rt Finish Predecessors February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024
Mode 28300103050709 1113151719212325270103 05070911131517 1921232527293102040608 1012141618202224262830 0204060810121416182022 2426283001030507091113 1517192123252729010305 07091113151719 2123252729310204060810 1214161820222426283001 0305070911131517192123 2527290103050709111315 1719212325272931020406 08101214161820 2224262830020406081012 1416182022242628300103 0507091113151719212325 27
1 Tentative Project Plan for AOU Meeting Room Setup 306 days? Mon 30-01-23 Sun 21-01-24
2 Milestones
6 Delivery of materials
8 Dependencies
15 Storage Space
18 Pre-Installation Activities
19 Materials Pre-Inspection
25 Delivery of Speaker, DSP, Cable cubby, Audio Conf 45 days Mon 30-01-23 Wed 22-03-23 3
system, Barco
26 Delivery of ClearOne Cam, Extron Matrix switch 15 wks Mon 30-01-23 Wed 26-04-23 3
28 UTP Cabling for control system from cabinet room 1 day Sun 12-03-23 Sun 12-03-23 24
29 Speaker Cabling for ceiling speaker 1 day Sun 12-03-23 Sun 12-03-23 24
31 Cutting ceiling for installing speakers 1 day Mon 13-03-23 Mon 13-03-23 29
33 Table cutting for installing Cable cubby (by Contractor)1 day Mon 13-03-23 Mon 13-03-23 28
34 Installation of Cable cubby in the meeting room table 1 day Tue 14-03-23 Tue 14-03-23 33
36 Camera installation over the existing screen 1 day Thu 27-04-23 Thu 27-04-23 26
38 Wireless Access Point installation in the ceiling for 1 day Thu 23-03-23 Thu 23-03-23 25
touch pad
43 Cable termination/plugging, organizing and labeling 1 day Sat 25-03-23 Sat 25-03-23 40
44 Configuration and programming the system 3 days Sun 26-03-23 Tue 28-03-23 43
47 Completion of activities in the council room 0 days Wed 29-03-23 Wed 29-03-23 46 29-03
49 Active site survey and verification by client 1 day Sat 24-06-23 Sat 24-06-23 47,45
50 Formal acceptance of the project by signing Work 0 days Sat 24-06-23 Sat 24-06-23 49 24-06
Completion Report by client
Project: AOU AV Project Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Wed 22-03-23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress