ID Task Task Name Duration Start Finish 19 Sep '22 03 Oct '22 17 Oct '22 31 Oct '22 14 Nov

9 Sep '22 03 Oct '22 17 Oct '22 31 Oct '22 14 Nov '22 28 Nov '22 12 Dec '22 26 Dec '22 09 Jan '23 23 Jan '23 06 Feb '23 20 Feb '23
Mode T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S
1 SARIAYA WAREHOUSE 108 days Mon 26/09/22 Wed 22/02/23
2 ERECTION 108 days Mon 26/09/22 Wed 22/02/23
3 WAREHOUSE 2 45 days Mon 26/09/22 Fri 25/11/22
4 Sorting 7 days Mon 26/09/22 Tue 04/10/22
5 Main Frame Erection 20 days Mon 03/10/22 Fri 28/10/22
6 Purlins 20 days Mon 10/10/22 Fri 04/11/22
7 Sidewall and Endwall Girt 25 days Mon 17/10/22 Fri 18/11/22
8 Sag Rod 20 days Fri 28/10/22 Thu 24/11/22
9 Canopy and Frame Opening 10 days Fri 28/10/22 Thu 10/11/22
10 Sliding Door 10 days Fri 28/10/22 Thu 10/11/22
11 Cage Ladder 5 days Thu 10/11/22 Wed 16/11/22
12 Punch Listing 7 days Thu 17/11/22 Fri 25/11/22
13 WAREHOUSE 4 44 days Fri 28/10/22 Wed 28/12/22
14 Sorting 7 days Fri 28/10/22 Mon 07/11/22
15 Main Frame Erection 20 days Sat 29/10/22 Thu 24/11/22
16 Purlins 20 days Mon 07/11/22 Fri 02/12/22
17 Sidewall and Endwall Girt 25 days Mon 14/11/22 Fri 16/12/22
18 Sag Rod 20 days Mon 28/11/22 Fri 23/12/22
19 Canopy and Frame Opening 10 days Mon 28/11/22 Fri 09/12/22
20 Sliding Door 10 days Mon 28/11/22 Fri 09/12/22
21 Cage Ladder 5 days Tue 13/12/22 Mon 19/12/22
22 Punch Listing 7 days Tue 20/12/22 Wed 28/12/22
23 WAREHOUSE 3 44 days Fri 25/11/22 Wed 25/01/23
24 Sorting 7 days Fri 25/11/22 Mon 05/12/22
25 Main Frame Erection 20 days Sat 26/11/22 Thu 22/12/22
26 Purlins 20 days Mon 05/12/22 Fri 30/12/22
27 Sidewall and Endwall Girt30 days Mon 12/12/22 Fri 20/01/23
28 Sag Rod 20 days Tue 27/12/22 Mon 23/01/23
29 Canopy and Frame Opening 10 days Tue 27/12/22 Mon 09/01/23
30 Sliding Door 10 days Tue 27/12/22 Mon 09/01/23
31 Cage Ladder 5 days Tue 10/01/23 Mon 16/01/23
32 Punch Listing 7 days Tue 17/01/23 Wed 25/01/23
33 WAREHOUSE 1 44 days Fri 23/12/22 Wed 22/02/23
34 Sorting 7 days Fri 23/12/22 Mon 02/01/23
35 Main Frame Erection 20 days Tue 27/12/22 Mon 23/01/23
36 Purlins 20 days Tue 03/01/23 Mon 30/01/23
37 Sidewall and Endwall Girt30 days Tue 10/01/23 Mon 20/02/23
38 Sag Rod 20 days Tue 24/01/23 Mon 20/02/23
39 Canopy and Frame Opening 10 days Tue 24/01/23 Mon 06/02/23
40 Sliding Door 10 days Tue 24/01/23 Mon 06/02/23
41 Cage Ladder 5 days Tue 07/02/23 Mon 13/02/23
42 Punch Listing 7 days Tue 14/02/23 Wed 22/02/23
43 EQUIPMENT SCHEDULING 108 days Mon 26/09/22 Wed 22/02/23
44 Erection and Sorting 108 days Mon 26/09/22 Wed 22/02/23
45 16 tonner Boomtrck 86 days Mon 26/09/22 Mon 23/01/23
46 35 tonner Mobile Crane Unit86 days
1 Mon 26/09/22 Mon 23/01/23
47 Manlift 103 days Mon 03/10/22 Wed 22/02/23

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Sariaya Warehopuse Pr Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 22/09/22
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
20 Feb '23 06 Mar '23 20 Mar '23 03 Apr '23 17 Apr '23 01 May '23 15 May '23 29 May '23 12 Jun '23 26 Jun '23 10 Jul '23 24 Jul '23 07 Aug '23 21 Aug '23 04 Sep '23 18 Sep '23 02 Oct '23 16 Oct '23
S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Sariaya Warehopuse Pr Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 22/09/22
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress