ID Task Task Name Duration Start Finish Predecessors Jul '23 Aug '23 Sep '23 Oct '23

h Predecessors Jul '23 Aug '23 Sep '23 Oct '23 Nov '23
Mode 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12
1 SATS 91 days Fri 7/7/23 Fri 10/11/23
2 Design and Preliminary stages 36 days Fri 7/7/23 Fri 25/8/23
3 Site Visit 1 day Fri 7/7/23 Fri 7/7/23
4 Detail Design, Discussion, Review and Approval 15 days Mon 10/7/23 Fri 28/7/23
5 Procurement 25 days Mon 24/7/23 Fri 25/8/23
6 Site Mobilization 1 day Mon 21/8/23 Mon 21/8/23
7 Structural Works 16 days Mon 21/8/23 Mon 11/9/23
8 Material Delivery On Site 1 day Mon 21/8/23 Mon 21/8/23
9 Site Marking and Works 5 days Wed 23/8/23 Tue 29/8/23
10 Installation of Mini Rails 11 days Fri 25/8/23 Fri 8/9/23
11 Installation of Earthing Inter Module/ Tables 3 days Thu 7/9/23 Mon 11/9/23
12 Panel Works 20 days Mon 21/8/23 Fri 15/9/23
13 Material Delivery on Site 1 day Mon 21/8/23 Mon 21/8/23
14 Hoisting Panel (Terminal Block) 2 days Sat 26/8/23 Sun 27/8/23
15 Hoisting Panel (Terminal Block) 2 days Sat 2/9/23 Sun 3/9/23
16 Hoisting Panel (Carpark Block) 2 days Sat 9/9/23 Sun 10/9/23
17 Panel Alingment and Interconnection Module Works 15 days Mon 28/8/23 Fri 15/9/23
18 DC Works 25 days Mon 21/8/23 Fri 22/9/23
19 Material Delivery On Site 1 day Mon 21/8/23 Mon 21/8/23
20 Trunking Works 5 days Mon 4/9/23 Fri 8/9/23
21 DC Cable Laying 8 days Mon 11/9/23 Wed 20/9/23
22 DC Cable Testing 6 days Sun 17/9/23 Fri 22/9/23
23 AC Works 12 days Mon 4/9/23 Tue 19/9/23
24 Material Delivery On site 1 day Mon 4/9/23 Mon 4/9/23
25 Trunking Works 4 days Tue 5/9/23 Fri 8/9/23
26 AC Cable Laying 5 days Mon 11/9/23 Fri 15/9/23
27 AC Cable Testing 3 days Sat 16/9/23 Tue 19/9/23
28 Temination Works 2 days Sat 23/9/23 Sun 24/9/23
29 AC Termination and Shutdown Works 2 days Sat 23/9/23 Sun 24/9/23
30 Communication Works 6 days Mon 25/9/23 Mon 2/10/23
31 Installation of Sensor and Wiring Works 2 days Mon 25/9/23 Tue 26/9/23
32 Sensor Testing 4 days Wed 27/9/23 Mon 2/10/23
33 Testing and Commisioning 11 days Mon 2/10/23 Sun 15/10/23
34 DC Cable Testing 1 day Mon 2/10/23 Mon 2/10/23
35 Inverter Testing 1 day Mon 2/10/23 Mon 2/10/23
36 AC Cable Testing 1 day Mon 2/10/23 Mon 2/10/23
37 System Commisioning 6 days Tue 3/10/23 Tue 10/10/23
38 System PR Testing 4 days Wed 11/10/23Sun 15/10/23
39 Defect List 6 days Mon 16/10/23Mon 23/10/23
40 Site Walk and Findings 2 days Mon 16/10/23Tue 17/10/23
41 DL Makegood 4 days Wed 18/10/23Mon 23/10/23
42 Handing Over 13 days Wed 25/10/23Fri 10/11/23
43 Documentation Preparation 13 days Wed 25/10/23Fri 10/11/23
44 Request for Meeting 7 days Thu 2/11/23 Fri 10/11/23

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: SATS Split External Tasks Inactive Summary Manual Summary Progress
Date: Wed 16/8/23 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors Jul '23 Aug '23 Sep '23 Oct '23 Nov '23
Mode 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12
45 Handover Meeting and Training 5 days Mon 6/11/23 Fri 10/11/23

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: SATS Split External Tasks Inactive Summary Manual Summary Progress
Date: Wed 16/8/23 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only