Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 34% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 44% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 40% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 40% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 40% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name March 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
62 The provision of underground electrical 36% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2