ID Task Name Duration Predecessors % Work Start Finish

Complete February 20 March 2024 April 2024 May 2024 June 2024 July 2024
1 OVERALL PROJECT DURATION 152 days 0% Mon 2/12/24 Fri 7/12/24
2 Preliminary Works 40 days 0% Mon 2/12/24 Fri 3/22/24
4 Submission Of all required documents related to the project 1 day 100% Mon 2/12/24 Mon 2/12/24
6 Submission Of Material Submittal For Civil Materials- First Stage 1 day 4 100% Tue 2/13/24 Tue 2/13/24
7 Submission Of Material Submittal For MEP Materials- First Stage 1 day 4 100% Tue 2/13/24 Tue 2/13/24
5 Submission For Authority Approval & permits including Abu dhabi Municipality 1 day 4FS+3 days 100% Fri 2/16/24 Fri 2/16/24
8 Arrangement of Sign Boards, Temporary Power DB inside the Site & Setting Out 2 days 5,3 0% Thu 3/21/24 Fri 3/22/24
3 Site Mobilization 2 days 100% Tue 3/19/24 Wed 3/20/24
39 Coring & Covering Works 44 days 0% Mon 2/19/24 Tue 4/2/24
40 Marking on the Slab & Protecting from Down Side 4 days 8,3 0% Mon 2/19/24 Sat 3/23/24
41 Coring Works For the Slab 5 days 40FS+5 days 0% Fri 3/29/24 Tue 4/2/24
11 Civil Works 67 days 0% Thu 3/21/24 Sun 5/26/24
12 Supply & Installation of 20cm thick Block Wall with Lintel & Plastering 18 days 3FS+10 days,6 0% Sun 3/31/24 Wed 4/17/24
13 Supply and installation of 100 mm Mortar & 50mm thick polystrene for whole floor 12 days 24 0% Wed 4/10/24 Sun 4/21/24
14 Internal Partition Works- Single Side 12 days 5,3 0% Thu 3/21/24 Mon 4/1/24
15 Supply & Installation of Rockwool inside the Partition 6 days 14,24,25,29FS-5 days 0% Wed 4/10/24 Mon 4/15/24
16 Internal Partition Works - Double Side 15 days 29FS-5 days,25FS-5 days,15FS-5 days 0% Thu 4/11/24 Thu 4/25/24
20 Joint Filling Works On Gypsum Wall 10 days 16FS-10 days 0% Tue 4/16/24 Thu 4/25/24
17 Supply and fix water proofing and screed to match finish level in floor area 5 days 14,24,16 0% Fri 4/26/24 Tue 4/30/24
22 Supply and fix Wall Tiles 5 days 24,25,16,17 0% Wed 5/1/24 Sun 5/5/24
18 False Ceiling Installation 12 days 34,24,25,29,30,31,37,38 0% Tue 5/7/24 Sat 5/18/24
21 Ceiling Painting Works 10 days 18FS-10 days 0% Thu 5/9/24 Sat 5/18/24
19 Wall Painting Works 8 days 16,29,30,31,18,20FS-5 days,21FS-5 days 0% Sun 5/19/24 Sun 5/26/24
23 Plumbing Works 58 days 0% Sun 3/31/24 Mon 5/27/24
24 Drainage Piping Works 10 days 41FS-3 days 0% Sun 3/31/24 Tue 4/9/24
25 Hot & Cold Water Piping Woks 8 days 14,7FS+3 days,3 0% Tue 4/2/24 Tue 4/9/24
26 Supply & Installation of necessary Plumbing Services 3 days 25 0% Wed 4/10/24 Fri 4/12/24
27 Supply & Installation of Sanitary Fittings 4 days 45FS-3 days,22FS-3 days,24FS-3 days,25FS-3 days,19FS-3
0% days,21FS-3
Fri 5/24/24 days Mon 5/27/24
34 Fire Alarm , Emergency Lighting & Fire Fighting Works 40 days 0% Thu 3/28/24 Mon 5/6/24
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days 14FS-5 days 0% Thu 3/28/24 Mon 5/6/24
36 HVAC Works 32 days 0% Thu 3/28/24 Sun 4/28/24
37 Supply & Instllation of Ducting Works 30 days 14FS-5 days,7 0% Thu 3/28/24 Fri 4/26/24
38 Supply & Installation Of FCU 15 days 7FS+60 days 0% Sun 4/14/24 Sun 4/28/24
28 Electrical Works 60 days 0% Tue 4/2/24 Fri 5/31/24
29 Conduiting Works 10 days 14 0% Tue 4/2/24 Thu 4/11/24
30 Supply & Installation of PDB 5 days 29 0% Fri 4/12/24 Tue 4/16/24
31 Cable Pulling Works 10 days 30,29FS-2 days 0% Wed 4/17/24 Fri 4/26/24
32 Installation of Lights 10 days 18 0% Sun 5/19/24 Tue 5/28/24
33 Installation of Sockets 10 days 19FS-5 days 0% Wed 5/22/24 Fri 5/31/24
42 Floor Finishing Works 24 days 0% Mon 5/6/24 Wed 5/29/24
45 Floor Tiles Installation Works 10 days 22,17,24,25 0% Mon 5/6/24 Wed 5/15/24
43 Supply & Installation of Self leveing to floor to receive vinyl flooring 5 days 19FS-10 days,21FS-10 days 0% Fri 5/17/24 Tue 5/21/24
44 Vinyl flooring Installation Works 10 days 43FS-2 days 0% Mon 5/20/24 Wed 5/29/24
9 ELV System 30 days 0% Wed 5/22/24 Thu 6/20/24
10 Supply & Installation of ELV Systems 30 days 19FS-5 days,21FS-5 days 0% Wed 5/22/24 Thu 6/20/24
46 Joinery Works 20 days 0% Fri 5/24/24 Wed 6/12/24
48 Supply & Installation of Counters & Cabinets 20 days 44FS-6 days 0% Fri 5/24/24 Wed 6/12/24
47 Supply & Installation of Doors 10 days 19 0% Mon 5/27/24 Wed 6/5/24
51 Curtains, Handrails & Signages 6 days 0% Mon 5/27/24 Sat 6/1/24
52 Supply & Installation of Curtains 6 days 21,19 0% Mon 5/27/24 Sat 6/1/24
53 Supply & Installation of Handrails 6 days 19,21 0% Mon 5/27/24 Sat 6/1/24

Project: Tarmeem Ortho & Spine Task Progress Summary External Tasks Deadline
Date: 12-01-24 Split Milestone Project Summary External Milestone

Note: The above dates will change subject to Authority approvals, Installation starting date, clearances and approvals of submittals.
ID Task Name Duration Predecessors % Work Start Finish
Complete February 20 March 2024 April 2024 May 2024 June 2024 July 2024
49 Access Control System 15 days 0% Tue 6/4/24 Tue 6/18/24
50 Supply & Installation of Access Control System 15 days 47FS-2 days 0% Tue 6/4/24 Tue 6/18/24
54 Authority Inspections & Approvals 22 days 0% Fri 6/21/24 Fri 7/12/24
55 Submission to ADCD 1 day 9,49,42,28,36,34,23,11,39,2 0% Fri 6/21/24 Fri 6/21/24
57 ADMCC Inspection & Approval 5 days 55 0% Sat 6/22/24 Wed 6/26/24
56 ADCD Inspection 1 day 55FS+5 days 0% Thu 6/27/24 Thu 6/27/24
58 Submission to ADM 1 day 56FS+3 days,57,2,39,11,23,34,36,28,42,46,49,9,51
0% Mon 7/1/24 Mon 7/1/24
59 ADM Inspection 1 day 58FS+5 days 0% Sun 7/7/24 Sun 7/7/24
60 Building Completion from ADM 1 day 59FS+2 days 0% Wed 7/10/24 Wed 7/10/24
61 As Build Drawings & Documents to Client for DOH Submission 1 day 55,60FS+1 day 0% Fri 7/12/24 Fri 7/12/24

Project: Tarmeem Ortho & Spine Task Progress Summary External Tasks Deadline
Date: 12-01-24 Split Milestone Project Summary External Milestone

Note: The above dates will change subject to Authority approvals, Installation starting date, clearances and approvals of submittals.