PRELIMINARRY CONSTRUCTION PROGRAM OF WORKS - ISSUED FOR TENDER

ID Task Name Duration Start Finish Feb 2023 Jun 2023 Oct 2023 Dec 2023
28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10
PRELIMINARY PROGRAMME – WATER SUPPLY IN
1 BLOUBERG 76 days Mon 12-02-23 Mon 26-12-23

2 SITE HANDOVER 1 day Wed 28-02-23 Wed 28-02-23


3 PRELIMINARIES AND GENERAL REQUIREMENTS 14 days Mon 12-02-23 Thu 29-02-23
4 Contactual Obligations / Documents 14 days Mon 12-02-23 Thu 29-02-23
5 Surety / Guarantees 14 days Mon 12-02-23 Thu 29-02-23
6 Contractor All Risk Policy 14 days Mon 12-02-23 Thu 29-02-23
7 Safety File / Works Programme 14 days Mon 12-02-23 Thu 29-02-23
8 Site Establishment 4 days Thu 29-02-23 Tue 04-03-23
9 Offices 2 days Thu 29-02-23 Fri 30-02-23
10 Equipments & Tools 2 days Mon 03-03-23 Tue 04-03-23
11 CLO Appointment & Labour Recruitment 1 day Mon 12-02-23 Mon 12-02-23
12 OHS Requirements 2 days Mon 03-03-23 Tue 04-03-23
13 Training 5 days Tue 13-02-23 Mon 19-02-23
14 Generic 5 days Tue 13-02-23 Mon 19-02-23
15 Technical & OHS 5 days Tue 13-02-23 Mon 19-02-23
16 Accommodation of Traffic & Temporary Works 5 days Wed 14-02-23 Tue 20-02-23
17 Temporary Deviations & Maintenance 5 days Wed 14-02-23 Tue 20-02-23
18 Dealing With Existing Services 5 days Wed 14-02-23 Tue 20-02-23
19 CONTSRUCTION WORKS 300 days Tue 08-02-23 Tue 29-12-23
20 Preparation 16 days Tue 08-02-23 Tue 29-02-23
21 Clearing and grubbing 10 days Tue 08-02-23 Mon 21-02-23
22 Cutting down large Trees 15 days Wed 09-02-23 Tue 29-02-23
23 Excavations 260 days Wed 14-02-23 Wed 19-10-23
24 Bedding 200 days Wed 14-03-23 Tue 11-11-23
25 Pipe Laying 200 days Mon 19-03-23 Fri 14-10-23
26 Pipe testing 20 days Thu 22-04-23 Wed 19-05-23
27 Backfill 28 days Thu 03-06-23 Mon 12-07-23
28 Valve chamber and Manholes 15 days Thu 03-08-23 Wed 23-08-23
29 Yard connections 150 days Tue 08-09-23 Mon 08-12-23
30 Steel Elavated Tank 20 days Tue 15-10-23 Mon 12-011-23
31 Pump House 10 days Thu 10-10-23 Wed 23-10-23
32 Borehole 10 days Thu 10-10-23 Wed 23-10-23
33 Electrification 30 days Thu 01-11-23 Mon 01-12-23
34 Tie ins 3 days Thu 24-11-23 Mon 28-11-23
35 Reinstating existing services 5 days Tue 24-11-23 Mon 29-11-23
36 TRAFFIC CALMING DEVICES, ROAD SIGNS AND 3 days Tue 20-07-23 Thu 22-07-23
MARKINGS
37 Traffic calming devices 3 days Tue 02-12-23 Thu 05-12-23
38 Signs 3 days Tue 02-12-23 Thu 05-12-23
39 FINISHING OFF & COMPLETION 2 days Fri 03-12-23 Mon 08-12-23
40 Cleaning and Finishing Off 1 day Fri 03-12-23 Fri 03-07-23
41 Practical Completion 1 day Mon 04-12-23 Mon 04-12-23 26-07

Task Project Summary Inactive Summary Manual Summary External Milestone


Split External Tasks Manual Task Start-only Progress
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks