Prepared By:
Content
01 02 03 04
Master Plan Project District Cooling Construction
Layout Priorities & and Gas Network KPI
Milestones Progress
Summary
05 06 07
Engineering/ HSE Update QA/QC
Procurement &
Progress Status RFI status
08 09
Critical Activities Photographs
&
Issues & Concerns
2
01 DataDate:
Master Plan Layout 24 Mar 2023
3
02 Data Date:
Project Priorities & Milestones 24 Mar 2023
Original
Approved
S No. Milestone Description Completion Revise Baseline Dates Variance Remarks
Baseline Dates
Date
1 Project Start 15-Nov-21A 15-Nov-21A 15-Nov-21A Completed
0
4
02 Data Date:
Project Priorities & Milestones 24 Mar 2023
4
02 Data Date:
Project Priorities & Milestones 24 Mar 2023
31 31 0 0 31 31 0
31 31 0 0 31 31 0
31 31 0 0 31 31 0
31 19 0 0 31 19 0
31 31 0 0 31 31 0
31 24 0 0 31 24 0
4
02 Data Date:
Project Priorities & Milestones 24 Mar 2023
4
02 Data Date:
Project Priorities & Milestones 24 Mar 2023
81 81 0 0 81 81 0
81 79 0 0 81 79 0
81 79 0 0 81 79 0
81 78 0 0 81 78 0
81 75 0 0 81 75 0
66 64 0 0 66 64 0
106 50 0 25 106 75 0
81 0 0 0 81 0 0
4
03 District Cooling and Gas Data Date: 2
24 Mar 2023
Network Progress Weekly
Note : All Values has been taken as per Revised Baseline
Engineering DC and Gas 100.00% 100.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 0.00% Completed
Procurement Dc and Gas Network 100.00% 99.87% -0.13% 0.00% 0.00% 0.00% 100.00% 99.87% -0.13%
Construction DC and Gas 100.00% 98.75% -1.25% 0.5% 100.00% 98.80% -1.2%
0.00% 0.5%
network
Section 1 DC and Gas Network 100.00% 100.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 0.00%
Section 3 DC and Gas Network 100.00% 98.67% -1.25% 0.00% 0.9% 0.05% 100.00% 98.72% -1.28%
Testing and Commissioning 100.00% 52.54% -47.46% 0.00% 0.00% 0.00% 100.00% 52.71% -47.29%
Overall DC And Gas Network 100.00% 97.00% -3.00% 0.00% 0.04 % 0.04% 100.00% 97.04% -2.96%
9
05 Data Date:
Engineering/ Procurement 24 Mar 2023 7
Progress Status 14
Shop Drawing Submittal
Gas Line 68 0 0 2 64 3 0 68
10
05 Data Date:
Engineering/ Procurement 24 Mar 2023 7
Progress Status 14
As Built Drawing Submittal
Gas Line 8 0 0 0 0 8 0 8
Total 42 28 0 6 0 8 0 42
11
06 Data Date:
24 Mar 2023
HSE Update 14
Manpower Status
Project Team 10 9 1
Equipment Operator 4 5 1
Grand Total 32 27 5
12
06 DataDate:
24 Mar 2023
HSE Update 14
Equipment Status
Equipment 4 5 1
13
06 DataDate:
HSE Update 24 Mar 2023
HSE Statistics
8 HSE NCR 0 03 0
07 DataDate:
24 Mar 2023
QA/QC & WIR status
14
Work Inspection Request (WIR)
WIR Submittal
15
07 DataDate:
QA/QC & RFI status 24 Mar
20232
1
Method Statement
4
Under Issued Issued Issued Issued For CODE
Discipline Submitted Overdue
Review Code A Code B Code C Information Sub Total
Gas Line 1 0 0 0 1 0 0 1
Total 8 0 0 1 7 0 0 8
16
07 DataDate:
QA/QC & RFI status 14 24 Mar
2023
Request For Information RFI
Total 7 0 0 7 0 100%
17
07 DataDate:
QA/QC & V.O status 14 24 Mar
2023
Value Engineering
Total 2 1 0 0 1 0%
18
07 DataDate:
24 Mar 2023
Internal NCR status 14
Internal Non-Conformance Report NCR (QHSE)
19
11 DataDate:
Progress Photos 14
24 Mar 2023
20
11 DataDate:
Progress Photos 14
24 Mar 2023
21
09 DataDate:
24 Mar 2023
Progress Photos 14
23