '23
F S S M T W T F S S
23 Internal and External Plastering 5 days Wed 06/12/23 Tue 12/12/23
24
25
26 COVERED WALKWAYS 15 days Mon 20/11/23 Fri 08/12/23
27 Substructure 31 days Mon 20/11/23 Mon 01/01/24
28 Setting out for disability ramps and ground beams and slabs 2 days Mon 20/11/23 Tue 21/11/23

29 Blockwork 3 days Wed 22/11/23 Fri 24/11/23


30 Installation of reinforcement for ground beam 4 days Mon 27/11/23 Thu 30/11/23
31 Fixing of formwork for edges of ground beam 3 days Fri 01/12/23 Tue 05/12/23
32 Casting of Ground beam 4 days Wed 06/12/23 Mon 11/12/23
33 Bituminous painting on Blockwork and Ground beams 2 days Tue 12/12/23 Wed 13/12/23
34 Hardcore filiing and compaction 6 days Tue 12/12/23 Tue 19/12/23
35 Placing of DPM sheetes and BRC Mesh on hardcore filling 2 days Wed 20/12/23 Thu 21/12/23

36 Formwork to edges of blockwork 3 days Fri 22/12/23 Tue 26/12/23


37 Casting of oversite concrete 4 days Wed 27/12/23 Mon 01/01/24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: WEEKLY WORK PROGR
Summary Manual Summary Rollup Progress
Date: Sun 19/11/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
26 Nov '23 03 Dec '23 10 Dec '23 17 Dec '23 24 Dec '23 31 Dec '23
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: WEEKLY WORK PROGR
Summary Manual Summary Rollup Progress
Date: Sun 19/11/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
26 Nov '23 03 Dec '23 10 Dec '23 17 Dec '23 24 Dec '23 31 Dec '23
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: WEEKLY WORK PROGR
Summary Manual Summary Rollup Progress
Date: Sun 19/11/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4

You might also like