ID Task Name Duration Start Finish Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1
2 Jumeirah 2 Villa - Project Duration 251 days Wed 20/12/23 Wed 04/12/24
3 Moblization 6 days Wed 20/12/23 Wed 27/12/23
4 Fencing, Porta Cabin and Signage 12 days Wed 20/12/23 Thu 04/01/24
5 Sub Structure
6 Excavation 6 days Mon 08/01/24 Mon 15/01/24
7 Dewatering (N/A as per recived
drawings/soil report) )
8 Soil Compation and Testing 5 days Fri 12/01/24 Thu 18/01/24
9 Road base 2 layers 10 days Mon 15/01/24 Fri 26/01/24
10 Pcc work 3 days Fri 26/01/24 Tue 30/01/24
11 Footing 12 days Tue 30/01/24 Wed 14/02/24
12 Block work for Foundation 10 days Sat 10/02/24 Thu 22/02/24
13 Water proofing on block wall (Bitumin) 3 days Mon 19/02/24 Wed 21/02/24

14 Neck Column 3 days Wed 21/02/24 Fri 23/02/24


15 Back filling with compaction 6 days Fri 23/02/24 Fri 01/03/24
16 Tie Beam (Steel, form work and concrete 10 days Fri 01/03/24 Thu 14/03/24
with all approval
17 Super Structure
18 Grade Slab (Steel work with concrete) 6 days Mon 11/03/24 Mon 18/03/24
19 Column work Ground Floor (Steel work, 10 days Tue 19/03/24 Mon 01/04/24
form work, concrete work)
20 Ground floor slab 15 days Thu 28/03/24 Wed 17/04/24
21 Ground floor slab deshuttring 12 days Wed 17/04/24 Thu 02/05/24
22 Block work for Ground floor 9 days Sat 04/05/24 Wed 15/05/24
23 Internal plaster for Ground floor walls 11 days Fri 17/05/24 Fri 31/05/24
with MEP containments
24 Column work first Floor (Steel work, 7 days Fri 19/04/24 Mon 29/04/24
form work, concrete work)
25 First Floor Slab 15 days Tue 30/04/24 Mon 20/05/24
26 First Floor Slab deshuttring 12 days Mon 20/05/24 Tue 04/06/24
27 Block work First Floor 9 days Wed 05/06/24 Sat 15/06/24
28 Internal plaster for Ground floor walls 11 days Mon 17/06/24 Mon 01/07/24
with MEP containments
29 Parapet Wall 9 days Mon 20/05/24 Thu 30/05/24
30 Outer plaster 8 days Thu 30/05/24 Sun 09/06/24
31 Compound Wall, Pcc, Footing, Block 18 days Fri 31/05/24 Tue 25/06/24
works
32 Electrical works - Containment 50 days Thu 02/05/24 Wed 10/07/24
wall/flooring, Cabling,
33 HVAC works 60 days Fri 10/05/24 Thu 01/08/24
34 Joinery Works 50 days Tue 20/08/24 Mon 28/10/24
35 Fire Fighting works 45 days Fri 10/05/24 Thu 11/07/24
36 IT works 50 days Sat 11/05/24 Thu 18/07/24
37 Authority Approvals 22 days Fri 01/11/24 Mon 02/12/24
38 Site Handover with Deep cleaning 3 days Mon 02/12/24 Wed 04/12/24
Task Project Summary Manual Task Start-only Deadline

Project: Jumeirah 2 Villa Split Inactive Task Duration-only Finish-only Progress


Date: Mon 15/01/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1