AES LNG - ARCHITECTURAL PACKAGE

ID Task Name Duration Start Finish May June July August September October November December January February March April May June
30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19
1 POSCO - AES LNG GAS EXPANSION 30 days Mon 6/7/21 Fri 7/16/21 0%
2 preliminary works 30 days Mon 6/7/21 Fri 7/16/21 0%
3 Offer Submission 0 days Mon 6/7/21 Mon 6/7/21 6/7
4 Approval and contract 15 days Mon 6/7/21 Fri 6/25/21 0%
5 Mobilization to site and purchase of materiales to start with
15 days
the worksMon 6/28/21 Fri 7/16/21 0%
6 CONSTRUCTION PROCESS 220 days Mon 7/19/21 Fri 5/20/22 0%
7 BUILDING WORKS 220 days Mon 7/19/21 Fri 5/20/22 0%
8 Electrical Building (700 M2) 178 days Mon 7/19/21 Wed 3/23/22 0%
9 Excavation works 24 days Mon 7/19/21 Thu 8/19/21 0%
10 Foundation works 60 days Mon 8/9/21 Fri 10/29/21 0%
11 Ground Slab 60 days Mon 9/20/21 Fri 12/10/21 0%
12 Columns and Walls for electrical building 60 days Thu 9/9/21 Wed 12/1/21 0%
13 Roof termination 60 days Tue 11/9/21 Mon 1/31/22 0%
14 Masonry and terminations 50 days Thu 10/28/21 Wed 1/5/22 0%
15 Internal and external termination and painting 60 days Thu 12/30/21 Wed 3/23/22 0%
16 Switchyard electrical building (97.5 M2) 127 days Wed 9/15/21 Thu 3/10/22 0%
17 Excavation works 7 days Wed 9/15/21 Thu 9/23/21 0%
18 Foundation works 30 days Fri 9/24/21 Thu 11/4/21 0%
19 Ground Slab 30 days Thu 10/28/21 Wed 12/8/21 0%
20 Columns and Walls for electrical building 30 days Fri 10/22/21 Thu 12/2/21 0%
21 Roof termination 30 days Fri 11/19/21 Thu 12/30/21 0%
22 Masonry and terminations 32 days Fri 12/24/21 Mon 2/7/22 0%
23 Internal and external termination and painting 32 days Wed 1/26/22 Thu 3/10/22 0%
24 Control Building (200 M2) 187 days Thu 9/2/21 Fri 5/20/22 0%
25 Excavation works 12 days Thu 9/2/21 Fri 9/17/21 0%
26 Foundation works 27 days Mon 9/20/21 Tue 10/26/21 0%
27 Ground Slab 20 days Tue 10/19/21 Mon 11/15/21 0%
28 1 floor Columns and Walls for electrical building 35 days Mon 11/15/21 Fri 12/31/21 0%
29 2nd floor slab 30 days Tue 12/14/21 Mon 1/24/22 0%
30 2nd Floor Columns and walls 35 days Thu 12/30/21 Wed 2/16/22 0%
31 1 Floor Masonry and terminations 45 days Mon 1/24/22 Fri 3/25/22 0%
32 1 Floor Internal and external termination and painting45 days Wed 2/16/22 Tue 4/19/22 0%
33 Roof for control building 30 days Thu 2/17/22 Wed 3/30/22 0%
34 2 Floor Masonry and terminations 30 days Thu 3/10/22 Wed 4/20/22 0%
35 2 Floor Internal and external termination and painting42 days Thu 3/24/22 Fri 5/20/22 0%
36 Warehouse (192 M2) 134 days Mon 11/8/21 Thu 5/12/22 0%
37 Excavation works 21 days Mon 11/8/21 Mon 12/6/21 0%
38 Foundation works 37 days Fri 11/26/21 Mon 1/17/22 0%
39 Ground Slab 37 days Thu 12/23/21 Fri 2/11/22 0%
40 Columns and Walls for electrical building 37 days Fri 12/10/21 Mon 1/31/22 0%
41 Installation of Corridor for Warehouse 28 days Wed 1/19/22 Fri 2/25/22 0%
42 Roof termination 28 days Mon 2/14/22 Wed 3/23/22 0%

Page 1
AES LNG - ARCHITECTURAL PACKAGE
ID Task Name Duration Start Finish May June July August September October November December January February March April May June
30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19
43 Masonry and terminations 28 days Wed 3/9/22 Fri 4/15/22 0%
44 Internal and external termination and painting 28 days Tue 4/5/22 Thu 5/12/22 0%
45 Guard House (16 M2) 64 days Mon 9/20/21 Thu 12/16/21 0%
46 Excavation works 6 days Mon 9/20/21 Mon 9/27/21 0%
47 Foundation works 9 days Tue 9/28/21 Fri 10/8/21 0%
48 Ground Slab 9 days Mon 10/11/21 Thu 10/21/21 0%
49 Columns and Walls for electrical building 15 days Thu 10/21/21 Wed 11/10/21 0%
50 Roof termination 15 days Tue 11/9/21 Mon 11/29/21 0%
51 Masonry and terminations 15 days Fri 11/19/21 Thu 12/9/21 0%
52 Internal and external termination and painting 10 days Fri 12/3/21 Thu 12/16/21 0%
53 Gate House (5 M2) 43 days Fri 10/22/21 Tue 12/21/21 0%
54 Excavation works 4 days Fri 10/22/21 Wed 10/27/21 0%
55 Foundation works 7 days Thu 10/28/21 Fri 11/5/21 0%
56 Ground Slab 7 days Mon 11/8/21 Tue 11/16/21 0%
57 Columns and Walls for electrical building 12 days Tue 11/16/21 Wed 12/1/21 0%
58 Roof termination 12 days Tue 11/30/21 Wed 12/15/21 0%
59 Masonry and terminations 8 days Tue 12/7/21 Thu 12/16/21 0%
60 Internal and external termination and painting 8 days Fri 12/10/21 Tue 12/21/21 0%
61 SHELTER 165 days Fri 9/24/21 Thu 5/12/22 0%
62 BOG AND SOG Compressor (1733.30 M2) 165 days Fri 9/24/21 Thu 5/12/22 0%
63 Excavation works 20 days Fri 9/24/21 Thu 10/21/21 0%
64 Foundation works 35 days Fri 10/22/21 Thu 12/9/21 0%
65 Ground Slab 60 days Fri 11/19/21 Thu 2/10/22 0%
66 Pedestals 30 days Fri 11/5/21 Thu 12/16/21 0%
67 Structure prefabrication and erection 80 days Fri 12/10/21 Thu 3/31/22 0%
68 Interior and exterior termination works 70 days Fri 2/4/22 Thu 5/12/22 0%
69 Instrument Air compressor Shelter (163.40 M2) 59 days Wed 12/1/21 Mon 2/21/22 0%
70 Excavation works 7 days Wed 12/1/21 Thu 12/9/21 0%
71 Foundation works 12 days Fri 12/10/21 Mon 12/27/21 0%
72 Ground Slab 15 days Tue 12/28/21 Mon 1/17/22 0%
73 Pedestals 12 days Fri 12/24/21 Mon 1/10/22 0%
74 Structure prefabrication and erection 25 days Tue 12/28/21 Mon 1/31/22 0%
75 Interior and exterior termination works 15 days Tue 2/1/22 Mon 2/21/22 0%
76 Truck loading operation shelter (4 M2) 44 days Fri 12/10/21 Wed 2/9/22 0%
77 Excavation works 5 days Fri 12/10/21 Thu 12/16/21 0%
78 Foundation works 7 days Fri 12/17/21 Mon 12/27/21 0%
79 Ground Slab 8 days Tue 12/28/21 Thu 1/6/22 0%
80 Pedestals 7 days Fri 12/31/21 Mon 1/10/22 0%
81 Structure prefabrication and erection 11 days Tue 1/11/22 Tue 1/25/22 0%
82 Interior and exterior termination works 11 days Wed 1/26/22 Wed 2/9/22 0%
83 Fire water pump Shelter (24 M2) 58 days Tue 12/28/21 Thu 3/17/22 0%
84 Excavation works 9 days Tue 12/28/21 Fri 1/7/22 0%

Page 2
AES LNG - ARCHITECTURAL PACKAGE
ID Task Name Duration Start Finish May June July August September October November December January February March April May June
30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19
85 Foundation works 19 days Mon 1/10/22 Thu 2/3/22 0%
86 Ground Slab 15 days Fri 2/4/22 Thu 2/24/22 0%
87 Pedestals 19 days Mon 1/24/22 Thu 2/17/22 0%
88 Structure prefabrication and erection 17 days Fri 2/4/22 Mon 2/28/22 0%
89 Interior and exterior termination works 17 days Wed 2/23/22 Thu 3/17/22 0%
90 STRUCTURE 119 days Thu 10/28/21 Tue 4/12/22 0%
91 Truck loading Rack (1,093.24 M2) 57 days Thu 10/28/21 Fri 1/14/22 0%
92 Excavation works 25 days Thu 10/28/21 Wed 12/1/21 0%
93 Foundation works 40 days Mon 11/22/21 Fri 1/14/22 0%
94 Over Bridge 1 (198 M2) 22 days Thu 12/2/21 Fri 12/31/21 0%
95 Excavation works 7 days Thu 12/2/21 Fri 12/10/21 0%
96 Foundation works 15 days Mon 12/13/21 Fri 12/31/21 0%
97 Piperack 1 (234 M2) 25 days Fri 12/17/21 Thu 1/20/22 0%
98 Excavation works 8 days Fri 12/17/21 Tue 12/28/21 0%
99 Foundation works 17 days Wed 12/29/21 Thu 1/20/22 0%
100 Piperack 2 (2050.80 M2) 59 days Wed 12/29/21 Mon 3/21/22 0%
101 Excavation works 30 days Wed 12/29/21 Tue 2/8/22 0%
102 Foundation works 42 days Fri 1/21/22 Mon 3/21/22 0%
103 Piperack 3 (420 M2) 33 days Wed 2/9/22 Fri 3/25/22 0%
104 Excavation works 15 days Wed 2/9/22 Tue 3/1/22 0%
105 Foundation works 18 days Wed 3/2/22 Fri 3/25/22 0%
106 Process Structure 1 (364.50 M2) 30 days Wed 3/2/22 Tue 4/12/22 0%
107 Excavation works 14 days Wed 3/2/22 Mon 3/21/22 0%
108 Foundation works 16 days Tue 3/22/22 Tue 4/12/22 0%