ID Task Name Duration Start Finish Predecessors Resource Names

Oct '21

1 ACSI G+4 OFFICE 420 days Mon 10/11/21 Sun 12/04/22

2 Mobilization 0 days Mon 10/11/21 Mon 10/11/21 11.10

3 G+4 OFFICE Building 420 days Mon 10/11/21 Sun 12/04/22

4 sub structure 130 days Mon 10/11/21 Thu 2/17/22

5 Excavation and Earth work 50 days Mon 10/11/21 Mon 11/29/21

6 Concrete work 80 days Tue 11/30/21 Thu 2/17/22 5

7 Masonry Work 30 days Tue 12/28/21 Wed 1/26/22 6SS+28 days

8 super structure 290 days Fri 2/18/22 Sun 12/04/22

9 concrete work 102 days Fri 2/18/22 Mon 5/30/22 6

10 Block Work 60 days Tue 5/31/22 Fri 7/29/22 9

11 Plastering and pointing 40 days Tue 6/28/22 Sat 8/06/22 10SS+28 days

12 Carpentry joinery 30 days Sun 8/07/22 Mon 9/05/22 11

13 Steel Structure 30 days Tue 5/31/22 Wed 6/29/22 9

14 Alluminum work 30 days Tue 9/06/22 Wed 10/05/22 12

15 Roofing 30 days Thu 6/30/22 Fri 7/29/22 13

16 Floor and wall finishing 30 days Thu 10/06/22 Fri 11/04/22 14

17 Painting 30 days Sat 11/05/22 Sun 12/04/22 16

18 Electrical instalation 50 days Sat 7/30/22 Sat 9/17/22 15

19 Sanitary instalation 50 days Sat 7/30/22 Sat 9/17/22 15

20 Gourd House 147 days Mon 10/11/21 Sun 3/06/22

21 A.Sub structure 41 days Mon 10/11/21 Sat 11/20/21

22 Excavation and Earth work 11 days Mon 10/11/21 Thu 10/21/21

23 Concrete work 30 days Fri 10/22/21 Sat 11/20/21 22

24 Masonry Work 15 days Wed 10/27/21 Wed 11/10/21 23SS+5 days

25 B.Supper Structure 106 days Sun 11/21/21 Sun 3/06/22

26 Concrete Work 30 days Sun 11/21/21 Mon 12/20/21 23

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: zobit and ambela Split External Tasks Inactive Summary Manual Summary Deadline
Date: 12/13/2021 2:28 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Name Duration Start Finish Predecessors Resource Names

Oct '21

27 Block Work 20 days Tue 12/21/21 Sun 1/09/22 26

28 Carpenter and joinery 20 days Tue 12/21/21 Sun 1/09/22 26

29 Roofing 20 days Mon 1/10/22 Sat 1/29/22 28

30 Finishing Work 20 days Mon 1/10/22 Sat 1/29/22 27

31 Metal work 20 days Sun 1/30/22 Fri 2/18/22 30

32 Glazing Work 16 days Sat 2/19/22 Sun 3/06/22 31

33 Painting work 20 days Sun 1/30/22 Fri 2/18/22 30

34 Electrical Instalation 20 days Tue 12/21/21 Sun 1/09/22 27SS

35 Sanitary Instalation 20 days Mon 1/10/22 Sat 1/29/22 27

36 Generator House 120 days Mon 10/11/21 Mon 2/07/22

37 A.Sub structure 40 days Mon 10/11/21 Fri 11/19/21

38 Excavation and Earth work 10 days Mon 10/11/21 Wed 10/20/21

39 Masonry Work 10 days Thu 10/21/21 Sat 10/30/21 38

40 Concrete work 20 days Sun 10/31/21 Fri 11/19/21 39

41 B.Supper Structure 80 days Sat 11/20/21 Mon 2/07/22

42 Concrete Work 20 days Sat 11/20/21 Thu 12/09/21 40

43 Carpenter and joinery 20 days Fri 12/10/21 Wed 12/29/21 42

44 Block Work 20 days Fri 12/10/21 Wed 12/29/21 42

45 Roofing 20 days Thu 12/30/21 Tue 1/18/22 43

46 Metal work 20 days Thu 12/30/21 Tue 1/18/22 44

47 Finishing Work 20 days Thu 12/30/21 Tue 1/18/22 44

48 Glazing Work 20 days Wed 1/19/22 Mon 2/07/22 46

49 Painting work 15 days Wed 1/19/22 Wed 2/02/22 47

50 Electrical Instalation 15 days Fri 12/10/21 Fri 12/24/21 44SS

51 Sanitary Instalation 15 days Thu 12/30/21 Thu 1/13/22 44

52 Fence Work 70 days Tue 7/26/22 Mon 10/03/22

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: zobit and ambela Split External Tasks Inactive Summary Manual Summary Deadline
Date: 12/13/2021 2:28 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Name Duration Start Finish Predecessors Resource Names

Oct '21

53 Earth and Excavation work 8 days Tue 7/26/22 Tue 8/02/22

54 Concrete work 20 days Wed 8/03/22 Mon 8/22/22 53

55 Block work 17 days Tue 8/23/22 Thu 9/08/22 54

56 Pointing and plastering 15 days Fri 9/09/22 Fri 9/23/22 55

57 Steel Structure and metal work 15 days Fri 9/09/22 Fri 9/23/22 55

58 Electrical work 10 days Sat 9/24/22 Mon 10/03/22 57

59 Site work 25 days Tue 7/26/22 Fri 8/19/22

60 Earth and Excavation work 5 days Tue 7/26/22 Sat 7/30/22

61 Borow Fill 10 days Sun 7/31/22 Tue 8/09/22 60

62 Pavement Work 10 days Wed 8/10/22 Fri 8/19/22 61

63 Flag pole 10 days Wed 8/10/22 Fri 8/19/22 61

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: zobit and ambela Split External Tasks Inactive Summary Manual Summary Deadline
Date: 12/13/2021 2:28 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3
2022 2023

Dec '21 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: zobit and ambela Split External Tasks Inactive Summary Manual Summary Deadline
Date: 12/13/2021 2:28 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 4
2022 2023

Dec '21 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: zobit and ambela Split External Tasks Inactive Summary Manual Summary Deadline
Date: 12/13/2021 2:28 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 5
2022 2023

Dec '21 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: zobit and ambela Split External Tasks Inactive Summary Manual Summary Deadline
Date: 12/13/2021 2:28 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 6