PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE

ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1 NOVOTEL MASTER CONSTRUCTION SCHEDULE 诺富特项目总进度计划
457 days4/8/2021 7/31/2022 4/8 NO
2 MILESTONE 关键节点 224 days12/19/2021 7/31/2022 12/19 M
3 Structural Works主题结构 0 days 12/19/2021 12/19/2021 12/19
4 Architecture Work 建筑 0 days 4/13/2022 4/13/2022 4/13
5 Interior Decoration 精装修 0 days 7/6/2022 7/6/2022 7/6
6 MEP Installation Work 机电工程 0 days 6/3/2022 6/3/2022 6/3
7 Façade Work玻璃幕墙 0 days 2/14/2022 2/14/2022 2/14
8 External/landscape 室外景观 0 days 6/5/2022 6/5/2022 6/5
9 Construction Hoist Removal 施工电梯拆除 0 days 2/19/2022 2/19/2022 2/19
10 Tower Crane Removal 塔吊拆除 0 days 3/6/2022 3/6/2022 3/6
11 Scaffolding Removal 外架拆除 0 days 2/24/2022 2/24/2022 2/24
12 MEP Testing and Commissioning Work机电调试及测试 0 days 7/31/2022 7/31/2022 7
13 Defect and Hand Over 缺陷修正及移交 0 days 7/31/2022 7/31/2022 7
14 Procurement Schedule 材料采购计划 350 days4/8/2021 4/15/2022 4/8 Procurement Schedule 材料采购
15 Material Ordering Fabrication and Delivery to Site 材料生 350 4/8/2021 4/15/2022 4/8 Material Ordering Fabrication an
产及采购计划 days
16 MEP 机电材料 296 days4/8/2021 2/20/2022 4/8 MEP 机电材料
17 Electrical System电气系统 271 days5/26/2021 2/20/2022 5/26 Electrical System电气系统
18 Grounding System接地系统 46 days 5/26/2021 7/10/2021 5/26
19 Cable Tray (Fitting)桥架+管件 23 days 9/6/2021 9/28/2021 9/6
20 ELV、LV cable (1st Fix) 强弱电电缆 96 days 9/1/2021 12/5/2021 9/1
21 All Bracket & Support(1st Fix) 支架 30 days 6/20/2021 7/19/2021 6/20
22 Fire alarm system (1st Fix) 火警系统 42 days 12/10/20211/20/2022 12/10
23 Public address system (1st Fix) 公共广播系统 42 days 12/10/20211/20/2022 12/10
24 Access control system (1st Fix) 门禁系统 42 days 12/10/20211/20/2022 12/10
25 Normal & Emergency Luminaires (Final Fix)普通和应 90 days 11/17/20212/14/2022 11/17
急照明
26 Bus Duct 56 days 10/16/202112/10/2021 10/16
27 Main Switchboard, Switchboard and Distribution 91 days 9/26/2021 12/25/2021 9/26
Board 配电盘
28 DB户内配电箱 26 days 8/26/2021 9/20/2021 8/26
29 Lighting Cable 防雷接地 41 days 9/20/2021 10/30/2021 9/20
30 Switch and Socket 开关插座 86 days 11/27/20212/20/2022 11/27
31 Fire Protection System消防系统 270 days4/13/2021 1/30/2022 4/13 Fire Protection System消防系统
32 Galvanized Steel Pipe (GSP) (1st Fix) 镀锌铁皮 35 days 4/14/2021 6/10/2021 4/14
33 Black Steel Pipe (BS)(1st Fix) 黑铁管 112 days 4/13/2021 8/25/2021 4/13
34 Fire Hose Cabinet (Final Fix) 消防箱带卷盘 51 days 11/21/2021 1/10/2022 11/21
35 Hose Reel (Final Fix) 软管卷轴 51 days 11/21/2021 1/10/2022 11/21
36 Fire Extinguisher (Final Fix) 灭火器 50 days 12/12/20211/30/2022 12/12
37 Sprinkler Head (Final Fix) 喷淋头 50 days 11/6/2021 12/25/2021 11/6
38 Fire Barrier 70 days 9/22/2021 11/30/2021 9/22
39 Valves(For FF )消防阀门 66 days 9/21/2021 11/25/2021 9/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 1
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
40 PVR Station 加压阀组 55 days 9/22/2021 11/15/2021 9/22
41 MVAC System 空调系统 214 days7/12/2021 2/10/2022 7/12 MVAC System 空调系统
42 Copper Pipe (Cu) (1st Fix) 10 days 10/27/202111/5/2021 10/27
43 Galvanized Steel Sheet (1st Fix) 17 days 8/25/2021 9/10/2021 8/25
44 Fire Resistant Coated Duct (1st Fix) 23 days 11/28/202112/20/2021 11/28
45 Closed Cell Insulation(1st Fix) 闭孔绝缘橡塑保温棉20 days 7/12/2021 7/31/2021 7/12
46 Chiller water pipe Valves and Accessories 冷水阀门 56 days 10/26/202112/20/2021 10/26
和管件)
47 Mechanical Fan (Final Fix) 60 days 12/13/20212/10/2022 12/13
48 Split-System Air-Conditioners (Final Fix) 分体空调机50 days 11/11/202112/30/2021 11/11
49 Fiberglass Insulation 19 days 7/12/2021 7/30/2021 7/12
50 Chill water pump 86 days 9/26/2021 12/20/2021 9/26
51 Diffusers Grilles and Louvers (Final Fix) 51 days 11/21/20211/10/2022 11/21
52 FCU (Final Fix) 81 days 10/1/2021 12/20/2021 10/1
53 Expansion Tank 膨胀水箱 90 days 9/18/2021 12/16/2021 9/18
54 Plumbing System 水系统 286 days4/8/2021 2/10/2022 4/8 Plumbing System 水系统
55 Manhole Covers井盖 41 days 1/1/2022 2/10/2022 1/1
56 HDPE Pipe HDPE 16 days 9/25/2021 10/10/2021 9/25
57 PP-R Pipe PPR 10 days 5/8/2021 5/17/2021 5/8
58 Valves 给水阀门 65 days 9/17/2021 11/20/2021 9/17
59 Drain pipe 排水管 10 days 4/8/2021 5/10/2021 4/8
60 Cast iron pipe铸铁管 25 days 4/13/2021 5/30/2021 4/13
61 Swimming pool (include UV Disinfection)泳池系统 46 days 11/15/202112/30/2021 11/15
62 Clean out(CO) + Floor clean out检查口 40 days 4/9/2021 6/10/2021 4/9
63 Planter drain&Scupper Drain 97 days 8/11/2021 11/15/2021 8/11
64 Flow Switches, Supervisory Switches (UL & FM)流量开关
60 days 9/17/2021 11/15/2021 9/17
65 Sewage Pump排水泵 86 days 9/26/2021 12/20/2021 9/26
66 Make up water pump补水泵 86 days 9/26/2021 12/20/2021 9/26
67 Water supply pump(cold & hot)给水冷热水泵 86 days 9/26/2021 12/20/2021 9/26
68 Air to Water Heat Pumps空气热源泵 86 days 9/16/2021 12/10/2021 9/16
69 Long Lead Items Delivery to Site 大设备 203 days7/2/2021 1/20/2022 7/2 Long Lead Items Delivery to Site 大设备
70 Generator Set发电机 75 days 9/7/2021 11/20/2021 9/7
71 Cooling Towers冷却塔 91 days 7/2/2021 9/30/2021 7/2
72 AHU/PAU空调机 100 days 9/12/2021 12/20/2021 9/12
73 Chiller冷水机 110 days 9/2/2021 12/20/2021 9/2
74 MV Switchgear & Transformer高低压配电柜和变压器 106 days 9/6/2021 12/20/2021 9/6
75 Water Treatment Plant & Equipment污水处理 81 days 11/1/2021 1/20/2022 11/1
76 LPG SYSTEM & EQUIPMENT煤气站 36 days 11/15/202112/20/2021 11/15
77 Diesel Engine Fire Pump柴油机消防泵 86 days 9/26/2021 12/20/2021 9/26
78 Jockey Pump消防加压泵 86 days 9/26/2021 12/20/2021 9/26
79 Condenser water pump冷冻水泵 86 days 9/26/2021 12/20/2021 9/26
80 Chiller Water Pump 冷却水泵 86 days 9/26/2021 12/20/2021 9/26

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 2
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
81 ID精装修材料 339 days5/12/2021 4/15/2022 5/12 ID精装修材料
82 Guest room 325 days5/12/2021 4/1/2022 5/12 Guest room
83 Keels龙骨 45 days 5/12/2021 6/25/2021 5/12
84 Floor tiles地面瓷砖 37 days 9/5/2021 10/15/2021 9/5
85 Wall tiles墙面瓷砖 37 days 9/9/2021 10/15/2021 9/9
86 Skirting踢脚瓷砖 61 days 8/21/2021 10/20/2021 8/21
87 Base board 5 days 8/10/2021 8/14/2021 8/10
88 Skim coat腻子粉 40 days 9/16/2021 10/25/2021 9/16
89 Gypsum board石膏板 25 days 10/1/2021 10/25/2021 10/1
90 Paint油漆 101 days 8/1/2021 11/9/2021 8/1
91 Wallpaper墙纸 40 days 11/5/2021 12/14/2021 11/5
92 Stainless steel不锈钢 31 days 1/2/2022 2/1/2022 1/2
93 Sanitary ware洁具 90 days 1/2/2022 4/1/2022 1/2
94 Acrylic Solid Surface 亚克力 41 days 11/10/2021 12/20/2021 11/10
95 Carpet地毯 50 days 12/15/2021 2/2/2022 12/15
96 Silver mirror & glass door玻璃门 40 days 12/24/2021 2/1/2022 12/24
97 Solid Wood 木制品 70 days 10/31/2021 1/8/2022 10/31
98 Wooden door, Fire door&Sliding doors门,防火门 70 days 12/8/2021 2/15/2022 12/8
99 Wall to Wall Carpet 50 days 12/15/2021 2/2/2022 12/15
100 Leather Lanminate皮草 60 days 11/10/2021 1/8/2022 11/10
101 Upholstery 饰面材料 41 days 11/14/2021 12/24/2021 11/14
102 Composite Stone 石子品 40 days 11/1/2021 12/10/2021 11/1
103 Public area公共区域材料 173 days10/25/2021 4/15/2022 10/25 Public area公共区域材料
104 Homogeneous,Porcelain, Mosaic, Stone Tile均质,瓷 40 days 1/7/2022 2/15/2022 1/7
,马赛克,石砖
105 Natural StoneNatural Stone 35 days 11/30/2021 1/3/2022 11/30
106 Carpet地毯 122 days 12/15/2021 4/15/2022 12/15
107 Leather皮草 20 days 10/25/2021 11/13/2021 10/25
108 Wallpaper墙纸 40 days 12/15/2021 1/23/2022 12/15
109 Stainless steel Sheet不锈钢皮 40 days 11/29/2021 1/7/2022 11/29
110 Anodized Aluminum 阳极电镀铝 60 days 10/25/2021 12/23/2021 10/25
111 Wooden door, Fire door&Sliding doors木门,防火门 70 days 1/15/2022 3/25/2022 1/15
112 Sanitary ware洁具 90 days 1/16/2022 4/15/2022 1/16
113 Interior Paint油漆 60 days 10/25/2021 12/23/2021 10/25
114 Frosted Glass & Spy Mirror 镜子 60 days 10/25/2021 12/23/2021 10/25
115 Expanded Metal & Metal Ceiling 40 days 11/29/2021 1/7/2022 11/29
116 Powder Coated Steel 40 days 10/25/2021 12/3/2021 10/25
117 Perforated Aluminium Plate 40 days 11/29/2021 1/7/2022 11/29
118 Construction Work 269 days11/5/2021 7/31/2022 11/5 Co
119 Structural Works主体结构(剩余工作) 45 days 11/5/2021 12/19/2021 11/5 Structural Works主体结构(剩余工作)
120 Level 5 Swimming Pool Concrete Casting 五层泳池砼浇筑1 day 12/5/2021 12/5/2021 12/5
121 Roof Floor 屋面 45 days 11/5/2021 12/19/2021 11/5 Roof Floor 屋面

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 3
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
122 Roof Steel Structure 钢结构 45 days 11/5/2021 12/19/2021 11/5 Roof Steel Structure 钢结构
123 Fabrication 生产 10 days 11/5/2021 11/14/2021 11/5
124 Installation 安装 20 days 11/30/202112/19/2021 11/30
125 Canopy and Stair Steel Structure Installation 雨棚钢构及 57 days 12/30/20212/24/2022 12/30 Canopy and Stair Steel Structure Installation 雨棚
二楼钢构楼梯
126 19F Executive Lounge Steel Stucture Installation 19层酒廊钢构安装
7 days 12/30/2021 1/5/2022 12/30
127 5F Pool Bar Canopy 5层雨棚安装 10 days 1/6/2022 1/15/2022 1/6
128 +6.575m Canopy Installation 雨棚安装 10 days 1/16/2022 1/25/2022 1/16
129 +4.95m Canopy Installation 雨棚安装 12 days 1/26/2022 2/6/2022 1/26
130 +7.55m Banquet Steel Stair Installation 雨棚安装 18 days 2/7/2022 2/24/2022 2/7
131 Façade Work玻璃幕墙 97 days 11/10/2021 2/14/2022 11/10 Façade Work玻璃幕墙
132 Exterior Façade 幕墙 97 days 11/10/2021 2/14/2022 11/10 Exterior Façade 幕墙
133 Façade Frame Installation 幕墙框架安装 40 days 12/10/2021 1/18/2022 12/10 Façade Frame Installation 幕墙框架安装
134 MF-5F 30 days 12/20/2021 1/18/2022 12/20 MF-5F
135 Axis A~D 5F Steel Frame installation 3 days 12/20/2021 12/22/2021 12/20
136 Axis A~D 4F Steel Frame installation 3 days 12/23/2021 12/25/2021 12/23
137 Axis A~D 3F Steel Frame installation 3 days 12/26/2021 12/28/2021 12/26
138 Axis A~D 2F Steel Frame installation 3 days 12/29/2021 12/31/2021 12/29
139 Axis A~D MF Steel Frame installation 3 days 1/1/2022 1/3/2022 1/1
140 Axis 1~7 5F Steel Frame installation 3 days 1/4/2022 1/6/2022 1/4
141 Axis 1~7 4F Steel Frame installation 3 days 1/7/2022 1/9/2022 1/7
142 Axis 1~7 3F Steel Frame installation 3 days 1/10/2022 1/12/2022 1/10
143 Axis 1~7 2F Steel Frame installation 3 days 1/13/2022 1/15/2022 1/13
144 Axis 1~7 MF Steel Frame installation 3 days 1/16/2022 1/18/2022 1/16
145 Axis D~A 5F Steel Frame installation 3 days 12/20/2021 12/22/2021 12/20
146 Axis D~A 4F Steel Frame installation 3 days 12/23/2021 12/25/2021 12/23
147 Axis D~A 3F Steel Frame installation 3 days 12/26/2021 12/28/2021 12/26
148 Axis D~A 2F Steel Frame installation 3 days 12/29/2021 12/31/2021 12/29
149 Axis D~A MF Steel Frame installation 3 days 1/1/2022 1/3/2022 1/1
150 Axis 7~1 5F Steel Frame installation 3 days 1/4/2022 1/6/2022 1/4
151 Axis 7~1 4F Steel Frame installation 3 days 1/7/2022 1/9/2022 1/7
152 Axis 7~1 3F Steel Frame installation 3 days 1/10/2022 1/12/2022 1/10
153 Axis 7~1 2F Steel Frame installation 3 days 1/13/2022 1/15/2022 1/13
154 Axis 7~1 MF Steel Frame installation 3 days 1/16/2022 1/18/2022 1/16
155 23F-RF 20 days 12/10/2021 12/29/2021 12/10 23F-RF
156 Axis A~D 24F Steel Frame installation 5 days 12/10/2021 12/14/2021 12/10
157 Axis A~D 25F Steel Frame installation 5 days 12/15/2021 12/19/2021 12/15
158 Axis A~D 26F Steel Frame installation 5 days 12/20/2021 12/24/2021 12/20
159 Axis A~D 27F Steel Frame installation 5 days 12/25/2021 12/29/2021 12/25
160 Axis 1~7 24F Steel Frame installation 5 days 12/10/2021 12/14/2021 12/10
161 Axis 1~7 25F Steel Frame installation 5 days 12/15/2021 12/19/2021 12/15
162 Axis 1~7 26F Steel Frame installation 5 days 12/20/2021 12/24/2021 12/20

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 4
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
163 Axis 1~7 27F Steel Frame installation 5 days 12/25/2021 12/29/2021 12/25
164 Axis D~A 24F Steel Frame installation 5 days 12/10/2021 12/14/2021 12/10
165 Axis D~A 25F Steel Frame installation 5 days 12/15/2021 12/19/2021 12/15
166 Axis D~A 26F Steel Frame installation 5 days 12/20/2021 12/24/2021 12/20
167 Axis D~A 27F Steel Frame installation 5 days 12/25/2021 12/29/2021 12/25
168 Axis 1~7 24F Steel Frame installation 5 days 12/10/2021 12/14/2021 12/10
169 Axis 1~7 25F Steel Frame installation 5 days 12/15/2021 12/19/2021 12/15
170 Axis 1~7 26F Steel Frame installation 5 days 12/20/2021 12/24/2021 12/20
171 Axis 1~7 27F Steel Frame installation 5 days 12/25/2021 12/29/2021 12/25
172 Aluminium Panel Framing Installation 铝板钢架安装 60 days 11/10/20211/8/2022 11/10
173 Façade Glass Panel Installation玻璃安装 42 days 12/25/2021 2/4/2022 12/25 Façade Glass Panel Installation玻璃安装
174 MF-5F 15 days 1/19/2022 2/2/2022 1/19 MF-5F
175 Axis A~D 5F Glass installation 3 days 1/19/2022 1/21/2022 1/19
176 Axis A~D 4F Glass installation 3 days 1/22/2022 1/24/2022 1/22
177 Axis A~D 3F Glass installation 3 days 1/25/2022 1/27/2022 1/25
178 Axis A~D 2F Glass installation 3 days 1/28/2022 1/30/2022 1/28
179 Axis A~D MF Glass installation 3 days 1/31/2022 2/2/2022 1/31
180 Axis 1~7 5F Glass installation 3 days 1/19/2022 1/21/2022 1/19
181 Axis 1~7 4F Glass installation 3 days 1/22/2022 1/24/2022 1/22
182 Axis 1~7 3F Glass installation 3 days 1/25/2022 1/27/2022 1/25
183 Axis 1~7 2F Glass installation 3 days 1/28/2022 1/30/2022 1/28
184 Axis 1~7 MF Glass installation 3 days 1/31/2022 2/2/2022 1/31
185 Axis D~A 5F Glass installation 3 days 1/19/2022 1/21/2022 1/19
186 Axis D~A 4F Glass installation 3 days 1/22/2022 1/24/2022 1/22
187 Axis D~A 3F Glass installation 3 days 1/25/2022 1/27/2022 1/25
188 Axis D~A 2F Glass installation 3 days 1/28/2022 1/30/2022 1/28
189 Axis D~A MF Glass installation 3 days 1/31/2022 2/2/2022 1/31
190 Axis 7~1 5F Glass installation 3 days 1/19/2022 1/21/2022 1/19
191 Axis 7~1 4F Glass installation 3 days 1/22/2022 1/24/2022 1/22
192 Axis 7~1 3F Glass installation 3 days 1/25/2022 1/27/2022 1/25
193 Axis 7~12F Glass installation 3 days 1/28/2022 1/30/2022 1/28
194 Axis 7~1 MF Glass installation 3 days 1/31/2022 2/2/2022 1/31
195 23F-24F 9 days 12/25/2021 1/2/2022 12/25 23F-24F
196 Axis A~D 23F Glass installation 4 days 12/25/2021 12/28/2021 12/25
197 Axis A~D 24F Glass installation 4 days 12/29/2021 1/1/2022 12/29
198 Axis 1~7 23F Glass installation 4 days 12/25/2021 12/28/2021 12/25
199 Axis 1~7 24F Glass installation 4 days 12/29/2021 1/1/2022 12/29
200 Axis D~A 24F Glass installation 4 days 12/30/2021 1/2/2022 12/30
201 Axis 7~1 24F Glass installation 4 days 12/30/2021 1/2/2022 12/30
202 25F-27F Louver Installation 百叶窗安装 33 days 1/3/2022 2/4/2022 1/3
203 Aluminium Panel Installation 铝板安装 40 days 1/6/2022 2/14/2022 1/6

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 5
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
204 Façade work( Hoist and Tower Crane Area)玻璃幕墙施工电梯 20 days 3/7/2022 3/26/2022 3/7
及塔吊收尾
205 Swimming Pool泳池 40 days 12/31/2021 2/8/2022 12/31 Swimming Pool泳池
206 Pipeline, Swimming pool Equipment and Pool Wall 3 days 12/31/20211/2/2022 12/31
Pipeline Setting-Out and Installation
207 Pipe Bottom Construction and Pipeline Pressure Test 2 days 1/3/2022 1/4/2022 1/3
208 Pool Water Resistance Test 2 days 1/4/2022 1/5/2022 1/4
209 Installation of Equipment and water supply 4 days 1/6/2022 1/9/2022 1/6
210 Swimming Pool Tile Work 10 days 1/10/2022 1/19/2022 1/10
211 Equipment Room Setteing-Out 7 days 1/20/2022 1/26/2022 1/20
212 Equipment Room(Equipment Installation) 7 days 1/27/2022 2/2/2022 1/27
213 Swimming Pool Equipment Commisioning 3 days 2/3/2022 2/5/2022 2/3
214 Acceptance and Handover 3 days 2/6/2022 2/8/2022 2/6
215 Architectural Work 建筑 155 days11/10/2021 4/13/2022 11/10 Architectural Work 建筑
216 Brick and Plastering Work 砌体抹灰(剩余工作) 117 days11/10/20213/6/2022 11/10 Brick and Plastering Work 砌体抹灰(剩余工
217 Ground Floor 首层砌体 35 days 1/31/2022 3/6/2022 1/31 Ground Floor 首层砌体
218 Brick Work 砌筑 21 days 1/31/2022 2/20/2022 1/31 Brick Work 砌筑
219 Setting Out Preparation 2 days 1/31/2022 2/1/2022 1/31 Setting Out Preparation
222 Stiffener Column and Lintel Rebar Installation 4 days 2/2/2022 2/5/2022 2/2 Stiffener Column and Lintel Rebar Installation
227 Brick Laying 15 days 2/6/2022 2/20/2022 2/6 Brick Laying
243 Wall Plastering Work抹灰 7 days 2/28/2022 3/6/2022 2/28
244 2nd Floor 26 days 12/21/2021 1/15/2022 12/21 2nd Floor
245 Brick Work 砌筑 16 days 12/21/2021 1/5/2022 12/21 Brick Work 砌筑
246 Setting Out Preparation 2 days 12/21/2021 12/22/2021 12/21 Setting Out Preparation
249 4
Curb ,Stiffener Column and Lintel Rebar Installation days 12/23/2021 12/26/2021 12/23 Curb ,Stiffener Column and Lintel Rebar Installation
254 Brick Laying 10 days 12/27/2021 1/5/2022 12/27 Brick Laying
265 Wall Plastering Work抹灰 10 days 1/6/2022 1/15/2022 1/6
266 Mezzanine Floor 夹层 33 days 12/27/2021 1/28/2022 12/27 Mezzanine Floor 夹层
267 Brick Work 砌筑 16 days 12/27/2021 1/11/2022 12/27 Brick Work 砌筑
268 Setting Out Preparation 2 days 12/27/2021 12/28/2021 12/27 Setting Out Preparation
271 Stiffener Column and Lintel Rebar Installation 4 days 12/29/2021 1/1/2022 12/29 Stiffener Column and Lintel Rebar Installation
276 Brick Laying 10 days 1/2/2022 1/11/2022 1/2 Brick Laying
287 Wall Plastering Work抹灰 10 days 1/19/2022 1/28/2022 1/19
288 3rd Floor 37 days 12/25/2021 1/30/2022 12/25 3rd Floor
289 Brick Work 砌筑 20 days 12/25/2021 1/13/2022 12/25 Brick Work 砌筑
290 Setting Out Preparation 2 days 12/25/2021 12/26/2021 12/25 Setting Out Preparation
293 Stiffener Column and Lintel Rebar Installation 4 days 12/27/2021 12/30/2021 12/27 Stiffener Column and Lintel Rebar Installation
298 Brick Laying 14 days 12/31/2021 1/13/2022 12/31 Brick Laying
309 Wall Plastering Work抹灰 10 days 1/21/2022 1/30/2022 1/21
310 4th Floor 15 days 11/10/2021 11/24/2021 11/10 4th Floor
311 Wall Plastering Work抹灰 15 days 11/10/2021 11/24/2021 11/10
312 5th Floor 10 days 11/10/202111/19/2021 11/10 5th Floor

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 6
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
313 Wall Plastering Work 抹灰 10 days 11/10/2021 11/19/2021 11/10
314 Waterproofing and Floor Screeding 防水和地坪 86 days 11/20/2021 2/13/2022 11/20 Waterproofing and Floor Screeding 防水和地坪
315 Waterproofing 防水 66 days 11/20/20211/24/2022 11/20 Waterproofing 防水
316 B3-B1 20 days 12/30/2021 1/18/2022 12/30
317 MF- 5F 20 days 1/5/2022 1/24/2022 1/5
318 7F-9F(toilet)卫生间 3 days 11/20/202111/23/2021 11/20
319 10F-12F(toilet)卫生间 3 days 11/27/202111/30/2021 11/27
320 13F-15F(toilet)卫生间 3 days 12/4/2021 12/7/2021 12/4
321 16F-18F(toilet)卫生间 3 days 12/11/202112/14/2021 12/11
322 19F-21F(toilet)卫生间 3 days 12/18/202112/21/2021 12/18
323 22F,23F,6F (toilet)卫生间 3 days 12/25/202112/28/2021 12/25
324 Floor Screeding 地坪工程 80 days 11/26/20212/13/2022 11/26 Floor Screeding 地坪工程
325 B3-B1 15 days 1/24/2022 2/7/2022 1/24
326 MF- 5F 20 days 1/25/2022 2/13/2022 1/25
327 7F-9F(toilet)卫生间 3 days 11/26/2021 11/29/2021 11/26
328 10F-12F(toilet)卫生间 3 days 12/3/2021 12/6/2021 12/3
329 13F-15F(toilet)卫生间 3 days 12/10/202112/13/2021 12/10
330 16F-18F(toilet)卫生间 3 days 12/17/202112/20/2021 12/17
331 19F-21F(toilet)卫生间 3 days 12/24/202112/27/2021 12/24
332 22F,23F,6F (toilet)卫生间 3 days 12/31/20211/3/2022 12/31
333 Stair Handrail扶手工程 45 days 2/28/2022 4/13/2022 2/28 Stair Handrail扶手工程
334 3B to 1B 10 days 2/28/2022 3/9/2022 2/28
335 GF-5F 10 days 3/10/2022 3/19/2022 3/10
336 6F-23F 15 days 3/20/2022 4/3/2022 3/20
337 24F-RF 10 days 4/4/2022 4/13/2022 4/4
338 Interior Decoration Work 精装修 239 days11/10/20217/6/2022 11/10 Interior D
339 Guest Room Interior Decoration 客房精装修 232 days11/10/2021 6/29/2022 11/10 Guest Room
340 ID Work level 6 精装修6层 200 days12/12/20216/29/2022 12/12 ID Work lev
341 Guest Room 200 days12/12/20216/29/2022 12/12 Guest Room
342 Room 6-001-S2 84 days 3/1/2022 5/23/2022 3/1 Room 6-001-S2
343 Setting ou放线 1 day 3/25/2022 3/25/2022 3/25
344 Steel Frame (Toilet and Vanity Sink) 3 days 3/26/2022 3/28/2022 3/26
Installation钢架安装
345 Skirting Tile Installation踢脚线 2 days 3/26/2022 3/27/2022 3/26
346 Bathroom Wall and Floor Tile Installation墙和 3 days 3/26/2022 3/28/2022 3/26
地板瓷砖
347 Wall Skim Coat墙 腻子 3 days 4/8/2022 4/10/2022 4/8
348 Base of TV Back Drop 电视背景基层 4 days 4/14/2022 4/17/2022 4/14
349 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/1/2022 3/3/2022 3/1
350 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/4/2022 3/6/2022 3/4
351 Ceiling Skim Coat 天花板腻子 3 days 3/9/2022 3/11/2022 3/9
352 Door Frame 门框 2 days 3/12/2022 3/13/2022 3/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 7
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
353 Glass Door Installation 固定玻璃,玻璃们安装 3 days 3/19/2022 3/21/2022 3/19
354 Acrylic Installation 洗手台盘面+隔墙 3 days 3/27/2022 3/29/2022 3/27
355 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/25/2022 4/27/2022 4/25
356 Door Installation门安装+门扇 2 days 4/11/2022 4/12/2022 4/11
357 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/28/2022 4/30/2022 4/28
358 Wardrope 衣柜 3 days 4/28/2022 4/30/2022 4/28
359 Illuminated Mirior 洗手台镜子 2 days 3/30/2022 3/31/2022 3/30
360 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/20/2022 5/23/2022 5/20
Installation 卫生间五金和洁具
361 Room 6-002-S2 84 days 3/1/2022 5/23/2022 3/1 Room 6-002-S2
362 Setting ou放线 1 day 3/20/2022 3/20/2022 3/20
363 Steel Frame (Toilet and Vanity Sink) 3 days 3/21/2022 3/23/2022 3/21
Installation钢架安装
364 Skirting Tile Installation踢脚线 2 days 3/21/2022 3/22/2022 3/21
365 Bathroom Wall and Floor Tile Installation墙和 3 days 3/21/2022 3/23/2022 3/21
地板瓷砖
366 Wall Skim Coat墙 腻子 3 days 4/3/2022 4/5/2022 4/3
367 Base of TV Back Drop 电视背景基层 4 days 4/9/2022 4/12/2022 4/9
368 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/1/2022 3/3/2022 3/1
369 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/4/2022 3/6/2022 3/4
370 Ceiling Skim Coat 天花板腻子 3 days 3/9/2022 3/11/2022 3/9
371 Door Frame 门框 2 days 3/12/2022 3/13/2022 3/12
372 Glass Door Installation 固定玻璃,玻璃们安装 3 days 3/19/2022 3/21/2022 3/19
373 Acrylic Installation 洗手台盘面+隔墙 3 days 3/27/2022 3/29/2022 3/27
374 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/25/2022 4/27/2022 4/25
375 Door Installation门安装+门扇 2 days 4/6/2022 4/7/2022 4/6
376 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/28/2022 4/30/2022 4/28
377 Wardrope 衣柜 3 days 4/28/2022 4/30/2022 4/28
378 Illuminated Mirior 洗手台镜子 2 days 3/30/2022 3/31/2022 3/30
379 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/20/2022 5/23/2022 5/20
Installation 卫生间五金和洁具
380 Room 6-003-S2 200 days12/12/20216/29/2022 12/12 Room 6-003
381 Setting ou放线 1 day 12/12/202112/12/2021 12/12
382 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
383 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
384 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
385 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
386 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
387 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
388 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 8
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
389 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
390 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
391 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
392 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
393 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
394 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
395 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
396 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
397 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
398 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
399 Room 6-004-S1 200 days12/12/20216/29/2022 12/12 Room 6-004
400 Setting ou放线 1 day 12/12/202112/12/2021 12/12
401 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
402 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
403 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
404 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
405 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
406 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
407 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
408 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
409 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
410 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
411 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
412 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
413 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
414 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
415 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
416 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
417 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
418 Room 6-005-S2b 200 days12/12/20216/29/2022 12/12 Room 6-005
419 Setting ou放线 1 day 12/12/202112/12/2021 12/12
420 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
421 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
422 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
423 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
424 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 9
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
425 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
426 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
427 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
428 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
429 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
430 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
431 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
432 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
433 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
434 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
435 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
436 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
437 Room 6-006-S4 200 days12/12/20216/29/2022 12/12 Room 6-006
438 Setting ou放线 1 day 12/12/202112/12/2021 12/12
439 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
440 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
441 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
442 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
443 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
444 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
445 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
446 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
447 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
448 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
449 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
450 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
451 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
452 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
453 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
454 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
455 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
456 Room 6-007-S2 200 days12/12/20216/29/2022 12/12 Room 6-007
457 Setting ou放线 1 day 12/12/202112/12/2021 12/12
458 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
459 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
460 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 10
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
461 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
462 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
463 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
464 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
465 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
466 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
467 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
468 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
469 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
470 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
471 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
472 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
473 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
474 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
475 Room 6-008-S2 200 days12/12/20216/29/2022 12/12 Room 6-008
476 Setting ou放线 1 day 12/12/202112/12/2021 12/12
477 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
478 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
479 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
480 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
481 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
482 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
483 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
484 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
485 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
486 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
487 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
488 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
489 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
490 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
491 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
492 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
493 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
494 Room 6-009-S4 200 days12/12/20216/29/2022 12/12 Room 6-009
495 Setting ou放线 1 day 12/12/202112/12/2021 12/12
496 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
497 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 11
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
498 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
499 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
500 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
501 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
502 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
503 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
504 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
505 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
506 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
507 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
508 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
509 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
510 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
511 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
512 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
513 Room 6-010-S2 200 days12/12/20216/29/2022 12/12 Room 6-010
514 Setting ou放线 1 day 12/12/202112/12/2021 12/12
515 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
516 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
517 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
518 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
519 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
520 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
521 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
522 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
523 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
524 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
525 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
526 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
527 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
528 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
529 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
530 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
531 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
532 Room 6-011-S2 200 days12/12/20216/29/2022 12/12 Room 6-011
533 Setting ou放线 1 day 12/12/202112/12/2021 12/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 12
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
534 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
535 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
536 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
537 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
538 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
539 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
540 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
541 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
542 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
543 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
544 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
545 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
546 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
547 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
548 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
549 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
550 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
551 Room 6-012-S1ds 200 days12/12/20216/29/2022 12/12 Room 6-012
552 Setting ou放线 1 day 12/12/202112/12/2021 12/12
553 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
554 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
555 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
556 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
557 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
558 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
559 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
560 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
561 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
562 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
563 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
564 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
565 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
566 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
567 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
568 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
569 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 13
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
570 Room 6-013-S1 200 days12/12/20216/29/2022 12/12 Room 6-013
571 Setting ou放线 1 day 12/12/202112/12/2021 12/12
572 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
573 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
574 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
575 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
576 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
577 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
578 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
579 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
580 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
581 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
582 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
583 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
584 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
585 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
586 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
587 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
588 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
589 Room 6-014-S2 200 days12/12/20216/29/2022 12/12 Room 6-014
590 Setting ou放线 1 day 12/12/202112/12/2021 12/12
591 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
592 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
593 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
594 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
595 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
596 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
597 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
598 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
599 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
600 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
601 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
602 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
603 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
604 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
605 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
606 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 14
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
607 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
608 CORRIDOR & LIFT LOBBY走道 102 days3/12/2022 6/21/2022 3/12 CORRIDOR & L
609 Acoustic Insulation Wall Installaltion 隔音墙 10 days 3/12/2022 3/21/2022 3/12
610 Ceiling Frame Installation 吊顶龙安装 10 days 4/6/2022 4/15/2022 4/6
611 Close ceiling and wallgypsum boards石膏板封闭 5 days 4/16/2022 4/20/2022 4/16
612 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/21/2022 4/27/2022 4/21
613 Skirting Installation 踢脚线,木饰面 7 days 4/23/2022 4/29/2022 4/23
614 Fire Proofing Door Framing Installation 防火门框 7 days 4/14/2022 4/20/2022 4/14
615 Painting on Ceiling 天花板油漆 6 days 5/7/2022 5/12/2022 5/7
616 Fire Proofing Door Installation 防火门+门扇 3 days 5/16/2022 5/18/2022 5/16
617 Wall Papers on Corridors wall &Installation of 6 days 6/3/2022 6/8/2022 6/3
glasses 墙壁纸+玻璃
618 Carpet installation in corridor地毯 3 days 6/19/2022 6/21/2022 6/19
619 ID Work level 7 精装修7层 215 days11/10/20216/12/2022 11/10 ID Work level 7 精
620 Guest Room 215 days11/10/20216/12/2022 11/10 Guest Room
621 Room 7-001-S2 80 days 3/25/2022 6/12/2022 3/25 Room 7-001-S2
622 Setting ou放线 1 day 3/25/2022 3/25/2022 3/25
623 Steel Frame (Toilet and Vanity Sink) 3 days 3/26/2022 3/28/2022 3/26
Installation钢架安装
624 Skirting Tile Installation踢脚线 2 days 3/26/2022 3/27/2022 3/26
625 Bathroom Wall and Floor Tile Installation墙和 3 days 3/26/2022 3/28/2022 3/26
地板瓷砖
626 Wall Skim Coat墙 腻子 3 days 4/8/2022 4/10/2022 4/8
627 Base of TV Back Drop 电视背景基层 4 days 4/14/2022 4/17/2022 4/14
628 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/8/2022 4/10/2022 4/8
629 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/11/2022 4/13/2022 4/11
630 Ceiling Skim Coat 天花板腻子 3 days 4/16/2022 4/18/2022 4/16
631 Door Frame 门框 2 days 4/14/2022 4/15/2022 4/14
632 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/26/2022 4/28/2022 4/26
633 Acrylic Installation 洗手台盘面+隔墙 3 days 5/4/2022 5/6/2022 5/4
634 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/22/2022 4/24/2022 4/22
635 Door Installation门安装+门扇 2 days 4/21/2022 4/22/2022 4/21
636 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/25/2022 4/27/2022 4/25
637 Wardrope 衣柜 3 days 4/25/2022 4/27/2022 4/25
638 Illuminated Mirior 洗手台镜子 2 days 5/2/2022 5/3/2022 5/2
639 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/9/2022 6/12/2022 6/9
Installation 卫生间五金和洁具
640 Room 7-001-S2 80 days 3/25/2022 6/12/2022 3/25 Room 7-001-S2
641 Setting ou放线 1 day 3/25/2022 3/25/2022 3/25
642 Steel Frame (Toilet and Vanity Sink) 3 days 3/26/2022 3/28/2022 3/26
Installation钢架安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 15
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
643 Skirting Tile Installation踢脚线 2 days 3/26/2022 3/27/2022 3/26
644 Bathroom Wall and Floor Tile Installation墙和 3 days 3/26/2022 3/28/2022 3/26
地板瓷砖
645 Wall Skim Coat墙 腻子 3 days 4/8/2022 4/10/2022 4/8
646 Base of TV Back Drop 电视背景基层 4 days 4/14/2022 4/17/2022 4/14
647 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/8/2022 4/10/2022 4/8
648 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/11/2022 4/13/2022 4/11
649 Ceiling Skim Coat 天花板腻子 3 days 4/16/2022 4/18/2022 4/16
650 Door Frame 门框 2 days 4/14/2022 4/15/2022 4/14
651 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/26/2022 4/28/2022 4/26
652 Acrylic Installation 洗手台盘面+隔墙 3 days 5/4/2022 5/6/2022 5/4
653 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/22/2022 4/24/2022 4/22
654 Door Installation门安装+门扇 2 days 4/21/2022 4/22/2022 4/21
655 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/25/2022 4/27/2022 4/25
656 Wardrope 衣柜 3 days 4/25/2022 4/27/2022 4/25
657 Illuminated Mirior 洗手台镜子 2 days 5/2/2022 5/3/2022 5/2
658 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/9/2022 6/12/2022 6/9
Installation 卫生间五金和洁具
659 Room 7-003-S2 182 days11/10/20215/10/2022 11/10 Room 7-003-S2
660 Setting ou放线 1 day 11/10/202111/10/2021 11/10
661 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
662 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
663 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
664 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
665 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
666 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
667 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
668 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
669 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
670 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
671 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
672 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
673 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
674 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
675 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
676 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
677 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
678 Room 7-004-S1 182 days11/10/20215/10/2022 11/10 Room 7-004-S1
679 Setting ou放线 1 day 11/10/202111/10/2021 11/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 16
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
680 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
681 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
682 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
683 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
684 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
685 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
686 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
687 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
688 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
689 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
690 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
691 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
692 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
693 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
694 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
695 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
696 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
697 Room 7-005-S2b 182 days11/10/20215/10/2022 11/10 Room 7-005-S2b
698 Setting ou放线 1 day 11/10/202111/10/2021 11/10
699 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
700 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
701 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
702 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
703 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
704 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
705 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
706 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
707 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
708 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
709 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
710 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
711 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
712 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
713 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
714 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
715 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 17
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
716 Room 7-006-S4 182 days11/10/20215/10/2022 11/10 Room 7-006-S4
717 Setting ou放线 1 day 11/10/202111/10/2021 11/10
718 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
719 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
720 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
721 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
722 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
723 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
724 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
725 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
726 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
727 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
728 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
729 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
730 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
731 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
732 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
733 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
734 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
735 Room 7-007-S2 182 days11/10/20215/10/2022 11/10 Room 7-007-S2
736 Setting ou放线 1 day 11/10/202111/10/2021 11/10
737 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
738 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
739 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
740 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
741 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
742 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
743 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
744 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
745 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
746 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
747 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
748 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
749 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
750 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
751 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
752 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 18
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
753 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
754 Room 7-008-S2 182 days11/10/20215/10/2022 11/10 Room 7-008-S2
755 Setting ou放线 1 day 11/10/202111/10/2021 11/10
756 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
757 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
758 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
759 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
760 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
761 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
762 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
763 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
764 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
765 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
766 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
767 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
768 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
769 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
770 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
771 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
772 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
773 Room 7-009-S4 182 days11/10/20215/10/2022 11/10 Room 7-009-S4
774 Setting ou放线 1 day 11/10/202111/10/2021 11/10
775 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
776 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
777 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
778 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
779 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
780 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
781 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
782 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
783 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
784 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
785 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
786 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
787 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
788 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 19
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
789 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
790 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
791 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
792 Room 7-010-S2 182 days11/10/20215/10/2022 11/10 Room 7-010-S2
793 Setting ou放线 1 day 11/10/202111/10/2021 11/10
794 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
795 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
796 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
797 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
798 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
799 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
800 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
801 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
802 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
803 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
804 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
805 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
806 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
807 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
808 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
809 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
810 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
811 Room 7-011-S2 182 days11/10/20215/10/2022 11/10 Room 7-011-S2
812 Setting ou放线 1 day 11/10/202111/10/2021 11/10
813 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
814 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
815 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
816 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
817 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
818 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
819 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
820 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
821 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
822 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
823 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
824 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 20
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
825 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
826 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
827 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
828 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
829 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
830 Room 7-012-S1ds 182 days11/10/20215/10/2022 11/10 Room 7-012-S1ds
831 Setting ou放线 1 day 11/10/202111/10/2021 11/10
832 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
833 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
834 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
835 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
836 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
837 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
838 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
839 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
840 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
841 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
842 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
843 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
844 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
845 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
846 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
847 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
848 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
849 Room 7-013-S1 182 days11/10/20215/10/2022 11/10 Room 7-013-S1
850 Setting ou放线 1 day 11/10/202111/10/2021 11/10
851 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
852 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
853 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
854 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
855 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
856 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
857 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
858 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
859 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
860 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 21
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
861 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
862 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
863 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
864 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
865 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
866 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
867 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
868 Room 7-014-S2 182 days11/10/20215/10/2022 11/10 Room 7-014-S2
869 Setting ou放线 1 day 11/10/202111/10/2021 11/10
870 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
871 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
872 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
873 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
874 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
875 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
876 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
877 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
878 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
879 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
880 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
881 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
882 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
883 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
884 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
885 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
886 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
887 CORRIDOR & LIFT LOBBY走道 137 days1/21/2022 6/6/2022 1/21 CORRIDOR & LIFT
888 Acoustic Insulation Wall Installaltion 隔音墙 10 days 1/21/2022 1/30/2022 1/21
889 Ceiling Frame Installation 吊顶龙安装 10 days 2/15/2022 2/24/2022 2/15
890 Close ceiling and wallgypsum boards石膏板封闭 5 days 2/25/2022 3/1/2022 2/25
891 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/2/2022 3/8/2022 3/2
892 Skirting Installation 踢脚线,木饰面 7 days 3/19/2022 3/25/2022 3/19
893 Fire Proofing Door Framing Installation 防火门框 7 days 3/10/2022 3/16/2022 3/10
894 Painting on Ceiling 天花板油漆 6 days 4/2/2022 4/7/2022 4/2
895 Fire Proofing Door Installation 防火门+门扇 3 days 5/1/2022 5/3/2022 5/1
896 Wall Papers on Corridors wall &Installation of 6 days 5/4/2022 5/9/2022 5/4
glasses 墙壁纸+玻璃
897 Carpet installation in corridor地毯 3 days 6/4/2022 6/6/2022 6/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 22
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
898 ID Work level 8精装修8层 215 days11/10/20216/12/2022 11/10 ID Work level 8精
899 Guest Room 215 days11/10/20216/12/2022 11/10 Guest Room
900 Room 8-001-S2 80 days 3/25/2022 6/12/2022 3/25 Room 8-001-S2
901 Setting ou放线 1 day 3/25/2022 3/25/2022 3/25
902 Steel Frame (Toilet and Vanity Sink) 3 days 3/26/2022 3/28/2022 3/26
Installation钢架安装
903 Skirting Tile Installation踢脚线 2 days 3/26/2022 3/27/2022 3/26
904 Bathroom Wall and Floor Tile Installation墙和 3 days 3/26/2022 3/28/2022 3/26
地板瓷砖
905 Wall Skim Coat墙 腻子 3 days 4/8/2022 4/10/2022 4/8
906 Base of TV Back Drop 电视背景基层 4 days 4/14/2022 4/17/2022 4/14
907 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/8/2022 4/10/2022 4/8
908 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/11/2022 4/13/2022 4/11
909 Ceiling Skim Coat 天花板腻子 3 days 4/16/2022 4/18/2022 4/16
910 Door Frame 门框 2 days 4/14/2022 4/15/2022 4/14
911 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/26/2022 4/28/2022 4/26
912 Acrylic Installation 洗手台盘面+隔墙 3 days 5/4/2022 5/6/2022 5/4
913 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/22/2022 4/24/2022 4/22
914 Door Installation门安装+门扇 2 days 4/21/2022 4/22/2022 4/21
915 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/25/2022 4/27/2022 4/25
916 Wardrope 衣柜 3 days 4/25/2022 4/27/2022 4/25
917 Illuminated Mirior 洗手台镜子 2 days 5/2/2022 5/3/2022 5/2
918 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/9/2022 6/12/2022 6/9
Installation 卫生间五金和洁具
919 Room 8-001-S2 80 days 3/25/2022 6/12/2022 3/25 Room 8-001-S2
920 Setting ou放线 1 day 3/25/2022 3/25/2022 3/25
921 Steel Frame (Toilet and Vanity Sink) 3 days 3/26/2022 3/28/2022 3/26
Installation钢架安装
922 Skirting Tile Installation踢脚线 2 days 3/26/2022 3/27/2022 3/26
923 Bathroom Wall and Floor Tile Installation墙和 3 days 3/26/2022 3/28/2022 3/26
地板瓷砖
924 Wall Skim Coat墙 腻子 3 days 4/8/2022 4/10/2022 4/8
925 Base of TV Back Drop 电视背景基层 4 days 4/14/2022 4/17/2022 4/14
926 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/8/2022 4/10/2022 4/8
927 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/11/2022 4/13/2022 4/11
928 Ceiling Skim Coat 天花板腻子 3 days 4/16/2022 4/18/2022 4/16
929 Door Frame 门框 2 days 4/14/2022 4/15/2022 4/14
930 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/26/2022 4/28/2022 4/26
931 Acrylic Installation 洗手台盘面+隔墙 3 days 5/4/2022 5/6/2022 5/4
932 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/22/2022 4/24/2022 4/22
933 Door Installation门安装+门扇 2 days 4/21/2022 4/22/2022 4/21
934 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/25/2022 4/27/2022 4/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 23
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
935 Wardrope 衣柜 3 days 4/25/2022 4/27/2022 4/25
936 Illuminated Mirior 洗手台镜子 2 days 5/2/2022 5/3/2022 5/2
937 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/9/2022 6/12/2022 6/9
Installation 卫生间五金和洁具
938 Room 8-003-S2 182 days11/10/20215/10/2022 11/10 Room 8-003-S2
939 Setting ou放线 1 day 11/10/202111/10/2021 11/10
940 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
941 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
942 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
943 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
944 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
945 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
946 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
947 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
948 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
949 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
950 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
951 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
952 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
953 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
954 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
955 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
956 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
957 Room 8-004-S1 182 days11/10/20215/10/2022 11/10 Room 8-004-S1
958 Setting ou放线 1 day 11/10/202111/10/2021 11/10
959 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
960 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
961 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
962 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
963 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
964 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
965 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
966 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
967 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
968 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
969 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
970 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 24
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
971 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
972 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
973 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
974 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
975 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
976 Room 8-005-S2b 182 days11/10/20215/10/2022 11/10 Room 8-005-S2b
977 Setting ou放线 1 day 11/10/202111/10/2021 11/10
978 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
979 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
980 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
981 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
982 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
983 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
984 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
985 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
986 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
987 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
988 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
989 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
990 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
991 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
992 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
993 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
994 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
995 Room 8-006-S4 182 days11/10/20215/10/2022 11/10 Room 8-006-S4
996 Setting ou放线 1 day 11/10/202111/10/2021 11/10
997 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
998 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
999 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1000 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1001 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1002 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1003 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1004 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1005 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1006 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 25
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1007 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1008 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1009 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1010 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1011 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1012 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1013 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1014 Room 8-007-S2 182 days11/10/20215/10/2022 11/10 Room 8-007-S2
1015 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1016 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1017 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1018 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1019 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1020 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1021 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1022 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1023 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1024 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1025 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1026 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1027 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1028 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1029 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1030 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1031 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1032 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1033 Room 8-008-S2 182 days11/10/20215/10/2022 11/10 Room 8-008-S2
1034 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1035 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1036 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1037 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1038 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1039 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1040 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1041 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1042 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 26
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1043 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1044 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1045 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1046 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1047 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1048 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1049 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1050 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1051 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1052 Room 8-009-S4 182 days11/10/20215/10/2022 11/10 Room 8-009-S4
1053 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1054 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1055 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1056 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1057 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1058 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1059 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1060 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1061 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1062 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1063 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1064 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1065 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1066 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1067 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1068 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1069 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1070 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1071 Room 8-010-S2 182 days11/10/20215/10/2022 11/10 Room 8-010-S2
1072 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1073 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1074 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1075 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1076 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1077 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1078 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 27
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1079 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1080 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1081 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1082 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1083 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1084 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1085 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1086 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1087 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1088 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1089 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1090 Room 8-011-S2 182 days11/10/20215/10/2022 11/10 Room 8-011-S2
1091 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1092 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1093 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1094 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1095 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1096 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1097 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1098 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1099 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1100 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1101 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1102 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1103 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1104 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1105 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1106 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1107 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1108 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1109 Room 8-012-S1 182 days11/10/20215/10/2022 11/10 Room 8-012-S1
1110 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1111 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1112 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1113 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1114 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 28
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1115 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1116 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1117 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1118 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1119 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1120 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1121 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1122 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1123 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1124 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1125 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1126 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1127 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1128 Room 8-013-S2b 182 days11/10/20215/10/2022 11/10 Room 8-013-S2b
1129 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1130 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1131 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1132 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1133 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1134 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1135 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1136 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1137 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1138 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1139 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1140 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1141 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1142 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1143 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1144 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1145 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1146 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1147 Room 8-014-S2 182 days11/10/20215/10/2022 11/10 Room 8-014-S2
1148 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1149 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1150 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 29
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1151 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1152 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1153 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1154 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1155 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1156 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1157 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1158 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1159 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1160 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1161 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1162 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1163 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1164 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1165 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1166 CORRIDOR & LIFT LOBBY走道 137 days1/21/2022 6/6/2022 1/21 CORRIDOR & LIFT
1167 Acoustic Insulation Wall Installaltion 隔音墙 10 days 1/21/2022 1/30/2022 1/21
1168 Ceiling Frame Installation 吊顶龙安装 10 days 2/15/2022 2/24/2022 2/15
1169 Close ceiling and wallgypsum boards石膏板封闭 5 days 2/25/2022 3/1/2022 2/25
1170 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/2/2022 3/8/2022 3/2
1171 Skirting Installation 踢脚线,木饰面 7 days 3/19/2022 3/25/2022 3/19
1172 Fire Proofing Door Framing Installation 防火门框 7 days 3/10/2022 3/16/2022 3/10
1173 Painting on Ceiling 天花板油漆 6 days 4/2/2022 4/7/2022 4/2
1174 Fire Proofing Door Installation 防火门+门扇 3 days 5/1/2022 5/3/2022 5/1
1175 Wall Papers on Corridors wall &Installation of 6 days 5/4/2022 5/9/2022 5/4
glasses 墙壁纸+玻璃
1176 Carpet installation in corridor地毯 3 days 6/4/2022 6/6/2022 6/4
1177 ID Work level 9精装修9层 215 days11/10/20216/12/2022 11/10 ID Work level 9精
1178 Guest Room 215 days11/10/20216/12/2022 11/10 Guest Room
1179 Room 9-001-S2 80 days 3/25/2022 6/12/2022 3/25 Room 9-001-S2
1180 Setting ou放线 1 day 3/25/2022 3/25/2022 3/25
1181 Steel Frame (Toilet and Vanity Sink) 3 days 3/26/2022 3/28/2022 3/26
Installation钢架安装
1182 Skirting Tile Installation踢脚线 2 days 3/26/2022 3/27/2022 3/26
1183 Bathroom Wall and Floor Tile Installation墙和 3 days 3/26/2022 3/28/2022 3/26
地板瓷砖
1184 Wall Skim Coat墙 腻子 3 days 4/8/2022 4/10/2022 4/8
1185 Base of TV Back Drop 电视背景基层 4 days 4/14/2022 4/17/2022 4/14
1186 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/8/2022 4/10/2022 4/8
1187 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/11/2022 4/13/2022 4/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 30
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1188 Ceiling Skim Coat 天花板腻子 3 days 4/16/2022 4/18/2022 4/16
1189 Door Frame 门框 2 days 4/14/2022 4/15/2022 4/14
1190 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/26/2022 4/28/2022 4/26
1191 Acrylic Installation 洗手台盘面+隔墙 3 days 5/4/2022 5/6/2022 5/4
1192 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/22/2022 4/24/2022 4/22
1193 Door Installation门安装+门扇 2 days 4/21/2022 4/22/2022 4/21
1194 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/25/2022 4/27/2022 4/25
1195 Wardrope 衣柜 3 days 4/25/2022 4/27/2022 4/25
1196 Illuminated Mirior 洗手台镜子 2 days 5/2/2022 5/3/2022 5/2
1197 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/9/2022 6/12/2022 6/9
Installation 卫生间五金和洁具
1198 Room 9-001-S2 80 days 3/25/2022 6/12/2022 3/25 Room 9-001-S2
1199 Setting ou放线 1 day 3/25/2022 3/25/2022 3/25
1200 Steel Frame (Toilet and Vanity Sink) 3 days 3/26/2022 3/28/2022 3/26
Installation钢架安装
1201 Skirting Tile Installation踢脚线 2 days 3/26/2022 3/27/2022 3/26
1202 Bathroom Wall and Floor Tile Installation墙和 3 days 3/26/2022 3/28/2022 3/26
地板瓷砖
1203 Wall Skim Coat墙 腻子 3 days 4/8/2022 4/10/2022 4/8
1204 Base of TV Back Drop 电视背景基层 4 days 4/14/2022 4/17/2022 4/14
1205 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/8/2022 4/10/2022 4/8
1206 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/11/2022 4/13/2022 4/11
1207 Ceiling Skim Coat 天花板腻子 3 days 4/16/2022 4/18/2022 4/16
1208 Door Frame 门框 2 days 4/14/2022 4/15/2022 4/14
1209 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/26/2022 4/28/2022 4/26
1210 Acrylic Installation 洗手台盘面+隔墙 3 days 5/4/2022 5/6/2022 5/4
1211 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/22/2022 4/24/2022 4/22
1212 Door Installation门安装+门扇 2 days 4/21/2022 4/22/2022 4/21
1213 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/25/2022 4/27/2022 4/25
1214 Wardrope 衣柜 3 days 4/25/2022 4/27/2022 4/25
1215 Illuminated Mirior 洗手台镜子 2 days 5/2/2022 5/3/2022 5/2
1216 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/9/2022 6/12/2022 6/9
Installation 卫生间五金和洁具
1217 Room 9-003-S2 182 days11/10/20215/10/2022 11/10 Room 9-003-S2
1218 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1219 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1220 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1221 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1222 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1223 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 31
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1224 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1225 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1226 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1227 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1228 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1229 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1230 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1231 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1232 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1233 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1234 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1235 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1236 Room 9-004-S1 182 days11/10/20215/10/2022 11/10 Room 9-004-S1
1237 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1238 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1239 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1240 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1241 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1242 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1243 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1244 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1245 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1246 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1247 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1248 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1249 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1250 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1251 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1252 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1253 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1254 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1255 Room 9-005-S2b 182 days11/10/20215/10/2022 11/10 Room 9-005-S2b
1256 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1257 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1258 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1259 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 32
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1260 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1261 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1262 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1263 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1264 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1265 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1266 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1267 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1268 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1269 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1270 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1271 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1272 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1273 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1274 Room 9-004-S4 182 days11/10/20215/10/2022 11/10 Room 9-004-S4
1275 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1276 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1277 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1278 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1279 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1280 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1281 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1282 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1283 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1284 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1285 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1286 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1287 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1288 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1289 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1290 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1291 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1292 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1293 Room 9-007-S2 182 days11/10/20215/10/2022 11/10 Room 9-007-S2
1294 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1295 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1296 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 33
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1297 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1298 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1299 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1300 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1301 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1302 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1303 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1304 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1305 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1306 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1307 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1308 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1309 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1310 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1311 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1312 Room 9-008-S2 182 days11/10/20215/10/2022 11/10 Room 9-008-S2
1313 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1314 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1315 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1316 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1317 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1318 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1319 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1320 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1321 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1322 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1323 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1324 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1325 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1326 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1327 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1328 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1329 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1330 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1331 Room 9-009-S4 182 days11/10/20215/10/2022 11/10 Room 9-009-S4
1332 Setting ou放线 1 day 11/10/202111/10/2021 11/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 34
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1333 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1334 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1335 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1336 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1337 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1338 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1339 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1340 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1341 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1342 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1343 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1344 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1345 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1346 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1347 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1348 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1349 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1350 Room 9-010-S2 182 days11/10/20215/10/2022 11/10 Room 9-010-S2
1351 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1352 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1353 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1354 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1355 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1356 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1357 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1358 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1359 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1360 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1361 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1362 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1363 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1364 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1365 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1366 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1367 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1368 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 35
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1369 Room 9-011-S2 182 days11/10/20215/10/2022 11/10 Room 9-011-S2
1370 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1371 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1372 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1373 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1374 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1375 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1376 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1377 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1378 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1379 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1380 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1381 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1382 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1383 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1384 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1385 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1386 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1387 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1388 Room 9-012-S1 182 days11/10/20215/10/2022 11/10 Room 9-012-S1
1389 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1390 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1391 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1392 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1393 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1394 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1395 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1396 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1397 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1398 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1399 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1400 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1401 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1402 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1403 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1404 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1405 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 36
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1406 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1407 Room 9-013-S2b 182 days11/10/20215/10/2022 11/10 Room 9-013-S2b
1408 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1409 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1410 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1411 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1412 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1413 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1414 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1415 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1416 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1417 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1418 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1419 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1420 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1421 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1422 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10
1423 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1424 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1425 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1426 Room 9-014-S2 182 days11/10/20215/10/2022 11/10 Room 9-014-S2
1427 Setting ou放线 1 day 11/10/202111/10/2021 11/10
1428 Steel Frame (Toilet and Vanity Sink) 5 days 11/11/202111/15/2021 11/11
Installation钢架安装
1429 Skirting Tile Installation踢脚线 4 days 11/13/202111/16/2021 11/13
1430 Bathroom Wall and Floor Tile Installation墙和 7 days 12/1/2021 12/7/2021 12/1
地板瓷砖
1431 Wall Skim Coat墙 腻子 7 days 11/25/202112/1/2021 11/25
1432 Base of TV Back Drop 电视背景基层 7 days 12/15/202112/21/2021 12/15
1433 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 1/27/2022 1/31/2022 1/27
1434 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/1/2022 2/6/2022 2/1
1435 Ceiling Skim Coat 天花板腻子 6 days 2/9/2022 2/14/2022 2/9
1436 Door Frame 门框 5 days 2/10/2022 2/14/2022 2/10
1437 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/3/2022 2/9/2022 2/3
1438 Acrylic Installation 洗手台盘面+隔墙 7 days 2/17/2022 2/23/2022 2/17
1439 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/21/2022 2/27/2022 2/21
1440 Door Installation门安装+门扇 7 days 3/5/2022 3/11/2022 3/5
1441 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/10/2022 3/16/2022 3/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 37
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1442 Wardrope 衣柜 7 days 3/12/2022 3/18/2022 3/12
1443 Illuminated Mirior 洗手台镜子 3 days 3/12/2022 3/14/2022 3/12
1444 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/1/2022 5/10/2022 5/1
Installation 卫生间五金和洁具
1445 CORRIDOR & LIFT LOBBY走道 137 days1/21/2022 6/6/2022 1/21 CORRIDOR & LIFT
1446 Acoustic Insulation Wall Installaltion 隔音墙 10 days 1/21/2022 1/30/2022 1/21
1447 Ceiling Frame Installation 吊顶龙安装 10 days 2/15/2022 2/24/2022 2/15
1448 Close ceiling and wallgypsum boards石膏板封闭 5 days 2/25/2022 3/1/2022 2/25
1449 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/2/2022 3/8/2022 3/2
1450 Skirting Installation 踢脚线,木饰面 7 days 3/19/2022 3/25/2022 3/19
1451 Fire Proofing Door Framing Installation 防火门框 7 days 3/10/2022 3/16/2022 3/10
1452 Painting on Ceiling 天花板油漆 6 days 4/2/2022 4/7/2022 4/2
1453 Fire Proofing Door Installation 防火门+门扇 3 days 5/1/2022 5/3/2022 5/1
1454 Wall Papers on Corridors wall &Installation of 6 days 5/4/2022 5/9/2022 5/4
glasses 墙壁纸+玻璃
1455 Carpet installation in corridor地毯 3 days 6/4/2022 6/6/2022 6/4
1456 ID Work level 10 精装修10层 204 days11/18/20216/9/2022 11/18 ID Work level 10 精
1457 Guest Room 203 days11/18/20216/8/2022 11/18 Guest Room
1458 Room 10-001-S2 77 days 3/24/2022 6/8/2022 3/24 Room 10-001-S2
1459 Setting ou放线 1 day 3/24/2022 3/24/2022 3/24
1460 Steel Frame (Toilet and Vanity Sink) 3 days 3/25/2022 3/27/2022 3/25
Installation钢架安装
1461 Skirting Tile Installation踢脚线 2 days 3/25/2022 3/26/2022 3/25
1462 Bathroom Wall and Floor Tile Installation墙和 3 days 3/25/2022 3/27/2022 3/25
地板瓷砖
1463 Wall Skim Coat墙 腻子 3 days 4/7/2022 4/9/2022 4/7
1464 Base of TV Back Drop 电视背景基层 4 days 4/13/2022 4/16/2022 4/13
1465 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/5/2022 4/7/2022 4/5
1466 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/8/2022 4/10/2022 4/8
1467 Ceiling Skim Coat 天花板腻子 3 days 4/13/2022 4/15/2022 4/13
1468 Door Frame 门框 2 days 4/12/2022 4/13/2022 4/12
1469 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/23/2022 4/25/2022 4/23
1470 Acrylic Installation 洗手台盘面+隔墙 3 days 5/1/2022 5/3/2022 5/1
1471 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/19/2022 4/21/2022 4/19
1472 Door Installation门安装+门扇 2 days 4/14/2022 4/15/2022 4/14
1473 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/22/2022 4/24/2022 4/22
1474 Wardrope 衣柜 3 days 4/22/2022 4/24/2022 4/22
1475 Illuminated Mirior 洗手台镜子 2 days 4/30/2022 5/1/2022 4/30
1476 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/5/2022 6/8/2022 6/5
Installation 卫生间五金和洁具
1477 Room 10-001-S2 77 days 3/24/2022 6/8/2022 3/24 Room 10-001-S2
1478 Setting ou放线 1 day 3/24/2022 3/24/2022 3/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 38
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1479 Steel Frame (Toilet and Vanity Sink) 3 days 3/25/2022 3/27/2022 3/25
Installation钢架安装
1480 Skirting Tile Installation踢脚线 2 days 3/25/2022 3/26/2022 3/25
1481 Bathroom Wall and Floor Tile Installation墙和 3 days 3/25/2022 3/27/2022 3/25
地板瓷砖
1482 Wall Skim Coat墙 腻子 3 days 4/7/2022 4/9/2022 4/7
1483 Base of TV Back Drop 电视背景基层 4 days 4/13/2022 4/16/2022 4/13
1484 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/5/2022 4/7/2022 4/5
1485 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/8/2022 4/10/2022 4/8
1486 Ceiling Skim Coat 天花板腻子 3 days 4/13/2022 4/15/2022 4/13
1487 Door Frame 门框 2 days 4/12/2022 4/13/2022 4/12
1488 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/23/2022 4/25/2022 4/23
1489 Acrylic Installation 洗手台盘面+隔墙 3 days 5/1/2022 5/3/2022 5/1
1490 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/19/2022 4/21/2022 4/19
1491 Door Installation门安装+门扇 2 days 4/14/2022 4/15/2022 4/14
1492 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/22/2022 4/24/2022 4/22
1493 Wardrope 衣柜 3 days 4/22/2022 4/24/2022 4/22
1494 Illuminated Mirior 洗手台镜子 2 days 4/30/2022 5/1/2022 4/30
1495 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/5/2022 6/8/2022 6/5
Installation 卫生间五金和洁具
1496 Room 10-003-S2 184 days11/18/20215/20/2022 11/18 Room 10-003-S2
1497 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1498 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1499 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1500 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1501 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1502 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1503 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1504 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1505 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1506 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1507 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1508 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1509 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1510 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1511 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1512 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1513 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1514 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 39
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1515 Room 10-004-S1 184 days11/18/20215/20/2022 11/18 Room 10-004-S1
1516 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1517 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1518 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1519 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1520 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1521 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1522 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1523 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1524 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1525 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1526 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1527 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1528 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1529 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1530 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1531 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1532 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1533 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1534 Room 10-005-S2b 184 days11/18/20215/20/2022 11/18 Room 10-005-S2b
1535 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1536 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1537 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1538 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1539 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1540 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1541 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1542 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1543 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1544 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1545 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1546 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1547 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1548 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1549 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1550 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1551 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 40
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1552 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1553 Room 10-006-S4 184 days11/18/20215/20/2022 11/18 Room 10-006-S4
1554 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1555 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1556 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1557 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1558 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1559 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1560 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1561 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1562 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1563 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1564 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1565 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1566 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1567 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1568 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1569 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1570 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1571 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1572 Room 10-007-S2 184 days11/18/20215/20/2022 11/18 Room 10-007-S2
1573 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1574 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1575 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1576 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1577 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1578 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1579 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1580 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1581 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1582 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1583 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1584 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1585 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1586 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1587 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 41
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1588 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1589 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1590 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1591 Room 10-008-S2 184 days11/18/20215/20/2022 11/18 Room 10-008-S2
1592 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1593 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1594 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1595 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1596 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1597 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1598 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1599 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1600 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1601 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1602 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1603 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1604 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1605 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1606 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1607 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1608 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1609 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1610 Room 10-009-S4 184 days11/18/20215/20/2022 11/18 Room 10-009-S4
1611 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1612 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1613 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1614 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1615 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1616 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1617 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1618 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1619 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1620 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1621 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1622 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1623 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 42
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1624 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1625 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1626 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1627 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1628 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1629 Room 10-010-S2 184 days11/18/20215/20/2022 11/18 Room 10-010-S2
1630 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1631 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1632 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1633 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1634 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1635 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1636 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1637 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1638 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1639 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1640 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1641 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1642 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1643 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1644 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1645 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1646 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1647 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1648 Room 10-011-S2 184 days11/18/20215/20/2022 11/18 Room 10-011-S2
1649 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1650 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1651 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1652 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1653 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1654 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1655 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1656 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1657 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1658 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1659 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 43
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1660 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1661 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1662 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1663 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1664 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1665 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1666 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1667 Room 10-012-S1 184 days11/18/20215/20/2022 11/18 Room 10-012-S1
1668 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1669 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1670 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1671 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1672 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1673 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1674 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1675 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1676 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1677 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1678 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1679 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1680 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1681 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1682 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1683 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1684 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1685 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1686 Room 10-013-S2b 184 days11/18/20215/20/2022 11/18 Room 10-013-S2b
1687 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1688 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1689 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1690 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1691 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1692 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1693 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1694 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1695 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 44
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1696 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1697 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1698 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1699 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1700 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1701 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1702 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1703 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1704 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1705 Room 10-014-S2 184 days11/18/20215/20/2022 11/18 Room 10-014-S2
1706 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1707 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1708 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1709 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1710 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1711 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1712 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1713 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1714 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1715 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1716 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1717 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1718 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1719 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1720 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1721 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1722 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1723 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1724 CORRIDOR & LIFT LOBBY走道 130 days1/31/2022 6/9/2022 1/31 CORRIDOR & LIFT
1725 Acoustic Insulation Wall Installaltion 隔音墙 10 days 1/31/2022 2/9/2022 1/31
1726 Ceiling Frame Installation 吊顶龙安装 10 days 2/25/2022 3/6/2022 2/25
1727 Close ceiling and wallgypsum boards石膏板封闭 5 days 3/7/2022 3/11/2022 3/7
1728 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/12/2022 3/18/2022 3/12
1729 Skirting Installation 踢脚线,木饰面 7 days 3/26/2022 4/1/2022 3/26
1730 Fire Proofing Door Framing Installation 防火门框 7 days 3/17/2022 3/23/2022 3/17
1731 Painting on Ceiling 天花板油漆 6 days 4/9/2022 4/14/2022 4/9
1732 Fire Proofing Door Installation 防火门+门扇 3 days 5/4/2022 5/6/2022 5/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 45
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1733 Wall Papers on Corridors wall &Installation of 6 days 5/10/2022 5/15/2022 5/10
glasses 墙壁纸+玻璃
1734 Carpet installation in corridor地毯 3 days 6/7/2022 6/9/2022 6/7
1735 ID Work level 11 精装修11层 204 days11/18/20216/9/2022 11/18 ID Work level 11 精
1736 Guest Room 204 days11/18/20216/9/2022 11/18 Guest Room
1737 Room 11-001-S2 77 days 3/24/2022 6/8/2022 3/24 Room 11-001-S2
1738 Setting ou放线 1 day 3/24/2022 3/24/2022 3/24
1739 Steel Frame (Toilet and Vanity Sink) 3 days 3/25/2022 3/27/2022 3/25
Installation钢架安装
1740 Skirting Tile Installation踢脚线 2 days 3/25/2022 3/26/2022 3/25
1741 Bathroom Wall and Floor Tile Installation墙和 3 days 3/25/2022 3/27/2022 3/25
地板瓷砖
1742 Wall Skim Coat墙 腻子 3 days 4/7/2022 4/9/2022 4/7
1743 Base of TV Back Drop 电视背景基层 4 days 4/13/2022 4/16/2022 4/13
1744 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/5/2022 4/7/2022 4/5
1745 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/8/2022 4/10/2022 4/8
1746 Ceiling Skim Coat 天花板腻子 3 days 4/13/2022 4/15/2022 4/13
1747 Door Frame 门框 2 days 4/12/2022 4/13/2022 4/12
1748 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/23/2022 4/25/2022 4/23
1749 Acrylic Installation 洗手台盘面+隔墙 3 days 5/1/2022 5/3/2022 5/1
1750 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/19/2022 4/21/2022 4/19
1751 Door Installation门安装+门扇 2 days 4/14/2022 4/15/2022 4/14
1752 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/22/2022 4/24/2022 4/22
1753 Wardrope 衣柜 3 days 4/22/2022 4/24/2022 4/22
1754 Illuminated Mirior 洗手台镜子 2 days 4/30/2022 5/1/2022 4/30
1755 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/5/2022 6/8/2022 6/5
Installation 卫生间五金和洁具
1756 Room 11-001-S2 77 days 3/24/2022 6/8/2022 3/24 Room 11-001-S2
1757 Setting ou放线 1 day 3/24/2022 3/24/2022 3/24
1758 Steel Frame (Toilet and Vanity Sink) 3 days 3/25/2022 3/27/2022 3/25
Installation钢架安装
1759 Skirting Tile Installation踢脚线 2 days 3/25/2022 3/26/2022 3/25
1760 Bathroom Wall and Floor Tile Installation墙和 3 days 3/25/2022 3/27/2022 3/25
地板瓷砖
1761 Wall Skim Coat墙 腻子 3 days 4/7/2022 4/9/2022 4/7
1762 Base of TV Back Drop 电视背景基层 4 days 4/13/2022 4/16/2022 4/13
1763 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/5/2022 4/7/2022 4/5
1764 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/8/2022 4/10/2022 4/8
1765 Ceiling Skim Coat 天花板腻子 3 days 4/13/2022 4/15/2022 4/13
1766 Door Frame 门框 2 days 4/12/2022 4/13/2022 4/12
1767 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/23/2022 4/25/2022 4/23
1768 Acrylic Installation 洗手台盘面+隔墙 3 days 5/1/2022 5/3/2022 5/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 46
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1769 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/19/2022 4/21/2022 4/19
1770 Door Installation门安装+门扇 2 days 4/14/2022 4/15/2022 4/14
1771 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/22/2022 4/24/2022 4/22
1772 Wardrope 衣柜 3 days 4/22/2022 4/24/2022 4/22
1773 Illuminated Mirior 洗手台镜子 2 days 4/30/2022 5/1/2022 4/30
1774 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/5/2022 6/8/2022 6/5
Installation 卫生间五金和洁具
1775 Room 11-003-S2 184 days11/18/20215/20/2022 11/18 Room 11-003-S2
1776 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1777 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1778 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1779 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1780 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1781 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1782 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1783 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1784 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1785 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1786 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1787 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1788 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1789 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1790 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1791 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1792 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1793 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1794 Room 11-004-S1 184 days11/18/20215/20/2022 11/18 Room 11-004-S1
1795 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1796 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1797 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1798 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1799 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1800 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1801 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1802 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1803 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1804 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 47
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1805 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1806 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1807 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1808 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1809 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1810 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1811 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1812 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1813 Room 11-005-S2b 184 days11/18/20215/20/2022 11/18 Room 11-005-S2b
1814 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1815 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1816 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1817 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1818 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1819 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1820 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1821 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1822 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1823 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1824 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1825 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1826 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1827 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1828 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1829 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1830 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1831 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1832 Room 11-006-S4 184 days11/18/20215/20/2022 11/18 Room 11-006-S4
1833 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1834 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1835 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1836 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1837 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1838 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1839 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1840 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 48
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1841 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1842 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1843 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1844 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1845 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1846 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1847 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1848 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1849 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1850 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1851 Room 11-007-S2 184 days11/18/20215/20/2022 11/18 Room 11-007-S2
1852 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1853 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1854 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1855 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1856 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1857 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1858 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1859 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1860 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1861 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1862 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1863 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1864 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1865 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1866 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1867 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1868 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1869 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1870 Room 11-008-S2 184 days11/18/20215/20/2022 11/18 Room 11-008-S2
1871 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1872 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1873 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1874 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1875 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1876 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 49
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1877 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1878 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1879 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1880 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1881 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1882 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1883 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1884 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1885 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1886 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1887 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1888 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1889 Room 11-009-S4 184 days11/18/20215/20/2022 11/18 Room 11-009-S4
1890 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1891 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1892 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1893 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1894 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1895 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1896 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1897 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1898 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1899 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1900 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1901 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1902 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1903 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1904 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1905 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1906 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1907 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1908 Room 11-010-S2 184 days11/18/20215/20/2022 11/18 Room 11-010-S2
1909 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1910 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1911 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1912 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 50
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1913 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1914 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1915 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1916 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1917 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1918 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1919 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1920 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1921 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1922 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1923 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1924 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1925 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1926 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1927 Room 11-011-S2 184 days11/18/20215/20/2022 11/18 Room 11-011-S2
1928 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1929 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1930 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1931 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1932 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1933 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1934 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1935 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1936 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1937 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1938 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1939 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1940 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1941 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1942 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1943 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1944 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1945 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1946 Room 11-012-S1 184 days11/18/20215/20/2022 11/18 Room 11-012-S1
1947 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1948 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1949 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 51
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1950 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1951 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1952 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1953 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1954 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1955 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1956 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1957 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1958 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1959 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1960 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1961 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1962 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1963 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1964 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1965 Room 11-013-S2b 184 days11/18/20215/20/2022 11/18 Room 11-013-S2b
1966 Setting ou放线 1 day 11/18/202111/18/2021 11/18
1967 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1968 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1969 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1970 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1971 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1972 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1973 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1974 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1975 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1976 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1977 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1978 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1979 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1980 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
1981 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
1982 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
1983 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
1984 Room 11-014-S2 184 days11/18/20215/20/2022 11/18 Room 11-014-S2
1985 Setting ou放线 1 day 11/18/202111/18/2021 11/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 52
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
1986 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
1987 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
1988 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
1989 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
1990 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
1991 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
1992 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
1993 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
1994 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
1995 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
1996 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
1997 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
1998 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
1999 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2000 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2001 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2002 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2003 CORRIDOR & LIFT LOBBY走道 130 days1/31/2022 6/9/2022 1/31 CORRIDOR & LIFT
2004 Acoustic Insulation Wall Installaltion 隔音墙 10 days 1/31/2022 2/9/2022 1/31
2005 Ceiling Frame Installation 吊顶龙安装 10 days 2/25/2022 3/6/2022 2/25
2006 Close ceiling and wallgypsum boards石膏板封闭5 days 3/7/2022 3/11/2022 3/7
2007 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/12/2022 3/18/2022 3/12
2008 Skirting Installation 踢脚线,木饰面 7 days 3/26/2022 4/1/2022 3/26
2009 Fire Proofing Door Framing Installation 防火门框7 days 3/17/2022 3/23/2022 3/17
2010 Painting on Ceiling 天花板油漆 6 days 4/9/2022 4/14/2022 4/9
2011 Fire Proofing Door Installation 防火门+门扇 3 days 5/4/2022 5/6/2022 5/4
2012 Wall Papers on Corridors wall &Installation of 6 days 5/10/2022 5/15/2022 5/10
glasses 墙壁纸+玻璃
2013 Carpet installation in corridor地毯 3 days 6/7/2022 6/9/2022 6/7
2014 ID Work level 12 精装修12层 204 days11/18/20216/9/2022 11/18 ID Work level 12 精
2015 Guest Room 204 days11/18/20216/9/2022 11/18 Guest Room
2016 Room 12-001-S2 77 days 3/24/2022 6/8/2022 3/24 Room 12-001-S2
2017 Setting ou放线 1 day 3/24/2022 3/24/2022 3/24
2018 Steel Frame (Toilet and Vanity Sink) 3 days 3/25/2022 3/27/2022 3/25
Installation钢架安装
2019 Skirting Tile Installation踢脚线 2 days 3/25/2022 3/26/2022 3/25
2020 Bathroom Wall and Floor Tile Installation墙和 3 days 3/25/2022 3/27/2022 3/25
地板瓷砖
2021 Wall Skim Coat墙 腻子 3 days 4/7/2022 4/9/2022 4/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 53
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2022 Base of TV Back Drop 电视背景基层 4 days 4/13/2022 4/16/2022 4/13
2023 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/5/2022 4/7/2022 4/5
2024 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/8/2022 4/10/2022 4/8
2025 Ceiling Skim Coat 天花板腻子 3 days 4/13/2022 4/15/2022 4/13
2026 Door Frame 门框 2 days 4/12/2022 4/13/2022 4/12
2027 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/23/2022 4/25/2022 4/23
2028 Acrylic Installation 洗手台盘面+隔墙 3 days 5/1/2022 5/3/2022 5/1
2029 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/19/2022 4/21/2022 4/19
2030 Door Installation门安装+门扇 2 days 4/14/2022 4/15/2022 4/14
2031 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/22/2022 4/24/2022 4/22
2032 Wardrope 衣柜 3 days 4/22/2022 4/24/2022 4/22
2033 Illuminated Mirior 洗手台镜子 2 days 4/30/2022 5/1/2022 4/30
2034 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/5/2022 6/8/2022 6/5
Installation 卫生间五金和洁具
2035 Room 12-001-S2 77 days 3/24/2022 6/8/2022 3/24 Room 12-001-S2
2036 Setting ou放线 1 day 3/24/2022 3/24/2022 3/24
2037 Steel Frame (Toilet and Vanity Sink) 3 days 3/25/2022 3/27/2022 3/25
Installation钢架安装
2038 Skirting Tile Installation踢脚线 2 days 3/25/2022 3/26/2022 3/25
2039 Bathroom Wall and Floor Tile Installation墙和 3 days 3/25/2022 3/27/2022 3/25
地板瓷砖
2040 Wall Skim Coat墙 腻子 3 days 4/7/2022 4/9/2022 4/7
2041 Base of TV Back Drop 电视背景基层 4 days 4/13/2022 4/16/2022 4/13
2042 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/5/2022 4/7/2022 4/5
2043 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/8/2022 4/10/2022 4/8
2044 Ceiling Skim Coat 天花板腻子 3 days 4/13/2022 4/15/2022 4/13
2045 Door Frame 门框 2 days 4/12/2022 4/13/2022 4/12
2046 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/23/2022 4/25/2022 4/23
2047 Acrylic Installation 洗手台盘面+隔墙 3 days 5/1/2022 5/3/2022 5/1
2048 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/19/2022 4/21/2022 4/19
2049 Door Installation门安装+门扇 2 days 4/14/2022 4/15/2022 4/14
2050 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/22/2022 4/24/2022 4/22
2051 Wardrope 衣柜 3 days 4/22/2022 4/24/2022 4/22
2052 Illuminated Mirior 洗手台镜子 2 days 4/30/2022 5/1/2022 4/30
2053 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/5/2022 6/8/2022 6/5
Installation 卫生间五金和洁具
2054 Room 12-003-S2 184 days11/18/20215/20/2022 11/18 Room 12-003-S2
2055 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2056 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2057 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 54
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2058 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2059 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2060 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2061 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2062 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2063 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2064 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2065 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2066 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2067 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2068 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2069 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2070 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2071 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2072 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2073 Room 12-004-S1 184 days11/18/20215/20/2022 11/18 Room 12-004-S1
2074 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2075 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2076 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2077 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2078 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2079 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2080 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2081 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2082 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2083 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2084 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2085 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2086 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2087 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2088 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2089 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2090 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2091 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2092 Room 12-005-S2b 184 days11/18/20215/20/2022 11/18 Room 12-005-S2b
2093 Setting ou放线 1 day 11/18/202111/18/2021 11/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 55
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2094 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2095 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2096 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2097 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2098 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2099 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2100 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2101 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2102 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2103 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2104 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2105 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2106 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2107 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2108 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2109 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2110 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2111 Room 12-006-S4 184 days11/18/20215/20/2022 11/18 Room 12-006-S4
2112 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2113 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2114 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2115 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2116 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2117 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2118 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2119 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2120 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2121 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2122 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2123 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2124 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2125 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2126 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2127 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2128 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2129 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 56
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2130 Room 12-007-S2 184 days11/18/20215/20/2022 11/18 Room 12-007-S2
2131 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2132 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2133 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2134 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2135 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2136 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2137 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2138 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2139 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2140 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2141 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2142 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2143 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2144 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2145 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2146 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2147 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2148 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2149 Room 12-008-S2 184 days11/18/20215/20/2022 11/18 Room 12-008-S2
2150 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2151 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2152 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2153 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2154 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2155 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2156 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2157 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2158 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2159 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2160 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2161 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2162 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2163 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2164 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2165 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2166 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 57
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2167 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2168 Room 12-009-S4 184 days11/18/20215/20/2022 11/18 Room 12-009-S4
2169 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2170 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2171 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2172 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2173 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2174 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2175 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2176 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2177 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2178 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2179 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2180 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2181 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2182 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2183 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2184 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2185 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2186 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2187 Room 12-010-S2 184 days11/18/20215/20/2022 11/18 Room 12-010-S2
2188 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2189 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2190 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2191 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2192 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2193 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2194 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2195 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2196 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2197 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2198 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2199 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2200 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2201 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2202 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 58
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2203 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2204 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2205 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2206 Room 12-011-S2 184 days11/18/20215/20/2022 11/18 Room 12-011-S2
2207 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2208 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2209 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2210 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2211 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2212 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2213 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2214 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2215 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2216 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2217 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2218 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2219 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2220 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2221 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2222 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2223 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2224 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2225 Room 12-012-S1 184 days11/18/20215/20/2022 11/18 Room 12-012-S1
2226 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2227 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2228 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2229 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2230 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2231 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2232 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2233 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2234 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2235 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2236 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2237 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2238 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 59
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2239 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2240 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2241 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2242 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2243 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2244 Room 12-013-S2b 184 days11/18/20215/20/2022 11/18 Room 12-013-S2b
2245 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2246 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2247 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2248 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2249 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2250 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2251 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2252 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2253 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2254 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2255 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10
2256 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2257 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2258 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2259 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2260 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2261 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2262 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2263 Room 12-014-S2 184 days11/18/20215/20/2022 11/18 Room 12-014-S2
2264 Setting ou放线 1 day 11/18/202111/18/2021 11/18
2265 Steel Frame (Toilet and Vanity Sink) 5 days 11/19/202111/23/2021 11/19
Installation钢架安装
2266 Skirting Tile Installation踢脚线 4 days 11/21/202111/24/2021 11/21
2267 Bathroom Wall and Floor Tile Installation墙和 7 days 12/8/2021 12/14/2021 12/8
地板瓷砖
2268 Wall Skim Coat墙 腻子 7 days 12/2/2021 12/8/2021 12/2
2269 Base of TV Back Drop 电视背景基层 7 days 12/22/202112/28/2021 12/22
2270 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/10/2022 2/14/2022 2/10
2271 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 2/15/2022 2/20/2022 2/15
2272 Ceiling Skim Coat 天花板腻子 6 days 2/23/2022 2/28/2022 2/23
2273 Door Frame 门框 5 days 2/15/2022 2/19/2022 2/15
2274 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/10/2022 2/16/2022 2/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 60
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2275 Acrylic Installation 洗手台盘面+隔墙 7 days 2/24/2022 3/2/2022 2/24
2276 Ceiling and Wall Paint 墙和天花板油漆 7 days 2/28/2022 3/6/2022 2/28
2277 Door Installation门安装+门扇 7 days 3/12/2022 3/18/2022 3/12
2278 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/17/2022 3/23/2022 3/17
2279 Wardrope 衣柜 7 days 3/19/2022 3/25/2022 3/19
2280 Illuminated Mirior 洗手台镜子 3 days 3/15/2022 3/17/2022 3/15
2281 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/11/2022 5/20/2022 5/11
Installation 卫生间五金和洁具
2282 CORRIDOR & LIFT LOBBY走道 130 days1/31/2022 6/9/2022 1/31 CORRIDOR & LIFT
2283 Acoustic Insulation Wall Installaltion 隔音墙 10 days 1/31/2022 2/9/2022 1/31
2284 Ceiling Frame Installation 吊顶龙安装 10 days 2/25/2022 3/6/2022 2/25
2285 Close ceiling and wallgypsum boards石膏板封闭5 days 3/7/2022 3/11/2022 3/7
2286 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/12/2022 3/18/2022 3/12
2287 Skirting Installation 踢脚线,木饰面 7 days 3/26/2022 4/1/2022 3/26
2288 Fire Proofing Door Framing Installation 防火门框7 days 3/17/2022 3/23/2022 3/17
2289 Painting on Ceiling 天花板油漆 6 days 4/9/2022 4/14/2022 4/9
2290 Fire Proofing Door Installation 防火门+门扇 3 days 5/4/2022 5/6/2022 5/4
2291 Wall Papers on Corridors wall &Installation of 6 days 5/10/2022 5/15/2022 5/10
glasses 墙壁纸+玻璃
2292 Carpet installation in corridor地毯 3 days 6/7/2022 6/9/2022 6/7
2293 ID Work level 13 精装修13层 201 days11/24/20216/12/2022 11/24 ID Work level 13
2294 Guest Room 193 days11/24/20216/4/2022 11/24 Guest Room
2295 Room 13-001-S2 74 days 3/23/2022 6/4/2022 3/23 Room 13-001-S2
2296 Setting ou放线 1 day 3/23/2022 3/23/2022 3/23
2297 Steel Frame (Toilet and Vanity Sink) 3 days 3/24/2022 3/26/2022 3/24
Installation钢架安装
2298 Skirting Tile Installation踢脚线 2 days 3/24/2022 3/25/2022 3/24
2299 Bathroom Wall and Floor Tile Installation墙和 3 days 3/24/2022 3/26/2022 3/24
地板瓷砖
2300 Wall Skim Coat墙 腻子 3 days 4/6/2022 4/8/2022 4/6
2301 Base of TV Back Drop 电视背景基层 4 days 4/12/2022 4/15/2022 4/12
2302 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/2/2022 4/4/2022 4/2
2303 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/5/2022 4/7/2022 4/5
2304 Ceiling Skim Coat 天花板腻子 3 days 4/10/2022 4/12/2022 4/10
2305 Door Frame 门框 2 days 4/10/2022 4/11/2022 4/10
2306 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/20/2022 4/22/2022 4/20
2307 Acrylic Installation 洗手台盘面+隔墙 3 days 4/28/2022 4/30/2022 4/28
2308 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/16/2022 4/18/2022 4/16
2309 Door Installation门安装+门扇 2 days 4/12/2022 4/13/2022 4/12
2310 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/19/2022 4/21/2022 4/19
2311 Wardrope 衣柜 3 days 4/19/2022 4/21/2022 4/19
2312 Illuminated Mirior 洗手台镜子 2 days 4/28/2022 4/29/2022 4/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 61
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2313 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/1/2022 6/4/2022 6/1
Installation 卫生间五金和洁具
2314 Room 13-002-S2 74 days 3/23/2022 6/4/2022 3/23 Room 13-002-S2
2315 Setting ou放线 1 day 3/23/2022 3/23/2022 3/23
2316 Steel Frame (Toilet and Vanity Sink) 3 days 3/24/2022 3/26/2022 3/24
Installation钢架安装
2317 Skirting Tile Installation踢脚线 2 days 3/24/2022 3/25/2022 3/24
2318 Bathroom Wall and Floor Tile Installation墙和 3 days 3/24/2022 3/26/2022 3/24
地板瓷砖
2319 Wall Skim Coat墙 腻子 3 days 4/6/2022 4/8/2022 4/6
2320 Base of TV Back Drop 电视背景基层 4 days 4/12/2022 4/15/2022 4/12
2321 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/2/2022 4/4/2022 4/2
2322 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/5/2022 4/7/2022 4/5
2323 Ceiling Skim Coat 天花板腻子 3 days 4/10/2022 4/12/2022 4/10
2324 Door Frame 门框 2 days 4/10/2022 4/11/2022 4/10
2325 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/20/2022 4/22/2022 4/20
2326 Acrylic Installation 洗手台盘面+隔墙 3 days 4/28/2022 4/30/2022 4/28
2327 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/16/2022 4/18/2022 4/16
2328 Door Installation门安装+门扇 2 days 4/12/2022 4/13/2022 4/12
2329 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/19/2022 4/21/2022 4/19
2330 Wardrope 衣柜 3 days 4/19/2022 4/21/2022 4/19
2331 Illuminated Mirior 洗手台镜子 2 days 4/28/2022 4/29/2022 4/28
2332 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/1/2022 6/4/2022 6/1
Installation 卫生间五金和洁具
2333 Room 13-003-S2 188 days11/24/20215/30/2022 11/24 Room 13-003-S2
2334 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2335 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2336 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2337 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2338 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2339 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2340 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2341 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2342 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2343 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2344 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2345 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2346 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2347 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2348 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 62
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2349 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2350 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2351 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2352 Room 13-004-S1 188 days11/24/20215/30/2022 11/24 Room 13-004-S1
2353 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2354 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2355 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2356 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2357 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2358 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2359 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2360 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2361 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2362 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2363 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2364 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2365 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2366 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2367 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2368 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2369 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2370 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2371 Room 13-005-S2b 188 days11/24/20215/30/2022 11/24 Room 13-005-S2b
2372 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2373 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2374 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2375 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2376 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2377 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2378 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2379 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2380 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2381 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2382 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2383 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2384 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 63
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2385 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2386 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2387 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2388 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2389 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2390 Room 13-006-S4 188 days11/24/20215/30/2022 11/24 Room 13-006-S4
2391 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2392 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2393 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2394 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2395 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2396 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2397 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2398 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2399 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2400 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2401 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2402 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2403 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2404 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2405 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2406 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2407 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2408 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2409 Room 13-007-S2 188 days11/24/20215/30/2022 11/24 Room 13-007-S2
2410 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2411 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2412 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2413 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2414 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2415 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2416 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2417 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2418 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2419 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2420 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 64
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2421 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2422 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2423 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2424 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2425 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2426 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2427 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2428 Room 13-008-S2 188 days11/24/20215/30/2022 11/24 Room 13-008-S2
2429 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2430 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2431 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2432 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2433 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2434 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2435 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2436 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2437 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2438 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2439 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2440 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2441 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2442 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2443 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2444 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2445 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2446 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2447 Room 13-009-S4 188 days11/24/20215/30/2022 11/24 Room 13-009-S4
2448 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2449 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2450 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2451 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2452 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2453 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2454 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2455 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2456 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 65
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2457 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2458 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2459 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2460 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2461 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2462 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2463 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2464 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2465 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2466 Room 13-010-S2 188 days11/24/20215/30/2022 11/24 Room 13-010-S2
2467 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2468 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2469 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2470 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2471 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2472 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2473 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2474 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2475 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2476 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2477 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2478 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2479 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2480 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2481 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2482 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2483 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2484 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2485 Room 13-011-S2 188 days11/24/20215/30/2022 11/24 Room 13-011-S2
2486 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2487 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2488 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2489 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2490 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2491 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2492 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 66
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2493 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2494 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2495 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2496 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2497 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2498 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2499 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2500 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2501 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2502 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2503 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2504 Room 13-012-S1 188 days11/24/20215/30/2022 11/24 Room 13-012-S1
2505 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2506 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2507 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2508 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2509 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2510 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2511 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2512 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2513 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2514 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2515 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2516 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2517 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2518 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2519 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2520 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2521 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2522 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2523 Room 13-013-S2b 188 days11/24/20215/30/2022 11/24 Room 13-013-S2b
2524 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2525 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2526 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2527 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2528 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 67
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2529 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2530 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2531 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2532 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2533 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2534 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2535 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2536 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2537 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2538 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2539 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2540 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2541 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2542 Room 13-014-S2 188 days11/24/20215/30/2022 11/24 Room 13-014-S2
2543 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2544 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2545 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2546 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2547 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2548 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2549 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2550 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2551 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2552 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2553 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2554 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2555 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2556 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2557 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2558 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2559 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2560 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2561 CORRIDOR & LIFT LOBBY走道 123 days2/10/2022 6/12/2022 2/10 CORRIDOR & LIF
2562 Acoustic Insulation Wall Installaltion 隔音墙 10 days 2/10/2022 2/19/2022 2/10
2563 Ceiling Frame Installation 吊顶龙安装 10 days 3/7/2022 3/16/2022 3/7
2564 Close ceiling and wallgypsum boards石膏板封闭 5 days 3/17/2022 3/21/2022 3/17
2565 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/22/2022 3/28/2022 3/22
2566 Skirting Installation 踢脚线,木饰面 7 days 4/2/2022 4/8/2022 4/2

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 68
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2567 Fire Proofing Door Framing Installation 防火门框 7 days 3/24/2022 3/30/2022 3/24
2568 Painting on Ceiling 天花板油漆 6 days 4/16/2022 4/21/2022 4/16
2569 Fire Proofing Door Installation 防火门+门扇 3 days 5/7/2022 5/9/2022 5/7
2570 Wall Papers on Corridors wall &Installation of 6 days 5/16/2022 5/21/2022 5/16
glasses 墙壁纸+玻璃
2571 Carpet installation in corridor地毯 3 days 6/10/2022 6/12/2022 6/10
2572 ID Work level 14 精装修14层 201 days11/24/20216/12/2022 11/24 ID Work level 14
2573 Guest Room 193 days11/24/20216/4/2022 11/24 Guest Room
2574 Room 14-001-S3 188 days11/24/20215/30/2022 11/24 Room 14-001-S3
2575 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2576 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2577 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2578 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2579 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2580 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2581 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2582 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2583 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2584 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2585 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2586 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2587 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2588 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2589 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2590 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2591 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2592 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2593 Room 14-002-S3 188 days11/24/20215/30/2022 11/24 Room 14-002-S3
2594 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2595 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2596 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2597 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2598 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2599 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2600 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2601 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2602 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 69
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2603 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2604 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2605 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2606 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2607 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2608 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2609 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2610 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2611 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2612 Room 14-003-S1 74 days 3/23/2022 6/4/2022 3/23 Room 14-003-S1
2613 Setting ou放线 1 day 3/23/2022 3/23/2022 3/23
2614 Steel Frame (Toilet and Vanity Sink) 3 days 3/24/2022 3/26/2022 3/24
Installation钢架安装
2615 Skirting Tile Installation踢脚线 2 days 3/24/2022 3/25/2022 3/24
2616 Bathroom Wall and Floor Tile Installation墙和 3 days 3/24/2022 3/26/2022 3/24
地板瓷砖
2617 Wall Skim Coat墙 腻子 3 days 4/6/2022 4/8/2022 4/6
2618 Base of TV Back Drop 电视背景基层 4 days 4/12/2022 4/15/2022 4/12
2619 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/2/2022 4/4/2022 4/2
2620 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/5/2022 4/7/2022 4/5
2621 Ceiling Skim Coat 天花板腻子 3 days 4/10/2022 4/12/2022 4/10
2622 Door Frame 门框 2 days 4/10/2022 4/11/2022 4/10
2623 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/20/2022 4/22/2022 4/20
2624 Acrylic Installation 洗手台盘面+隔墙 3 days 4/28/2022 4/30/2022 4/28
2625 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/16/2022 4/18/2022 4/16
2626 Door Installation门安装+门扇 2 days 4/12/2022 4/13/2022 4/12
2627 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/19/2022 4/21/2022 4/19
2628 Wardrope 衣柜 3 days 4/19/2022 4/21/2022 4/19
2629 Illuminated Mirior 洗手台镜子 2 days 4/28/2022 4/29/2022 4/28
2630 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/1/2022 6/4/2022 6/1
Installation 卫生间五金和洁具
2631 Room 14-004-S1 74 days 3/23/2022 6/4/2022 3/23 Room 14-004-S1
2632 Setting ou放线 1 day 3/23/2022 3/23/2022 3/23
2633 Steel Frame (Toilet and Vanity Sink) 3 days 3/24/2022 3/26/2022 3/24
Installation钢架安装
2634 Skirting Tile Installation踢脚线 2 days 3/24/2022 3/25/2022 3/24
2635 Bathroom Wall and Floor Tile Installation墙和 3 days 3/24/2022 3/26/2022 3/24
地板瓷砖
2636 Wall Skim Coat墙 腻子 3 days 4/6/2022 4/8/2022 4/6
2637 Base of TV Back Drop 电视背景基层 4 days 4/12/2022 4/15/2022 4/12
2638 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/2/2022 4/4/2022 4/2

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 70
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2639 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/5/2022 4/7/2022 4/5
2640 Ceiling Skim Coat 天花板腻子 3 days 4/10/2022 4/12/2022 4/10
2641 Door Frame 门框 2 days 4/10/2022 4/11/2022 4/10
2642 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/20/2022 4/22/2022 4/20
2643 Acrylic Installation 洗手台盘面+隔墙 3 days 4/28/2022 4/30/2022 4/28
2644 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/16/2022 4/18/2022 4/16
2645 Door Installation门安装+门扇 2 days 4/12/2022 4/13/2022 4/12
2646 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/19/2022 4/21/2022 4/19
2647 Wardrope 衣柜 3 days 4/19/2022 4/21/2022 4/19
2648 Illuminated Mirior 洗手台镜子 2 days 4/28/2022 4/29/2022 4/28
2649 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/1/2022 6/4/2022 6/1
Installation 卫生间五金和洁具
2650 Room 14-005-S1 188 days11/24/20215/30/2022 11/24 Room 14-005-S1
2651 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2652 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2653 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2654 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2655 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2656 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2657 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2658 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2659 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2660 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2661 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2662 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2663 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2664 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2665 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2666 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2667 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2668 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2669 Room 14-006-S1 188 days11/24/20215/30/2022 11/24 Room 14-006-S1
2670 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2671 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2672 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2673 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2674 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 71
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2675 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2676 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2677 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2678 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2679 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2680 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2681 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2682 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2683 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2684 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2685 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2686 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2687 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2688 Room 14-007-S1 188 days11/24/20215/30/2022 11/24 Room 14-007-S1
2689 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2690 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2691 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2692 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2693 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2694 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2695 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2696 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2697 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2698 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2699 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2700 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2701 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2702 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2703 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2704 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2705 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2706 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2707 Room 14-008-S4 188 days11/24/20215/30/2022 11/24 Room 14-008-S4
2708 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2709 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2710 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 72
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2711 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2712 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2713 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2714 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2715 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2716 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2717 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2718 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2719 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2720 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2721 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2722 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2723 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2724 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2725 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2726 Room 14-009-S1 188 days11/24/20215/30/2022 11/24 Room 14-009-S1
2727 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2728 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2729 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2730 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2731 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2732 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2733 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2734 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2735 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2736 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2737 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2738 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2739 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2740 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2741 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2742 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2743 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2744 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2745 Room 14-010-S1 188 days11/24/20215/30/2022 11/24 Room 14-010-S1
2746 Setting ou放线 1 day 11/24/202111/24/2021 11/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 73
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2747 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2748 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2749 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2750 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2751 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2752 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2753 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2754 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2755 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2756 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2757 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2758 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2759 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2760 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2761 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2762 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2763 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2764 Room 14-011-S4 188 days11/24/20215/30/2022 11/24 Room 14-011-S4
2765 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2766 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2767 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2768 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2769 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2770 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2771 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2772 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2773 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2774 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2775 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2776 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2777 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2778 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2779 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2780 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2781 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2782 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 74
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2783 Room 14-012-S1 188 days11/24/20215/30/2022 11/24 Room 14-012-S1
2784 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2785 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2786 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2787 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2788 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2789 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2790 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2791 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2792 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2793 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2794 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2795 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2796 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2797 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2798 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2799 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2800 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2801 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2802 Room 14-013-S1 188 days11/24/20215/30/2022 11/24 Room 14-013-S1
2803 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2804 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2805 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2806 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2807 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2808 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2809 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2810 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2811 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2812 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2813 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2814 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2815 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2816 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2817 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2818 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2819 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 75
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2820 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2821 Room 14-014-S1 188 days11/24/20215/30/2022 11/24 Room 14-014-S1
2822 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2823 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2824 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2825 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2826 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2827 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2828 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2829 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2830 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2831 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2832 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2833 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2834 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2835 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2836 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2837 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2838 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2839 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2840 Room 14-015-S2 188 days11/24/20215/30/2022 11/24 Room 14-015-S2
2841 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2842 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2843 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2844 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2845 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2846 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2847 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2848 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2849 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2850 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2851 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2852 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2853 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2854 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2855 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 76
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2856 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2857 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2858 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2859 Room 14-016-S1 188 days11/24/20215/30/2022 11/24 Room 14-016-S1
2860 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2861 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2862 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2863 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2864 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2865 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2866 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2867 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2868 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2869 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2870 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2871 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2872 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2873 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2874 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2875 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2876 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2877 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2878 CORRIDOR & LIFT LOBBY走道 123 days2/10/2022 6/12/2022 2/10 CORRIDOR & LIF
2879 Acoustic Insulation Wall Installaltion 隔音墙 10 days 2/10/2022 2/19/2022 2/10
2880 Ceiling Frame Installation 吊顶龙安装 10 days 3/7/2022 3/16/2022 3/7
2881 Close ceiling and wallgypsum boards石膏板封闭 5 days 3/17/2022 3/21/2022 3/17
2882 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/22/2022 3/28/2022 3/22
2883 Skirting Installation 踢脚线,木饰面 7 days 4/2/2022 4/8/2022 4/2
2884 Fire Proofing Door Framing Installation 防火门框 7 days 3/24/2022 3/30/2022 3/24
2885 Painting on Ceiling 天花板油漆 6 days 4/16/2022 4/21/2022 4/16
2886 Fire Proofing Door Installation 防火门+门扇 3 days 5/7/2022 5/9/2022 5/7
2887 Wall Papers on Corridors wall &Installation of 6 days 5/16/2022 5/21/2022 5/16
glasses 墙壁纸+玻璃
2888 Carpet installation in corridor地毯 3 days 6/10/2022 6/12/2022 6/10
2889 ID Work level 15 精装修15层 201 days11/24/20216/12/2022 11/24 ID Work level 15
2890 Guest Room 193 days11/24/20216/4/2022 11/24 Guest Room
2891 Room 15-001-S3 188 days11/24/20215/30/2022 11/24 Room 15-001-S3
2892 Setting ou放线 1 day 11/24/202111/24/2021 11/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 77
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2893 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2894 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2895 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2896 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2897 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2898 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2899 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2900 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2901 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2902 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2903 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2904 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2905 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2906 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2907 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2908 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2909 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2910 Room 15-002-S3 188 days11/24/20215/30/2022 11/24 Room 15-002-S3
2911 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2912 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2913 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2914 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2915 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2916 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2917 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2918 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2919 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2920 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2921 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2922 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2923 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2924 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2925 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2926 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2927 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2928 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 78
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2929 Room 15-003-S1 74 days 3/23/2022 6/4/2022 3/23 Room 15-003-S1
2930 Setting ou放线 1 day 3/23/2022 3/23/2022 3/23
2931 Steel Frame (Toilet and Vanity Sink) 3 days 3/24/2022 3/26/2022 3/24
Installation钢架安装
2932 Skirting Tile Installation踢脚线 2 days 3/24/2022 3/25/2022 3/24
2933 Bathroom Wall and Floor Tile Installation墙和 3 days 3/24/2022 3/26/2022 3/24
地板瓷砖
2934 Wall Skim Coat墙 腻子 3 days 4/6/2022 4/8/2022 4/6
2935 Base of TV Back Drop 电视背景基层 4 days 4/12/2022 4/15/2022 4/12
2936 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/2/2022 4/4/2022 4/2
2937 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/5/2022 4/7/2022 4/5
2938 Ceiling Skim Coat 天花板腻子 3 days 4/10/2022 4/12/2022 4/10
2939 Door Frame 门框 2 days 4/10/2022 4/11/2022 4/10
2940 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/20/2022 4/22/2022 4/20
2941 Acrylic Installation 洗手台盘面+隔墙 3 days 4/28/2022 4/30/2022 4/28
2942 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/16/2022 4/18/2022 4/16
2943 Door Installation门安装+门扇 2 days 4/12/2022 4/13/2022 4/12
2944 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/19/2022 4/21/2022 4/19
2945 Wardrope 衣柜 3 days 4/19/2022 4/21/2022 4/19
2946 Illuminated Mirior 洗手台镜子 2 days 4/28/2022 4/29/2022 4/28
2947 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/1/2022 6/4/2022 6/1
Installation 卫生间五金和洁具
2948 Room 15-003-S1 74 days 3/23/2022 6/4/2022 3/23 Room 15-003-S1
2949 Setting ou放线 1 day 3/23/2022 3/23/2022 3/23
2950 Steel Frame (Toilet and Vanity Sink) 3 days 3/24/2022 3/26/2022 3/24
Installation钢架安装
2951 Skirting Tile Installation踢脚线 2 days 3/24/2022 3/25/2022 3/24
2952 Bathroom Wall and Floor Tile Installation墙和 3 days 3/24/2022 3/26/2022 3/24
地板瓷砖
2953 Wall Skim Coat墙 腻子 3 days 4/6/2022 4/8/2022 4/6
2954 Base of TV Back Drop 电视背景基层 4 days 4/12/2022 4/15/2022 4/12
2955 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 4/2/2022 4/4/2022 4/2
2956 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/5/2022 4/7/2022 4/5
2957 Ceiling Skim Coat 天花板腻子 3 days 4/10/2022 4/12/2022 4/10
2958 Door Frame 门框 2 days 4/10/2022 4/11/2022 4/10
2959 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/20/2022 4/22/2022 4/20
2960 Acrylic Installation 洗手台盘面+隔墙 3 days 4/28/2022 4/30/2022 4/28
2961 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/16/2022 4/18/2022 4/16
2962 Door Installation门安装+门扇 2 days 4/12/2022 4/13/2022 4/12
2963 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/19/2022 4/21/2022 4/19
2964 Wardrope 衣柜 3 days 4/19/2022 4/21/2022 4/19
2965 Illuminated Mirior 洗手台镜子 2 days 4/28/2022 4/29/2022 4/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 79
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
2966 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 6/1/2022 6/4/2022 6/1
Installation 卫生间五金和洁具
2967 Room 15-007-S1 188 days11/24/20215/30/2022 11/24 Room 15-007-S1
2968 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2969 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2970 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2971 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2972 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2973 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2974 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2975 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2976 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2977 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2978 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2979 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2980 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
2981 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
2982 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
2983 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
2984 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
2985 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
2986 Room 15-005-S1 188 days11/24/20215/30/2022 11/24 Room 15-005-S1
2987 Setting ou放线 1 day 11/24/202111/24/2021 11/24
2988 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
2989 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
2990 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
2991 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
2992 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
2993 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
2994 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
2995 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
2996 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
2997 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
2998 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
2999 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3000 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3001 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 80
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3002 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3003 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3004 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3005 Room 15-006-S1 188 days11/24/20215/30/2022 11/24 Room 15-006-S1
3006 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3007 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3008 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3009 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3010 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3011 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3012 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3013 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3014 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3015 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3016 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3017 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3018 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3019 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3020 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3021 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3022 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3023 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3024 Room 15-008-S4 188 days11/24/20215/30/2022 11/24 Room 15-008-S4
3025 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3026 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3027 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3028 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3029 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3030 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3031 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3032 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3033 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3034 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3035 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3036 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3037 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 81
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3038 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3039 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3040 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3041 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3042 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3043 Room 15-009-S1 188 days11/24/20215/30/2022 11/24 Room 15-009-S1
3044 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3045 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3046 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3047 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3048 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3049 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3050 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3051 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3052 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3053 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3054 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3055 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3056 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3057 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3058 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3059 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3060 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3061 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3062 Room 15-010-S1 188 days11/24/20215/30/2022 11/24 Room 15-010-S1
3063 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3064 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3065 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3066 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3067 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3068 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3069 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3070 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3071 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3072 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3073 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 82
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3074 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3075 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3076 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3077 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3078 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3079 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3080 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3081 Room 15-011-S4 188 days11/24/20215/30/2022 11/24 Room 15-011-S4
3082 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3083 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3084 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3085 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3086 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3087 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3088 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3089 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3090 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3091 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3092 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3093 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3094 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3095 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3096 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3097 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3098 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3099 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3100 Room 15-012-S1 188 days11/24/20215/30/2022 11/24 Room 15-012-S1
3101 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3102 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3103 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3104 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3105 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3106 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3107 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3108 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3109 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 83
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3110 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3111 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3112 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3113 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3114 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3115 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3116 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3117 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3118 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3119 Room 15-013-S1 188 days11/24/20215/30/2022 11/24 Room 15-013-S1
3120 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3121 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3122 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3123 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3124 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3125 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3126 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3127 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3128 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3129 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3130 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3131 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3132 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3133 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3134 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3135 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3136 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3137 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3138 Room 15-014-S1 188 days11/24/20215/30/2022 11/24 Room 15-014-S1
3139 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3140 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3141 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3142 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3143 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3144 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3145 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 84
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3146 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3147 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3148 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3149 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3150 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3151 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3152 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3153 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3154 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3155 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3156 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3157 Room 15-015-S2 188 days11/24/20215/30/2022 11/24 Room 15-015-S2
3158 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3159 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3160 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3161 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3162 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9
3163 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3164 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3165 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3166 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3167 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3168 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3169 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3170 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3171 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3172 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3173 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3174 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3175 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3176 Room 15-016-S1 188 days11/24/20215/30/2022 11/24 Room 15-016-S1
3177 Setting ou放线 1 day 11/24/202111/24/2021 11/24
3178 Steel Frame (Toilet and Vanity Sink) 5 days 11/25/202111/29/2021 11/25
Installation钢架安装
3179 Skirting Tile Installation踢脚线 4 days 11/27/202111/30/2021 11/27
3180 Bathroom Wall and Floor Tile Installation墙和 7 days 12/15/202112/21/2021 12/15
地板瓷砖
3181 Wall Skim Coat墙 腻子 7 days 12/9/2021 12/15/2021 12/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 85
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3182 Base of TV Back Drop 电视背景基层 7 days 12/29/20211/4/2022 12/29
3183 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 2/26/2022 3/2/2022 2/26
3184 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/3/2022 3/8/2022 3/3
3185 Ceiling Skim Coat 天花板腻子 6 days 3/11/2022 3/16/2022 3/11
3186 Door Frame 门框 5 days 2/20/2022 2/24/2022 2/20
3187 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/17/2022 2/23/2022 2/17
3188 Acrylic Installation 洗手台盘面+隔墙 7 days 3/3/2022 3/9/2022 3/3
3189 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/7/2022 3/13/2022 3/7
3190 Door Installation门安装+门扇 7 days 3/19/2022 3/25/2022 3/19
3191 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/24/2022 3/30/2022 3/24
3192 Wardrope 衣柜 7 days 3/26/2022 4/1/2022 3/26
3193 Illuminated Mirior 洗手台镜子 3 days 3/18/2022 3/20/2022 3/18
3194 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/21/2022 5/30/2022 5/21
Installation 卫生间五金和洁具
3195 CORRIDOR & LIFT LOBBY走道 123 days2/10/2022 6/12/2022 2/10 CORRIDOR & LIF
3196 Acoustic Insulation Wall Installaltion 隔音墙 10 days 2/10/2022 2/19/2022 2/10
3197 Ceiling Frame Installation 吊顶龙安装 10 days 3/7/2022 3/16/2022 3/7
3198 Close ceiling and wallgypsum boards石膏板封闭 5 days 3/17/2022 3/21/2022 3/17
3199 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 3/22/2022 3/28/2022 3/22
3200 Skirting Installation 踢脚线,木饰面 7 days 4/2/2022 4/8/2022 4/2
3201 Fire Proofing Door Framing Installation 防火门框 7 days 3/24/2022 3/30/2022 3/24
3202 Painting on Ceiling 天花板油漆 6 days 4/16/2022 4/21/2022 4/16
3203 Fire Proofing Door Installation 防火门+门扇 3 days 5/7/2022 5/9/2022 5/7
3204 Wall Papers on Corridors wall &Installation of 6 days 5/16/2022 5/21/2022 5/16
glasses 墙壁纸+玻璃
3205 Carpet installation in corridor地毯 3 days 6/10/2022 6/12/2022 6/10
3206 ID Work level 16 精装修16层 198 days11/30/20216/15/2022 11/30 ID Work level 16
3207 Guest Room 192 days11/30/20216/9/2022 11/30 Guest Room
3208 Room 16-001-S3 192 days11/30/20216/9/2022 11/30 Room 16-001-S3
3209 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3210 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3211 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3212 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3213 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3214 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3215 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3216 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3217 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3218 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3219 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 86
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3220 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3221 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3222 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3223 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3224 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3225 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3226 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3227 Room 16-002-S3 192 days11/30/20216/9/2022 11/30 Room 16-002-S3
3228 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3229 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3230 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3231 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3232 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3233 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3234 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3235 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3236 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3237 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3238 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3239 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3240 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3241 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3242 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3243 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3244 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3245 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3246 Room 16-003-S1 71 days 3/22/2022 5/31/2022 3/22 Room 16-003-S1
3247 Setting ou放线 1 day 3/22/2022 3/22/2022 3/22
3248 Steel Frame (Toilet and Vanity Sink) 3 days 3/23/2022 3/25/2022 3/23
Installation钢架安装
3249 Skirting Tile Installation踢脚线 2 days 3/23/2022 3/24/2022 3/23
3250 Bathroom Wall and Floor Tile Installation墙和 3 days 3/23/2022 3/25/2022 3/23
地板瓷砖
3251 Wall Skim Coat墙 腻子 3 days 4/5/2022 4/7/2022 4/5
3252 Base of TV Back Drop 电视背景基层 4 days 4/11/2022 4/14/2022 4/11
3253 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/30/2022 4/1/2022 3/30
3254 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/2/2022 4/4/2022 4/2
3255 Ceiling Skim Coat 天花板腻子 3 days 4/7/2022 4/9/2022 4/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 87
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3256 Door Frame 门框 2 days 4/8/2022 4/9/2022 4/8
3257 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/17/2022 4/19/2022 4/17
3258 Acrylic Installation 洗手台盘面+隔墙 3 days 4/25/2022 4/27/2022 4/25
3259 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/13/2022 4/15/2022 4/13
3260 Door Installation门安装+门扇 2 days 4/10/2022 4/11/2022 4/10
3261 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/16/2022 4/18/2022 4/16
3262 Wardrope 衣柜 3 days 4/16/2022 4/18/2022 4/16
3263 Illuminated Mirior 洗手台镜子 2 days 4/26/2022 4/27/2022 4/26
3264 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/28/2022 5/31/2022 5/28
Installation 卫生间五金和洁具
3265 Room 16-004-S1 71 days 3/22/2022 5/31/2022 3/22 Room 16-004-S1
3266 Setting ou放线 1 day 3/22/2022 3/22/2022 3/22
3267 Steel Frame (Toilet and Vanity Sink) 3 days 3/23/2022 3/25/2022 3/23
Installation钢架安装
3268 Skirting Tile Installation踢脚线 2 days 3/23/2022 3/24/2022 3/23
3269 Bathroom Wall and Floor Tile Installation墙和 3 days 3/23/2022 3/25/2022 3/23
地板瓷砖
3270 Wall Skim Coat墙 腻子 3 days 4/5/2022 4/7/2022 4/5
3271 Base of TV Back Drop 电视背景基层 4 days 4/11/2022 4/14/2022 4/11
3272 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/30/2022 4/1/2022 3/30
3273 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/2/2022 4/4/2022 4/2
3274 Ceiling Skim Coat 天花板腻子 3 days 4/7/2022 4/9/2022 4/7
3275 Door Frame 门框 2 days 4/8/2022 4/9/2022 4/8
3276 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/17/2022 4/19/2022 4/17
3277 Acrylic Installation 洗手台盘面+隔墙 3 days 4/25/2022 4/27/2022 4/25
3278 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/13/2022 4/15/2022 4/13
3279 Door Installation门安装+门扇 2 days 4/10/2022 4/11/2022 4/10
3280 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/16/2022 4/18/2022 4/16
3281 Wardrope 衣柜 3 days 4/16/2022 4/18/2022 4/16
3282 Illuminated Mirior 洗手台镜子 2 days 4/26/2022 4/27/2022 4/26
3283 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/28/2022 5/31/2022 5/28
Installation 卫生间五金和洁具
3284 Room 16-005-S1 192 days11/30/20216/9/2022 11/30 Room 16-005-S1
3285 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3286 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3287 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3288 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3289 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3290 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3291 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 88
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3292 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3293 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3294 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3295 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3296 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3297 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3298 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3299 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3300 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3301 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3302 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3303 Room 16-006-S1 192 days11/30/20216/9/2022 11/30 Room 16-006-S1
3304 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3305 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3306 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3307 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3308 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3309 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3310 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3311 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3312 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3313 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3314 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3315 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3316 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3317 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3318 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3319 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3320 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3321 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3322 Room 16-007-S1 192 days11/30/20216/9/2022 11/30 Room 16-007-S1
3323 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3324 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3325 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3326 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3327 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 89
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3328 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3329 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3330 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3331 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3332 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3333 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3334 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3335 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3336 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3337 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3338 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3339 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3340 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3341 Room 16-008-S4 192 days11/30/20216/9/2022 11/30 Room 16-008-S4
3342 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3343 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3344 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3345 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3346 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3347 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3348 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3349 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3350 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3351 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3352 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3353 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3354 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3355 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3356 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3357 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3358 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3359 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3360 Room 16-009-S1 192 days11/30/20216/9/2022 11/30 Room 16-009-S1
3361 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3362 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3363 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 90
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3364 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3365 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3366 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3367 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3368 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3369 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3370 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3371 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3372 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3373 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3374 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3375 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3376 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3377 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3378 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3379 Room 16-010-S1 192 days11/30/20216/9/2022 11/30 Room 16-010-S1
3380 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3381 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3382 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3383 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3384 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3385 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3386 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3387 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3388 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3389 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3390 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3391 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3392 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3393 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3394 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3395 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3396 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3397 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3398 Room 16-011-S4 192 days11/30/20216/9/2022 11/30 Room 16-011-S4
3399 Setting ou放线 1 day 11/30/202111/30/2021 11/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 91
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3400 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3401 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3402 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3403 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3404 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3405 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3406 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3407 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3408 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3409 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3410 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3411 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3412 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3413 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3414 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3415 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3416 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3417 Room 16-012-S1 192 days11/30/20216/9/2022 11/30 Room 16-012-S1
3418 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3419 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3420 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3421 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3422 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3423 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3424 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3425 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3426 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3427 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3428 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3429 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3430 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3431 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3432 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3433 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3434 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3435 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 92
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3436 Room 16-013-S1 192 days11/30/20216/9/2022 11/30 Room 16-013-S1
3437 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3438 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3439 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3440 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3441 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3442 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3443 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3444 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3445 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3446 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3447 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3448 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3449 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3450 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3451 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3452 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3453 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3454 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3455 Room 16-014-S1 192 days11/30/20216/9/2022 11/30 Room 16-014-S1
3456 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3457 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3458 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3459 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3460 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3461 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3462 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3463 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3464 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3465 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3466 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3467 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3468 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3469 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3470 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3471 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3472 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 93
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3473 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3474 Room 16-015-S2 192 days11/30/20216/9/2022 11/30 Room 16-015-S2
3475 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3476 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3477 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3478 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3479 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3480 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3481 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3482 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3483 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3484 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3485 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3486 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3487 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3488 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3489 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3490 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3491 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3492 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3493 Room 16-016-S1 192 days11/30/20216/9/2022 11/30 Room 16-016-S1
3494 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3495 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3496 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3497 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3498 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3499 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3500 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3501 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3502 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3503 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3504 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3505 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3506 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3507 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3508 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 94
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3509 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3510 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3511 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3512 CORRIDOR & LIFT LOBBY走道 116 days2/20/2022 6/15/2022 2/20 CORRIDOR & LIF
3513 Acoustic Insulation Wall Installaltion 隔音墙 10 days 2/20/2022 3/1/2022 2/20
3514 Ceiling Frame Installation 吊顶龙安装 10 days 3/17/2022 3/26/2022 3/17
3515 Close ceiling and wallgypsum boards石膏板封闭 5 days 3/27/2022 3/31/2022 3/27
3516 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/1/2022 4/7/2022 4/1
3517 Skirting Installation 踢脚线,木饰面 7 days 4/9/2022 4/15/2022 4/9
3518 Fire Proofing Door Framing Installation 防火门框 7 days 3/31/2022 4/6/2022 3/31
3519 Painting on Ceiling 天花板油漆 6 days 4/23/2022 4/28/2022 4/23
3520 Fire Proofing Door Installation 防火门+门扇 3 days 5/10/2022 5/12/2022 5/10
3521 Wall Papers on Corridors wall &Installation of 6 days 5/22/2022 5/27/2022 5/22
glasses 墙壁纸+玻璃
3522 Carpet installation in corridor地毯 3 days 6/13/2022 6/15/2022 6/13
3523 ID Work level 17 精装修17层 198 days11/30/20216/15/2022 11/30 ID Work level 17
3524 Guest Room 192 days11/30/20216/9/2022 11/30 Guest Room
3525 Room 17-001-S3 192 days11/30/20216/9/2022 11/30 Room 17-001-S3
3526 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3527 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3528 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3529 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3530 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3531 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3532 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3533 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3534 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3535 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3536 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3537 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3538 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3539 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3540 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3541 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3542 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3543 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3544 Room 17-002-S3 192 days11/30/20216/9/2022 11/30 Room 17-002-S3
3545 Setting ou放线 1 day 11/30/202111/30/2021 11/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 95
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3546 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3547 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3548 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3549 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3550 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3551 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3552 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3553 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3554 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3555 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3556 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3557 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3558 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3559 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3560 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3561 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3562 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3563 Room 17-003-S1 71 days 3/22/2022 5/31/2022 3/22 Room 17-003-S1
3564 Setting ou放线 1 day 3/22/2022 3/22/2022 3/22
3565 Steel Frame (Toilet and Vanity Sink) 3 days 3/23/2022 3/25/2022 3/23
Installation钢架安装
3566 Skirting Tile Installation踢脚线 2 days 3/23/2022 3/24/2022 3/23
3567 Bathroom Wall and Floor Tile Installation墙和 3 days 3/23/2022 3/25/2022 3/23
地板瓷砖
3568 Wall Skim Coat墙 腻子 3 days 4/5/2022 4/7/2022 4/5
3569 Base of TV Back Drop 电视背景基层 4 days 4/11/2022 4/14/2022 4/11
3570 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/30/2022 4/1/2022 3/30
3571 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/2/2022 4/4/2022 4/2
3572 Ceiling Skim Coat 天花板腻子 3 days 4/7/2022 4/9/2022 4/7
3573 Door Frame 门框 2 days 4/8/2022 4/9/2022 4/8
3574 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/17/2022 4/19/2022 4/17
3575 Acrylic Installation 洗手台盘面+隔墙 3 days 4/25/2022 4/27/2022 4/25
3576 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/13/2022 4/15/2022 4/13
3577 Door Installation门安装+门扇 2 days 4/10/2022 4/11/2022 4/10
3578 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/16/2022 4/18/2022 4/16
3579 Wardrope 衣柜 3 days 4/16/2022 4/18/2022 4/16
3580 Illuminated Mirior 洗手台镜子 2 days 4/26/2022 4/27/2022 4/26
3581 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/28/2022 5/31/2022 5/28
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 96
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3582 Room 17-004-S1 71 days 3/22/2022 5/31/2022 3/22 Room 17-004-S1
3583 Setting ou放线 1 day 3/22/2022 3/22/2022 3/22
3584 Steel Frame (Toilet and Vanity Sink) 3 days 3/23/2022 3/25/2022 3/23
Installation钢架安装
3585 Skirting Tile Installation踢脚线 2 days 3/23/2022 3/24/2022 3/23
3586 Bathroom Wall and Floor Tile Installation墙和 3 days 3/23/2022 3/25/2022 3/23
地板瓷砖
3587 Wall Skim Coat墙 腻子 3 days 4/5/2022 4/7/2022 4/5
3588 Base of TV Back Drop 电视背景基层 4 days 4/11/2022 4/14/2022 4/11
3589 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/30/2022 4/1/2022 3/30
3590 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/2/2022 4/4/2022 4/2
3591 Ceiling Skim Coat 天花板腻子 3 days 4/7/2022 4/9/2022 4/7
3592 Door Frame 门框 2 days 4/8/2022 4/9/2022 4/8
3593 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/17/2022 4/19/2022 4/17
3594 Acrylic Installation 洗手台盘面+隔墙 3 days 4/25/2022 4/27/2022 4/25
3595 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/13/2022 4/15/2022 4/13
3596 Door Installation门安装+门扇 2 days 4/10/2022 4/11/2022 4/10
3597 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/16/2022 4/18/2022 4/16
3598 Wardrope 衣柜 3 days 4/16/2022 4/18/2022 4/16
3599 Illuminated Mirior 洗手台镜子 2 days 4/26/2022 4/27/2022 4/26
3600 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/28/2022 5/31/2022 5/28
Installation 卫生间五金和洁具
3601 Room 17-005-S1 192 days11/30/20216/9/2022 11/30 Room 17-005-S1
3602 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3603 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3604 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3605 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3606 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3607 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3608 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3609 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3610 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3611 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3612 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3613 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3614 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3615 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3616 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3617 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3618 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 97
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3619 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3620 Room 17-006-S1 192 days11/30/20216/9/2022 11/30 Room 17-006-S1
3621 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3622 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3623 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3624 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3625 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3626 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3627 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3628 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3629 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3630 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3631 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3632 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3633 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3634 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3635 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3636 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3637 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3638 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3639 Room 17-007-S1 192 days11/30/20216/9/2022 11/30 Room 17-007-S1
3640 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3641 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3642 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3643 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3644 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3645 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3646 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3647 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3648 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3649 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3650 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3651 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3652 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3653 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3654 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 98
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3655 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3656 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3657 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3658 Room 17-008-S4 192 days11/30/20216/9/2022 11/30 Room 17-008-S4
3659 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3660 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3661 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3662 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3663 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3664 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3665 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3666 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3667 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3668 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3669 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3670 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3671 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3672 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3673 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3674 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3675 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3676 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3677 Room 17-009-S1 192 days11/30/20216/9/2022 11/30 Room 17-009-S1
3678 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3679 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3680 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3681 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3682 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3683 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3684 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3685 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3686 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3687 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3688 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3689 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3690 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 99
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3691 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3692 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3693 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3694 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3695 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3696 Room 17-010-S1 192 days11/30/20216/9/2022 11/30 Room 17-010-S1
3697 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3698 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3699 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3700 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3701 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3702 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3703 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3704 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3705 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3706 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3707 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3708 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3709 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3710 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3711 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3712 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3713 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3714 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3715 Room 17-011-S4 192 days11/30/20216/9/2022 11/30 Room 17-011-S4
3716 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3717 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3718 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3719 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3720 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3721 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3722 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3723 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3724 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3725 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3726 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 100
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3727 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3728 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3729 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3730 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3731 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3732 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3733 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3734 Room 17-012-S1 192 days11/30/20216/9/2022 11/30 Room 17-012-S1
3735 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3736 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3737 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3738 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3739 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3740 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3741 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3742 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3743 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3744 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3745 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3746 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3747 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3748 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3749 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3750 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3751 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3752 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3753 Room 17-013-S1 192 days11/30/20216/9/2022 11/30 Room 17-013-S1
3754 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3755 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3756 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3757 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3758 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3759 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3760 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3761 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3762 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 101
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3763 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3764 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3765 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3766 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3767 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3768 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3769 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3770 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3771 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3772 Room 17-014-S1 192 days11/30/20216/9/2022 11/30 Room 17-014-S1
3773 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3774 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3775 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3776 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3777 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3778 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3779 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3780 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3781 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3782 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3783 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3784 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3785 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3786 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3787 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3788 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3789 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3790 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3791 Room 17-015-S2 192 days11/30/20216/9/2022 11/30 Room 17-015-S2
3792 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3793 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3794 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3795 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3796 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3797 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3798 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 102
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3799 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3800 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3801 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3802 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3803 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3804 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3805 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3806 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3807 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3808 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3809 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3810 Room 17-016-S1 192 days11/30/20216/9/2022 11/30 Room 17-016-S1
3811 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3812 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3813 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3814 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3815 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3816 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3817 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3818 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3819 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3820 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3821 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3822 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3823 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3824 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3825 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3826 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3827 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3828 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3829 CORRIDOR & LIFT LOBBY走道 116 days2/20/2022 6/15/2022 2/20 CORRIDOR & LIF
3830 Acoustic Insulation Wall Installaltion 隔音墙 10 days 2/20/2022 3/1/2022 2/20
3831 Ceiling Frame Installation 吊顶龙安装 10 days 3/17/2022 3/26/2022 3/17
3832 Close ceiling and wallgypsum boards石膏板封闭 5 days 3/27/2022 3/31/2022 3/27
3833 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/1/2022 4/7/2022 4/1
3834 Skirting Installation 踢脚线,木饰面 7 days 4/9/2022 4/15/2022 4/9
3835 Fire Proofing Door Framing Installation 防火门框 7 days 3/31/2022 4/6/2022 3/31
3836 Painting on Ceiling 天花板油漆 6 days 4/23/2022 4/28/2022 4/23

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 103
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3837 Fire Proofing Door Installation 防火门+门扇 3 days 5/10/2022 5/12/2022 5/10
3838 Wall Papers on Corridors wall &Installation of 6 days 5/22/2022 5/27/2022 5/22
glasses 墙壁纸+玻璃
3839 Carpet installation in corridor地毯 3 days 6/13/2022 6/15/2022 6/13
3840 ID Work level 18 精装修18层 198 days11/30/20216/15/2022 11/30 ID Work level 18
3841 Guest Room 192 days11/30/20216/9/2022 11/30 Guest Room
3842 Room 18-001-S3 192 days11/30/20216/9/2022 11/30 Room 18-001-S3
3843 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3844 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3845 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3846 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3847 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3848 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3849 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3850 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3851 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3852 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3853 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3854 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3855 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3856 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3857 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3858 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3859 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3860 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3861 Room 18-002-S3 192 days11/30/20216/9/2022 11/30 Room 18-002-S3
3862 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3863 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3864 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3865 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3866 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3867 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3868 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3869 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3870 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3871 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3872 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 104
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3873 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3874 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3875 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3876 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3877 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3878 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3879 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3880 Room 18-003-S1 71 days 3/22/2022 5/31/2022 3/22 Room 18-003-S1
3881 Setting ou放线 1 day 3/22/2022 3/22/2022 3/22
3882 Steel Frame (Toilet and Vanity Sink) 3 days 3/23/2022 3/25/2022 3/23
Installation钢架安装
3883 Skirting Tile Installation踢脚线 2 days 3/23/2022 3/24/2022 3/23
3884 Bathroom Wall and Floor Tile Installation墙和 3 days 3/23/2022 3/25/2022 3/23
地板瓷砖
3885 Wall Skim Coat墙 腻子 3 days 4/5/2022 4/7/2022 4/5
3886 Base of TV Back Drop 电视背景基层 4 days 4/11/2022 4/14/2022 4/11
3887 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/30/2022 4/1/2022 3/30
3888 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/2/2022 4/4/2022 4/2
3889 Ceiling Skim Coat 天花板腻子 3 days 4/7/2022 4/9/2022 4/7
3890 Door Frame 门框 2 days 4/8/2022 4/9/2022 4/8
3891 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/17/2022 4/19/2022 4/17
3892 Acrylic Installation 洗手台盘面+隔墙 3 days 4/25/2022 4/27/2022 4/25
3893 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/13/2022 4/15/2022 4/13
3894 Door Installation门安装+门扇 2 days 4/10/2022 4/11/2022 4/10
3895 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/16/2022 4/18/2022 4/16
3896 Wardrope 衣柜 3 days 4/16/2022 4/18/2022 4/16
3897 Illuminated Mirior 洗手台镜子 2 days 4/26/2022 4/27/2022 4/26
3898 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/28/2022 5/31/2022 5/28
Installation 卫生间五金和洁具
3899 Room 18-004-S1 71 days 3/22/2022 5/31/2022 3/22 Room 18-004-S1
3900 Setting ou放线 1 day 3/22/2022 3/22/2022 3/22
3901 Steel Frame (Toilet and Vanity Sink) 3 days 3/23/2022 3/25/2022 3/23
Installation钢架安装
3902 Skirting Tile Installation踢脚线 2 days 3/23/2022 3/24/2022 3/23
3903 Bathroom Wall and Floor Tile Installation墙和 3 days 3/23/2022 3/25/2022 3/23
地板瓷砖
3904 Wall Skim Coat墙 腻子 3 days 4/5/2022 4/7/2022 4/5
3905 Base of TV Back Drop 电视背景基层 4 days 4/11/2022 4/14/2022 4/11
3906 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/30/2022 4/1/2022 3/30
3907 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 4/2/2022 4/4/2022 4/2
3908 Ceiling Skim Coat 天花板腻子 3 days 4/7/2022 4/9/2022 4/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 105
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3909 Door Frame 门框 2 days 4/8/2022 4/9/2022 4/8
3910 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/17/2022 4/19/2022 4/17
3911 Acrylic Installation 洗手台盘面+隔墙 3 days 4/25/2022 4/27/2022 4/25
3912 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/13/2022 4/15/2022 4/13
3913 Door Installation门安装+门扇 2 days 4/10/2022 4/11/2022 4/10
3914 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/16/2022 4/18/2022 4/16
3915 Wardrope 衣柜 3 days 4/16/2022 4/18/2022 4/16
3916 Illuminated Mirior 洗手台镜子 2 days 4/26/2022 4/27/2022 4/26
3917 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/28/2022 5/31/2022 5/28
Installation 卫生间五金和洁具
3918 Room 18-005-S1 192 days11/30/20216/9/2022 11/30 Room 18-005-S1
3919 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3920 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3921 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3922 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3923 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3924 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3925 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3926 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3927 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3928 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3929 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3930 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3931 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3932 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3933 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3934 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3935 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3936 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3937 Room 18-006-S1 192 days11/30/20216/9/2022 11/30 Room 18-006-S1
3938 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3939 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3940 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3941 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3942 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3943 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3944 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 106
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3945 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3946 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3947 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3948 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3949 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3950 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3951 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3952 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3953 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3954 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3955 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3956 Room 18-007-S1 192 days11/30/20216/9/2022 11/30 Room 18-007-S1
3957 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3958 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3959 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3960 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3961 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
3962 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3963 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3964 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3965 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3966 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3967 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3968 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3969 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3970 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3971 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3972 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3973 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3974 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3975 Room 18-008-S4 192 days11/30/20216/9/2022 11/30 Room 18-008-S4
3976 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3977 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3978 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3979 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3980 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 107
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
3981 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
3982 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
3983 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
3984 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
3985 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
3986 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
3987 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
3988 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
3989 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
3990 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
3991 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
3992 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
3993 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
3994 Room 18-009-S1 192 days11/30/20216/9/2022 11/30 Room 18-009-S1
3995 Setting ou放线 1 day 11/30/202111/30/2021 11/30
3996 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
3997 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
3998 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
3999 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4000 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4001 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4002 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4003 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4004 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4005 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4006 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4007 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4008 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4009 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4010 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4011 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
4012 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
4013 Room 18-010-S1 192 days11/30/20216/9/2022 11/30 Room 18-010-S1
4014 Setting ou放线 1 day 11/30/202111/30/2021 11/30
4015 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
4016 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 108
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4017 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
4018 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4019 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4020 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4021 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4022 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4023 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4024 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4025 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4026 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4027 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4028 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4029 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4030 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
4031 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
4032 Room 18-011-S4 192 days11/30/20216/9/2022 11/30 Room 18-011-S4
4033 Setting ou放线 1 day 11/30/202111/30/2021 11/30
4034 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
4035 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
4036 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
4037 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4038 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4039 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4040 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4041 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4042 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4043 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4044 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4045 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4046 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4047 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4048 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4049 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
4050 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
4051 Room 18-012-S1 192 days11/30/20216/9/2022 11/30 Room 18-012-S1
4052 Setting ou放线 1 day 11/30/202111/30/2021 11/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 109
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4053 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
4054 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
4055 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
4056 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4057 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4058 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4059 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4060 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4061 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4062 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4063 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4064 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4065 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4066 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4067 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4068 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
4069 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
4070 Room 18-013-S1 192 days11/30/20216/9/2022 11/30 Room 18-013-S1
4071 Setting ou放线 1 day 11/30/202111/30/2021 11/30
4072 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
4073 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
4074 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
4075 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4076 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4077 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4078 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4079 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4080 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4081 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4082 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4083 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4084 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4085 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4086 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4087 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
4088 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 110
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4089 Room 18-014-S1 192 days11/30/20216/9/2022 11/30 Room 18-014-S1
4090 Setting ou放线 1 day 11/30/202111/30/2021 11/30
4091 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
4092 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
4093 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
4094 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4095 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4096 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4097 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4098 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4099 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4100 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4101 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4102 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4103 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4104 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4105 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4106 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
4107 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
4108 Room 18-015-S2 192 days11/30/20216/9/2022 11/30 Room 18-015-S2
4109 Setting ou放线 1 day 11/30/202111/30/2021 11/30
4110 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
4111 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
4112 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
4113 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4114 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4115 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4116 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4117 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4118 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4119 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4120 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4121 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4122 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4123 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4124 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4125 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 111
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4126 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
4127 Room 18-016-S1 192 days11/30/20216/9/2022 11/30 Room 18-016-S1
4128 Setting ou放线 1 day 11/30/202111/30/2021 11/30
4129 Steel Frame (Toilet and Vanity Sink) 5 days 12/1/2021 12/5/2021 12/1
Installation钢架安装
4130 Skirting Tile Installation踢脚线 4 days 12/3/2021 12/6/2021 12/3
4131 Bathroom Wall and Floor Tile Installation墙和 7 days 12/22/202112/28/2021 12/22
地板瓷砖
4132 Wall Skim Coat墙 腻子 7 days 12/16/202112/22/2021 12/16
4133 Base of TV Back Drop 电视背景基层 7 days 1/5/2022 1/11/2022 1/5
4134 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/14/2022 3/18/2022 3/14
4135 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 3/19/2022 3/24/2022 3/19
4136 Ceiling Skim Coat 天花板腻子 6 days 3/27/2022 4/1/2022 3/27
4137 Door Frame 门框 5 days 2/25/2022 3/1/2022 2/25
4138 Glass Door Installation 固定玻璃,玻璃们安装 7 days 2/24/2022 3/2/2022 2/24
4139 Acrylic Installation 洗手台盘面+隔墙 7 days 3/10/2022 3/16/2022 3/10
4140 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/14/2022 3/20/2022 3/14
4141 Door Installation门安装+门扇 7 days 3/26/2022 4/1/2022 3/26
4142 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 3/31/2022 4/6/2022 3/31
4143 Wardrope 衣柜 7 days 4/2/2022 4/8/2022 4/2
4144 Illuminated Mirior 洗手台镜子 3 days 3/21/2022 3/23/2022 3/21
4145 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 5/31/2022 6/9/2022 5/31
Installation 卫生间五金和洁具
4146 CORRIDOR & LIFT LOBBY走道 116 days2/20/2022 6/15/2022 2/20 CORRIDOR & LIF
4147 Acoustic Insulation Wall Installaltion 隔音墙 10 days 2/20/2022 3/1/2022 2/20
4148 Ceiling Frame Installation 吊顶龙安装 10 days 3/17/2022 3/26/2022 3/17
4149 Close ceiling and wallgypsum boards石膏板封闭 5 days 3/27/2022 3/31/2022 3/27
4150 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/1/2022 4/7/2022 4/1
4151 Skirting Installation 踢脚线,木饰面 7 days 4/9/2022 4/15/2022 4/9
4152 Fire Proofing Door Framing Installation 防火门框 7 days 3/31/2022 4/6/2022 3/31
4153 Painting on Ceiling 天花板油漆 6 days 4/23/2022 4/28/2022 4/23
4154 Fire Proofing Door Installation 防火门+门扇 3 days 5/10/2022 5/12/2022 5/10
4155 Wall Papers on Corridors wall &Installation of 6 days 5/22/2022 5/27/2022 5/22
glasses 墙壁纸+玻璃
4156 Carpet installation in corridor地毯 3 days 6/13/2022 6/15/2022 6/13
4157 ID Work level 19 精装修19层 196 days12/6/2021 6/19/2022 12/6 ID Work level 1
4158 Guest Room 196 days12/6/2021 6/19/2022 12/6 Guest Room
4159 Room 19-001-S3 196 days12/6/2021 6/19/2022 12/6 Room 19-001-S
4160 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4161 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 112
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4162 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4163 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4164 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4165 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4166 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4167 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4168 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4169 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4170 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4171 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4172 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4173 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4174 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4175 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4176 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4177 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4178 Room 19-002-S3 196 days12/6/2021 6/19/2022 12/6 Room 19-002-S
4179 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4180 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4181 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4182 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4183 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4184 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4185 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4186 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4187 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4188 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4189 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4190 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4191 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4192 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4193 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4194 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4195 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4196 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4197 Room 19-003-S1 68 days 3/21/2022 5/27/2022 3/21 Room 19-003-S1
4198 Setting ou放线 1 day 3/21/2022 3/21/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 113
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4199 Steel Frame (Toilet and Vanity Sink) 3 days 3/22/2022 3/24/2022 3/22
Installation钢架安装
4200 Skirting Tile Installation踢脚线 2 days 3/22/2022 3/23/2022 3/22
4201 Bathroom Wall and Floor Tile Installation墙和 3 days 3/22/2022 3/24/2022 3/22
地板瓷砖
4202 Wall Skim Coat墙 腻子 3 days 4/4/2022 4/6/2022 4/4
4203 Base of TV Back Drop 电视背景基层 4 days 4/10/2022 4/13/2022 4/10
4204 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/27/2022 3/29/2022 3/27
4205 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/30/2022 4/1/2022 3/30
4206 Ceiling Skim Coat 天花板腻子 3 days 4/4/2022 4/6/2022 4/4
4207 Door Frame 门框 2 days 4/6/2022 4/7/2022 4/6
4208 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/14/2022 4/16/2022 4/14
4209 Acrylic Installation 洗手台盘面+隔墙 3 days 4/22/2022 4/24/2022 4/22
4210 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/10/2022 4/12/2022 4/10
4211 Door Installation门安装+门扇 2 days 4/8/2022 4/9/2022 4/8
4212 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/13/2022 4/15/2022 4/13
4213 Wardrope 衣柜 3 days 4/13/2022 4/15/2022 4/13
4214 Illuminated Mirior 洗手台镜子 2 days 4/24/2022 4/25/2022 4/24
4215 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/24/2022 5/27/2022 5/24
Installation 卫生间五金和洁具
4216 Room 19-004-S1 68 days 3/21/2022 5/27/2022 3/21 Room 19-004-S1
4217 Setting ou放线 1 day 3/21/2022 3/21/2022 3/21
4218 Steel Frame (Toilet and Vanity Sink) 3 days 3/22/2022 3/24/2022 3/22
Installation钢架安装
4219 Skirting Tile Installation踢脚线 2 days 3/22/2022 3/23/2022 3/22
4220 Bathroom Wall and Floor Tile Installation墙和 3 days 3/22/2022 3/24/2022 3/22
地板瓷砖
4221 Wall Skim Coat墙 腻子 3 days 4/4/2022 4/6/2022 4/4
4222 Base of TV Back Drop 电视背景基层 4 days 4/10/2022 4/13/2022 4/10
4223 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/27/2022 3/29/2022 3/27
4224 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/30/2022 4/1/2022 3/30
4225 Ceiling Skim Coat 天花板腻子 3 days 4/4/2022 4/6/2022 4/4
4226 Door Frame 门框 2 days 4/6/2022 4/7/2022 4/6
4227 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/14/2022 4/16/2022 4/14
4228 Acrylic Installation 洗手台盘面+隔墙 3 days 4/22/2022 4/24/2022 4/22
4229 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/10/2022 4/12/2022 4/10
4230 Door Installation门安装+门扇 2 days 4/8/2022 4/9/2022 4/8
4231 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/13/2022 4/15/2022 4/13
4232 Wardrope 衣柜 3 days 4/13/2022 4/15/2022 4/13
4233 Illuminated Mirior 洗手台镜子 2 days 4/24/2022 4/25/2022 4/24
4234 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/24/2022 5/27/2022 5/24
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 114
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4235 Room 19-005-S1 196 days12/6/2021 6/19/2022 12/6 Room 19-005-S
4236 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4237 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4238 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4239 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4240 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4241 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4242 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4243 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4244 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4245 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4246 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4247 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4248 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4249 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4250 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4251 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4252 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4253 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4254 Room 19-006-S1 196 days12/6/2021 6/19/2022 12/6 Room 19-006-S
4255 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4256 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4257 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4258 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4259 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4260 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4261 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4262 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4263 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4264 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4265 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4266 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4267 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4268 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4269 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4270 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4271 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 115
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4272 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4273 Room 19-012-S1 196 days12/6/2021 6/19/2022 12/6 Room 19-012-S
4274 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4275 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4276 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4277 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4278 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4279 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4280 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4281 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4282 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4283 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4284 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4285 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4286 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4287 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4288 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4289 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4290 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4291 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4292 Room 19-013-S1 196 days12/6/2021 6/19/2022 12/6 Room 19-013-S
4293 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4294 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4295 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4296 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4297 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4298 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4299 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4300 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4301 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4302 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4303 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4304 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4305 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4306 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4307 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 116
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4308 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4309 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4310 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4311 Room 19-014-S1 196 days12/6/2021 6/19/2022 12/6 Room 19-014-S
4312 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4313 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4314 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4315 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4316 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4317 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4318 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4319 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4320 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4321 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4322 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4323 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4324 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4325 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4326 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4327 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4328 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4329 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4330 Room 19-015-S1 196 days12/6/2021 6/19/2022 12/6 Room 19-015-S
4331 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4332 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4333 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4334 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4335 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4336 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4337 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4338 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4339 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4340 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4341 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4342 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4343 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 117
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4344 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4345 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4346 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4347 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4348 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4349 CORRIDOR & LIFT LOBBY走道 109 days3/2/2022 6/18/2022 3/2 CORRIDOR & L
4350 Acoustic Insulation Wall Installaltion 隔音墙 10 days 3/2/2022 3/11/2022 3/2
4351 Ceiling Frame Installation 吊顶龙安装 10 days 3/27/2022 4/5/2022 3/27
4352 Close ceiling and wallgypsum boards石膏板封闭 5 days 4/6/2022 4/10/2022 4/6
4353 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/11/2022 4/17/2022 4/11
4354 Skirting Installation 踢脚线,木饰面 7 days 4/16/2022 4/22/2022 4/16
4355 Fire Proofing Door Framing Installation 防火门框 7 days 4/7/2022 4/13/2022 4/7
4356 Painting on Ceiling 天花板油漆 6 days 4/30/2022 5/5/2022 4/30
4357 Fire Proofing Door Installation 防火门+门扇 3 days 5/13/2022 5/15/2022 5/13
4358 Wall Papers on Corridors wall &Installation of 6 days 5/28/2022 6/2/2022 5/28
glasses 墙壁纸+玻璃
4359 Carpet installation in corridor地毯 3 days 6/16/2022 6/18/2022 6/16
4360 ID Work level 20精装修20层 196 days12/6/2021 6/19/2022 12/6 ID Work level 2
4361 Guest Room 196 days12/6/2021 6/19/2022 12/6 Guest Room
4362 Room 20-001-S3 196 days12/6/2021 6/19/2022 12/6 Room 20-001-S
4363 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4364 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4365 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4366 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4367 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4368 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4369 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4370 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4371 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4372 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4373 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4374 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4375 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4376 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4377 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4378 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4379 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4380 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 118
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4381 Room 20-002-S3 196 days12/6/2021 6/19/2022 12/6 Room 20-002-S
4382 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4383 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4384 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4385 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4386 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4387 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4388 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4389 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4390 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4391 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4392 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4393 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4394 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4395 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4396 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4397 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4398 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4399 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4400 Room 20-003-S1 68 days 3/21/2022 5/27/2022 3/21 Room 20-003-S1
4401 Setting ou放线 1 day 3/21/2022 3/21/2022 3/21
4402 Steel Frame (Toilet and Vanity Sink) 3 days 3/22/2022 3/24/2022 3/22
Installation钢架安装
4403 Skirting Tile Installation踢脚线 2 days 3/22/2022 3/23/2022 3/22
4404 Bathroom Wall and Floor Tile Installation墙和 3 days 3/22/2022 3/24/2022 3/22
地板瓷砖
4405 Wall Skim Coat墙 腻子 3 days 4/4/2022 4/6/2022 4/4
4406 Base of TV Back Drop 电视背景基层 4 days 4/10/2022 4/13/2022 4/10
4407 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/27/2022 3/29/2022 3/27
4408 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/30/2022 4/1/2022 3/30
4409 Ceiling Skim Coat 天花板腻子 3 days 4/4/2022 4/6/2022 4/4
4410 Door Frame 门框 2 days 4/6/2022 4/7/2022 4/6
4411 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/14/2022 4/16/2022 4/14
4412 Acrylic Installation 洗手台盘面+隔墙 3 days 4/22/2022 4/24/2022 4/22
4413 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/10/2022 4/12/2022 4/10
4414 Door Installation门安装+门扇 2 days 4/8/2022 4/9/2022 4/8
4415 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/13/2022 4/15/2022 4/13
4416 Wardrope 衣柜 3 days 4/13/2022 4/15/2022 4/13
4417 Illuminated Mirior 洗手台镜子 2 days 4/24/2022 4/25/2022 4/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 119
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4418 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/24/2022 5/27/2022 5/24
Installation 卫生间五金和洁具
4419 Room 20-004-S1 68 days 3/21/2022 5/27/2022 3/21 Room 20-004-S1
4420 Setting ou放线 1 day 3/21/2022 3/21/2022 3/21
4421 Steel Frame (Toilet and Vanity Sink) 3 days 3/22/2022 3/24/2022 3/22
Installation钢架安装
4422 Skirting Tile Installation踢脚线 2 days 3/22/2022 3/23/2022 3/22
4423 Bathroom Wall and Floor Tile Installation墙和 3 days 3/22/2022 3/24/2022 3/22
地板瓷砖
4424 Wall Skim Coat墙 腻子 3 days 4/4/2022 4/6/2022 4/4
4425 Base of TV Back Drop 电视背景基层 4 days 4/10/2022 4/13/2022 4/10
4426 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/27/2022 3/29/2022 3/27
4427 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/30/2022 4/1/2022 3/30
4428 Ceiling Skim Coat 天花板腻子 3 days 4/4/2022 4/6/2022 4/4
4429 Door Frame 门框 2 days 4/6/2022 4/7/2022 4/6
4430 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/14/2022 4/16/2022 4/14
4431 Acrylic Installation 洗手台盘面+隔墙 3 days 4/22/2022 4/24/2022 4/22
4432 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/10/2022 4/12/2022 4/10
4433 Door Installation门安装+门扇 2 days 4/8/2022 4/9/2022 4/8
4434 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/13/2022 4/15/2022 4/13
4435 Wardrope 衣柜 3 days 4/13/2022 4/15/2022 4/13
4436 Illuminated Mirior 洗手台镜子 2 days 4/24/2022 4/25/2022 4/24
4437 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/24/2022 5/27/2022 5/24
Installation 卫生间五金和洁具
4438 Room 20-005-S1 196 days12/6/2021 6/19/2022 12/6 Room 20-005-S
4439 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4440 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4441 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4442 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4443 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4444 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4445 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4446 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4447 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4448 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4449 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4450 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4451 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4452 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4453 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 120
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4454 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4455 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4456 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4457 Room 20-006-S1 196 days12/6/2021 6/19/2022 12/6 Room 20-006-S
4458 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4459 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4460 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4461 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4462 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4463 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4464 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4465 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4466 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4467 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4468 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4469 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4470 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4471 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4472 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4473 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4474 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4475 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4476 Room 20-007-SUITE B 196 days12/6/2021 6/19/2022 12/6 Room 20-007-S
4477 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4478 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4479 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4480 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4481 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4482 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4483 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4484 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4485 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4486 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4487 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4488 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4489 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 121
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4490 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4491 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4492 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4493 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4494 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4495 Room 20-008-SUITE A 196 days12/6/2021 6/19/2022 12/6 Room 20-008-S
4496 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4497 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4498 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4499 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4500 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4501 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4502 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4503 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4504 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4505 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4506 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4507 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4508 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4509 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4510 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4511 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4512 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4513 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4514 Room 20-009-SUITE B 196 days12/6/2021 6/19/2022 12/6 Room 20-009-S
4515 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4516 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4517 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4518 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4519 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4520 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4521 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4522 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4523 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4524 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4525 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 122
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4526 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4527 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4528 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4529 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4530 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4531 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4532 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4533 Room 20-010-S1 196 days12/6/2021 6/19/2022 12/6 Room 20-010-S
4534 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4535 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4536 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4537 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4538 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4539 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4540 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4541 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4542 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4543 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4544 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4545 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4546 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4547 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4548 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4549 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4550 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4551 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4552 Room 20-011-S1 196 days12/6/2021 6/19/2022 12/6 Room 20-011-S
4553 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4554 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4555 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4556 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4557 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4558 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4559 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4560 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4561 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 123
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4562 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4563 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4564 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4565 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4566 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4567 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4568 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4569 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4570 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4571 Room 20-012-S1 196 days12/6/2021 6/19/2022 12/6 Room 20-012-S
4572 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4573 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4574 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4575 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4576 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4577 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4578 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4579 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4580 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4581 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4582 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4583 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4584 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4585 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4586 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4587 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4588 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4589 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4590 Room 20-013-S1 196 days12/6/2021 6/19/2022 12/6 Room 20-013-S
4591 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4592 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4593 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4594 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4595 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4596 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4597 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 124
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4598 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4599 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4600 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4601 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4602 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4603 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4604 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4605 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4606 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4607 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4608 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4609 CORRIDOR & LIFT LOBBY走道 109 days3/2/2022 6/18/2022 3/2 CORRIDOR & L
4610 Acoustic Insulation Wall Installaltion 隔音墙 10 days 3/2/2022 3/11/2022 3/2
4611 Ceiling Frame Installation 吊顶龙安装 10 days 3/27/2022 4/5/2022 3/27
4612 Close ceiling and wallgypsum boards石膏板封闭 5 days 4/6/2022 4/10/2022 4/6
4613 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/11/2022 4/17/2022 4/11
4614 Skirting Installation 踢脚线,木饰面 7 days 4/16/2022 4/22/2022 4/16
4615 Fire Proofing Door Framing Installation 防火门框 7 days 4/7/2022 4/13/2022 4/7
4616 Painting on Ceiling 天花板油漆 6 days 4/30/2022 5/5/2022 4/30
4617 Fire Proofing Door Installation 防火门+门扇 3 days 5/13/2022 5/15/2022 5/13
4618 Wall Papers on Corridors wall &Installation of 6 days 5/28/2022 6/2/2022 5/28
glasses 墙壁纸+玻璃
4619 Carpet installation in corridor地毯 3 days 6/16/2022 6/18/2022 6/16
4620 ID Work level 21精装修21层 196 days12/6/2021 6/19/2022 12/6 ID Work level 2
4621 Guest Room 196 days12/6/2021 6/19/2022 12/6 Guest Room
4622 Room 21-001-S3 196 days12/6/2021 6/19/2022 12/6 Room 21-001-S
4623 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4624 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4625 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4626 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4627 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4628 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4629 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4630 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4631 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4632 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4633 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4634 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4635 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 125
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4636 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4637 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4638 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4639 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4640 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4641 Room 21-002-S3 196 days12/6/2021 6/19/2022 12/6 Room 21-002-S
4642 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4643 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4644 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4645 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4646 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4647 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4648 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4649 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4650 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4651 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4652 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4653 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4654 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4655 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4656 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4657 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4658 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4659 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4660 Room 21-003-S1 68 days 3/21/2022 5/27/2022 3/21 Room 21-003-S1
4661 Setting ou放线 1 day 3/21/2022 3/21/2022 3/21
4662 Steel Frame (Toilet and Vanity Sink) 3 days 3/22/2022 3/24/2022 3/22
Installation钢架安装
4663 Skirting Tile Installation踢脚线 2 days 3/22/2022 3/23/2022 3/22
4664 Bathroom Wall and Floor Tile Installation墙和 3 days 3/22/2022 3/24/2022 3/22
地板瓷砖
4665 Wall Skim Coat墙 腻子 3 days 4/4/2022 4/6/2022 4/4
4666 Base of TV Back Drop 电视背景基层 4 days 4/10/2022 4/13/2022 4/10
4667 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/27/2022 3/29/2022 3/27
4668 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/30/2022 4/1/2022 3/30
4669 Ceiling Skim Coat 天花板腻子 3 days 4/4/2022 4/6/2022 4/4
4670 Door Frame 门框 2 days 4/6/2022 4/7/2022 4/6
4671 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/14/2022 4/16/2022 4/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 126
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4672 Acrylic Installation 洗手台盘面+隔墙 3 days 4/22/2022 4/24/2022 4/22
4673 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/10/2022 4/12/2022 4/10
4674 Door Installation门安装+门扇 2 days 4/8/2022 4/9/2022 4/8
4675 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/13/2022 4/15/2022 4/13
4676 Wardrope 衣柜 3 days 4/13/2022 4/15/2022 4/13
4677 Illuminated Mirior 洗手台镜子 2 days 4/24/2022 4/25/2022 4/24
4678 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/24/2022 5/27/2022 5/24
Installation 卫生间五金和洁具
4679 Room 21-004-S1 68 days 3/21/2022 5/27/2022 3/21 Room 21-004-S1
4680 Setting ou放线 1 day 3/21/2022 3/21/2022 3/21
4681 Steel Frame (Toilet and Vanity Sink) 3 days 3/22/2022 3/24/2022 3/22
Installation钢架安装
4682 Skirting Tile Installation踢脚线 2 days 3/22/2022 3/23/2022 3/22
4683 Bathroom Wall and Floor Tile Installation墙和 3 days 3/22/2022 3/24/2022 3/22
地板瓷砖
4684 Wall Skim Coat墙 腻子 3 days 4/4/2022 4/6/2022 4/4
4685 Base of TV Back Drop 电视背景基层 4 days 4/10/2022 4/13/2022 4/10
4686 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/27/2022 3/29/2022 3/27
4687 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/30/2022 4/1/2022 3/30
4688 Ceiling Skim Coat 天花板腻子 3 days 4/4/2022 4/6/2022 4/4
4689 Door Frame 门框 2 days 4/6/2022 4/7/2022 4/6
4690 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/14/2022 4/16/2022 4/14
4691 Acrylic Installation 洗手台盘面+隔墙 3 days 4/22/2022 4/24/2022 4/22
4692 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/10/2022 4/12/2022 4/10
4693 Door Installation门安装+门扇 2 days 4/8/2022 4/9/2022 4/8
4694 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/13/2022 4/15/2022 4/13
4695 Wardrope 衣柜 3 days 4/13/2022 4/15/2022 4/13
4696 Illuminated Mirior 洗手台镜子 2 days 4/24/2022 4/25/2022 4/24
4697 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/24/2022 5/27/2022 5/24
Installation 卫生间五金和洁具
4698 Room 21-005-S1 196 days12/6/2021 6/19/2022 12/6 Room 21-005-S
4699 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4700 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4701 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4702 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4703 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4704 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4705 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4706 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4707 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 127
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4708 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4709 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4710 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4711 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4712 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4713 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4714 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4715 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4716 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4717 Room 21-006-S1 196 days12/6/2021 6/19/2022 12/6 Room 21-006-S
4718 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4719 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4720 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4721 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4722 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4723 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4724 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4725 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4726 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4727 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4728 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4729 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4730 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4731 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4732 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4733 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4734 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4735 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4736 Room 21-007-SUITE B 196 days12/6/2021 6/19/2022 12/6 Room 21-007-S
4737 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4738 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4739 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4740 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4741 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4742 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4743 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 128
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4744 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4745 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4746 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4747 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4748 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4749 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4750 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4751 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4752 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4753 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4754 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4755 Room 21-008-SUITE A 196 days12/6/2021 6/19/2022 12/6 Room 21-008-S
4756 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4757 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4758 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4759 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4760 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4761 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4762 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4763 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4764 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4765 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4766 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4767 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4768 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4769 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4770 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4771 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4772 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4773 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4774 Room 21-009-SUITE B 196 days12/6/2021 6/19/2022 12/6 Room 21-009-S
4775 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4776 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4777 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4778 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4779 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 129
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4780 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4781 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4782 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4783 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4784 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4785 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4786 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4787 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4788 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4789 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4790 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4791 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4792 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4793 Room 21-010-S1 196 days12/6/2021 6/19/2022 12/6 Room 21-010-S
4794 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4795 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4796 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4797 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4798 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4799 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4800 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4801 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4802 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4803 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4804 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4805 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4806 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4807 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4808 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4809 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4810 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4811 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4812 Room 21-011-S1 196 days12/6/2021 6/19/2022 12/6 Room 21-011-S
4813 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4814 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4815 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 130
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4816 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4817 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4818 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4819 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4820 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4821 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4822 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4823 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4824 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4825 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4826 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4827 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4828 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4829 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4830 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4831 Room 21-012-S1 196 days12/6/2021 6/19/2022 12/6 Room 21-012-S
4832 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6
4833 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4834 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4835 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4836 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4837 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4838 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4839 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4840 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4841 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4842 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4843 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4844 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4845 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4846 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4847 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4848 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4849 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4850 Room 21-013-S1 196 days12/6/2021 6/19/2022 12/6 Room 21-013-S
4851 Setting ou放线 1 day 12/6/2021 12/6/2021 12/6

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 131
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4852 Steel Frame (Toilet and Vanity Sink) 5 days 12/7/2021 12/11/2021 12/7
Installation钢架安装
4853 Skirting Tile Installation踢脚线 4 days 12/9/2021 12/12/2021 12/9
4854 Bathroom Wall and Floor Tile Installation墙和 7 days 12/29/20211/4/2022 12/29
地板瓷砖
4855 Wall Skim Coat墙 腻子 7 days 12/23/202112/29/2021 12/23
4856 Base of TV Back Drop 电视背景基层 7 days 1/12/2022 1/18/2022 1/12
4857 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 3/30/2022 4/3/2022 3/30
4858 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/4/2022 4/9/2022 4/4
4859 Ceiling Skim Coat 天花板腻子 6 days 4/12/2022 4/17/2022 4/12
4860 Door Frame 门框 5 days 3/2/2022 3/6/2022 3/2
4861 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/3/2022 3/9/2022 3/3
4862 Acrylic Installation 洗手台盘面+隔墙 7 days 3/17/2022 3/23/2022 3/17
4863 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/21/2022 3/27/2022 3/21
4864 Door Installation门安装+门扇 7 days 4/2/2022 4/8/2022 4/2
4865 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/7/2022 4/13/2022 4/7
4866 Wardrope 衣柜 7 days 4/9/2022 4/15/2022 4/9
4867 Illuminated Mirior 洗手台镜子 3 days 3/24/2022 3/26/2022 3/24
4868 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/10/2022 6/19/2022 6/10
Installation 卫生间五金和洁具
4869 CORRIDOR & LIFT LOBBY走道 109 days3/2/2022 6/18/2022 3/2 CORRIDOR & L
4870 Acoustic Insulation Wall Installaltion 隔音墙 10 days 3/2/2022 3/11/2022 3/2
4871 Ceiling Frame Installation 吊顶龙安装 10 days 3/27/2022 4/5/2022 3/27
4872 Close ceiling and wallgypsum boards石膏板封闭 5 days 4/6/2022 4/10/2022 4/6
4873 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/11/2022 4/17/2022 4/11
4874 Skirting Installation 踢脚线,木饰面 7 days 4/16/2022 4/22/2022 4/16
4875 Fire Proofing Door Framing Installation 防火门框 7 days 4/7/2022 4/13/2022 4/7
4876 Painting on Ceiling 天花板油漆 6 days 4/30/2022 5/5/2022 4/30
4877 Fire Proofing Door Installation 防火门+门扇 3 days 5/13/2022 5/15/2022 5/13
4878 Wall Papers on Corridors wall &Installation of 6 days 5/28/2022 6/2/2022 5/28
glasses 墙壁纸+玻璃
4879 Carpet installation in corridor地毯 3 days 6/16/2022 6/18/2022 6/16
4880 ID Work level 22精装修22层 200 days12/12/20216/29/2022 12/12 ID Work lev
4881 Guest Room 200 days12/12/20216/29/2022 12/12 Guest Room
4882 Room 22-001-S3 200 days12/12/20216/29/2022 12/12 Room 22-00
4883 Setting ou放线 1 day 12/12/202112/12/2021 12/12
4884 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
4885 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
4886 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
4887 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 132
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4888 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
4889 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
4890 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
4891 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
4892 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
4893 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
4894 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
4895 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
4896 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
4897 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
4898 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
4899 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
4900 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
4901 Room 22-002-S3 200 days12/12/20216/29/2022 12/12 Room 22-00
4902 Setting ou放线 1 day 12/12/202112/12/2021 12/12
4903 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
4904 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
4905 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
4906 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
4907 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
4908 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
4909 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
4910 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
4911 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
4912 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
4913 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
4914 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
4915 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
4916 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
4917 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
4918 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
4919 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
4920 Room 22-003-S1 65 days 3/20/2022 5/23/2022 3/20 Room 22-003-S1
4921 Setting ou放线 1 day 3/20/2022 3/20/2022 3/20
4922 Steel Frame (Toilet and Vanity Sink) 3 days 3/21/2022 3/23/2022 3/21
Installation钢架安装
4923 Skirting Tile Installation踢脚线 2 days 3/21/2022 3/22/2022 3/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 133
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4924 Bathroom Wall and Floor Tile Installation墙和 3 days 3/21/2022 3/23/2022 3/21
地板瓷砖
4925 Wall Skim Coat墙 腻子 3 days 4/3/2022 4/5/2022 4/3
4926 Base of TV Back Drop 电视背景基层 4 days 4/9/2022 4/12/2022 4/9
4927 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/24/2022 3/26/2022 3/24
4928 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/27/2022 3/29/2022 3/27
4929 Ceiling Skim Coat 天花板腻子 3 days 4/1/2022 4/3/2022 4/1
4930 Door Frame 门框 2 days 4/4/2022 4/5/2022 4/4
4931 Glass Door Installation 固定玻璃,玻璃们安装 3 days 4/11/2022 4/13/2022 4/11
4932 Acrylic Installation 洗手台盘面+隔墙 3 days 4/19/2022 4/21/2022 4/19
4933 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/7/2022 4/9/2022 4/7
4934 Door Installation门安装+门扇 2 days 4/6/2022 4/7/2022 4/6
4935 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/10/2022 4/12/2022 4/10
4936 Wardrope 衣柜 3 days 4/10/2022 4/12/2022 4/10
4937 Illuminated Mirior 洗手台镜子 2 days 4/22/2022 4/23/2022 4/22
4938 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/20/2022 5/23/2022 5/20
Installation 卫生间五金和洁具
4939 Room 22-003-S1 84 days 3/1/2022 5/23/2022 3/1 Room 22-003-S1
4940 Setting ou放线 1 day 3/20/2022 3/20/2022 3/20
4941 Steel Frame (Toilet and Vanity Sink) 3 days 3/21/2022 3/23/2022 3/21
Installation钢架安装
4942 Skirting Tile Installation踢脚线 2 days 3/21/2022 3/22/2022 3/21
4943 Bathroom Wall and Floor Tile Installation墙和 3 days 3/21/2022 3/23/2022 3/21
地板瓷砖
4944 Wall Skim Coat墙 腻子 3 days 4/3/2022 4/5/2022 4/3
4945 Base of TV Back Drop 电视背景基层 4 days 4/9/2022 4/12/2022 4/9
4946 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/1/2022 3/3/2022 3/1
4947 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/4/2022 3/6/2022 3/4
4948 Ceiling Skim Coat 天花板腻子 3 days 3/9/2022 3/11/2022 3/9
4949 Door Frame 门框 2 days 3/12/2022 3/13/2022 3/12
4950 Glass Door Installation 固定玻璃,玻璃们安装 3 days 3/19/2022 3/21/2022 3/19
4951 Acrylic Installation 洗手台盘面+隔墙 3 days 3/27/2022 3/29/2022 3/27
4952 Ceiling and Wall Paint 墙和天花板油漆 3 days 3/15/2022 3/17/2022 3/15
4953 Door Installation门安装+门扇 2 days 4/6/2022 4/7/2022 4/6
4954 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 3/18/2022 3/20/2022 3/18
4955 Wardrope 衣柜 3 days 3/18/2022 3/20/2022 3/18
4956 Illuminated Mirior 洗手台镜子 2 days 3/30/2022 3/31/2022 3/30
4957 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/20/2022 5/23/2022 5/20
Installation 卫生间五金和洁具
4958 Room 22-005-S1 200 days12/12/20216/29/2022 12/12 Room 22-00
4959 Setting ou放线 1 day 12/12/202112/12/2021 12/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 134
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4960 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
4961 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
4962 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
4963 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
4964 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
4965 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
4966 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
4967 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
4968 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
4969 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
4970 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
4971 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
4972 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
4973 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
4974 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
4975 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
4976 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
4977 Room 22-006-S1 200 days12/12/20216/29/2022 12/12 Room 22-00
4978 Setting ou放线 1 day 12/12/202112/12/2021 12/12
4979 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
4980 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
4981 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
4982 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
4983 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
4984 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
4985 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
4986 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
4987 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
4988 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
4989 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
4990 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
4991 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
4992 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
4993 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
4994 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
4995 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 135
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
4996 Room 22-007-SUITE B 200 days12/12/20216/29/2022 12/12 Room 22-00
4997 Setting ou放线 1 day 12/12/202112/12/2021 12/12
4998 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
4999 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5000 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5001 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5002 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5003 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5004 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5005 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5006 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5007 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5008 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5009 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5010 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5011 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5012 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5013 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5014 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5015 Room 22-008-SUITE A 200 days12/12/20216/29/2022 12/12 Room 22-00
5016 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5017 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5018 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5019 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5020 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5021 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5022 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5023 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5024 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5025 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5026 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5027 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5028 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5029 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5030 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5031 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5032 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 136
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5033 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5034 Room 22-009-SUITE B 200 days12/12/20216/29/2022 12/12 Room 22-00
5035 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5036 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5037 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5038 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5039 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5040 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5041 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5042 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5043 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5044 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5045 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5046 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5047 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5048 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5049 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5050 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5051 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5052 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5053 Room 22-010-S1 200 days12/12/20216/29/2022 12/12 Room 22-01
5054 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5055 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5056 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5057 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5058 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5059 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5060 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5061 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5062 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5063 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5064 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5065 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5066 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5067 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5068 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 137
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5069 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5070 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5071 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5072 Room 22-011-S1 200 days12/12/20216/29/2022 12/12 Room 22-01
5073 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5074 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5075 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5076 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5077 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5078 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5079 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5080 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5081 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5082 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5083 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5084 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5085 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5086 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5087 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5088 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5089 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5090 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5091 Room 22-012-S1 200 days12/12/20216/29/2022 12/12 Room 22-01
5092 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5093 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5094 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5095 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5096 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5097 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5098 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5099 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5100 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5101 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5102 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5103 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5104 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 138
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5105 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5106 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5107 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5108 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5109 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5110 Room 22-013-S1 200 days12/12/20216/29/2022 12/12 Room 22-01
5111 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5112 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5113 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5114 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5115 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5116 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5117 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5118 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5119 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5120 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5121 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5122 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5123 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5124 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5125 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5126 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5127 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5128 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5129 CORRIDOR & LIFT LOBBY走道 102 days3/12/2022 6/21/2022 3/12 CORRIDOR & L
5130 Acoustic Insulation Wall Installaltion 隔音墙 10 days 3/12/2022 3/21/2022 3/12
5131 Ceiling Frame Installation 吊顶龙安装 10 days 4/6/2022 4/15/2022 4/6
5132 Close ceiling and wallgypsum boards石膏板封闭 5 days 4/16/2022 4/20/2022 4/16
5133 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/21/2022 4/27/2022 4/21
5134 Skirting Installation 踢脚线,木饰面 7 days 4/23/2022 4/29/2022 4/23
5135 Fire Proofing Door Framing Installation 防火门框 7 days 4/14/2022 4/20/2022 4/14
5136 Painting on Ceiling 天花板油漆 6 days 5/7/2022 5/12/2022 5/7
5137 Fire Proofing Door Installation 防火门+门扇 3 days 5/16/2022 5/18/2022 5/16
5138 Wall Papers on Corridors wall &Installation of 6 days 6/3/2022 6/8/2022 6/3
glasses 墙壁纸+玻璃
5139 Carpet installation in corridor地毯 3 days 6/19/2022 6/21/2022 6/19
5140 ID Work level 23精装修23层 200 days12/12/20216/29/2022 12/12 ID Work lev
5141 Guest Room 200 days12/12/20216/29/2022 12/12 Guest Room

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 139
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5142 Room 23-001-S3 200 days12/12/20216/29/2022 12/12 Room 23-00
5143 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5144 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5145 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5146 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5147 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5148 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5149 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5150 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5151 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5152 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5153 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5154 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5155 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5156 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5157 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5158 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5159 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5160 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5161 Room 23-002-S3 200 days12/12/20216/29/2022 12/12 Room 23-00
5162 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5163 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5164 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5165 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5166 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5167 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5168 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5169 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5170 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5171 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5172 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5173 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5174 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5175 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5176 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5177 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5178 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 140
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5179 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5180 Room 23-003-S1 84 days 3/1/2022 5/23/2022 3/1 Room 23-003-S1
5181 Setting ou放线 1 day 3/20/2022 3/20/2022 3/20
5182 Steel Frame (Toilet and Vanity Sink) 3 days 3/21/2022 3/23/2022 3/21
Installation钢架安装
5183 Skirting Tile Installation踢脚线 2 days 3/21/2022 3/22/2022 3/21
5184 Bathroom Wall and Floor Tile Installation墙和 3 days 3/21/2022 3/23/2022 3/21
地板瓷砖
5185 Wall Skim Coat墙 腻子 3 days 4/3/2022 4/5/2022 4/3
5186 Base of TV Back Drop 电视背景基层 4 days 4/9/2022 4/12/2022 4/9
5187 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/1/2022 3/3/2022 3/1
5188 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/4/2022 3/6/2022 3/4
5189 Ceiling Skim Coat 天花板腻子 3 days 3/9/2022 3/11/2022 3/9
5190 Door Frame 门框 2 days 3/12/2022 3/13/2022 3/12
5191 Glass Door Installation 固定玻璃,玻璃们安装 3 days 3/19/2022 3/21/2022 3/19
5192 Acrylic Installation 洗手台盘面+隔墙 3 days 3/27/2022 3/29/2022 3/27
5193 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/25/2022 4/27/2022 4/25
5194 Door Installation门安装+门扇 2 days 4/6/2022 4/7/2022 4/6
5195 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/28/2022 4/30/2022 4/28
5196 Wardrope 衣柜 3 days 4/28/2022 4/30/2022 4/28
5197 Illuminated Mirior 洗手台镜子 2 days 3/30/2022 3/31/2022 3/30
5198 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/20/2022 5/23/2022 5/20
Installation 卫生间五金和洁具
5199 Room 23-004-S1 84 days 3/1/2022 5/23/2022 3/1 Room 23-004-S1
5200 Setting ou放线 1 day 3/20/2022 3/20/2022 3/20
5201 Steel Frame (Toilet and Vanity Sink) 3 days 3/21/2022 3/23/2022 3/21
Installation钢架安装
5202 Skirting Tile Installation踢脚线 2 days 3/21/2022 3/22/2022 3/21
5203 Bathroom Wall and Floor Tile Installation墙和 3 days 3/21/2022 3/23/2022 3/21
地板瓷砖
5204 Wall Skim Coat墙 腻子 3 days 4/3/2022 4/5/2022 4/3
5205 Base of TV Back Drop 电视背景基层 4 days 4/9/2022 4/12/2022 4/9
5206 Ceiling Light Stud Keel Installation 天花板龙骨 3 days 3/1/2022 3/3/2022 3/1
5207 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 3 days 3/4/2022 3/6/2022 3/4
5208 Ceiling Skim Coat 天花板腻子 3 days 3/9/2022 3/11/2022 3/9
5209 Door Frame 门框 2 days 3/12/2022 3/13/2022 3/12
5210 Glass Door Installation 固定玻璃,玻璃们安装 3 days 3/19/2022 3/21/2022 3/19
5211 Acrylic Installation 洗手台盘面+隔墙 3 days 3/27/2022 3/29/2022 3/27
5212 Ceiling and Wall Paint 墙和天花板油漆 3 days 4/25/2022 4/27/2022 4/25
5213 Door Installation门安装+门扇 2 days 4/6/2022 4/7/2022 4/6
5214 Wall Paper &TV Leather Installation墙纸和背景皮草 3 days 4/28/2022 4/30/2022 4/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 141
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5215 Wardrope 衣柜 3 days 4/28/2022 4/30/2022 4/28
5216 Illuminated Mirior 洗手台镜子 2 days 3/30/2022 3/31/2022 3/30
5217 Bathroom Sanitary Ware, Fitting & Accessaries 4 days 5/20/2022 5/23/2022 5/20
Installation 卫生间五金和洁具
5218 Room 23-005-S1 200 days12/12/20216/29/2022 12/12 Room 23-00
5219 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5220 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5221 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5222 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5223 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5224 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5225 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5226 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5227 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5228 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5229 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5230 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5231 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5232 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5233 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5234 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5235 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5236 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5237 Room 23-006-S1 200 days12/12/20216/29/2022 12/12 Room 23-00
5238 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5239 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5240 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5241 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5242 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5243 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5244 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5245 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5246 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5247 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5248 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5249 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5250 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 142
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5251 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5252 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5253 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5254 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5255 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5256 Room 23-007-SUITE B 200 days12/12/20216/29/2022 12/12 Room 23-00
5257 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5258 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5259 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5260 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5261 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5262 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5263 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5264 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5265 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5266 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5267 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5268 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5269 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5270 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5271 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5272 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5273 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5274 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5275 Room 23-008-SUITE A 200 days12/12/20216/29/2022 12/12 Room 23-00
5276 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5277 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5278 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5279 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5280 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5281 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5282 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5283 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5284 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5285 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5286 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 143
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5287 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5288 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5289 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5290 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5291 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5292 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5293 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5294 Room 23-009-SUITE B 200 days12/12/20216/29/2022 12/12 Room 23-00
5295 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5296 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5297 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5298 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5299 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5300 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5301 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5302 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5303 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5304 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5305 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5306 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5307 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5308 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5309 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5310 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5311 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5312 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5313 Room 23-010-S1 200 days12/12/20216/29/2022 12/12 Room 23-01
5314 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5315 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5316 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5317 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5318 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5319 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5320 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5321 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5322 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 144
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5323 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5324 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5325 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5326 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5327 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5328 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5329 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5330 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5331 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5332 Room 23-011-S1 200 days12/12/20216/29/2022 12/12 Room 23-01
5333 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5334 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5335 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5336 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5337 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5338 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5339 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5340 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5341 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5342 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5343 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5344 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5345 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5346 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5347 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5348 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5349 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5350 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5351 Room 23-012-S1 200 days12/12/20216/29/2022 12/12 Room 23-01
5352 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5353 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5354 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5355 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5356 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5357 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5358 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 145
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5359 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5360 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5361 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5362 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5363 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5364 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5365 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5366 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5367 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5368 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5369 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5370 Room 23-013-S1 200 days12/12/20216/29/2022 12/12 Room 23-01
5371 Setting ou放线 1 day 12/12/202112/12/2021 12/12
5372 Steel Frame (Toilet and Vanity Sink) 5 days 12/13/202112/17/2021 12/13
Installation钢架安装
5373 Skirting Tile Installation踢脚线 4 days 12/15/202112/18/2021 12/15
5374 Bathroom Wall and Floor Tile Installation墙和 7 days 1/5/2022 1/11/2022 1/5
地板瓷砖
5375 Wall Skim Coat墙 腻子 7 days 12/30/20211/5/2022 12/30
5376 Base of TV Back Drop 电视背景基层 7 days 1/19/2022 1/25/2022 1/19
5377 Ceiling Light Stud Keel Installation 天花板龙骨 5 days 4/15/2022 4/19/2022 4/15
5378 Ceiling Gypsum Board Installation 石膏封板,窗帘盒 6 days 4/20/2022 4/25/2022 4/20
5379 Ceiling Skim Coat 天花板腻子 6 days 4/28/2022 5/3/2022 4/28
5380 Door Frame 门框 5 days 3/7/2022 3/11/2022 3/7
5381 Glass Door Installation 固定玻璃,玻璃们安装 7 days 3/10/2022 3/16/2022 3/10
5382 Acrylic Installation 洗手台盘面+隔墙 7 days 3/24/2022 3/30/2022 3/24
5383 Ceiling and Wall Paint 墙和天花板油漆 7 days 3/28/2022 4/3/2022 3/28
5384 Door Installation门安装+门扇 7 days 4/9/2022 4/15/2022 4/9
5385 Wall Paper &TV Leather Installation墙纸和背景皮草 7 days 4/14/2022 4/20/2022 4/14
5386 Wardrope 衣柜 7 days 4/16/2022 4/22/2022 4/16
5387 Illuminated Mirior 洗手台镜子 3 days 3/27/2022 3/29/2022 3/27
5388 Bathroom Sanitary Ware, Fitting & Accessaries 10 days 6/20/2022 6/29/2022 6/20
Installation 卫生间五金和洁具
5389 CORRIDOR & LIFT LOBBY走道 102 days3/12/2022 6/21/2022 3/12 CORRIDOR & L
5390 Acoustic Insulation Wall Installaltion 隔音墙 10 days 3/12/2022 3/21/2022 3/12
5391 Ceiling Frame Installation 吊顶龙安装 10 days 4/6/2022 4/15/2022 4/6
5392 Close ceiling and wallgypsum boards石膏板封闭 5 days 4/16/2022 4/20/2022 4/16
5393 Ceiling & Wall Skimcaot 墙和天花板腻子 7 days 4/21/2022 4/27/2022 4/21
5394 Skirting Installation 踢脚线,木饰面 7 days 4/23/2022 4/29/2022 4/23
5395 Fire Proofing Door Framing Installation 防火门框 7 days 4/14/2022 4/20/2022 4/14
5396 Painting on Ceiling 天花板油漆 6 days 5/7/2022 5/12/2022 5/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 146
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5397 Fire Proofing Door Installation 防火门+门扇 3 days 5/16/2022 5/18/2022 5/16
5398 Wall Papers on Corridors wall &Installation of 6 days 6/3/2022 6/8/2022 6/3
glasses 墙壁纸+玻璃
5399 Carpet installation in corridor地毯 3 days 6/19/2022 6/21/2022 6/19
5400 ID Work level 25 精装修25层 42 days 3/1/2022 4/11/2022 3/1 ID Work level 25 精装修25层
5401 ID Construction 42 days 3/1/2022 4/11/2022 3/1 ID Construction
5402 Work place handover 1 day 3/1/2022 3/1/2022 3/1
5403 Setting out 3 days 3/2/2022 3/4/2022 3/2
5404 Wall and Ceiling(Fair Face) Skim Coat 10 days 3/5/2022 3/14/2022 3/5
5405 Painting 7 days 3/15/2022 3/21/2022 3/15
5406 Ventilation shutter installation 7 days 3/22/2022 3/28/2022 3/22
5407 Skirting installation 6 days 3/29/2022 4/3/2022 3/29
5408 Doors installation 5 days 4/4/2022 4/8/2022 4/4
5409 Cleaning works 3 days 4/9/2022 4/11/2022 4/9
5410 ID Work level 26 精装修26层 34 days 4/12/2022 5/15/2022 4/12 ID Work level 26 精装修
5411 ID Construction 34 days 4/12/2022 5/15/2022 4/12 ID Construction
5412 Work place handover 1 day 4/12/2022 4/12/2022 4/12
5413 Setting out 3 days 4/13/2022 4/15/2022 4/13
5414 Wall and Ceiling(Fair Face) Skim Coat 7 days 4/16/2022 4/22/2022 4/16
5415 Painting 5 days 4/23/2022 4/27/2022 4/23
5416 Ventilation shutter installation 6 days 4/28/2022 5/3/2022 4/28
5417 Skirting installation 5 days 5/4/2022 5/8/2022 5/4
5418 Doors installation 4 days 5/9/2022 5/12/2022 5/9
5419 Cleaning works 3 days 5/13/2022 5/15/2022 5/13
5420 ID work B1-B3GF-5F精装修B1-B3及GF-5F 136 days2/21/2022 7/6/2022 2/21 ID work B
5421 B1地下室一层 27 days 4/10/2022 5/6/2022 4/10 B1地下室一层
5422 Work place handover工作面移交 1 day 4/10/2022 4/10/2022 4/10
5423 Setting out放线 3 days 4/11/2022 4/13/2022 4/11
5424 Skirting installation踢脚瓷砖安装 5 days 4/14/2022 4/18/2022 4/14
5425 Wall and Ceiling(Fair Face) Skim Coat 腻子 7 days 4/19/2022 4/25/2022 4/19
5426 Painting 油漆 5 days 4/26/2022 4/30/2022 4/26
5427 Ventilation shutter installation 通风百叶窗安装 6 days 5/1/2022 5/6/2022 5/1
5428 Doors installation门安装 4 days 4/29/2022 5/2/2022 4/29
5429 Cleaning works清理 3 days 5/3/2022 5/5/2022 5/3
5430 B2地下室二层 27 days 4/16/2022 5/12/2022 4/16 B2地下室二层
5431 Work place handover工作面移交 1 day 4/16/2022 4/16/2022 4/16
5432 Setting out放线 3 days 4/17/2022 4/19/2022 4/17
5433 Skirting installation踢脚瓷砖安装 5 days 4/20/2022 4/24/2022 4/20
5434 Wall and Ceiling(Fair Face) Skim Coat 腻子 7 days 4/25/2022 5/1/2022 4/25
5435 Painting 油漆 5 days 5/2/2022 5/6/2022 5/2
5436 Ventilation shutter installation 通风百叶窗安装 6 days 5/7/2022 5/12/2022 5/7
5437 Doors installation门安装 4 days 5/5/2022 5/8/2022 5/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 147
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5438 Cleaning works清理 3 days 5/9/2022 5/11/2022 5/9
5439 B3地下室三层 27 days 4/24/2022 5/20/2022 4/24 B3地下室三层
5440 Work place handover工作面移交 1 day 4/24/2022 4/24/2022 4/24
5441 Setting out放线 3 days 4/25/2022 4/27/2022 4/25
5442 Skirting installation踢脚瓷砖安装 5 days 4/28/2022 5/2/2022 4/28
5443 Wall and Ceiling(Fair Face) Skim Coat 腻子 7 days 5/3/2022 5/9/2022 5/3
5444 Painting 油漆 5 days 5/10/2022 5/14/2022 5/10
5445 Ventilation shutter installation 通风百叶窗安装 6 days 5/15/2022 5/20/2022 5/15
5446 Doors installation门安装 4 days 5/13/2022 5/16/2022 5/13
5447 Cleaning works清理 3 days 5/17/2022 5/19/2022 5/17
5448 GF(ground floor)首层 106 days3/7/2022 6/20/2022 3/7 GF(ground floo
5449 work place handover工作面移交 1 day 3/7/2022 3/7/2022 3/7
5450 FUNCTIONAL AREA 公共区域及功能区域 105 days 3/8/2022 6/20/2022 3/8 FUNCTIONAL A
5451 Setting out放线 5 days 3/8/2022 3/12/2022 3/8
5452 Steel Frame on Ceiling & Wall钢架安装 15 days 3/13/2022 3/27/2022 3/13
5453 ceiling frame吊顶龙骨 10 days 3/13/2022 3/22/2022 3/13
5454 Wall Tiles Construction墙瓷砖安装 20 days 4/22/2022 5/11/2022 4/22
5455 Wood laminate on ceiling吊顶木饰面 10 days 4/22/2022 5/1/2022 4/22
5456 Close gypsum board on ceiling吊顶石膏板安装 5 days 5/2/2022 5/6/2022 5/2
5457 Glass installation 玻璃安装 4 days 5/7/2022 5/10/2022 5/7
5458 Base of ceiling paint 墙涂料施工 5 days 5/7/2022 5/11/2022 5/7
5459 Metal ceiling installation 7 days 5/7/2022 5/13/2022 5/7
5460 Floor granite stone 地板花岗石 10 days 5/14/2022 5/23/2022 5/14
5461 Ceiling paint 吊顶涂料 6 days 5/15/2022 5/20/2022 5/15
5462 Fixed furniture & semi-finished products 25 days 5/21/2022 6/14/2022 5/21
installation 固定家具
5463 Door installation 门安装 6 days 6/15/2022 6/20/2022 6/15
5464 Ground Floor BOH 67 days 3/16/2022 5/21/2022 3/16 Ground Floor BOH
5465 Kitchen, Bakery and Pastry Room 厨房、面包房 67 days 3/16/2022 5/21/2022 3/16 Kitchen, Bakery and Pa
和糕点室
5466 setting out and Inspection 放线 2 days 3/16/2022 3/17/2022 3/16
5467 Floor Finishing 地面工程 20 days 3/18/2022 4/6/2022 3/18 Floor Finishing 地面工程
5468 Water Proofing Work防水 2 days 3/18/2022 3/19/2022 3/18
5469 Floor Screeding Work地坪 2 days 3/23/2022 3/24/2022 3/23
5470 Rigid Insulation Installation Work 刚性绝缘安装
4 days 3/27/2022 3/30/2022 3/27
5471 WWF Reinforced Concrete Topping SlabWWF 3 days 3/31/2022 4/2/2022 3/31
钢筋混凝土顶板
5472 Epoxy Coating Work 环氧树脂涂层 1 day 4/6/2022 4/6/2022 4/6
5473 Wall Finishing Work 墙面施工 10 days 4/8/2022 4/17/2022 4/8 Wall Finishing Work 墙面施工
5474 Wall Skim Coat Work 腻子 4 days 4/8/2022 4/11/2022 4/8
5475 Wall Painting Work 油漆 3 days 4/15/2022 4/17/2022 4/15
5476 Ceiling Work 吊顶施工 15 days 5/7/2022 5/21/2022 5/7 Ceiling Work 吊顶施工

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 148
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5477 Galvanized Steel Ceiling Frame Installation 吊 4 days 5/7/2022 5/10/2022 5/7
顶龙骨
5478 Gypsum board Installation 吊顶封板 2 days 5/10/2022 5/11/2022 5/10
5479 Gypsum Board Skim Coat Work 腻子 4 days 5/12/2022 5/15/2022 5/12
5480 Painting Work 油漆 3 days 5/19/2022 5/21/2022 5/19
5481 Freezer and Chiller Room 冷藏库 28 days 3/16/2022 4/12/2022 3/16 Freezer and Chiller Room 冷藏库
5482 setting out and Inspection 2 days 3/16/2022 3/17/2022 3/16
5483 Floor Finishing 19 days 3/18/2022 4/5/2022 3/18 Floor Finishing
5484 Water Proofing Work 2 days 3/18/2022 3/19/2022 3/18
5485 Floor Screeding Work 2 days 3/23/2022 3/24/2022 3/23
5486 Ventilation Spacer Installation 3 days 3/27/2022 3/29/2022 3/27
5487 Insulated Floor Panel Installation Work 2 days 3/30/2022 3/31/2022 3/30
5488 WWF Reinforced Concrete Topping Slab 2 days 4/1/2022 4/2/2022 4/1
5489 Epoxy Coating Work 1 day 4/5/2022 4/5/2022 4/5
5490 Wall Finishing Work 5 days 4/6/2022 4/10/2022 4/6 Wall Finishing Work
5491 Insulated Panel Installation 2 days 4/6/2022 4/7/2022 4/6
5492 Stainless Steel Installation 3 days 4/8/2022 4/10/2022 4/8
5493 Ceiling Work 7 days 4/6/2022 4/12/2022 4/6 Ceiling Work
5494 Ceiling and Finishing( By Kitchen Consultant) 7 days 4/6/2022 4/12/2022 4/6
5495 RMU Room 14 days 3/21/2022 4/3/2022 3/21 RMU Room
5496 setting out and Inspection 2 days 3/21/2022 3/22/2022 3/21
5497 Floor Finishing 2 days 3/23/2022 3/24/2022 3/23 Floor Finishing
5498 Floor Screeding and Polishing Work 2 days 3/23/2022 3/24/2022 3/23
5499 Wall Finishing Work 8 days 3/27/2022 4/3/2022 3/27 Wall Finishing Work
5500 Wall Skim Coat Work 2 days 3/27/2022 3/28/2022 3/27
5501 Wall Painting work 3 days 4/1/2022 4/3/2022 4/1
5502 Ceiling Work 9 days 3/25/2022 4/2/2022 3/25 Ceiling Work
5503 Skim Coat Work 4 days 3/25/2022 3/28/2022 3/25
5504 Painting Work 2 days 4/1/2022 4/2/2022 4/1
5505 Toilet area卫生间 99 days 3/13/2022 6/19/2022 3/13 Toilet area卫生
5506 setting out 1 day 3/13/2022 3/13/2022 3/13
5507 steel frame on ceiling & wall 2 days 3/28/2022 3/29/2022 3/28
5508 ceiling frame 2 days 3/23/2022 3/24/2022 3/23
5509 close gypsum board on ceiling 2 days 5/7/2022 5/8/2022 5/7
5510 waterproof construction & inspection 1 day 3/30/2022 3/30/2022 3/30
5511 protective layer of waterproof 1 day 3/31/2022 3/31/2022 3/31
5512 base of ceiling paint 7 days 5/9/2022 5/15/2022 5/9
5513 granite stone on toilet floor 3 days 5/24/2022 5/26/2022 5/24
5514 granite stone on toilet wall 4 days 5/22/2022 5/25/2022 5/22
5515 ceiling paint 3 days 5/21/2022 5/23/2022 5/21
5516 sanitary ware installation 5 days 6/15/2022 6/19/2022 6/15
5517 2F(LEVEL 2)二层 97 days 3/17/2022 6/21/2022 3/17 2F(LEVEL 2)二

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 149
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5518 work place handover 1 day 3/17/2022 3/17/2022 3/17
5519 FUNCTIONAL AREA公共区域 92 days 3/18/2022 6/17/2022 3/18 FUNCTIONAL A
5520 Setting out 7 days 3/18/2022 3/24/2022 3/18
5521 Ceiling frame 10 days 3/25/2022 4/3/2022 3/25
5522 Close ceiling gypsum boards 7 days 5/7/2022 5/13/2022 5/7
5523 Skim coat 10 days 5/14/2022 5/23/2022 5/14
5524 Paint 10 days 5/24/2022 6/2/2022 5/24
5525 Perforated aluminum plate installation 7 days 6/3/2022 6/9/2022 6/3
5526 Wall tiles 10 days 5/26/2022 6/4/2022 5/26
5527 Upholstery frame on banquet hall wall 15 days 5/24/2022 6/7/2022 5/24
5528 Steel frame of basin on wall 7 days 5/14/2022 5/20/2022 5/14
5529 Door installation 7 days 6/3/2022 6/9/2022 6/3
5530 Semi-finished products installation 7 days 6/10/2022 6/16/2022 6/10
5531 Carpet installation 10 days 6/8/2022 6/17/2022 6/8
5532 2nd Floor BOH 33 days 4/4/2022 5/6/2022 4/4 2nd Floor BOH
5533 Kitchen厨房 33 days 4/4/2022 5/6/2022 4/4 Kitchen厨房
5534 setting out and Inspection 3 days 4/4/2022 4/6/2022 4/4
5535 Floor Finishing 16 days 4/7/2022 4/22/2022 4/7 Floor Finishing
5536 Water Proofing Work 2 days 4/7/2022 4/8/2022 4/7
5537 Floor Screeding Work 2 days 4/12/2022 4/13/2022 4/12
5538 Rigid Insulation Installation Work 3 days 4/16/2022 4/18/2022 4/16
5539 WWF Reinforced Concrete Topping Slab 3 days 4/19/2022 4/21/2022 4/19
5540 Epoxy Coating Work 1 day 4/22/2022 4/22/2022 4/22
5541 Wall Finishing Work 8 days 4/23/2022 4/30/2022 4/23 Wall Finishing Work
5542 Wall Skim Coat Work 3 days 4/23/2022 4/25/2022 4/23
5543 Wall Painting Work 2 days 4/29/2022 4/30/2022 4/29
5544 Ceiling Work 14 days 4/23/2022 5/6/2022 4/23 Ceiling Work
5545 Galvanized Steel Ceiling Frame Installation 4 days 4/23/2022 4/26/2022 4/23
5546 Gypsum board/Cement Board Installation 2 days 4/26/2022 4/27/2022 4/26
5547 Gypsum Board Skim Coat Work 3 days 4/28/2022 4/30/2022 4/28
5548 Painting Work 3 days 5/4/2022 5/6/2022 5/4
5549 Banquet BOH宴会厅BOH 31 days 4/4/2022 5/4/2022 4/4 Banquet BOH宴会厅BOH
5550 setting out and Inspection 2 days 4/4/2022 4/5/2022 4/4
5551 Floor Finishing 15 days 4/6/2022 4/20/2022 4/6 Floor Finishing
5552 Water Proofing Work 2 days 4/6/2022 4/7/2022 4/6
5553 Floor Screeding Work 1 day 4/11/2022 4/11/2022 4/11
5554 Tile Installation Work 7 days 4/14/2022 4/20/2022 4/14
5555 Wall Finishing Work 8 days 4/21/2022 4/28/2022 4/21 Wall Finishing Work
5556 Skim Coat Work 3 days 4/21/2022 4/23/2022 4/21
5557 Painting Work 2 days 4/27/2022 4/28/2022 4/27
5558 Ceiling Work 14 days 4/21/2022 5/4/2022 4/21 Ceiling Work

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 150
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5559 Galvanized Steel Ceiling Frame Installation 4 days 4/21/2022 4/24/2022 4/21
5560 Gypsum board Installation 2 days 4/24/2022 4/25/2022 4/24
5561 Gypsum Board Skim Coat Work 4 days 4/26/2022 4/29/2022 4/26
5562 Painting Work 2 days 5/3/2022 5/4/2022 5/3
5563 Toilet area 卫生间 89 days 3/25/2022 6/21/2022 3/25 Toilet area 卫
5564 setting out 1 day 3/25/2022 3/25/2022 3/25
5565 ceiling frame 2 days 3/26/2022 3/27/2022 3/26
5566 close ceiling gypsum boards 2 days 5/9/2022 5/10/2022 5/9
5567 base of paint 2 days 5/11/2022 5/12/2022 5/11
5568 paint 1 day 5/13/2022 5/13/2022 5/13
5569 steel frame of basin on wall 2 days 5/21/2022 5/22/2022 5/21
5570 toilet waterproof construction & inspection 1 day 5/23/2022 5/23/2022 5/23
5571 waterproof protective layer 1 day 5/24/2022 5/24/2022 5/24
5572 floor granite stone in toilet 2 days 5/27/2022 5/28/2022 5/27
5573 wall marble stone on toilet wall 2 days 5/26/2022 5/27/2022 5/26
5574 sanitary ware installation 2 days 6/20/2022 6/21/2022 6/20
5575 (LEVEL MEZZANINE FLOOR)夹层 81 days 4/17/2022 7/6/2022 4/17 (LEVEL ME
5576 MF Functional Room功能区域 81 days 4/17/2022 7/6/2022 4/17 MF Funct
5577 Setting out 4 days 4/17/2022 4/20/2022 4/17
5578 Wall tiles 7 days 5/11/2022 5/17/2022 5/11
5579 Ceiling frame 10 days 5/21/2022 5/30/2022 5/21
5580 Close ceiling gypsum boards 8 days 6/5/2022 6/12/2022 6/5
5581 Base of paint on ceiling & wall 7 days 6/18/2022 6/24/2022 6/18
5582 Paint 5 days 6/25/2022 6/29/2022 6/25
5583 Ventilation shutter installation 3 days 6/20/2022 6/22/2022 6/20
5584 Doors installation 4 days 7/3/2022 7/6/2022 7/3
5585 Freezer and Chiller Room 冷藏库 35 days 4/24/2022 5/28/2022 4/24 Freezer and Chiller R
5586 Setting out and Inspection 2 days 4/24/2022 4/25/2022 4/24
5587 Floor Finishing 19 days 4/26/2022 5/14/2022 4/26 Floor Finishing
5588 Water Proofing Work 3 days 4/26/2022 4/28/2022 4/26
5589 Floor Screeding Work 3 days 5/2/2022 5/4/2022 5/2
5590 Ventilation Spacer Installation 2 days 5/7/2022 5/8/2022 5/7
5591 Insulated Floor Panel Installation Work 2 days 5/9/2022 5/10/2022 5/9
5592 WWF Reinforced Concrete Topping Slab 2 days 5/11/2022 5/12/2022 5/11
5593 Epoxy Coating Work 2 days 5/13/2022 5/14/2022 5/13
5594 Wall Finishing Work 5 days 5/15/2022 5/19/2022 5/15 Wall Finishing Work
5595 Insulated Panel Installation 2 days 5/15/2022 5/16/2022 5/15
5596 Stainless Steel Installation 3 days 5/17/2022 5/19/2022 5/17
5597 Ceiling Work 9 days 5/20/2022 5/28/2022 5/20 Ceiling Work
5598 Ceiling and Finishing( By Kitchen Consultant) 9 days 5/20/2022 5/28/2022 5/20
5599 3F(Level 3)三层 65 days 3/26/2022 5/29/2022 3/26 3F(Level 3)三层

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 151
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5600 work place handover工作面移交 1 day 3/29/2022 3/29/2022 3/29
5601 FUNCTIONAL AREA功能区域 64 days 3/26/2022 5/28/2022 3/26 FUNCTIONAL AREA功
5602 Setting out 5 days 3/26/2022 3/30/2022 3/26
5603 Ceiling frame 7 days 3/31/2022 4/6/2022 3/31
5604 Close ceiling gypsum boards 7 days 4/24/2022 4/30/2022 4/24
5605 Base of paint on wall & ceiling 5 days 5/1/2022 5/5/2022 5/1
5606 Paint 4 days 5/8/2022 5/11/2022 5/8
5607 Dry partition wall 3 days 5/1/2022 5/3/2022 5/1
5608 Wall tiles 8 days 5/4/2022 5/11/2022 5/4
5609 Steel frame of basin on wall 5 days 5/12/2022 5/16/2022 5/12
5610 Door installation 3 days 5/20/2022 5/22/2022 5/20
5611 Semi-finished products installation 3 days 5/23/2022 5/25/2022 5/23
5612 Carpet installation 3 days 5/26/2022 5/28/2022 5/26
5613 3F BOH 23 days 3/30/2022 4/21/2022 3/30 3F BOH
5614 3F Pantry Room 茶水间 17 days 3/30/2022 4/15/2022 3/30 3F Pantry Room 茶水间
5615 setting out and Inspection 1 day 3/30/2022 3/30/2022 3/30
5616 Floor Finishing 8 days 3/31/2022 4/7/2022 3/31 Floor Finishing
5617 Floor Screeding Work 2 days 3/31/2022 4/1/2022 3/31
5618 Tilling Work 3 days 4/5/2022 4/7/2022 4/5
5619 Wall Finishing Work 8 days 4/8/2022 4/15/2022 4/8 Wall Finishing Work
5620 Wall Skim Coat Work 2 days 4/8/2022 4/9/2022 4/8
5621 Wall Painting Work 3 days 4/13/2022 4/15/2022 4/13
5622 Ceiling Work 8 days 4/8/2022 4/15/2022 4/8 Ceiling Work
5623 Skim Coat 3 days 4/8/2022 4/10/2022 4/8
5624 Painting 2 days 4/14/2022 4/15/2022 4/14
5625 3F AV Room 影音室 23 days 3/30/2022 4/21/2022 3/30 3F AV Room 影音室
5626 setting out and Inspection 2 days 3/30/2022 3/31/2022 3/30
5627 Floor Finishing 7 days 4/1/2022 4/7/2022 4/1 Floor Finishing
5628 Floor Screeding Work 2 days 4/1/2022 4/2/2022 4/1
5629 Tilling Work 3 days 4/5/2022 4/7/2022 4/5
5630 Wall Finishing Work 7 days 4/8/2022 4/14/2022 4/8 Wall Finishing Work
5631 Wall Skim Coat Work 2 days 4/8/2022 4/9/2022 4/8
5632 Wall Painting Work 3 days 4/12/2022 4/14/2022 4/12
5633 Ceiling Work 14 days 4/8/2022 4/21/2022 4/8 Ceiling Work
5634 Galvanized Steel Ceiling Frame Installation 3 days 4/8/2022 4/10/2022 4/8
5635 Gypsum board Installation 2 days 4/11/2022 4/12/2022 4/11
5636 Gypsum Board Skim Coat Work 4 days 4/13/2022 4/16/2022 4/13
5637 Painting Work 2 days 4/20/2022 4/21/2022 4/20
5638 Toilet area卫生间 60 days 3/31/2022 5/29/2022 3/31 Toilet area卫生间
5639 setting out 5 days 3/31/2022 4/4/2022 3/31
5640 ceiling frame 7 days 4/5/2022 4/11/2022 4/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 152
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5641 close ceiling gypsum boards 7 days 5/1/2022 5/7/2022 5/1
5642 Skimcoating 5 days 5/6/2022 5/10/2022 5/6
5643 Paint 4 days 5/12/2022 5/15/2022 5/12
5644 steel frame of basin on wall 5 days 5/17/2022 5/21/2022 5/17
5645 toilet waterproof construction & inspection 7 days 5/22/2022 5/28/2022 5/22
5646 waterproof protective layer 1 day 5/29/2022 5/29/2022 5/29
5647 floor granite stone in toilet 4 days 5/12/2022 5/15/2022 5/12
5648 wall marble stone on toilet wall 6 days 5/16/2022 5/21/2022 5/16
5649 sanitary ware installation 3 days 5/22/2022 5/24/2022 5/22
5650 4F(Level 4)四层 54 days 4/6/2022 5/29/2022 4/6 4F(Level 4)四层
5651 Functional AREA功能区域 54 days 4/6/2022 5/29/2022 4/6 Functional AREA功能
5652 Work place handover 1 day 4/6/2022 4/6/2022 4/6
5653 Setting out 3 days 4/7/2022 4/9/2022 4/7
5654 Ceiling frame 7 days 4/10/2022 4/16/2022 4/10
5655 Wall tiles 3 days 4/22/2022 4/24/2022 4/22
5656 Close ceiling gypsum boards 7 days 5/1/2022 5/7/2022 5/1
5657 Base of paint on ceiling & wall 10 days 5/15/2022 5/24/2022 5/15
5658 Paint 5 days 5/25/2022 5/29/2022 5/25
5659 Doors installation 3 days 5/9/2022 5/11/2022 5/9
5660 Skirting installation 4 days 5/9/2022 5/12/2022 5/9
5661 Staff Kitchen 员工厨房 42 days 4/10/2022 5/21/2022 4/10 Staff Kitchen 员工厨房
5662 setting out and Inspection 2 days 4/10/2022 4/11/2022 4/10
5663 Floor Finishing 18 days 4/12/2022 4/29/2022 4/12 Floor Finishing
5664 Water Proofing Work 2 days 4/12/2022 4/13/2022 4/12
5665 Floor Screeding Work 2 days 4/16/2022 4/17/2022 4/16
5666 Rigid Insulation Installation Work 4 days 4/20/2022 4/23/2022 4/20
5667 WWF Reinforced Concrete Topping Slab 3 days 4/24/2022 4/26/2022 4/24
5668 Epoxy Coating Work 3 days 4/27/2022 4/29/2022 4/27
5669 Wall Finishing Work 7 days 4/30/2022 5/6/2022 4/30 Wall Finishing Work
5670 Wall Skim Coat Work 2 days 4/30/2022 5/1/2022 4/30
5671 Wall Painting Work 2 days 5/5/2022 5/6/2022 5/5
5672 Ceiling Work 22 days 4/30/2022 5/21/2022 4/30 Ceiling Work
5673 Galvanized Steel Ceiling Frame Installation 4 days 4/30/2022 5/3/2022 4/30
5674 Gypsum Board Installation 2 days 5/4/2022 5/5/2022 5/4
5675 Gypsum Board Skim Coat Work 3 days 5/6/2022 5/8/2022 5/6
5676 Painting Work 3 days 5/12/2022 5/14/2022 5/12
5677 Vapor Barrier Interlayer Installation 2 days 5/20/2022 5/21/2022 5/20
5678 5F(LEVEL 5)五层 93 days 3/6/2022 6/6/2022 3/6 5F(LEVEL 5)五层
5679 FUNCTIONAL AREA功能区域 88 days 3/6/2022 6/1/2022 3/6 FUNCTIONAL AREA功
5680 Setting out 5 days 3/31/2022 4/4/2022 3/31
5681 Ceiling frame 10 days 4/5/2022 4/14/2022 4/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 153
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5682 Close ceiling gypsum boards 7 days 3/6/2022 3/12/2022 3/6
5683 Base of wall paper & ceiling paint 10 days 3/15/2022 3/24/2022 3/15
5684 Ceiling paint 7 days 3/25/2022 3/31/2022 3/25
5685 Steel frame of basin on wall 3 days 4/15/2022 4/17/2022 4/15
5686 Floor tiles 10 days 4/16/2022 4/25/2022 4/16
5687 Door installation 7 days 5/2/2022 5/8/2022 5/2
5688 Fixed furniture 4 days 5/26/2022 5/29/2022 5/26
5689 Carpet 3 days 5/30/2022 6/1/2022 5/30
5690 Toilet area卫生间 86 days 3/13/2022 6/6/2022 3/13 Toilet area卫生间
5691 Setting out 1 day 4/5/2022 4/5/2022 4/5
5692 Ceiling frame 2 days 4/15/2022 4/16/2022 4/15
5693 Close ceiling gypsum boards 3 days 3/13/2022 3/15/2022 3/13
5694 Base of paint 2 days 3/16/2022 3/17/2022 3/16
5695 Paint 2 days 3/18/2022 3/19/2022 3/18
5696 Steel frame of basin on wall 2 days 3/16/2022 3/17/2022 3/16
5697 Toilet waterproof construction & inspection 7 days 5/29/2022 6/4/2022 5/29
5698 Waterproof protective layer 2 days 6/5/2022 6/6/2022 6/5
5699 Floor granite stone in toilet 5 days 5/31/2022 6/4/2022 5/31
5700 Wall marble stone on toilet wall 5 days 5/31/2022 6/4/2022 5/31
5701 Sanitary ware installation 2 days 6/5/2022 6/6/2022 6/5
5702 19F(LEVEL 19)EXECUTIVE LOUNGE BAR酒廊精装修 88 days 2/21/2022 5/19/2022 2/21 19F(LEVEL 19)EXECUTIV
5703 work place handover 1 day 4/8/2022 4/8/2022 4/8
5704 FUNCTIONAL AREA 65 days 2/21/2022 4/26/2022 2/21 FUNCTIONAL AREA
5705 Setting out 3 days 4/9/2022 4/11/2022 4/9
5706 Ceiling frame 10 days 4/12/2022 4/21/2022 4/12
5707 Close ceiling gypsum boards 10 days 2/21/2022 3/2/2022 2/21
5708 Base of wall paper & ceiling paint 10 days 3/3/2022 3/12/2022 3/3
5709 Base of paint 8 days 3/18/2022 3/25/2022 3/18
5710 Paint 5 days 3/26/2022 3/30/2022 3/26
5711 Floor tiles 15 days 2/21/2022 3/7/2022 2/21
5712 Wall tiles 7 days 2/21/2022 2/27/2022 2/21
5713 Wall laminate installation 15 days 2/28/2022 3/14/2022 2/28
5714 Sanitary ware installation 3 days 4/20/2022 4/22/2022 4/20
5715 Door installation 4 days 4/23/2022 4/26/2022 4/23
5716 Toilet area 85 days 2/24/2022 5/19/2022 2/24 Toilet area
5717 Setting out 2 days 4/12/2022 4/13/2022 4/12
5718 Ceiling frame 2 days 2/24/2022 2/25/2022 2/24
5719 Close ceiling gypsum boards 2 days 3/3/2022 3/4/2022 3/3
5720 Base of paint 2 days 3/5/2022 3/6/2022 3/5
5721 Paint 1 day 3/7/2022 3/7/2022 3/7
5722 Floor tiles 2 days 3/8/2022 3/9/2022 3/8

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 154
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5723 Wall tiles in toilet 2 days 3/10/2022 3/11/2022 3/10
5724 Sanitary ware installation 2 days 5/18/2022 5/19/2022 5/18
5725 MEP Work机电 198 days11/18/20216/3/2022 11/18 MEP Work机电
5726 Guest Room & Corridor MEP Work 客房及走廊 194 days11/20/2021 6/1/2022 11/20 Guest Room & Corri
5727 MEP Level 6 机电6层 138 days12/9/2021 4/25/2022 12/9 MEP Level 6 机电6层
5728 Guest Room MEP Installation(1&2 Fix)客房机电安装127 days12/9/2021 4/14/2022 12/9 Guest Room MEP Installation(1&2
5729 Room 6-001-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-001-S2
5730 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5731 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5732 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5733 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5734 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5735 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5736 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5737 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5738 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5739 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5740 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5741 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5742 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5743 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5744 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5745 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5746 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5747 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5748 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5749 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5750 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5751 Room 6-002-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-002-S2
5752 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5753 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5754 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5755 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5756 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5757 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5758 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5759 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5760 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5761 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5762 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5763 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 155
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5764 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5765 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5766 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5767 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5768 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5769 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5770 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5771 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5772 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5773 Room 6-003-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-003-S2
5774 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5775 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5776 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5777 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5778 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5779 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5780 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5781 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5782 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5783 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5784 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5785 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5786 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5787 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5788 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5789 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5790 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5791 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5792 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5793 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5794 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5795 Room 6-004-S1 127 days12/9/2021 4/14/2022 12/9 Room 6-004-S1
5796 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5797 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5798 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5799 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5800 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5801 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5802 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5803 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5804 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 156
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5805 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5806 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5807 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5808 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5809 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5810 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5811 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5812 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5813 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5814 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5815 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5816 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5817 Room 6-005-S2b 127 days12/9/2021 4/14/2022 12/9 Room 6-005-S2b
5818 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5819 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5820 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5821 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5822 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5823 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5824 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5825 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5826 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5827 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5828 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5829 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5830 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5831 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5832 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5833 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5834 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5835 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5836 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5837 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5838 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5839 Room 6-006-S4 127 days12/9/2021 4/14/2022 12/9 Room 6-006-S4
5840 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5841 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5842 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5843 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5844 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5845 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 157
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5846 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5847 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5848 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5849 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5850 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5851 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5852 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5853 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5854 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5855 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5856 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5857 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5858 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5859 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5860 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5861 Room 6-007-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-007-S2
5862 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5863 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5864 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5865 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5866 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5867 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5868 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5869 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5870 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5871 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5872 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5873 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5874 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5875 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5876 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5877 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5878 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5879 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5880 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5881 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5882 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5883 Room 6-008-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-008-S2
5884 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5885 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5886 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 158
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5887 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5888 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5889 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5890 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5891 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5892 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5893 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5894 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5895 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5896 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5897 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5898 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5899 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5900 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5901 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5902 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5903 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5904 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5905 Room 6-009-S4 127 days12/9/2021 4/14/2022 12/9 Room 6-009-S4
5906 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5907 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5908 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5909 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5910 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5911 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5912 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5913 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5914 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5915 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5916 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5917 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5918 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5919 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5920 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5921 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5922 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5923 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5924 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5925 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5926 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5927 Room 6-010-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-010-S2

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 159
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5928 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5929 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5930 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5931 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5932 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5933 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5934 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5935 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5936 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5937 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5938 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5939 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5940 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5941 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5942 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5943 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5944 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5945 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5946 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5947 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5948 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5949 Room 6-011-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-011-S2
5950 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5951 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5952 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5953 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5954 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5955 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5956 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5957 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5958 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5959 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5960 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5961 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5962 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5963 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5964 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5965 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5966 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5967 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5968 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 160
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
5969 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5970 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5971 Room 6-012-S1 127 days12/9/2021 4/14/2022 12/9 Room 6-012-S1
5972 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5973 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5974 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5975 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5976 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5977 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
5978 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
5979 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
5980 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
5981 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
5982 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
5983 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
5984 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
5985 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
5986 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
5987 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
5988 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
5989 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
5990 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
5991 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
5992 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
5993 Room 6-013-S2b 127 days12/9/2021 4/14/2022 12/9 Room 6-013-S2b
5994 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
5995 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
5996 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
5997 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
5998 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
5999 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
6000 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
6001 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
6002 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
6003 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
6004 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
6005 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
6006 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
6007 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
6008 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
6009 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 161
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6010 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
6011 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
6012 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
6013 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
6014 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
6015 Room 6-014-S2 127 days12/9/2021 4/14/2022 12/9 Room 6-014-S2
6016 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
6017 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
6018 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
6019 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
6020 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
6021 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
6022 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
6023 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
6024 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
6025 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
6026 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
6027 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
6028 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
6029 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
6030 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
6031 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
6032 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
6033 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
6034 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
6035 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
6036 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
6037 MEP Corridor机电走廊安装 39 days 12/15/2021 1/22/2022 12/15 MEP Corridor机电走廊安装
6038 Electrical System installation 29 days 12/15/2021 1/12/2022 12/15 Electrical System installation
6039 Cable tray installation 桥架安装 4 days 12/15/2021 12/18/2021 12/15
6040 LV cable installation 强电电缆安装 4 days 12/26/202112/29/2021 12/26
6041 ELV cable installation 弱电电缆安装 4 days 1/9/2022 1/12/2022 1/9
6042 Fire fighting piping installation消防系统 14 days 1/9/2022 1/22/2022 1/9 Fire fighting piping installation消防系统
6043 Fire fighting pipe installation消防管安装 10 days 1/9/2022 1/18/2022 1/9
6044 Testing 测试 4 days 1/19/2022 1/22/2022 1/19
6045 MVAC System installation空调系统 20 days 12/25/2021 1/13/2022 12/25 MVAC System installation空调系统
6046 Ducting for AC installation风管安装 7 days 12/25/2021 12/31/2021 12/25
6047 Chiller water pipe installation冷冻水管安装 14 days 12/25/2021 1/7/2022 12/25
6048 AC drain pipe installation空调排水管安装 5 days 12/30/2021 1/3/2022 12/30
6049 Testing 测试 3 days 1/8/2022 1/10/2022 1/8
6050 Duct/pipe insulation保温安装 3 days 1/11/2022 1/13/2022 1/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 162
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6051 MEP Final Fix机电末端安装 15 days 4/11/2022 4/25/2022 4/11 MEP Final Fix机电末端安装
6052 Electrical Installation 15 days 4/11/2022 4/25/2022 4/11 Electrical Installation
6053 Fire alarm system 火警系统安装 5 days 4/11/2022 4/15/2022 4/11
6054 Public address system 公共广播系统 5 days 4/13/2022 4/17/2022 4/13
6055 Access control system 门禁系统 5 days 4/19/2022 4/23/2022 4/19
6056 Sockets and Switches Installation 开关插座 5 days 4/16/2022 4/20/2022 4/16
6057 Normal & Emergency Luminaires installation 普 5 days 4/21/2022 4/25/2022 4/21
通和应急照明安装
6058 MVAC Installation 10 days 4/14/2022 4/23/2022 4/14 MVAC Installation
6059 Air grille/louver installation 通风格棚、百叶窗安装 5 days 4/14/2022 4/18/2022 4/14
6060 Wall controller units installation墙壁控制器 5 days 4/19/2022 4/23/2022 4/19
6061 Fire Protection Installation 10 days 4/14/2022 4/23/2022 4/14 Fire Protection Installation
6062 Sprinkler Installation 喷淋头安装 5 days 4/19/2022 4/23/2022 4/19
6063 Fire hose reel cabinet消防箱带卷盘 5 days 4/14/2022 4/19/2022 4/14
6064 MEP Level 7 机电7层 108 days11/20/2021 3/7/2022 11/20 MEP Level 7 机电7层
6065 Guest Room MEP Installation(1&2 Fix)客房机电安装67 days 11/21/2021 1/26/2022 11/21 Guest Room MEP Installation(1&2 Fix)客房机电安装
6066 Room 7-001-S2 67 days 11/21/20211/26/2022 11/21 Room 7-001-S2
6067 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6068 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6069 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6070 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6071 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6072 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6073 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6074 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6075 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6076 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6077 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6078 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6079 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6080 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6081 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6082 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6083 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6084 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6085 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6086 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6087 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6088 Room 7-002-S2 67 days 11/21/20211/26/2022 11/21 Room 7-002-S2
6089 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6090 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6091 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 163
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6092 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6093 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6094 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6095 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6096 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6097 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6098 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6099 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6100 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6101 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6102 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6103 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6104 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6105 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6106 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6107 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6108 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6109 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6110 Room 7-003-S2 67 days 11/21/20211/26/2022 11/21 Room 7-003-S2
6111 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6112 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6113 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6114 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6115 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6116 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6117 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6118 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6119 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6120 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6121 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6122 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6123 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6124 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6125 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6126 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6127 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6128 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6129 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6130 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6131 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6132 Room 7-004-S1 67 days 11/21/20211/26/2022 11/21 Room 7-004-S1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 164
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6133 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6134 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6135 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6136 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6137 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6138 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6139 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6140 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6141 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6142 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6143 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6144 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6145 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6146 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6147 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6148 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6149 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6150 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6151 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6152 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6153 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6154 Room 7-005-S2b 67 days 11/21/20211/26/2022 11/21 Room 7-005-S2b
6155 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6156 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6157 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6158 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6159 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6160 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6161 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6162 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6163 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6164 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6165 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6166 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6167 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6168 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6169 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6170 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6171 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6172 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6173 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 165
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6174 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6175 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6176 Room 7-006-S4 67 days 11/21/20211/26/2022 11/21 Room 7-006-S4
6177 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6178 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6179 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6180 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6181 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6182 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6183 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6184 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6185 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6186 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6187 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6188 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6189 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6190 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6191 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6192 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6193 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6194 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6195 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6196 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6197 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6198 Room 7-007-S2 67 days 11/21/20211/26/2022 11/21 Room 7-007-S2
6199 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6200 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6201 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6202 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6203 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6204 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6205 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6206 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6207 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6208 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6209 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6210 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6211 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6212 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6213 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6214 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 166
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6215 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6216 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6217 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6218 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6219 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6220 Room 7-008-S2 67 days 11/21/20211/26/2022 11/21 Room 7-008-S2
6221 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6222 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6223 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6224 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6225 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6226 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6227 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6228 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6229 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6230 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6231 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6232 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6233 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6234 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6235 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6236 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6237 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6238 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6239 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6240 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6241 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6242 Room 7-009-S4 67 days 11/21/20211/26/2022 11/21 Room 7-009-S4
6243 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6244 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6245 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6246 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6247 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6248 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6249 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6250 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6251 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6252 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6253 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6254 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6255 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 167
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6256 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6257 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6258 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6259 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6260 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6261 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6262 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6263 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6264 Room 7-010-S2 67 days 11/21/20211/26/2022 11/21 Room 7-010-S2
6265 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6266 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6267 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6268 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6269 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6270 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6271 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6272 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6273 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6274 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6275 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6276 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6277 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6278 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6279 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6280 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6281 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6282 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6283 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6284 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6285 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6286 Room 7-011-S2 67 days 11/21/20211/26/2022 11/21 Room 7-011-S2
6287 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6288 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6289 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6290 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6291 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6292 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6293 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6294 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6295 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6296 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 168
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6297 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6298 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6299 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6300 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6301 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6302 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6303 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6304 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6305 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6306 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6307 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6308 Room 7-012-S1ds 67 days 11/21/20211/26/2022 11/21 Room 7-012-S1ds
6309 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6310 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6311 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6312 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6313 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6314 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6315 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6316 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6317 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6318 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6319 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6320 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6321 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6322 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6323 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6324 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6325 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6326 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6327 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6328 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6329 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6330 Room 7-013-S1 67 days 11/21/20211/26/2022 11/21 Room 7-013-S1
6331 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6332 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6333 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6334 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6335 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6336 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6337 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 169
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6338 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6339 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6340 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6341 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6342 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6343 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6344 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6345 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6346 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6347 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6348 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6349 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6350 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6351 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6352 Room 7-014-S2 67 days 11/21/20211/26/2022 11/21 Room 7-014-S2
6353 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6354 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6355 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6356 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6357 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6358 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6359 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6360 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6361 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6362 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6363 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6364 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6365 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6366 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6367 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6368 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6369 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6370 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6371 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6372 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6373 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6374 MEP Corridor机电走廊安装 20 days 11/20/2021 12/9/2021 11/20 MEP Corridor机电走廊安装
6375 Electrical System installation 15 days 11/25/2021 12/9/2021 11/25 Electrical System installation
6376 Cable tray installation 桥架安装 4 days 11/25/2021 11/28/2021 11/25
6377 LV cable installation 强电电缆安装 4 days 12/6/2021 12/9/2021 12/6
6378 ELV cable installation 弱电电缆安装 4 days 12/6/2021 12/9/2021 12/6

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 170
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6379 Fire fighting piping installation消防系统 14 days 11/20/2021 12/3/2021 11/20 Fire fighting piping installation消防系统
6380 Fire fighting pipe installation消防管安装 10 days 11/20/2021 11/29/2021 11/20
6381 Testing 测试 4 days 11/30/2021 12/3/2021 11/30
6382 MVAC System installation空调系统 20 days 11/20/2021 12/9/2021 11/20 MVAC System installation空调系统
6383 Ducting for AC installation风管安装 7 days 11/20/2021 11/26/2021 11/20
6384 Chiller water pipe installation冷冻水管安装 14 days 11/20/2021 12/3/2021 11/20
6385 AC drain pipe installation空调排水管安装 5 days 11/25/2021 11/29/2021 11/25
6386 Testing 测试 3 days 12/4/2021 12/6/2021 12/4
6387 Duct/pipe insulation保温安装 3 days 12/7/2021 12/9/2021 12/7
6388 MEP Final Fix机电末端安装 31 days 2/5/2022 3/7/2022 2/5 MEP Final Fix机电末端安装
6389 Electrical Installation电气系统末端安装 31 days 2/5/2022 3/7/2022 2/5 Electrical Installation电气系统末端安装
6390 Fire alarm system 火警系统安装 7 days 2/5/2022 2/11/2022 2/5
6391 Public address system 公共广播系统 5 days 2/17/2022 2/21/2022 2/17
6392 Access control system 门禁系统 5 days 2/22/2022 2/26/2022 2/22
6393 Sockets and Switches Installation 开关插座 4 days 2/27/2022 3/2/2022 2/27
6394 Normal & Emergency Luminaires installation 普 5 days 3/3/2022 3/7/2022 3/3
通和应急照明安装
6395 MVAC Installation空调系统末端安装 8 days 2/15/2022 2/22/2022 2/15 MVAC Installation空调系统末端安装
6396 Air grille/louver installation 通风格棚、百叶窗安装 4 days 2/15/2022 2/18/2022 2/15
6397 Wall controller units installation墙壁控制器 4 days 2/19/2022 2/22/2022 2/19
6398 Fire Protection Installation消防系统末端安装 17 days 2/19/2022 3/7/2022 2/19 Fire Protection Installation消防系统末端安装
6399 Sprinkler Installation 喷淋头安装 5 days 2/19/2022 2/23/2022 2/19
6400 Fire hose reel cabinet消防箱带卷盘 4 days 3/4/2022 3/7/2022 3/4
6401 MEP Level 8 机电8层 112 days11/20/2021 3/11/2022 11/20 MEP Level 8 机电8层
6402 Guest Room MEP Installation(1&2 Fix)客房机电安装67 days 11/21/2021 1/26/2022 11/21 Guest Room MEP Installation(1&2 Fix)客房机电安装
6403 Room 8-001-S2 67 days 11/21/20211/26/2022 11/21 Room 8-001-S2
6404 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6405 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6406 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6407 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6408 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6409 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6410 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6411 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6412 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6413 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6414 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6415 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6416 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6417 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6418 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6419 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 171
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6420 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6421 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6422 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6423 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6424 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6425 Room 8-002-S2 67 days 11/21/20211/26/2022 11/21 Room 8-002-S2
6426 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6427 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6428 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6429 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6430 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6431 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6432 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6433 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6434 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6435 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6436 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6437 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6438 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6439 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6440 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6441 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6442 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6443 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6444 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6445 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6446 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6447 Room 8-003-S2 67 days 11/21/20211/26/2022 11/21 Room 8-003-S2
6448 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6449 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6450 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6451 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6452 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6453 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6454 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6455 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6456 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6457 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6458 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6459 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6460 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 172
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6461 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6462 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6463 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6464 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6465 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6466 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6467 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6468 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6469 Room 8-004-S1 67 days 11/21/20211/26/2022 11/21 Room 8-004-S1
6470 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6471 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6472 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6473 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6474 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6475 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6476 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6477 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6478 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6479 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6480 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6481 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6482 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6483 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6484 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6485 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6486 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6487 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6488 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6489 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6490 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6491 Room 8-005-S2b 67 days 11/21/20211/26/2022 11/21 Room 8-005-S2b
6492 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6493 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6494 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6495 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6496 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6497 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6498 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6499 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6500 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6501 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 173
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6502 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6503 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6504 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6505 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6506 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6507 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6508 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6509 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6510 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6511 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6512 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6513 Room 8-006-S4 67 days 11/21/20211/26/2022 11/21 Room 8-006-S4
6514 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6515 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6516 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6517 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6518 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6519 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6520 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6521 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6522 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6523 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6524 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6525 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6526 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6527 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6528 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6529 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6530 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6531 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6532 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6533 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6534 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6535 Room 8-007-S2 67 days 11/21/20211/26/2022 11/21 Room 8-007-S2
6536 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6537 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6538 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6539 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6540 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6541 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6542 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 174
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6543 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6544 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6545 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6546 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6547 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6548 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6549 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6550 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6551 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6552 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6553 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6554 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6555 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6556 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6557 Room 8-008-S2 67 days 11/21/20211/26/2022 11/21 Room 8-008-S2
6558 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6559 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6560 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6561 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6562 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6563 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6564 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6565 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6566 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6567 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6568 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6569 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6570 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6571 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6572 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6573 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6574 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6575 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6576 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6577 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6578 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6579 Room 8-009-S4 67 days 11/21/20211/26/2022 11/21 Room 8-009-S4
6580 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6581 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6582 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6583 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 175
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6584 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6585 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6586 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6587 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6588 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6589 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6590 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6591 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6592 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6593 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6594 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6595 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6596 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6597 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6598 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6599 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6600 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6601 Room 8-010-S2 67 days 11/21/20211/26/2022 11/21 Room 8-010-S2
6602 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6603 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6604 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6605 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6606 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6607 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6608 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6609 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6610 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6611 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6612 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6613 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6614 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6615 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6616 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6617 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6618 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6619 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6620 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6621 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6622 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6623 Room 8-011-S2 67 days 11/21/20211/26/2022 11/21 Room 8-011-S2
6624 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 176
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6625 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6626 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6627 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6628 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6629 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6630 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6631 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6632 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6633 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6634 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6635 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6636 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6637 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6638 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6639 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6640 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6641 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6642 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6643 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6644 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6645 Room 8-012-S1 67 days 11/21/20211/26/2022 11/21 Room 8-012-S1
6646 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6647 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6648 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6649 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6650 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6651 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6652 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6653 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6654 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6655 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6656 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6657 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6658 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6659 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6660 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6661 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6662 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6663 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6664 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6665 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 177
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6666 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6667 Room 8-013-S2b 67 days 11/21/20211/26/2022 11/21 Room 8-013-S2b
6668 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6669 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6670 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6671 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6672 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6673 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6674 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6675 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6676 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6677 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6678 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6679 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6680 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6681 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6682 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6683 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6684 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6685 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6686 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6687 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6688 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6689 Room 8-014-S2 67 days 11/21/20211/26/2022 11/21 Room 8-014-S2
6690 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6691 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6692 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6693 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6694 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6695 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6696 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6697 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6698 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6699 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6700 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6701 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6702 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6703 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6704 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6705 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6706 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 178
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6707 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6708 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6709 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6710 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6711 MEP Corridor机电走廊安装 20 days 11/20/2021 12/9/2021 11/20 MEP Corridor机电走廊安装
6712 Electrical System installation 15 days 11/25/2021 12/9/2021 11/25 Electrical System installation
6713 Cable tray installation 桥架安装 4 days 11/25/2021 11/28/2021 11/25
6714 LV cable installation 强电电缆安装 4 days 12/6/2021 12/9/2021 12/6
6715 ELV cable installation 弱电电缆安装 4 days 12/6/2021 12/9/2021 12/6
6716 Fire fighting piping installation消防系统 14 days 11/20/2021 12/3/2021 11/20 Fire fighting piping installation消防系统
6717 Fire fighting pipe installation消防管安装 10 days 11/20/2021 11/29/2021 11/20
6718 Testing 测试 4 days 11/30/2021 12/3/2021 11/30
6719 MVAC System installation空调系统 20 days 11/20/2021 12/9/2021 11/20 MVAC System installation空调系统
6720 Ducting for AC installation风管安装 7 days 11/20/2021 11/26/2021 11/20
6721 Chiller water pipe installation冷冻水管安装 14 days 11/20/2021 12/3/2021 11/20
6722 AC drain pipe installation空调排水管安装 5 days 11/25/2021 11/29/2021 11/25
6723 Testing 测试 3 days 12/4/2021 12/6/2021 12/4
6724 Duct/pipe insulation保温安装 3 days 12/7/2021 12/9/2021 12/7
6725 MEP Final Fix机电末端安装 28 days 2/12/2022 3/11/2022 2/12 MEP Final Fix机电末端安装
6726 Electrical Installation电气系统末端安装 28 days 2/12/2022 3/11/2022 2/12 Electrical Installation电气系统末端安装
6727 Fire alarm system 火警系统安装 7 days 2/12/2022 2/18/2022 2/12
6728 Public address system 公共广播系统 5 days 2/14/2022 2/18/2022 2/14
6729 Access control system 门禁系统 5 days 2/17/2022 2/21/2022 2/17
6730 Sockets and Switches Installation 开关插座 4 days 3/3/2022 3/6/2022 3/3
6731 Normal & Emergency Luminaires installation 普 5 days 3/7/2022 3/11/2022 3/7
通和应急照明安装
6732 MVAC Installation空调系统末端安装 12 days 2/19/2022 3/2/2022 2/19 MVAC Installation空调系统末端安装
6733 Air grille/louver installation 通风格棚、百叶窗安装 7 days 2/19/2022 2/25/2022 2/19
6734 Wall controller units installation墙壁控制器 5 days 2/26/2022 3/2/2022 2/26
6735 Fire Protection Installation消防系统末端安装 16 days 2/24/2022 3/11/2022 2/24 Fire Protection Installation消防系统末端安
6736 Sprinkler Installation 喷淋头安装 5 days 2/24/2022 2/28/2022 2/24
6737 Fire hose reel cabinet消防箱带卷盘 4 days 3/8/2022 3/11/2022 3/8
6738 MEP Level 9 机电9层 116 days11/20/2021 3/15/2022 11/20 MEP Level 9 机电9层
6739 Guest Room MEP Installation(1&2 Fix)客房机电安装67 days 11/21/2021 1/26/2022 11/21 Guest Room MEP Installation(1&2 Fix)客房机电安装
6740 Room 9-001-S2 67 days 11/21/20211/26/2022 11/21 Room 9-001-S2
6741 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6742 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6743 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6744 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6745 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6746 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6747 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 179
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6748 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6749 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6750 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6751 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6752 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6753 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6754 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6755 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6756 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6757 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6758 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6759 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6760 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6761 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6762 Room 9-002-S2 67 days 11/21/20211/26/2022 11/21 Room 9-002-S2
6763 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6764 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6765 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6766 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6767 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6768 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6769 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6770 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6771 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6772 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6773 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6774 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6775 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6776 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6777 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6778 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6779 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6780 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6781 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6782 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6783 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6784 Room 9-003-S2 67 days 11/21/20211/26/2022 11/21 Room 9-003-S2
6785 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6786 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6787 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6788 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 180
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6789 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6790 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6791 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6792 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6793 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6794 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6795 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6796 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6797 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6798 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6799 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6800 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6801 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6802 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6803 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6804 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6805 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6806 Room 9-004-S1 67 days 11/21/20211/26/2022 11/21 Room 9-004-S1
6807 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6808 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6809 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6810 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6811 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6812 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6813 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6814 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6815 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6816 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6817 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6818 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6819 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6820 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6821 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6822 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6823 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6824 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6825 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6826 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6827 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6828 Room 9-005-S2b 67 days 11/21/20211/26/2022 11/21 Room 9-005-S2b
6829 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 181
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6830 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6831 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6832 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6833 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6834 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6835 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6836 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6837 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6838 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6839 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6840 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6841 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6842 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6843 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6844 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6845 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6846 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6847 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6848 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6849 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6850 Room 9-006-S4 67 days 11/21/20211/26/2022 11/21 Room 9-006-S4
6851 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6852 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6853 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6854 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6855 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6856 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6857 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6858 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6859 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6860 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6861 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6862 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6863 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6864 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6865 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6866 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6867 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6868 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6869 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6870 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 182
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6871 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6872 Room 9-007-S2 67 days 11/21/20211/26/2022 11/21 Room 9-007-S2
6873 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6874 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6875 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6876 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6877 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6878 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6879 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6880 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6881 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6882 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6883 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6884 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6885 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6886 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6887 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6888 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6889 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6890 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6891 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6892 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6893 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6894 Room 9-008-S2 67 days 11/21/20211/26/2022 11/21 Room 9-008-S2
6895 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6896 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6897 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6898 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6899 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6900 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6901 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6902 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6903 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6904 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6905 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6906 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6907 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6908 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6909 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6910 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6911 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 183
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6912 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6913 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6914 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6915 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6916 Room 10-009-S4 67 days 11/21/20211/26/2022 11/21 Room 10-009-S4
6917 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6918 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6919 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6920 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6921 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6922 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6923 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6924 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6925 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6926 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6927 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6928 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6929 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6930 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6931 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6932 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6933 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6934 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6935 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6936 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6937 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6938 Room 9-010-S2 67 days 11/21/20211/26/2022 11/21 Room 9-010-S2
6939 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6940 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6941 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6942 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6943 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6944 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6945 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6946 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6947 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6948 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6949 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6950 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6951 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6952 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 184
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6953 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6954 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6955 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6956 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6957 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6958 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6959 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6960 Room 9-011-S2 67 days 11/21/20211/26/2022 11/21 Room 9-011-S2
6961 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6962 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6963 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6964 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6965 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6966 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6967 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6968 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6969 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6970 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6971 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
6972 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6973 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6974 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6975 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6976 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6977 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
6978 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
6979 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
6980 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
6981 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
6982 Room 9-012-S1 67 days 11/21/20211/26/2022 11/21 Room 9-012-S1
6983 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
6984 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
6985 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
6986 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
6987 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
6988 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
6989 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
6990 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
6991 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
6992 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
6993 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 185
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
6994 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
6995 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
6996 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
6997 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
6998 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
6999 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
7000 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
7001 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
7002 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
7003 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
7004 Room 9-013-S2b 67 days 11/21/20211/26/2022 11/21 Room 9-013-S2b
7005 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
7006 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
7007 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
7008 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
7009 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
7010 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
7011 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
7012 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21
7013 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
7014 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
7015 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
7016 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
7017 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
7018 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
7019 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
7020 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
7021 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
7022 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
7023 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
7024 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
7025 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
7026 Room 9-014-S2 67 days 11/21/20211/26/2022 11/21 Room 9-014-S2
7027 Plumbing system piping installation水管系统 62 days 11/24/20211/24/2022 11/24 Plumbing system piping installation水管系统
7028 Sanitary ware Piping installation 排水安装 3 days 11/24/202111/26/2021 11/24
7029 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/27/202112/1/2021 11/27
7030 Cold water piping installation冷水安装 16 days 12/15/202112/30/2021 12/15
7031 Hot water piping installation热水管安装 16 days 1/4/2022 1/19/2022 1/4
7032 Pre-Testing 测试 5 days 1/20/2022 1/24/2022 1/20
7033 Fire fighting piping installation消防系统安装 15 days 11/21/202112/5/2021 11/21 Fire fighting piping installation消防系统安装
7034 Fire fighting pipe installation消防管安装 11 days 11/21/2021 12/1/2021 11/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 186
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7035 Pre-Testing 测试 4 days 12/2/2021 12/5/2021 12/2
7036 MVAC System installation空调系统 53 days 12/5/2021 1/26/2022 12/5 MVAC System installation空调系统
7037 FCU installation风机盘安装 10 days 1/5/2022 1/14/2022 1/5
7038 15 days
Chiller Water Piping installation冷冻水管安装 1/5/2022 1/19/2022 1/5
7039 Valve Installation 空调阀门安装 15 days 1/5/2022 1/19/2022 1/5
7040 Ducting installation风管安装 15 days 12/5/2021 12/19/2021 12/5
7041 Pre-Testing 测试 4 days 1/20/2022 1/23/2022 1/20
7042 AC duct/pipe insulation 保温安装 7 days 1/20/2022 1/26/2022 1/20
7043 Electrical System installation电气系统 13 days 12/11/2021 12/23/2021 12/11 Electrical System installation电气系统
7044 EMT Conduit Installation EMT导管安装 7 days 12/11/202112/17/2021 12/11
7045 Electrical Tray Installation 桥架安装 7 days 12/11/202112/17/2021 12/11
7046 LV cable installation 强电电缆安装 7 days 12/11/202112/17/2021 12/11
7047 Circuit & Mega Testing 电路,回路测试 6 days 12/18/202112/23/2021 12/18
7048 MEP Corridor机电走廊安装 20 days 11/20/2021 12/9/2021 11/20 MEP Corridor机电走廊安装
7049 Electrical System installation 15 days 11/25/2021 12/9/2021 11/25 Electrical System installation
7050 Cable tray installation 桥架安装 4 days 11/25/2021 11/28/2021 11/25
7051 LV cable installation 强电电缆安装 4 days 12/6/2021 12/9/2021 12/6
7052 ELV cable installation 弱电电缆安装 4 days 12/6/2021 12/9/2021 12/6
7053 Fire fighting piping installation消防系统 14 days 11/20/2021 12/3/2021 11/20 Fire fighting piping installation消防系统
7054 Fire fighting pipe installation消防管安装 10 days 11/20/2021 11/29/2021 11/20
7055 Testing 测试 4 days 11/30/2021 12/3/2021 11/30
7056 MVAC System installation空调系统 20 days 11/20/2021 12/9/2021 11/20 MVAC System installation空调系统
7057 Ducting for AC installation风管安装 7 days 11/20/2021 11/26/2021 11/20
7058 Chiller water pipe installation冷冻水管安装 14 days 11/20/2021 12/3/2021 11/20
7059 AC drain pipe installation空调排水管安装 5 days 11/25/2021 11/29/2021 11/25
7060 Testing 测试 3 days 12/4/2021 12/6/2021 12/4
7061 Duct/pipe insulation保温安装 3 days 12/7/2021 12/9/2021 12/7
7062 MEP Final Fix机电末端安装 25 days 2/19/2022 3/15/2022 2/19 MEP Final Fix机电末端安装
7063 Electrical Installation电气系统末端安装 25 days 2/19/2022 3/15/2022 2/19 Electrical Installation电气系统末端安装
7064 Fire alarm system 火警系统安装 7 days 2/19/2022 2/25/2022 2/19
7065 Public address system 公共广播系统 5 days 2/21/2022 2/25/2022 2/21
7066 Access control system 门禁系统 5 days 2/24/2022 2/28/2022 2/24
7067 Sockets and Switches Installation 开关插座 4 days 3/7/2022 3/10/2022 3/7
7068 Normal & Emergency Luminaires installation 普 5 days 3/11/2022 3/15/2022 3/11
通和应急照明安装
7069 MVAC Installation空调系统末端安装 12 days 2/26/2022 3/9/2022 2/26 MVAC Installation空调系统末端安装
7070 Air grille/louver installation 通风格棚、百叶窗安装 7 days 2/26/2022 3/4/2022 2/26
7071 Wall controller units installation墙壁控制器 5 days 3/5/2022 3/9/2022 3/5
7072 Fire Protection Installation消防系统末端安装 15 days 3/1/2022 3/15/2022 3/1 Fire Protection Installation消防系统末端安
7073 Sprinkler Installation 喷淋头安装 5 days 3/1/2022 3/5/2022 3/1
7074 Fire hose reel cabinet消防箱带卷盘 4 days 3/12/2022 3/15/2022 3/12
7075 MEP Level 10 机电10层 113 days11/27/2021 3/19/2022 11/27 MEP Level 10 机电10层

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 187
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7076 Guest Room MEP Installation(1&2 Fix)客房机电安装75 days 11/27/2021 2/9/2022 11/27 Guest Room MEP Installation(1&2 Fix)客房机电安装
7077 Room 10-001-S2 75 days 11/27/20212/9/2022 11/27 Room 10-001-S2
7078 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7079 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7080 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7081 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7082 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7083 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7084 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7085 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7086 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7087 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7088 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7089 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7090 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7091 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7092 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7093 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7094 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7095 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7096 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7097 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7098 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7099 Room 10-002-S2 75 days 11/27/20212/9/2022 11/27 Room 10-002-S2
7100 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7101 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7102 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7103 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7104 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7105 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7106 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7107 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7108 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7109 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7110 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7111 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7112 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7113 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7114 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7115 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7116 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 188
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7117 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7118 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7119 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7120 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7121 Room 10-003-S2 75 days 11/27/20212/9/2022 11/27 Room 10-003-S2
7122 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7123 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7124 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7125 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7126 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7127 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7128 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7129 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7130 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7131 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7132 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7133 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7134 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7135 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7136 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7137 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7138 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7139 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7140 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7141 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7142 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7143 Room 10-004-S1 75 days 11/27/20212/9/2022 11/27 Room 10-004-S1
7144 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7145 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7146 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7147 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7148 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7149 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7150 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7151 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7152 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7153 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7154 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7155 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7156 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7157 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 189
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7158 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7159 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7160 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7161 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7162 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7163 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7164 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7165 Room 10-005-S2b 75 days 11/27/20212/9/2022 11/27 Room 10-005-S2b
7166 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7167 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7168 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7169 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7170 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7171 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7172 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7173 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7174 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7175 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7176 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7177 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7178 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7179 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7180 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7181 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7182 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7183 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7184 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7185 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7186 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7187 Room 10-006-S4 75 days 11/27/20212/9/2022 11/27 Room 10-006-S4
7188 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7189 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7190 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7191 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7192 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7193 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7194 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7195 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7196 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7197 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7198 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 190
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7199 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7200 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7201 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7202 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7203 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7204 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7205 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7206 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7207 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7208 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7209 Room 10-007-S2 75 days 11/27/20212/9/2022 11/27 Room 10-007-S2
7210 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7211 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7212 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7213 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7214 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7215 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7216 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7217 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7218 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7219 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7220 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7221 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7222 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7223 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7224 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7225 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7226 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7227 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7228 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7229 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7230 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7231 Room 10-008-S2 75 days 11/27/20212/9/2022 11/27 Room 10-008-S2
7232 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7233 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7234 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7235 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7236 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7237 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7238 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7239 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 191
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7240 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7241 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7242 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7243 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7244 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7245 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7246 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7247 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7248 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7249 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7250 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7251 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7252 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7253 Room 10-009-S4 75 days 11/27/20212/9/2022 11/27 Room 10-009-S4
7254 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7255 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7256 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7257 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7258 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7259 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7260 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7261 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7262 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7263 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7264 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7265 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7266 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7267 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7268 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7269 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7270 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7271 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7272 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7273 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7274 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7275 Room 10-010-S2 75 days 11/27/20212/9/2022 11/27 Room 10-010-S2
7276 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7277 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7278 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7279 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7280 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 192
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7281 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7282 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7283 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7284 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7285 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7286 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7287 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7288 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7289 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7290 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7291 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7292 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7293 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7294 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7295 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7296 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7297 Room 10-011-S2 75 days 11/27/20212/9/2022 11/27 Room 10-011-S2
7298 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7299 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7300 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7301 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7302 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7303 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7304 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7305 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7306 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7307 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7308 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7309 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7310 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7311 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7312 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7313 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7314 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7315 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7316 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7317 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7318 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7319 Room 10-012-S1 75 days 11/27/20212/9/2022 11/27 Room 10-012-S1
7320 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7321 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 193
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7322 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7323 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7324 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7325 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7326 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7327 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7328 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7329 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7330 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7331 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7332 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7333 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7334 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7335 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7336 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7337 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7338 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7339 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7340 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7341 Room 10-013-S2b 75 days 11/27/20212/9/2022 11/27 Room 10-013-S2b
7342 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7343 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7344 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7345 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7346 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7347 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7348 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7349 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7350 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7351 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7352 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7353 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7354 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7355 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7356 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7357 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7358 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7359 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7360 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7361 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7362 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 194
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7363 Room 10-014-S2 75 days 11/27/20212/9/2022 11/27 Room 10-014-S2
7364 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7365 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7366 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7367 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7368 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7369 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7370 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7371 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7372 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7373 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7374 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7375 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7376 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7377 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7378 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7379 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7380 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7381 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7382 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7383 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7384 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7385 MEP Corridor机电走廊安装 20 days 11/27/2021 12/16/2021 11/27 MEP Corridor机电走廊安装
7386 Electrical System installation 15 days 11/29/2021 12/13/2021 11/29 Electrical System installation
7387 Cable tray installation 桥架安装 4 days 11/29/2021 12/2/2021 11/29
7388 LV cable installation 强电电缆安装 4 days 12/10/202112/13/2021 12/10
7389 ELV cable installation 弱电电缆安装 4 days 12/10/202112/13/2021 12/10
7390 Fire fighting piping installation消防系统 14 days 11/30/2021 12/13/2021 11/30 Fire fighting piping installation消防系统
7391 Fire fighting pipe installation消防管安装 10 days 11/30/2021 12/9/2021 11/30
7392 Testing 测试 4 days 12/10/2021 12/13/2021 12/10
7393 MVAC System installation空调系统 20 days 11/27/2021 12/16/2021 11/27 MVAC System installation空调系统
7394 Ducting for AC installation风管安装 7 days 11/27/2021 12/3/2021 11/27
7395 Chiller water pipe installation冷冻水管安装 14 days 11/27/2021 12/10/2021 11/27
7396 AC drain pipe installation空调排水管安装 5 days 12/2/2021 12/6/2021 12/2
7397 Testing 测试 3 days 12/11/2021 12/13/2021 12/11
7398 Duct/pipe insulation保温安装 3 days 12/14/2021 12/16/2021 12/14
7399 MEP Final Fix机电末端安装 22 days 2/26/2022 3/19/2022 2/26 MEP Final Fix机电末端安装
7400 Electrical Installation电气系统末端安装 22 days 2/26/2022 3/19/2022 2/26 Electrical Installation电气系统末端安装
7401 Fire alarm system 火警系统安装 7 days 2/26/2022 3/4/2022 2/26
7402 Public address system 公共广播系统 5 days 2/28/2022 3/4/2022 2/28
7403 Access control system 门禁系统 5 days 3/3/2022 3/7/2022 3/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 195
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7404 Sockets and Switches Installation 开关插座 4 days 3/11/2022 3/14/2022 3/11
7405 Normal & Emergency Luminaires installation 普 5 days 3/15/2022 3/19/2022 3/15
通和应急照明安装
7406 MVAC Installation空调系统末端安装 12 days 3/5/2022 3/16/2022 3/5 MVAC Installation空调系统末端安装
7407 Air grille/louver installation 通风格棚、百叶窗安装 7 days 3/5/2022 3/11/2022 3/5
7408 Wall controller units installation墙壁控制器 5 days 3/12/2022 3/16/2022 3/12
7409 Fire Protection Installation消防系统末端安装 14 days 3/6/2022 3/19/2022 3/6 Fire Protection Installation消防系统末端
7410 Sprinkler Installation 喷淋头安装 5 days 3/6/2022 3/10/2022 3/6
7411 Fire hose reel cabinet消防箱带卷盘 4 days 3/16/2022 3/19/2022 3/16
7412 MEP Level 11 机电11层 117 days11/27/2021 3/23/2022 11/27 MEP Level 11 机电11层
7413 Guest Room MEP Installation(1&2 Fix)客房机电安装75 days 11/27/2021 2/9/2022 11/27 Guest Room MEP Installation(1&2 Fix)客房机电安装
7414 Room 11-001-S2 75 days 11/27/20212/9/2022 11/27 Room 11-001-S2
7415 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7416 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7417 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7418 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7419 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7420 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7421 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7422 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7423 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7424 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7425 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7426 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7427 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7428 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7429 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7430 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7431 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7432 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7433 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7434 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7435 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7436 Room 11-002-S2 75 days 11/27/20212/9/2022 11/27 Room 11-002-S2
7437 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7438 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7439 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7440 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7441 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7442 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7443 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7444 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 196
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7445 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7446 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7447 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7448 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7449 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7450 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7451 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7452 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7453 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7454 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7455 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7456 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7457 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7458 Room 11-003-S2 75 days 11/27/20212/9/2022 11/27 Room 11-003-S2
7459 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7460 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7461 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7462 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7463 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7464 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7465 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7466 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7467 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7468 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7469 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7470 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7471 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7472 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7473 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7474 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7475 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7476 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7477 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7478 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7479 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7480 Room 11-004-S1 75 days 11/27/20212/9/2022 11/27 Room 11-004-S1
7481 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7482 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7483 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7484 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7485 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 197
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7486 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7487 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7488 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7489 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7490 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7491 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7492 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7493 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7494 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7495 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7496 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7497 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7498 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7499 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7500 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7501 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7502 Room 11-005-S2b 75 days 11/27/20212/9/2022 11/27 Room 11-005-S2b
7503 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7504 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7505 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7506 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7507 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7508 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7509 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7510 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7511 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7512 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7513 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7514 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7515 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7516 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7517 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7518 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7519 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7520 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7521 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7522 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7523 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7524 Room 11-006-S4 75 days 11/27/20212/9/2022 11/27 Room 11-006-S4
7525 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7526 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 198
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7527 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7528 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7529 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7530 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7531 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7532 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7533 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7534 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7535 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7536 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7537 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7538 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7539 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7540 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7541 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7542 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7543 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7544 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7545 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7546 Room 11-007-S2 75 days 11/27/20212/9/2022 11/27 Room 11-007-S2
7547 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7548 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7549 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7550 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7551 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7552 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7553 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7554 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7555 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7556 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7557 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7558 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7559 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7560 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7561 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7562 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7563 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7564 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7565 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7566 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7567 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 199
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7568 Room 11-008-S2 75 days 11/27/20212/9/2022 11/27 Room 11-008-S2
7569 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7570 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7571 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7572 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7573 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7574 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7575 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7576 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7577 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7578 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7579 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7580 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7581 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7582 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7583 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7584 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7585 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7586 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7587 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7588 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7589 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7590 Room 11-009-S4 75 days 11/27/20212/9/2022 11/27 Room 11-009-S4
7591 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7592 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7593 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7594 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7595 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7596 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7597 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7598 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7599 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7600 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7601 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7602 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7603 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7604 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7605 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7606 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7607 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7608 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 200
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7609 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7610 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7611 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7612 Room 11-010-S2 75 days 11/27/20212/9/2022 11/27 Room 11-010-S2
7613 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7614 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7615 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7616 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7617 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7618 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7619 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7620 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7621 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7622 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7623 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7624 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7625 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7626 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7627 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7628 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7629 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7630 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7631 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7632 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7633 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7634 Room 11-011-S2 75 days 11/27/20212/9/2022 11/27 Room 11-011-S2
7635 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7636 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7637 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7638 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7639 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7640 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7641 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7642 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7643 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7644 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7645 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7646 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7647 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7648 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7649 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 201
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7650 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7651 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7652 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7653 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7654 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7655 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7656 Room 11-012-S1 75 days 11/27/20212/9/2022 11/27 Room 11-012-S1
7657 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7658 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7659 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7660 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7661 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7662 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7663 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7664 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7665 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7666 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7667 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7668 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7669 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7670 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7671 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7672 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7673 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7674 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7675 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7676 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7677 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7678 Room 11-013-S2b 75 days 11/27/20212/9/2022 11/27 Room 11-013-S2b
7679 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7680 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7681 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7682 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7683 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7684 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7685 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7686 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7687 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7688 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7689 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7690 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 202
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7691 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7692 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7693 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7694 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7695 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7696 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7697 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7698 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7699 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7700 Room 11-014-S2 75 days 11/27/20212/9/2022 11/27 Room 11-014-S2
7701 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7702 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7703 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7704 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7705 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7706 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7707 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7708 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7709 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7710 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7711 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7712 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7713 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7714 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7715 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7716 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7717 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7718 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7719 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7720 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7721 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7722 MEP Corridor机电走廊安装 20 days 11/27/2021 12/16/2021 11/27 MEP Corridor机电走廊安装
7723 Electrical System installation 15 days 11/29/2021 12/13/2021 11/29 Electrical System installation
7724 Cable tray installation 桥架安装 4 days 11/29/2021 12/2/2021 11/29
7725 LV cable installation 强电电缆安装 4 days 12/10/202112/13/2021 12/10
7726 ELV cable installation 弱电电缆安装 4 days 12/10/202112/13/2021 12/10
7727 Fire fighting piping installation消防系统 14 days 11/30/2021 12/13/2021 11/30 Fire fighting piping installation消防系统
7728 Fire fighting pipe installation消防管安装 10 days 11/30/2021 12/9/2021 11/30
7729 Testing 测试 4 days 12/10/2021 12/13/2021 12/10
7730 MVAC System installation空调系统 20 days 11/27/2021 12/16/2021 11/27 MVAC System installation空调系统
7731 Ducting for AC installation风管安装 7 days 11/27/2021 12/3/2021 11/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 203
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7732 Chiller water pipe installation冷冻水管安装 14 days 11/27/2021 12/10/2021 11/27
7733 AC drain pipe installation空调排水管安装 5 days 12/2/2021 12/6/2021 12/2
7734 Testing 测试 3 days 12/11/2021 12/13/2021 12/11
7735 Duct/pipe insulation保温安装 3 days 12/14/2021 12/16/2021 12/14
7736 MEP Final Fix机电末端安装 19 days 3/5/2022 3/23/2022 3/5 MEP Final Fix机电末端安装
7737 Electrical Installation电气系统末端安装 19 days 3/5/2022 3/23/2022 3/5 Electrical Installation电气系统末端安装
7738 Fire alarm system 火警系统安装 7 days 3/5/2022 3/11/2022 3/5
7739 Public address system 公共广播系统 5 days 3/7/2022 3/11/2022 3/7
7740 Access control system 门禁系统 5 days 3/10/2022 3/14/2022 3/10
7741 Sockets and Switches Installation 开关插座 4 days 3/15/2022 3/18/2022 3/15
7742 Normal & Emergency Luminaires installation 普 5 days 3/19/2022 3/23/2022 3/19
通和应急照明安装
7743 MVAC Installation空调系统末端安装 12 days 3/5/2022 3/16/2022 3/5 MVAC Installation空调系统末端安装
7744 Air grille/louver installation 通风格棚、百叶窗安装 7 days 3/5/2022 3/11/2022 3/5
7745 Wall controller units installation墙壁控制器 5 days 3/12/2022 3/16/2022 3/12
7746 Fire Protection Installation消防系统末端安装 13 days 3/11/2022 3/23/2022 3/11 Fire Protection Installation消防系统末端
7747 Sprinkler Installation 喷淋头安装 5 days 3/11/2022 3/15/2022 3/11
7748 Fire hose reel cabinet消防箱带卷盘 4 days 3/20/2022 3/23/2022 3/20
7749 MEP Level 12 机电12层 121 days11/27/2021 3/27/2022 11/27 MEP Level 12 机电12层
7750 Guest Room MEP Installation(1&2 Fix)客房机电安装75 days 11/27/2021 2/9/2022 11/27 Guest Room MEP Installation(1&2 Fix)客房机电安装
7751 Room 12-001-S2 75 days 11/27/20212/9/2022 11/27 Room 12-001-S2
7752 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7753 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7754 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7755 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7756 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7757 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7758 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7759 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7760 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7761 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7762 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7763 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7764 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7765 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7766 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7767 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7768 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7769 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7770 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7771 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7772 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 204
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7773 Room 12-002-S2 75 days 11/27/20212/9/2022 11/27 Room 12-002-S2
7774 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7775 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7776 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7777 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7778 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7779 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7780 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7781 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7782 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7783 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7784 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7785 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7786 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7787 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7788 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7789 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7790 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7791 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7792 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7793 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7794 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7795 Room 12-003-S2 75 days 11/27/20212/9/2022 11/27 Room 12-003-S2
7796 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7797 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7798 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7799 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7800 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7801 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7802 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7803 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7804 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7805 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7806 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7807 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7808 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7809 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7810 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7811 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7812 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7813 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 205
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7814 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7815 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7816 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7817 Room 12-004-S1 75 days 11/27/20212/9/2022 11/27 Room 12-004-S1
7818 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7819 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7820 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7821 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7822 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7823 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7824 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7825 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7826 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7827 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7828 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7829 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7830 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7831 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7832 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7833 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7834 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7835 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7836 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7837 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7838 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7839 Room 12-005-S2b 75 days 11/27/20212/9/2022 11/27 Room 12-005-S2b
7840 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7841 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7842 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7843 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7844 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7845 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7846 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7847 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7848 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7849 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7850 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7851 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7852 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7853 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7854 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 206
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7855 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7856 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7857 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7858 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7859 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7860 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7861 Room 12-006-S4 75 days 11/27/20212/9/2022 11/27 Room 12-006-S4
7862 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7863 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7864 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7865 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7866 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7867 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7868 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7869 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7870 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7871 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7872 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7873 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7874 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7875 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7876 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7877 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7878 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7879 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7880 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7881 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7882 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7883 Room 12-007-S2 75 days 11/27/20212/9/2022 11/27 Room 12-007-S2
7884 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7885 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7886 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7887 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7888 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7889 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7890 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7891 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7892 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7893 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7894 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7895 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 207
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7896 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7897 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7898 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7899 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7900 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7901 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7902 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7903 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7904 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7905 Room 12-008-S2 75 days 11/27/20212/9/2022 11/27 Room 12-008-S2
7906 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7907 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7908 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7909 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7910 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7911 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7912 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7913 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7914 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7915 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7916 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7917 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7918 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7919 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7920 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7921 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7922 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7923 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7924 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7925 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7926 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7927 Room 12-009-S4 75 days 11/27/20212/9/2022 11/27 Room 12-009-S4
7928 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7929 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7930 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7931 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7932 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7933 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7934 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7935 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7936 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 208
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7937 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7938 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7939 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7940 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7941 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7942 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7943 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7944 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7945 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7946 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7947 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7948 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7949 Room 12-010-S2 75 days 11/27/20212/9/2022 11/27 Room 12-010-S2
7950 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7951 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7952 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7953 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7954 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7955 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
7956 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7957 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7958 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7959 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7960 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7961 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7962 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7963 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7964 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7965 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7966 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7967 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7968 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7969 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7970 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7971 Room 12-011-S2 75 days 11/27/20212/9/2022 11/27 Room 12-011-S2
7972 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7973 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7974 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7975 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7976 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7977 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 209
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
7978 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
7979 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
7980 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
7981 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
7982 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
7983 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
7984 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
7985 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
7986 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
7987 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
7988 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
7989 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
7990 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
7991 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
7992 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
7993 Room 12-012-S1 75 days 11/27/20212/9/2022 11/27 Room 12-012-S1
7994 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
7995 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
7996 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
7997 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
7998 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
7999 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
8000 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
8001 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
8002 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
8003 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
8004 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
8005 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
8006 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
8007 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
8008 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
8009 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
8010 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
8011 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
8012 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
8013 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
8014 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
8015 Room 12-013-S2b 75 days 11/27/20212/9/2022 11/27 Room 12-013-S2b
8016 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
8017 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
8018 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 210
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8019 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
8020 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
8021 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
8022 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
8023 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
8024 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
8025 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
8026 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
8027 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
8028 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
8029 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
8030 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
8031 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
8032 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
8033 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
8034 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
8035 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
8036 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
8037 Room 12-014-S2 75 days 11/27/20212/9/2022 11/27 Room 12-014-S2
8038 Plumbing system piping installation水管系统 75 days 11/27/20212/9/2022 11/27 Plumbing system piping installation水管系统
8039 Sanitary ware Piping installation 排水安装 3 days 11/27/202111/29/2021 11/27
8040 Pre-Testing(Sanitary Pipe) 排水测试 5 days 11/30/202112/4/2021 11/30
8041 Cold water piping installation冷水安装 16 days 12/31/20211/15/2022 12/31
8042 Hot water piping installation热水管安装 16 days 1/20/2022 2/4/2022 1/20
8043 Pre-Testing 测试 5 days 2/5/2022 2/9/2022 2/5
8044 Fire fighting piping installation消防系统安装 15 days 12/2/2021 12/16/2021 12/2 Fire fighting piping installation消防系统安装
8045 Fire fighting pipe installation消防管安装 11 days 12/2/2021 12/12/2021 12/2
8046 Pre-Testing 测试 4 days 12/13/202112/16/2021 12/13
8047 MVAC System installation空调系统 48 days 12/20/20212/5/2022 12/20 MVAC System installation空调系统
8048 FCU installation风机盘安装 10 days 1/15/2022 1/24/2022 1/15
8049 15 days
Chiller Water Piping installation冷冻水管安装 1/15/2022 1/29/2022 1/15
8050 Valve Installation 空调阀门安装 15 days 1/15/2022 1/29/2022 1/15
8051 Ducting installation风管安装 15 days 12/20/20211/3/2022 12/20
8052 Pre-Testing 测试 4 days 1/30/2022 2/2/2022 1/30
8053 AC duct/pipe insulation 保温安装 7 days 1/30/2022 2/5/2022 1/30
8054 Electrical System installation电气系统 13 days 12/18/2021 12/30/2021 12/18 Electrical System installation电气系统
8055 EMT Conduit Installation EMT导管安装 7 days 12/18/202112/24/2021 12/18
8056 Electrical Tray Installation 桥架安装 7 days 12/18/202112/24/2021 12/18
8057 LV cable installation 强电电缆安装 7 days 12/18/202112/24/2021 12/18
8058 Circuit & Mega Testing 电路,回路测试 6 days 12/25/202112/30/2021 12/25
8059 MEP Corridor机电走廊安装 20 days 11/27/2021 12/16/2021 11/27 MEP Corridor机电走廊安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 211
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8060 Electrical System installation 15 days 11/29/2021 12/13/2021 11/29 Electrical System installation
8061 Cable tray installation 桥架安装 4 days 11/29/2021 12/2/2021 11/29
8062 LV cable installation 强电电缆安装 4 days 12/10/202112/13/2021 12/10
8063 ELV cable installation 弱电电缆安装 4 days 12/10/202112/13/2021 12/10
8064 Fire fighting piping installation消防系统 14 days 11/30/2021 12/13/2021 11/30 Fire fighting piping installation消防系统
8065 Fire fighting pipe installation消防管安装 10 days 11/30/2021 12/9/2021 11/30
8066 Testing 测试 4 days 12/10/2021 12/13/2021 12/10
8067 MVAC System installation空调系统 20 days 11/27/2021 12/16/2021 11/27 MVAC System installation空调系统
8068 Ducting for AC installation风管安装 7 days 11/27/2021 12/3/2021 11/27
8069 Chiller water pipe installation冷冻水管安装 14 days 11/27/2021 12/10/2021 11/27
8070 AC drain pipe installation空调排水管安装 5 days 12/2/2021 12/6/2021 12/2
8071 Testing 测试 3 days 12/11/2021 12/13/2021 12/11
8072 Duct/pipe insulation保温安装 3 days 12/14/2021 12/16/2021 12/14
8073 MEP Final Fix机电末端安装 16 days 3/12/2022 3/27/2022 3/12 MEP Final Fix机电末端安装
8074 Electrical Installation电气系统末端安装 16 days 3/12/2022 3/27/2022 3/12 Electrical Installation电气系统末端安装
8075 Fire alarm system 火警系统安装 7 days 3/12/2022 3/18/2022 3/12
8076 Public address system 公共广播系统 5 days 3/14/2022 3/18/2022 3/14
8077 Access control system 门禁系统 5 days 3/17/2022 3/21/2022 3/17
8078 Sockets and Switches Installation 开关插座 4 days 3/19/2022 3/22/2022 3/19
8079 Normal & Emergency Luminaires installation 普 5 days 3/23/2022 3/27/2022 3/23
通和应急照明安装
8080 MVAC Installation空调系统末端安装 12 days 3/12/2022 3/23/2022 3/12 MVAC Installation空调系统末端安装
8081 Air grille/louver installation 通风格棚、百叶窗安装 7 days 3/12/2022 3/18/2022 3/12
8082 Wall controller units installation墙壁控制器 5 days 3/19/2022 3/23/2022 3/19
8083 Fire Protection Installation消防系统末端安装 12 days 3/16/2022 3/27/2022 3/16 Fire Protection Installation消防系统末
8084 Sprinkler Installation 喷淋头安装 5 days 3/16/2022 3/20/2022 3/16
8085 Fire hose reel cabinet消防箱带卷盘 4 days 3/24/2022 3/27/2022 3/24
8086 MEP Level 13 机电13层 122 days11/30/2021 3/31/2022 11/30 MEP Level 13 机电13层
8087 Guest Room MEP Installation(1&2 Fix)客房机电安装88 days 11/30/2021 2/25/2022 11/30 Guest Room MEP Installation(1&2 Fix)客房机电
8088 Room 13-001-S2 88 days 11/30/20212/25/2022 11/30 Room 13-001-S2
8089 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8090 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8091 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8092 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8093 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8094 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8095 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8096 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8097 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8098 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8099 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8100 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 212
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8101 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8102 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8103 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8104 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8105 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8106 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8107 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8108 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8109 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8110 Room 13-002-S2 88 days 11/30/20212/25/2022 11/30 Room 13-002-S2
8111 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8112 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8113 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8114 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8115 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8116 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8117 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8118 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8119 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8120 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8121 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8122 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8123 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8124 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8125 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8126 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8127 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8128 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8129 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8130 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8131 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8132 Room 13-003-S2 88 days 11/30/20212/25/2022 11/30 Room 13-003-S2
8133 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8134 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8135 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8136 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8137 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8138 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8139 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8140 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8141 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 213
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8142 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8143 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8144 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8145 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8146 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8147 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8148 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8149 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8150 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8151 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8152 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8153 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8154 Room 13-004-S1 88 days 11/30/20212/25/2022 11/30 Room 13-004-S1
8155 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8156 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8157 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8158 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8159 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8160 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8161 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8162 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8163 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8164 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8165 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8166 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8167 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8168 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8169 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8170 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8171 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8172 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8173 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8174 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8175 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8176 Room 13-005-S2b 88 days 11/30/20212/25/2022 11/30 Room 13-005-S2b
8177 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8178 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8179 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8180 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8181 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8182 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 214
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8183 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8184 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8185 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8186 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8187 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8188 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8189 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8190 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8191 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8192 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8193 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8194 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8195 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8196 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8197 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8198 Room 12-006-S4 88 days 11/30/20212/25/2022 11/30 Room 12-006-S4
8199 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8200 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8201 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8202 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8203 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8204 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8205 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8206 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8207 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8208 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8209 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8210 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8211 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8212 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8213 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8214 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8215 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8216 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8217 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8218 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8219 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8220 Room 13-007-S2 88 days 11/30/20212/25/2022 11/30 Room 13-007-S2
8221 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8222 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8223 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 215
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8224 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8225 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8226 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8227 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8228 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8229 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8230 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8231 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8232 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8233 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8234 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8235 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8236 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8237 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8238 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8239 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8240 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8241 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8242 Room 13-008-S2 88 days 11/30/20212/25/2022 11/30 Room 13-008-S2
8243 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8244 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8245 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8246 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8247 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8248 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8249 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8250 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8251 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8252 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8253 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8254 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8255 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8256 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8257 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8258 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8259 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8260 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8261 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8262 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8263 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8264 Room 13-009-S4 88 days 11/30/20212/25/2022 11/30 Room 13-009-S4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 216
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8265 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8266 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8267 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8268 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8269 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8270 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8271 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8272 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8273 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8274 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8275 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8276 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8277 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8278 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8279 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8280 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8281 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8282 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8283 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8284 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8285 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8286 Room 13-010-S2 88 days 11/30/20212/25/2022 11/30 Room 13-010-S2
8287 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8288 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8289 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8290 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8291 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8292 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8293 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8294 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8295 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8296 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8297 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8298 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8299 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8300 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8301 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8302 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8303 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8304 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8305 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 217
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8306 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8307 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8308 Room 13-011-S2 88 days 11/30/20212/25/2022 11/30 Room 13-011-S2
8309 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8310 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8311 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8312 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8313 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8314 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8315 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8316 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8317 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8318 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8319 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8320 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8321 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8322 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8323 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8324 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8325 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8326 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8327 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8328 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8329 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8330 Room 13-012-S1 88 days 11/30/20212/25/2022 11/30 Room 13-012-S1
8331 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8332 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8333 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8334 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8335 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8336 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8337 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8338 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8339 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8340 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8341 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8342 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8343 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8344 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8345 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8346 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 218
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8347 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8348 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8349 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8350 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8351 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8352 Room 13-013-S2b 88 days 11/30/20212/25/2022 11/30 Room 13-013-S2b
8353 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8354 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8355 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8356 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8357 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8358 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8359 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8360 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8361 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8362 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8363 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8364 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8365 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8366 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8367 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8368 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8369 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8370 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8371 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8372 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8373 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8374 Room 13-014-S2 88 days 11/30/20212/25/2022 11/30 Room 13-014-S2
8375 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8376 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8377 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8378 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8379 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8380 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8381 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8382 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8383 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8384 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8385 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8386 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8387 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 219
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8388 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8389 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8390 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8391 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8392 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8393 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8394 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8395 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8396 MEP Corridor机电走廊安装 21 days 12/3/2021 12/23/2021 12/3 MEP Corridor机电走廊安装
8397 Electrical System installation 15 days 12/3/2021 12/17/2021 12/3 Electrical System installation
8398 Cable tray installation 桥架安装 4 days 12/3/2021 12/6/2021 12/3
8399 LV cable installation 强电电缆安装 4 days 12/14/202112/17/2021 12/14
8400 ELV cable installation 弱电电缆安装 4 days 12/14/202112/17/2021 12/14
8401 Fire fighting piping installation消防系统 14 days 12/10/2021 12/23/2021 12/10 Fire fighting piping installation消防系统
8402 Fire fighting pipe installation消防管安装 10 days 12/10/2021 12/19/2021 12/10
8403 Testing 测试 4 days 12/20/2021 12/23/2021 12/20
8404 MVAC System installation空调系统 20 days 12/4/2021 12/23/2021 12/4 MVAC System installation空调系统
8405 Ducting for AC installation风管安装 7 days 12/4/2021 12/10/2021 12/4
8406 Chiller water pipe installation冷冻水管安装 14 days 12/4/2021 12/17/2021 12/4
8407 AC drain pipe installation空调排水管安装 5 days 12/9/2021 12/13/2021 12/9
8408 Testing 测试 3 days 12/18/2021 12/20/2021 12/18
8409 Duct/pipe insulation保温安装 3 days 12/21/2021 12/23/2021 12/21
8410 MEP Final Fix机电末端安装 13 days 3/19/2022 3/31/2022 3/19 MEP Final Fix机电末端安装
8411 Electrical Installation电气系统末端安装 13 days 3/19/2022 3/31/2022 3/19 Electrical Installation电气系统末端安
8412 Fire alarm system 火警系统安装 7 days 3/19/2022 3/25/2022 3/19
8413 Public address system 公共广播系统 5 days 3/21/2022 3/25/2022 3/21
8414 Access control system 门禁系统 5 days 3/24/2022 3/28/2022 3/24
8415 Sockets and Switches Installation 开关插座 4 days 3/23/2022 3/26/2022 3/23
8416 Normal & Emergency Luminaires installation 普 5 days 3/27/2022 3/31/2022 3/27
通和应急照明安装
8417 MVAC Installation空调系统末端安装 12 days 3/19/2022 3/30/2022 3/19 MVAC Installation空调系统末端安装
8418 Air grille/louver installation 通风格棚、百叶窗安装 7 days 3/19/2022 3/25/2022 3/19
8419 Wall controller units installation墙壁控制器 5 days 3/26/2022 3/30/2022 3/26
8420 Fire Protection Installation消防系统末端安装 11 days 3/21/2022 3/31/2022 3/21 Fire Protection Installation消防系统末
8421 Sprinkler Installation 喷淋头安装 5 days 3/21/2022 3/25/2022 3/21
8422 Fire hose reel cabinet消防箱带卷盘 4 days 3/28/2022 3/31/2022 3/28
8423 MEP Level 14 机电14层 128 days11/30/2021 4/6/2022 11/30 MEP Level 14 机电14层
8424 Guest Room MEP Installation(1&2 Fix)客房机电安装88 days 11/30/2021 2/25/2022 11/30 Guest Room MEP Installation(1&2 Fix)客房机电
8425 Room 14-001-S3 88 days 11/30/20212/25/2022 11/30 Room 14-001-S3
8426 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8427 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8428 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 220
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8429 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8430 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8431 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8432 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8433 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8434 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8435 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8436 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8437 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8438 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8439 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8440 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8441 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8442 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8443 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8444 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8445 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8446 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8447 Room 14-002-S3 88 days 11/30/20212/25/2022 11/30 Room 14-002-S3
8448 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8449 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8450 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8451 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8452 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8453 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8454 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8455 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8456 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8457 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8458 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8459 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8460 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8461 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8462 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8463 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8464 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8465 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8466 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8467 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8468 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8469 Room 14-003-S2 88 days 11/30/20212/25/2022 11/30 Room 14-003-S2

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 221
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8470 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8471 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8472 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8473 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8474 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8475 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8476 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8477 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8478 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8479 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8480 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8481 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8482 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8483 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8484 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8485 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8486 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8487 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8488 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8489 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8490 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8491 Room 14-004-S1 88 days 11/30/20212/25/2022 11/30 Room 14-004-S1
8492 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8493 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8494 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8495 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8496 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8497 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8498 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8499 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8500 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8501 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8502 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8503 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8504 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8505 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8506 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8507 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8508 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8509 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8510 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 222
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8511 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8512 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8513 Room 14-005-S1 88 days 11/30/20212/25/2022 11/30 Room 14-005-S1
8514 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8515 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8516 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8517 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8518 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8519 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8520 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8521 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8522 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8523 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8524 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8525 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8526 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8527 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8528 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8529 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8530 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8531 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8532 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8533 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8534 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8535 Room 14-006-S1 88 days 11/30/20212/25/2022 11/30 Room 14-006-S1
8536 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8537 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8538 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8539 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8540 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8541 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8542 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8543 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8544 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8545 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8546 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8547 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8548 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8549 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8550 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8551 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 223
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8552 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8553 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8554 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8555 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8556 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8557 Room 14-007-S1 88 days 11/30/20212/25/2022 11/30 Room 14-007-S1
8558 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8559 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8560 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8561 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8562 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8563 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8564 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8565 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8566 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8567 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8568 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8569 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8570 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8571 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8572 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8573 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8574 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8575 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8576 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8577 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8578 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8579 Room 14-008-S2 88 days 11/30/20212/25/2022 11/30 Room 14-008-S2
8580 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8581 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8582 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8583 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8584 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8585 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8586 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8587 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8588 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8589 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8590 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8591 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8592 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 224
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8593 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8594 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8595 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8596 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8597 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8598 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8599 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8600 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8601 Room 14-009-S2 88 days 11/30/20212/25/2022 11/30 Room 14-009-S2
8602 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8603 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8604 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8605 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8606 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8607 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8608 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8609 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8610 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8611 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8612 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8613 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8614 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8615 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8616 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8617 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8618 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8619 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8620 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8621 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8622 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8623 Room 14-010-S1 88 days 11/30/20212/25/2022 11/30 Room 14-010-S1
8624 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8625 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8626 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8627 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8628 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8629 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8630 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8631 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8632 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8633 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 225
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8634 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8635 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8636 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8637 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8638 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8639 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8640 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8641 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8642 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8643 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8644 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8645 Room 14-011-S4 88 days 11/30/20212/25/2022 11/30 Room 14-011-S4
8646 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8647 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8648 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8649 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8650 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8651 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8652 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8653 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8654 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8655 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8656 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8657 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8658 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8659 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8660 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8661 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8662 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8663 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8664 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8665 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8666 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8667 Room 14-012-S1 88 days 11/30/20212/25/2022 11/30 Room 14-012-S1
8668 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8669 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8670 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8671 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8672 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8673 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8674 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 226
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8675 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8676 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8677 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8678 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8679 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8680 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8681 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8682 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8683 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8684 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8685 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8686 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8687 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8688 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8689 Room 14-013-S1 88 days 11/30/20212/25/2022 11/30 Room 14-013-S1
8690 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8691 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8692 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8693 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8694 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8695 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8696 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8697 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8698 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8699 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8700 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8701 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8702 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8703 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8704 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8705 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8706 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8707 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8708 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8709 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8710 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8711 Room 14-014-S21 88 days 11/30/20212/25/2022 11/30 Room 14-014-S21
8712 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8713 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8714 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8715 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 227
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8716 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8717 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8718 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8719 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8720 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8721 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8722 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8723 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8724 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8725 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8726 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8727 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8728 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8729 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8730 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8731 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8732 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8733 Room 14-015-S2 88 days 11/30/20212/25/2022 11/30 Room 14-015-S2
8734 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8735 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8736 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8737 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8738 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8739 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8740 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8741 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8742 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8743 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8744 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8745 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8746 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8747 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8748 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8749 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8750 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8751 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8752 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8753 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8754 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8755 Room 14-016-S1 88 days 11/30/20212/25/2022 11/30 Room 14-016-S1
8756 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 228
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8757 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8758 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8759 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8760 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8761 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8762 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8763 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8764 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8765 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8766 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8767 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8768 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8769 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8770 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8771 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8772 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8773 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8774 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8775 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8776 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8777 MEP Corridor机电走廊安装 21 days 12/3/2021 12/23/2021 12/3 MEP Corridor机电走廊安装
8778 Electrical System installation 15 days 12/3/2021 12/17/2021 12/3 Electrical System installation
8779 Cable tray installation 桥架安装 4 days 12/3/2021 12/6/2021 12/3
8780 LV cable installation 强电电缆安装 4 days 12/14/202112/17/2021 12/14
8781 ELV cable installation 弱电电缆安装 4 days 12/14/202112/17/2021 12/14
8782 Fire fighting piping installation消防系统 14 days 12/10/2021 12/23/2021 12/10 Fire fighting piping installation消防系统
8783 Fire fighting pipe installation消防管安装 10 days 12/10/2021 12/19/2021 12/10
8784 Testing 测试 4 days 12/20/2021 12/23/2021 12/20
8785 MVAC System installation空调系统 20 days 12/4/2021 12/23/2021 12/4 MVAC System installation空调系统
8786 Ducting for AC installation风管安装 7 days 12/4/2021 12/10/2021 12/4
8787 Chiller water pipe installation冷冻水管安装 14 days 12/4/2021 12/17/2021 12/4
8788 AC drain pipe installation空调排水管安装 5 days 12/9/2021 12/13/2021 12/9
8789 Testing 测试 3 days 12/18/2021 12/20/2021 12/18
8790 Duct/pipe insulation保温安装 3 days 12/21/2021 12/23/2021 12/21
8791 MEP Final Fix机电末端安装 12 days 3/26/2022 4/6/2022 3/26 MEP Final Fix机电末端安装
8792 Electrical Installation电气系统末端安装 10 days 3/26/2022 4/4/2022 3/26 Electrical Installation电气系统末端安
8793 Fire alarm system 火警系统安装 7 days 3/26/2022 4/1/2022 3/26
8794 Public address system 公共广播系统 5 days 3/28/2022 4/1/2022 3/28
8795 Access control system 门禁系统 5 days 3/31/2022 4/4/2022 3/31
8796 Sockets and Switches Installation 开关插座 4 days 3/27/2022 3/30/2022 3/27
8797 Normal & Emergency Luminaires installation 普 5 days 3/31/2022 4/4/2022 3/31
通和应急照明安装
Task External Tasks Manual Task Finish-only
Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 229
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8798 MVAC Installation空调系统末端安装 12 days 3/26/2022 4/6/2022 3/26 MVAC Installation空调系统末端安装
8799 Air grille/louver installation 通风格棚、百叶窗安装
7 days 3/26/2022 4/1/2022 3/26
8800 Wall controller units installation墙壁控制器 5 days 4/2/2022 4/6/2022 4/2
8801 Fire Protection Installation消防系统末端安装 10 days 3/26/2022 4/4/2022 3/26 Fire Protection Installation消防系统
8802 Sprinkler Installation 喷淋头安装 5 days 3/26/2022 3/30/2022 3/26
8803 Fire hose reel cabinet消防箱带卷盘 4 days 4/1/2022 4/4/2022 4/1
8804 MEP Level 15 机电15层 135 days11/30/2021 4/13/2022 11/30 MEP Level 15 机电15层
8805 Guest Room MEP Installation(1&2 Fix)客房机电安装88 days 11/30/2021 2/25/2022 11/30 Guest Room MEP Installation(1&2 Fix)客房机电
8806 Room 15-001-S3 88 days 11/30/20212/25/2022 11/30 Room 15-001-S3
8807 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8808 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8809 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8810 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8811 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8812 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8813 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8814 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8815 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8816 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8817 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8818 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8819 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8820 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8821 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8822 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8823 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8824 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8825 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8826 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8827 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8828 Room 15-002-S3 88 days 11/30/20212/25/2022 11/30 Room 15-002-S3
8829 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8830 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8831 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8832 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8833 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8834 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8835 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8836 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8837 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8838 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 230
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8839 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8840 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8841 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8842 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8843 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8844 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8845 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8846 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8847 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8848 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8849 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8850 Room 15-003-S2 88 days 11/30/20212/25/2022 11/30 Room 15-003-S2
8851 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8852 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8853 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8854 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8855 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8856 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8857 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8858 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8859 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8860 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8861 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8862 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8863 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8864 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8865 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8866 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8867 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8868 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8869 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8870 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8871 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8872 Room 15-004-S1 88 days 11/30/20212/25/2022 11/30 Room 15-004-S1
8873 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8874 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8875 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8876 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8877 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8878 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8879 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 231
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8880 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8881 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8882 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8883 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8884 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8885 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8886 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8887 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8888 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8889 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8890 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8891 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8892 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8893 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8894 Room 15-005-S1 88 days 11/30/20212/25/2022 11/30 Room 15-005-S1
8895 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8896 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8897 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8898 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8899 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8900 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8901 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8902 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8903 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8904 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8905 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8906 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8907 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8908 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8909 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8910 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8911 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8912 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8913 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8914 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8915 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8916 Room 15-006-S1 88 days 11/30/20212/25/2022 11/30 Room 15-006-S1
8917 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8918 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8919 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8920 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 232
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8921 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8922 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8923 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8924 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8925 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8926 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8927 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8928 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8929 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8930 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8931 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8932 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8933 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8934 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8935 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8936 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8937 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8938 Room 15-007-S1 88 days 11/30/20212/25/2022 11/30 Room 15-007-S1
8939 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8940 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8941 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8942 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8943 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8944 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8945 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8946 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8947 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8948 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8949 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8950 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8951 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8952 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8953 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8954 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8955 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8956 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8957 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8958 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8959 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8960 Room 15-008-S2 88 days 11/30/20212/25/2022 11/30 Room 15-008-S2
8961 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 233
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
8962 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8963 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8964 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8965 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8966 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8967 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8968 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8969 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8970 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8971 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8972 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8973 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8974 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8975 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8976 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8977 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
8978 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
8979 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
8980 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
8981 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
8982 Room 15-009-S2 88 days 11/30/20212/25/2022 11/30 Room 15-009-S2
8983 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
8984 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
8985 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
8986 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
8987 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
8988 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
8989 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
8990 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
8991 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
8992 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
8993 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
8994 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
8995 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
8996 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
8997 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
8998 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
8999 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
9000 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9001 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9002 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 234
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9003 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9004 Room 15-010-S1 88 days 11/30/20212/25/2022 11/30 Room 15-010-S1
9005 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
9006 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
9007 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
9008 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
9009 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
9010 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
9011 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
9012 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
9013 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
9014 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
9015 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
9016 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
9017 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
9018 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
9019 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
9020 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
9021 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
9022 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9023 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9024 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
9025 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9026 Room 15-011-S4 88 days 11/30/20212/25/2022 11/30 Room 15-011-S4
9027 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
9028 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
9029 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
9030 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
9031 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
9032 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
9033 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
9034 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
9035 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
9036 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
9037 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
9038 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
9039 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
9040 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
9041 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
9042 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
9043 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 235
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9044 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9045 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9046 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
9047 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9048 Room 15-012-S1 88 days 11/30/20212/25/2022 11/30 Room 15-012-S1
9049 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
9050 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
9051 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
9052 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
9053 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
9054 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
9055 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
9056 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
9057 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
9058 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
9059 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
9060 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
9061 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
9062 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
9063 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
9064 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
9065 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
9066 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9067 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9068 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
9069 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9070 Room 15-013-S1 88 days 11/30/20212/25/2022 11/30 Room 15-013-S1
9071 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
9072 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
9073 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
9074 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
9075 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
9076 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
9077 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
9078 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
9079 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
9080 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
9081 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
9082 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
9083 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
9084 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 236
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9085 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
9086 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
9087 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
9088 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9089 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9090 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
9091 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9092 Room 15-014-S21 88 days 11/30/20212/25/2022 11/30 Room 15-014-S21
9093 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
9094 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
9095 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
9096 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
9097 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
9098 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
9099 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
9100 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
9101 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
9102 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
9103 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
9104 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
9105 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
9106 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
9107 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
9108 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
9109 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
9110 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9111 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9112 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
9113 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9114 Room 15-015-S2 88 days 11/30/20212/25/2022 11/30 Room 15-015-S2
9115 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
9116 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
9117 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
9118 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
9119 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
9120 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
9121 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
9122 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
9123 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
9124 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
9125 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 237
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9126 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
9127 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
9128 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
9129 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
9130 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
9131 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
9132 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9133 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9134 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
9135 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9136 Room 15-016-S1 88 days 11/30/20212/25/2022 11/30 Room 15-016-S1
9137 Plumbing system piping installation水管系统 88 days 11/30/20212/25/2022 11/30 Plumbing system piping installation水管系统
9138 Sanitary ware Piping installation 排水安装 3 days 11/30/202112/2/2021 11/30
9139 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/3/2021 12/7/2021 12/3
9140 Cold water piping installation冷水安装 16 days 1/16/2022 1/31/2022 1/16
9141 Hot water piping installation热水管安装 16 days 2/5/2022 2/20/2022 2/5
9142 Pre-Testing 测试 5 days 2/21/2022 2/25/2022 2/21
9143 Fire fighting piping installation消防系统安装 15 days 12/13/202112/27/2021 12/13 Fire fighting piping installation消防系统安装
9144 Fire fighting pipe installation消防管安装 11 days 12/13/2021 12/23/2021 12/13
9145 Pre-Testing 测试 4 days 12/24/202112/27/2021 12/24
9146 MVAC System installation空调系统 43 days 1/4/2022 2/15/2022 1/4 MVAC System installation空调系统
9147 FCU installation风机盘安装 10 days 1/25/2022 2/3/2022 1/25
9148 15 days
Chiller Water Piping installation冷冻水管安装 1/25/2022 2/8/2022 1/25
9149 Valve Installation 空调阀门安装 15 days 1/25/2022 2/8/2022 1/25
9150 Ducting installation风管安装 15 days 1/4/2022 1/18/2022 1/4
9151 Pre-Testing 测试 4 days 2/9/2022 2/12/2022 2/9
9152 AC duct/pipe insulation 保温安装 7 days 2/9/2022 2/15/2022 2/9
9153 Electrical System installation电气系统 13 days 12/25/2021 1/6/2022 12/25 Electrical System installation电气系统
9154 EMT Conduit Installation EMT导管安装 7 days 12/25/202112/31/2021 12/25
9155 Electrical Tray Installation 桥架安装 7 days 12/25/202112/31/2021 12/25
9156 LV cable installation 强电电缆安装 7 days 12/25/202112/31/2021 12/25
9157 Circuit & Mega Testing 电路,回路测试 6 days 1/1/2022 1/6/2022 1/1
9158 MEP Corridor机电走廊安装 21 days 12/3/2021 12/23/2021 12/3 MEP Corridor机电走廊安装
9159 Electrical System installation 15 days 12/3/2021 12/17/2021 12/3 Electrical System installation
9160 Cable tray installation 桥架安装 4 days 12/3/2021 12/6/2021 12/3
9161 LV cable installation 强电电缆安装 4 days 12/14/202112/17/2021 12/14
9162 ELV cable installation 弱电电缆安装 4 days 12/14/202112/17/2021 12/14
9163 Fire fighting piping installation消防系统 14 days 12/10/2021 12/23/2021 12/10 Fire fighting piping installation消防系统
9164 Fire fighting pipe installation消防管安装 10 days 12/10/2021 12/19/2021 12/10
9165 Testing 测试 4 days 12/20/2021 12/23/2021 12/20
9166 MVAC System installation空调系统 20 days 12/4/2021 12/23/2021 12/4 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 238
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9167 Ducting for AC installation风管安装 7 days 12/4/2021 12/10/2021 12/4
9168 Chiller water pipe installation冷冻水管安装 14 days 12/4/2021 12/17/2021 12/4
9169 AC drain pipe installation空调排水管安装 5 days 12/9/2021 12/13/2021 12/9
9170 Testing 测试 3 days 12/18/2021 12/20/2021 12/18
9171 Duct/pipe insulation保温安装 3 days 12/21/2021 12/23/2021 12/21
9172 MEP Final Fix机电末端安装 14 days 3/31/2022 4/13/2022 3/31 MEP Final Fix机电末端安装
9173 Electrical Installation电气系统末端安装 12 days 3/31/2022 4/11/2022 3/31 Electrical Installation电气系统末端
9174 Fire alarm system 火警系统安装 7 days 4/2/2022 4/8/2022 4/2
9175 Public address system 公共广播系统 5 days 4/4/2022 4/8/2022 4/4
9176 Access control system 门禁系统 5 days 4/7/2022 4/11/2022 4/7
9177 Sockets and Switches Installation 开关插座 4 days 3/31/2022 4/3/2022 3/31
9178 Normal & Emergency Luminaires installation 普 5 days 4/4/2022 4/8/2022 4/4
通和应急照明安装
9179 MVAC Installation空调系统末端安装 12 days 4/2/2022 4/13/2022 4/2 MVAC Installation空调系统末端安
9180 Air grille/louver installation 通风格棚、百叶窗安装 7 days 4/2/2022 4/8/2022 4/2
9181 Wall controller units installation墙壁控制器 5 days 4/9/2022 4/13/2022 4/9
9182 Fire Protection Installation消防系统末端安装 9 days 3/31/2022 4/8/2022 3/31 Fire Protection Installation消防系统
9183 Sprinkler Installation 喷淋头安装 5 days 3/31/2022 4/4/2022 3/31
9184 Fire hose reel cabinet消防箱带卷盘 4 days 4/5/2022 4/8/2022 4/5
9185 MEP Level 16 机电16层 139 days12/3/2021 4/20/2022 12/3 MEP Level 16 机电16层
9186 Guest Room MEP Installation(1&2 Fix)客房机电安装101 days12/3/2021 3/13/2022 12/3 Guest Room MEP Installation(1&2 Fix)客房
9187 Room 16-001-S3 101 days12/3/2021 3/13/2022 12/3 Room 16-001-S3
9188 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9189 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9190 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9191 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9192 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9193 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9194 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9195 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9196 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9197 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9198 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9199 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9200 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9201 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9202 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9203 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9204 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9205 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9206 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9207 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 239
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9208 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9209 Room 16-002-S3 101 days12/3/2021 3/13/2022 12/3 Room 16-002-S3
9210 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9211 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9212 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9213 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9214 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9215 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9216 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9217 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9218 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9219 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9220 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9221 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9222 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9223 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9224 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9225 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9226 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9227 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9228 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9229 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9230 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9231 Room 16-003-S2 101 days12/3/2021 3/13/2022 12/3 Room 16-003-S2
9232 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9233 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9234 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9235 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9236 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9237 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9238 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9239 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9240 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9241 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9242 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9243 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9244 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9245 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9246 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9247 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9248 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 240
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9249 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9250 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9251 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9252 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9253 Room 16-004-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-004-S1
9254 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9255 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9256 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9257 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9258 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9259 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9260 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9261 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9262 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9263 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9264 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9265 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9266 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9267 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9268 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9269 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9270 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9271 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9272 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9273 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9274 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9275 Room 16-005-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-005-S1
9276 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9277 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9278 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9279 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9280 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9281 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9282 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9283 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9284 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9285 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9286 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9287 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9288 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9289 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 241
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9290 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9291 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9292 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9293 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9294 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9295 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9296 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9297 Room 16-006-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-006-S1
9298 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9299 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9300 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9301 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9302 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9303 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9304 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9305 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9306 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9307 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9308 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9309 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9310 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9311 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9312 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9313 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9314 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9315 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9316 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9317 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9318 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9319 Room 16-007-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-007-S1
9320 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9321 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9322 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9323 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9324 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9325 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9326 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9327 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9328 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9329 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9330 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 242
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9331 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9332 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9333 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9334 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9335 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9336 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9337 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9338 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9339 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9340 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9341 Room 16-008-S2 101 days12/3/2021 3/13/2022 12/3 Room 16-008-S2
9342 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9343 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9344 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9345 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9346 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9347 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9348 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9349 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9350 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9351 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9352 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9353 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9354 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9355 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9356 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9357 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9358 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9359 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9360 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9361 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9362 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9363 Room 16-009-S2 101 days12/3/2021 3/13/2022 12/3 Room 16-009-S2
9364 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9365 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9366 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9367 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9368 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9369 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9370 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9371 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 243
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9372 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9373 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9374 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9375 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9376 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9377 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9378 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9379 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9380 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9381 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9382 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9383 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9384 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9385 Room 16-010-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-010-S1
9386 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9387 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9388 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9389 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9390 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9391 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9392 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9393 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9394 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9395 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9396 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9397 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9398 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9399 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9400 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9401 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9402 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9403 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9404 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9405 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9406 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9407 Room 16-011-S4 101 days12/3/2021 3/13/2022 12/3 Room 16-011-S4
9408 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9409 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9410 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9411 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9412 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 244
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9413 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9414 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9415 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9416 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9417 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9418 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9419 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9420 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9421 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9422 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9423 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9424 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9425 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9426 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9427 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9428 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9429 Room 16-012-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-012-S1
9430 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9431 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9432 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9433 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9434 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9435 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9436 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9437 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9438 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9439 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9440 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9441 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9442 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9443 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9444 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9445 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9446 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9447 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9448 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9449 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9450 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9451 Room 16-013-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-013-S1
9452 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9453 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 245
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9454 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9455 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9456 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9457 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9458 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9459 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9460 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9461 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9462 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9463 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9464 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9465 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9466 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9467 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9468 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9469 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9470 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9471 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9472 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9473 Room 16-014-S21 101 days12/3/2021 3/13/2022 12/3 Room 16-014-S21
9474 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9475 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9476 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9477 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9478 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9479 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9480 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9481 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9482 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9483 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9484 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9485 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9486 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9487 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9488 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9489 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9490 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9491 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9492 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9493 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9494 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 246
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9495 Room 16-015-S2 101 days12/3/2021 3/13/2022 12/3 Room 16-015-S2
9496 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9497 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9498 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9499 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9500 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9501 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9502 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9503 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9504 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9505 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9506 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9507 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9508 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9509 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9510 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9511 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9512 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9513 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9514 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9515 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9516 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9517 Room 16-016-S1 101 days12/3/2021 3/13/2022 12/3 Room 16-016-S1
9518 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9519 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9520 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9521 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9522 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9523 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9524 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9525 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9526 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9527 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9528 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9529 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9530 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9531 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9532 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9533 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9534 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9535 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 247
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9536 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9537 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9538 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9539 MEP Corridor机电走廊安装 27 days 12/7/2021 1/2/2022 12/7 MEP Corridor机电走廊安装
9540 Electrical System installation 15 days 12/7/2021 12/21/2021 12/7 Electrical System installation
9541 Cable tray installation 桥架安装 4 days 12/7/2021 12/10/2021 12/7
9542 LV cable installation 强电电缆安装 4 days 12/18/202112/21/2021 12/18
9543 ELV cable installation 弱电电缆安装 4 days 12/18/202112/21/2021 12/18
9544 Fire fighting piping installation消防系统 14 days 12/20/2021 1/2/2022 12/20 Fire fighting piping installation消防系统
9545 Fire fighting pipe installation消防管安装 10 days 12/20/2021 12/29/2021 12/20
9546 Testing 测试 4 days 12/30/2021 1/2/2022 12/30
9547 MVAC System installation空调系统 20 days 12/11/2021 12/30/2021 12/11 MVAC System installation空调系统
9548 Ducting for AC installation风管安装 7 days 12/11/2021 12/17/2021 12/11
9549 Chiller water pipe installation冷冻水管安装 14 days 12/11/2021 12/24/2021 12/11
9550 AC drain pipe installation空调排水管安装 5 days 12/16/2021 12/20/2021 12/16
9551 Testing 测试 3 days 12/25/2021 12/27/2021 12/25
9552 Duct/pipe insulation保温安装 3 days 12/28/2021 12/30/2021 12/28
9553 MEP Final Fix机电末端安装 17 days 4/4/2022 4/20/2022 4/4 MEP Final Fix机电末端安装
9554 Electrical Installation电气系统末端安装 15 days 4/4/2022 4/18/2022 4/4 Electrical Installation电气系统末
9555 Fire alarm system 火警系统安装 7 days 4/9/2022 4/15/2022 4/9
9556 Public address system 公共广播系统 5 days 4/11/2022 4/15/2022 4/11
9557 Access control system 门禁系统 5 days 4/14/2022 4/18/2022 4/14
9558 Sockets and Switches Installation 开关插座 4 days 4/4/2022 4/7/2022 4/4
9559 Normal & Emergency Luminaires installation 普 5 days 4/8/2022 4/12/2022 4/8
通和应急照明安装
9560 MVAC Installation空调系统末端安装 12 days 4/9/2022 4/20/2022 4/9 MVAC Installation空调系统末端
9561 Air grille/louver installation 通风格棚、百叶窗安装 7 days 4/9/2022 4/15/2022 4/9
9562 Wall controller units installation墙壁控制器 5 days 4/16/2022 4/20/2022 4/16
9563 Fire Protection Installation消防系统末端安装 8 days 4/5/2022 4/12/2022 4/5 Fire Protection Installation消防系
9564 Sprinkler Installation 喷淋头安装 5 days 4/5/2022 4/9/2022 4/5
9565 Fire hose reel cabinet消防箱带卷盘 4 days 4/9/2022 4/12/2022 4/9
9566 MEP Level 17机电17层 146 days12/3/2021 4/27/2022 12/3 MEP Level 17机电17层
9567 Guest Room MEP Installation(1&2 Fix)客房机电安装101 days12/3/2021 3/13/2022 12/3 Guest Room MEP Installation(1&2 Fix)客房
9568 Room 17-001-S3 101 days12/3/2021 3/13/2022 12/3 Room 17-001-S3
9569 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9570 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9571 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9572 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9573 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9574 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9575 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9576 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 248
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9577 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9578 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9579 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9580 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9581 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9582 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9583 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9584 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9585 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9586 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9587 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9588 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9589 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9590 Room 17-002-S3 101 days12/3/2021 3/13/2022 12/3 Room 17-002-S3
9591 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9592 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9593 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9594 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9595 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9596 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9597 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9598 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9599 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9600 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9601 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9602 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9603 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9604 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9605 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9606 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9607 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9608 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9609 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9610 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9611 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9612 Room 17-003-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-003-S1
9613 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9614 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9615 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9616 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9617 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 249
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9618 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9619 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9620 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9621 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9622 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9623 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9624 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9625 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9626 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9627 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9628 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9629 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9630 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9631 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9632 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9633 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9634 Room 17-004-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-004-S1
9635 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9636 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9637 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9638 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9639 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9640 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9641 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9642 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9643 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9644 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9645 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9646 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9647 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9648 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9649 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9650 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9651 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9652 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9653 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9654 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9655 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9656 Room 17-005-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-005-S1
9657 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9658 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 250
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9659 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9660 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9661 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9662 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9663 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9664 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9665 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9666 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9667 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9668 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9669 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9670 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9671 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9672 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9673 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9674 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9675 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9676 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9677 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9678 Room 17-006-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-006-S1
9679 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9680 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9681 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9682 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9683 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9684 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9685 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9686 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9687 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9688 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9689 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9690 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9691 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9692 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9693 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9694 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9695 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9696 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9697 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9698 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9699 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 251
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9700 Room 17-007-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-007-S1
9701 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9702 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9703 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9704 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9705 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9706 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9707 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9708 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9709 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9710 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9711 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9712 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9713 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9714 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9715 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9716 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9717 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9718 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9719 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9720 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9721 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9722 Room 18-008-S4 101 days12/3/2021 3/13/2022 12/3 Room 18-008-S4
9723 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9724 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9725 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9726 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9727 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9728 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9729 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9730 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9731 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9732 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9733 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9734 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9735 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9736 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9737 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9738 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9739 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9740 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 252
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9741 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9742 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9743 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9744 Room 17-009-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-009-S1
9745 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9746 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9747 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9748 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9749 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9750 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9751 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9752 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9753 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9754 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9755 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9756 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9757 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9758 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9759 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9760 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9761 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9762 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9763 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9764 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9765 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9766 Room 17-010-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-010-S1
9767 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9768 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9769 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9770 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9771 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9772 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9773 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9774 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9775 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9776 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9777 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9778 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9779 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9780 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9781 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 253
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9782 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9783 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9784 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9785 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9786 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9787 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9788 Room 17-011-S4 101 days12/3/2021 3/13/2022 12/3 Room 17-011-S4
9789 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9790 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9791 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9792 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9793 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9794 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9795 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9796 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9797 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9798 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9799 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9800 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9801 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9802 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9803 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9804 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9805 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9806 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9807 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9808 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9809 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9810 Room 17-012-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-012-S1
9811 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9812 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9813 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9814 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9815 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9816 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9817 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9818 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9819 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9820 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9821 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9822 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 254
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9823 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9824 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9825 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9826 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9827 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9828 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9829 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9830 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9831 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9832 Room 17-013-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-013-S1
9833 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9834 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9835 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9836 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9837 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9838 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9839 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9840 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9841 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9842 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9843 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9844 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9845 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9846 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9847 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9848 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9849 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9850 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9851 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9852 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9853 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9854 Room 17-014-S2 101 days12/3/2021 3/13/2022 12/3 Room 17-014-S2
9855 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9856 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9857 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9858 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9859 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9860 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9861 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9862 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9863 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 255
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9864 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9865 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9866 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9867 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9868 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9869 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9870 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9871 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9872 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9873 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9874 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9875 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9876 Room 17-015-S2 101 days12/3/2021 3/13/2022 12/3 Room 17-015-S2
9877 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9878 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9879 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9880 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9881 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9882 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9883 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9884 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9885 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9886 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9887 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9888 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9889 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9890 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9891 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9892 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9893 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9894 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9895 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9896 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9897 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9898 Room 17-016-S1 101 days12/3/2021 3/13/2022 12/3 Room 17-016-S1
9899 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9900 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9901 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9902 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9903 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9904 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 256
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9905 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9906 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9907 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9908 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9909 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9910 15 days
Chiller Water Piping installation冷冻水管安装 2/4/2022 2/18/2022 2/4
9911 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9912 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9913 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9914 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9915 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9916 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9917 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9918 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9919 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9920 MEP Corridor机电走廊安装 27 days 12/7/2021 1/2/2022 12/7 MEP Corridor机电走廊安装
9921 Electrical System installation 15 days 12/7/2021 12/21/2021 12/7 Electrical System installation
9922 Cable tray installation 桥架安装 4 days 12/7/2021 12/10/2021 12/7
9923 LV cable installation 强电电缆安装 4 days 12/18/202112/21/2021 12/18
9924 ELV cable installation 弱电电缆安装 4 days 12/18/202112/21/2021 12/18
9925 Fire fighting piping installation消防系统 14 days 12/20/2021 1/2/2022 12/20 Fire fighting piping installation消防系统
9926 Fire fighting pipe installation消防管安装 10 days 12/20/2021 12/29/2021 12/20
9927 Testing 测试 4 days 12/30/2021 1/2/2022 12/30
9928 MVAC System installation空调系统 20 days 12/11/2021 12/30/2021 12/11 MVAC System installation空调系统
9929 Ducting for AC installation风管安装 7 days 12/11/2021 12/17/2021 12/11
9930 Chiller water pipe installation冷冻水管安装 14 days 12/11/2021 12/24/2021 12/11
9931 AC drain pipe installation空调排水管安装 5 days 12/16/2021 12/20/2021 12/16
9932 Testing 测试 3 days 12/25/2021 12/27/2021 12/25
9933 Duct/pipe insulation保温安装 3 days 12/28/2021 12/30/2021 12/28
9934 MEP Final Fix机电末端安装 20 days 4/8/2022 4/27/2022 4/8 MEP Final Fix机电末端安装
9935 Electrical Installation电气系统末端安装 18 days 4/8/2022 4/25/2022 4/8 Electrical Installation电气系统
9936 Fire alarm system 火警系统安装 7 days 4/16/2022 4/22/2022 4/16
9937 Public address system 公共广播系统 5 days 4/18/2022 4/22/2022 4/18
9938 Access control system 门禁系统 5 days 4/21/2022 4/25/2022 4/21
9939 Sockets and Switches Installation 开关插座 4 days 4/8/2022 4/11/2022 4/8
9940 Normal & Emergency Luminaires installation 普 5 days 4/12/2022 4/16/2022 4/12
通和应急照明安装
9941 MVAC Installation空调系统末端安装 12 days 4/16/2022 4/27/2022 4/16 MVAC Installation空调系统末
9942 Air grille/louver installation 通风格棚、百叶窗安装 7 days 4/16/2022 4/22/2022 4/16
9943 Wall controller units installation墙壁控制器 5 days 4/23/2022 4/27/2022 4/23
9944 Fire Protection Installation消防系统末端安装 7 days 4/10/2022 4/16/2022 4/10 Fire Protection Installation消防系
9945 Sprinkler Installation 喷淋头安装 5 days 4/10/2022 4/14/2022 4/10

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 257
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9946 Fire hose reel cabinet消防箱带卷盘 4 days 4/13/2022 4/16/2022 4/13
9947 MEP Level 18 机电18层 153 days12/3/2021 5/4/2022 12/3 MEP Level 18 机电18层
9948 Guest Room MEP Installation(1&2 Fix)客房机电安装101 days12/3/2021 3/13/2022 12/3 Guest Room MEP Installation(1&2 Fix)客房
9949 Room 18-001-S3 101 days12/3/2021 3/13/2022 12/3 Room 18-001-S3
9950 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9951 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9952 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9953 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9954 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9955 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9956 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9957 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9958 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9959 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9960 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9961 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9962 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9963 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9964 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
9965 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9966 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9967 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9968 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9969 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9970 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9971 Room 18-002-S3 101 days12/3/2021 3/13/2022 12/3 Room 18-002-S3
9972 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9973 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9974 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9975 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9976 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9977 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
9978 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
9979 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
9980 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
9981 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
9982 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
9983 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
9984 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
9985 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
9986 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 258
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
9987 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
9988 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
9989 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
9990 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
9991 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
9992 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
9993 Room 18-003-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-003-S1
9994 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
9995 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
9996 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
9997 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
9998 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
9999 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10000 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10001 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10002 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10003 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10004 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10005 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10006 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10007 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10008 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10009 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10010 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10011 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10012 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10013 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10014 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10015 Room 18-004-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-004-S1
10016 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10017 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10018 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10019 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10020 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10021 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10022 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10023 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10024 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10025 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10026 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10027 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 259
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10028 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10029 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10030 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10031 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10032 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10033 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10034 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10035 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10036 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10037 Room 18-005-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-005-S1
10038 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10039 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10040 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10041 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10042 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10043 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10044 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10045 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10046 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10047 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10048 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10049 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10050 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10051 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10052 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10053 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10054 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10055 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10056 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10057 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10058 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10059 Room 18-006-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-006-S1
10060 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10061 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10062 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10063 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10064 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10065 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10066 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10067 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10068 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 260
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10069 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10070 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10071 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10072 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10073 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10074 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10075 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10076 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10077 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10078 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10079 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10080 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10081 Room 18-007-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-007-S1
10082 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10083 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10084 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10085 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10086 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10087 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10088 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10089 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10090 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10091 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10092 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10093 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10094 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10095 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10096 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10097 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10098 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10099 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10100 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10101 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10102 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10103 Room 18-008-S4 101 days12/3/2021 3/13/2022 12/3 Room 18-008-S4
10104 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10105 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10106 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10107 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10108 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10109 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 261
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10110 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10111 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10112 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10113 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10114 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10115 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10116 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10117 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10118 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10119 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10120 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10121 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10122 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10123 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10124 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10125 Room 18-009-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-009-S1
10126 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10127 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10128 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10129 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10130 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10131 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10132 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10133 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10134 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10135 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10136 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10137 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10138 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10139 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10140 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10141 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10142 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10143 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10144 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10145 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10146 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10147 Room 18-010-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-010-S1
10148 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10149 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10150 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 262
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10151 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10152 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10153 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10154 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10155 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10156 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10157 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10158 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10159 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10160 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10161 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10162 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10163 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10164 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10165 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10166 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10167 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10168 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10169 Room 18-011-S4 101 days12/3/2021 3/13/2022 12/3 Room 18-011-S4
10170 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10171 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10172 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10173 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10174 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10175 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10176 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10177 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10178 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10179 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10180 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10181 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10182 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10183 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10184 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10185 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10186 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10187 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10188 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10189 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10190 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10191 Room 18-012-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-012-S1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 263
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10192 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10193 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10194 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10195 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10196 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10197 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10198 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10199 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10200 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10201 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10202 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10203 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10204 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10205 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10206 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10207 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10208 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10209 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10210 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10211 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10212 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10213 Room 18-013-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-013-S1
10214 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10215 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10216 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10217 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10218 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10219 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10220 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10221 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10222 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10223 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10224 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10225 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10226 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10227 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10228 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10229 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10230 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10231 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10232 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 264
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10233 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10234 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10235 Room 18-014-S2 101 days12/3/2021 3/13/2022 12/3 Room 18-014-S2
10236 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10237 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10238 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10239 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10240 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10241 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10242 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10243 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10244 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10245 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10246 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10247 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10248 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10249 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10250 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10251 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10252 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10253 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10254 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10255 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10256 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10257 Room 18-015-S2 101 days12/3/2021 3/13/2022 12/3 Room 18-015-S2
10258 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10259 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10260 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10261 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10262 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10263 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10264 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10265 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10266 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10267 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10268 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10269 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10270 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10271 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10272 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10273 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 265
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10274 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10275 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10276 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10277 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10278 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10279 Room 18-016-S1 101 days12/3/2021 3/13/2022 12/3 Room 18-016-S1
10280 Plumbing system piping installation水管系统 101 days12/3/2021 3/13/2022 12/3 Plumbing system piping installation水管系
10281 Sanitary ware Piping installation 排水安装 3 days 12/3/2021 12/5/2021 12/3
10282 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/6/2021 12/10/2021 12/6
10283 Cold water piping installation冷水安装 16 days 2/1/2022 2/16/2022 2/1
10284 Hot water piping installation热水管安装 16 days 2/21/2022 3/8/2022 2/21
10285 Pre-Testing 测试 5 days 3/9/2022 3/13/2022 3/9
10286 Fire fighting piping installation消防系统安装 15 days 12/24/20211/7/2022 12/24 Fire fighting piping installation消防系统安装
10287 Fire fighting pipe installation消防管安装 11 days 12/24/2021 1/3/2022 12/24
10288 Pre-Testing 测试 4 days 1/4/2022 1/7/2022 1/4
10289 MVAC System installation空调系统 38 days 1/19/2022 2/25/2022 1/19 MVAC System installation空调系统
10290 FCU installation风机盘安装 10 days 2/4/2022 2/13/2022 2/4
10291 15 days 2/4/2022 2/18/2022
Chiller Water Piping installation冷冻水管安装 2/4
10292 Valve Installation 空调阀门安装 15 days 2/4/2022 2/18/2022 2/4
10293 Ducting installation风管安装 15 days 1/19/2022 2/2/2022 1/19
10294 Pre-Testing 测试 4 days 2/19/2022 2/22/2022 2/19
10295 AC duct/pipe insulation 保温安装 7 days 2/19/2022 2/25/2022 2/19
10296 Electrical System installation电气系统 13 days 1/1/2022 1/13/2022 1/1 Electrical System installation电气系统
10297 EMT Conduit Installation EMT导管安装 7 days 1/1/2022 1/7/2022 1/1
10298 Electrical Tray Installation 桥架安装 7 days 1/1/2022 1/7/2022 1/1
10299 LV cable installation 强电电缆安装 7 days 1/1/2022 1/7/2022 1/1
10300 Circuit & Mega Testing 电路,回路测试 6 days 1/8/2022 1/13/2022 1/8
10301 MEP Corridor机电走廊安装 27 days 12/7/2021 1/2/2022 12/7 MEP Corridor机电走廊安装
10302 Electrical System installation 15 days 12/7/2021 12/21/2021 12/7 Electrical System installation
10303 Cable tray installation 桥架安装 4 days 12/7/2021 12/10/2021 12/7
10304 LV cable installation 强电电缆安装 4 days 12/18/202112/21/2021 12/18
10305 ELV cable installation 弱电电缆安装 4 days 12/18/202112/21/2021 12/18
10306 Fire fighting piping installation消防系统 14 days 12/20/2021 1/2/2022 12/20 Fire fighting piping installation消防系统
10307 Fire fighting pipe installation消防管安装 10 days 12/20/2021 12/29/2021 12/20
10308 Testing 测试 4 days 12/30/2021 1/2/2022 12/30
10309 MVAC System installation空调系统 20 days 12/11/2021 12/30/2021 12/11 MVAC System installation空调系统
10310 Ducting for AC installation风管安装 7 days 12/11/2021 12/17/2021 12/11
10311 Chiller water pipe installation冷冻水管安装 14 days 12/11/2021 12/24/2021 12/11
10312 AC drain pipe installation空调排水管安装 5 days 12/16/2021 12/20/2021 12/16
10313 Testing 测试 3 days 12/25/2021 12/27/2021 12/25
10314 Duct/pipe insulation保温安装 3 days 12/28/2021 12/30/2021 12/28

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 266
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10315 MEP Final Fix机电末端安装 23 days 4/12/2022 5/4/2022 4/12 MEP Final Fix机电末端安装
10316 Electrical Installation电气系统末端安装 21 days 4/12/2022 5/2/2022 4/12 Electrical Installation电气系统
10317 Fire alarm system 火警系统安装 7 days 4/23/2022 4/29/2022 4/23
10318 Public address system 公共广播系统 5 days 4/25/2022 4/29/2022 4/25
10319 Access control system 门禁系统 5 days 4/28/2022 5/2/2022 4/28
10320 Sockets and Switches Installation 开关插座 4 days 4/12/2022 4/15/2022 4/12
10321 Normal & Emergency Luminaires installation 普 5 days 4/16/2022 4/20/2022 4/16
通和应急照明安装
10322 MVAC Installation空调系统末端安装 12 days 4/23/2022 5/4/2022 4/23 MVAC Installation空调系统
10323 Air grille/louver installation 通风格棚、百叶窗安装 7 days 4/23/2022 4/29/2022 4/23
10324 Wall controller units installation墙壁控制器 5 days 4/30/2022 5/4/2022 4/30
10325 Fire Protection Installation消防系统末端安装 6 days 4/15/2022 4/20/2022 4/15 Fire Protection Installation消防
10326 Sprinkler Installation 喷淋头安装 5 days 4/15/2022 4/19/2022 4/15
10327 Fire hose reel cabinet消防箱带卷盘 4 days 4/17/2022 4/20/2022 4/17
10328 MEP Level 19机电19层 157 days12/6/2021 5/11/2022 12/6 MEP Level 19机电19层
10329 Guest Room MEP Installation(1&2 Fix)客房机电安装114 days12/6/2021 3/29/2022 12/6 Guest Room MEP Installation(1&2 Fix)
10330 Room 19-001-S3 114 days12/6/2021 3/29/2022 12/6 Room 19-001-S3
10331 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10332 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10333 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10334 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10335 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10336 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10337 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10338 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10339 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10340 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10341 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10342 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10343 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10344 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10345 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10346 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10347 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10348 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10349 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10350 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10351 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10352 Room 19-002-S3 114 days12/6/2021 3/29/2022 12/6 Room 19-002-S3
10353 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10354 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10355 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 267
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10356 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10357 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10358 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10359 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10360 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10361 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10362 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10363 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10364 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10365 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10366 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10367 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10368 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10369 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10370 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10371 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10372 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10373 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10374 Room 19-003-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-003-S1
10375 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10376 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10377 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10378 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10379 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10380 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10381 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10382 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10383 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10384 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10385 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10386 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10387 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10388 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10389 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10390 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10391 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10392 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10393 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10394 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10395 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10396 Room 19-004-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-004-S1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 268
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10397 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10398 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10399 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10400 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10401 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10402 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10403 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10404 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10405 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10406 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10407 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10408 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10409 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10410 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10411 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10412 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10413 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10414 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10415 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10416 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10417 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10418 Room 19-005-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-005-S1
10419 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10420 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10421 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10422 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10423 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10424 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10425 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10426 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10427 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10428 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10429 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10430 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10431 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10432 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10433 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10434 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10435 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10436 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10437 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 269
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10438 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10439 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10440 Room 19-006-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-006-S1
10441 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10442 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10443 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10444 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10445 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10446 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10447 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10448 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10449 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10450 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10451 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10452 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10453 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10454 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10455 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10456 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10457 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10458 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10459 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10460 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10461 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10462 Room 19-012-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-012-S1
10463 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10464 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10465 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10466 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10467 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10468 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10469 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10470 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10471 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10472 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10473 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10474 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10475 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10476 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10477 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10478 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 270
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10479 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10480 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10481 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10482 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10483 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10484 Room 19-013-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-013-S1
10485 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10486 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10487 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10488 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10489 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10490 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10491 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10492 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10493 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10494 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10495 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10496 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10497 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10498 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10499 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10500 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10501 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10502 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10503 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10504 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10505 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10506 Room 19-014-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-014-S1
10507 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10508 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10509 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10510 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10511 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10512 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10513 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10514 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10515 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10516 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10517 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10518 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10519 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 271
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10520 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10521 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10522 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10523 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10524 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10525 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10526 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10527 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10528 Room 19-015-S1 114 days12/6/2021 3/29/2022 12/6 Room 19-015-S1
10529 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10530 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10531 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10532 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10533 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10534 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10535 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10536 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10537 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10538 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10539 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10540 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10541 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10542 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10543 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10544 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10545 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10546 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10547 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10548 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10549 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10550 MEP Corridor机电走廊安装 33 days 12/11/2021 1/12/2022 12/11 MEP Corridor机电走廊安装
10551 Electrical System installation 15 days 12/11/2021 12/25/2021 12/11 Electrical System installation
10552 Cable tray installation 桥架安装 4 days 12/11/2021 12/14/2021 12/11
10553 LV cable installation 强电电缆安装 4 days 12/22/202112/25/2021 12/22
10554 ELV cable installation 弱电电缆安装 4 days 12/22/202112/25/2021 12/22
10555 Fire fighting piping installation消防系统 14 days 12/30/2021 1/12/2022 12/30 Fire fighting piping installation消防系统
10556 Fire fighting pipe installation消防管安装 10 days 12/30/2021 1/8/2022 12/30
10557 Testing 测试 4 days 1/9/2022 1/12/2022 1/9
10558 MVAC System installation空调系统 20 days 12/18/2021 1/6/2022 12/18 MVAC System installation空调系统
10559 Ducting for AC installation风管安装 7 days 12/18/2021 12/24/2021 12/18
10560 Chiller water pipe installation冷冻水管安装 14 days 12/18/2021 12/31/2021 12/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 272
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10561 AC drain pipe installation空调排水管安装 5 days 12/23/2021 12/27/2021 12/23
10562 Testing 测试 3 days 1/1/2022 1/3/2022 1/1
10563 Duct/pipe insulation保温安装 3 days 1/4/2022 1/6/2022 1/4
10564 MEP Final Fix机电末端安装 26 days 4/16/2022 5/11/2022 4/16 MEP Final Fix机电末端安装
10565 Electrical Installation电气系统末端安装 24 days 4/16/2022 5/9/2022 4/16 Electrical Installation电气系
10566 Fire alarm system 火警系统安装 7 days 4/30/2022 5/6/2022 4/30
10567 Public address system 公共广播系统 5 days 5/2/2022 5/6/2022 5/2
10568 Access control system 门禁系统 5 days 5/5/2022 5/9/2022 5/5
10569 Sockets and Switches Installation 开关插座 4 days 4/16/2022 4/19/2022 4/16
10570 Normal & Emergency Luminaires installation 普 5 days 4/20/2022 4/24/2022 4/20
通和应急照明安装
10571 MVAC Installation空调系统末端安装 12 days 4/30/2022 5/11/2022 4/30 MVAC Installation空调系统
10572 Air grille/louver installation 通风格棚、百叶窗安装 7 days 4/30/2022 5/6/2022 4/30
10573 Wall controller units installation墙壁控制器 5 days 5/7/2022 5/11/2022 5/7
10574 Fire Protection Installation消防系统末端安装 5 days 4/20/2022 4/24/2022 4/20 Fire Protection Installation消防
10575 Sprinkler Installation 喷淋头安装 5 days 4/20/2022 4/24/2022 4/20
10576 Fire hose reel cabinet消防箱带卷盘 4 days 4/21/2022 4/24/2022 4/21
10577 MEP Level 20 机电20层 164 days12/6/2021 5/18/2022 12/6 MEP Level 20 机电20层
10578 Guest Room MEP Installation(1&2 Fix)客房机电安装114 days12/6/2021 3/29/2022 12/6 Guest Room MEP Installation(1&2 Fix)
10579 Room 20-001-S3 114 days12/6/2021 3/29/2022 12/6 Room 20-001-S3
10580 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10581 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10582 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10583 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10584 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10585 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10586 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10587 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10588 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10589 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10590 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10591 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10592 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10593 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10594 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10595 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10596 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10597 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10598 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10599 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10600 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10601 Room 20-002-S3 114 days12/6/2021 3/29/2022 12/6 Room 20-002-S3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 273
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10602 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10603 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10604 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10605 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10606 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10607 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10608 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10609 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10610 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10611 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10612 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10613 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10614 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10615 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10616 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10617 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10618 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10619 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10620 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10621 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10622 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10623 Room 20-003-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-003-S1
10624 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10625 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10626 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10627 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10628 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10629 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10630 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10631 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10632 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10633 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10634 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10635 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10636 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10637 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10638 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10639 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10640 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10641 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10642 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 274
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10643 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10644 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10645 Room 20-004-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-004-S1
10646 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10647 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10648 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10649 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10650 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10651 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10652 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10653 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10654 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10655 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10656 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10657 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10658 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10659 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10660 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10661 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10662 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10663 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10664 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10665 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10666 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10667 Room 20-005-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-005-S1
10668 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10669 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10670 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10671 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10672 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10673 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10674 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10675 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10676 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10677 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10678 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10679 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10680 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10681 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10682 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10683 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 275
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10684 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10685 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10686 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10687 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10688 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10689 Room 20-006-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-006-S1
10690 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10691 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10692 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10693 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10694 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10695 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10696 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10697 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10698 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10699 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10700 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10701 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10702 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10703 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10704 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10705 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10706 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10707 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10708 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10709 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10710 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10711 Room 20-007-SUITE B 114 days12/6/2021 3/29/2022 12/6 Room 20-007-SUITE B
10712 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10713 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10714 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10715 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10716 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10717 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10718 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10719 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10720 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10721 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10722 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10723 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10724 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 276
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10725 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10726 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10727 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10728 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10729 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10730 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10731 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10732 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10733 Room 20-008-SUITE A 114 days12/6/2021 3/29/2022 12/6 Room 20-008-SUITE A
10734 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10735 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10736 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10737 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10738 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10739 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10740 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10741 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10742 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10743 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10744 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10745 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10746 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10747 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10748 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10749 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10750 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10751 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10752 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10753 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10754 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10755 Room 20-009-SUITE B 114 days12/6/2021 3/29/2022 12/6 Room 20-009-SUITE B
10756 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10757 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10758 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10759 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10760 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10761 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10762 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10763 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10764 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10765 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 277
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10766 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10767 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10768 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10769 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10770 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10771 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10772 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10773 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10774 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10775 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10776 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10777 Room 20-010-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-010-S1
10778 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10779 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10780 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10781 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10782 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10783 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10784 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10785 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10786 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10787 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10788 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10789 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10790 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10791 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10792 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10793 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10794 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10795 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10796 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10797 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10798 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10799 Room 20-011-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-011-S1
10800 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10801 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10802 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10803 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10804 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10805 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10806 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 278
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10807 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10808 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10809 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10810 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10811 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10812 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10813 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10814 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10815 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10816 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10817 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10818 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10819 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10820 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10821 Room 20-012-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-012-S1
10822 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10823 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10824 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10825 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10826 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10827 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10828 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10829 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10830 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10831 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10832 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10833 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10834 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10835 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10836 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10837 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10838 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10839 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10840 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10841 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10842 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10843 Room 20-013-S1 114 days12/6/2021 3/29/2022 12/6 Room 20-013-S1
10844 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10845 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10846 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10847 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 279
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10848 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10849 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10850 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10851 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10852 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10853 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10854 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10855 15 days
Chiller Water Piping installation冷冻水管安装 2/14/2022 2/28/2022 2/14
10856 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10857 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10858 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10859 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10860 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10861 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10862 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10863 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10864 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10865 MEP Corridor机电走廊安装 33 days 12/11/2021 1/12/2022 12/11 MEP Corridor机电走廊安装
10866 Electrical System installation 15 days 12/11/2021 12/25/2021 12/11 Electrical System installation
10867 Cable tray installation 桥架安装 4 days 12/11/2021 12/14/2021 12/11
10868 LV cable installation 强电电缆安装 4 days 12/22/202112/25/2021 12/22
10869 ELV cable installation 弱电电缆安装 4 days 12/22/202112/25/2021 12/22
10870 Fire fighting piping installation消防系统 14 days 12/30/2021 1/12/2022 12/30 Fire fighting piping installation消防系统
10871 Fire fighting pipe installation消防管安装 10 days 12/30/2021 1/8/2022 12/30
10872 Testing 测试 4 days 1/9/2022 1/12/2022 1/9
10873 MVAC System installation空调系统 20 days 12/18/2021 1/6/2022 12/18 MVAC System installation空调系统
10874 Ducting for AC installation风管安装 7 days 12/18/2021 12/24/2021 12/18
10875 Chiller water pipe installation冷冻水管安装 14 days 12/18/2021 12/31/2021 12/18
10876 AC drain pipe installation空调排水管安装 5 days 12/23/2021 12/27/2021 12/23
10877 Testing 测试 3 days 1/1/2022 1/3/2022 1/1
10878 Duct/pipe insulation保温安装 3 days 1/4/2022 1/6/2022 1/4
10879 MEP Final Fix机电末端安装 29 days 4/20/2022 5/18/2022 4/20 MEP Final Fix机电末端安
10880 Electrical Installation电气系统末端安装 27 days 4/20/2022 5/16/2022 4/20 Electrical Installation电气
10881 Fire alarm system 火警系统安装 7 days 5/7/2022 5/13/2022 5/7
10882 Public address system 公共广播系统 5 days 5/9/2022 5/13/2022 5/9
10883 Access control system 门禁系统 5 days 5/12/2022 5/16/2022 5/12
10884 Sockets and Switches Installation 开关插座 4 days 4/20/2022 4/23/2022 4/20
10885 Normal & Emergency Luminaires installation 普 5 days 4/24/2022 4/28/2022 4/24
通和应急照明安装
10886 MVAC Installation空调系统末端安装 12 days 5/7/2022 5/18/2022 5/7 MVAC Installation空调系
10887 Air grille/louver installation 通风格棚、百叶窗安装 7 days 5/7/2022 5/13/2022 5/7
10888 Wall controller units installation墙壁控制器 5 days 5/14/2022 5/18/2022 5/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 280
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10889 Fire Protection Installation消防系统末端安装 5 days 4/25/2022 4/29/2022 4/25 Fire Protection Installation消
10890 Sprinkler Installation 喷淋头安装 5 days 4/25/2022 4/29/2022 4/25
10891 Fire hose reel cabinet消防箱带卷盘 4 days 4/25/2022 4/28/2022 4/25
10892 MEP Level 21 机电21层 171 days12/6/2021 5/25/2022 12/6 MEP Level 21 机电21层
10893 Guest Room MEP Installation(1&2 Fix)客房机电安装114 days12/6/2021 3/29/2022 12/6 Guest Room MEP Installation(1&2 Fix)
10894 Room 21-001-S3 114 days12/6/2021 3/29/2022 12/6 Room 21-001-S3
10895 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10896 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10897 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10898 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10899 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10900 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10901 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10902 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10903 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10904 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10905 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10906 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10907 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10908 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10909 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10910 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10911 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10912 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10913 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10914 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10915 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10916 Room 21-002-S3 114 days12/6/2021 3/29/2022 12/6 Room 21-002-S3
10917 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10918 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10919 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10920 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10921 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10922 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10923 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10924 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10925 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10926 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10927 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10928 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10929 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 281
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10930 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10931 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10932 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10933 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10934 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10935 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10936 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10937 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10938 Room 21-003-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-003-S1
10939 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10940 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10941 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10942 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10943 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10944 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10945 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10946 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10947 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10948 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10949 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10950 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10951 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10952 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10953 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10954 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10955 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10956 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10957 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10958 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10959 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10960 Room 21-004-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-004-S1
10961 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10962 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10963 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10964 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10965 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10966 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10967 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10968 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10969 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10970 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 282
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
10971 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10972 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10973 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10974 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10975 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10976 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10977 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
10978 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
10979 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
10980 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
10981 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
10982 Room 21-005-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-005-S1
10983 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
10984 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
10985 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
10986 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
10987 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
10988 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
10989 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
10990 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
10991 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
10992 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
10993 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
10994 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
10995 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
10996 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
10997 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
10998 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
10999 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11000 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11001 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11002 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11003 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11004 Room 21-006-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-006-S1
11005 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
11006 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11007 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11008 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
11009 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11010 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11011 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 283
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11012 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11013 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11014 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11015 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11016 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11017 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11018 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11019 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11020 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11021 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11022 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11023 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11024 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11025 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11026 Room 21-007-SUITE B 114 days12/6/2021 3/29/2022 12/6 Room 21-007-SUITE B
11027 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
11028 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11029 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11030 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
11031 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11032 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11033 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11034 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11035 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11036 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11037 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11038 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11039 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11040 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11041 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11042 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11043 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11044 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11045 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11046 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11047 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11048 Room 21-008-SUITE A 114 days12/6/2021 3/29/2022 12/6 Room 21-008-SUITE A
11049 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
11050 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11051 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11052 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 284
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11053 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11054 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11055 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11056 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11057 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11058 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11059 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11060 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11061 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11062 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11063 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11064 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11065 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11066 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11067 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11068 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11069 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11070 Room 21-009-SUITE B 114 days12/6/2021 3/29/2022 12/6 Room 21-009-SUITE B
11071 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
11072 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11073 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11074 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
11075 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11076 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11077 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11078 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11079 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11080 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11081 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11082 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11083 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11084 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11085 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11086 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11087 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11088 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11089 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11090 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11091 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11092 Room 21-010-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-010-S1
11093 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 285
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11094 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11095 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11096 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
11097 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11098 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11099 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11100 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11101 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11102 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11103 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11104 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11105 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11106 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11107 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11108 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11109 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11110 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11111 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11112 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11113 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11114 Room 21-011-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-011-S1
11115 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
11116 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11117 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11118 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
11119 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11120 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11121 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11122 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11123 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11124 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11125 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11126 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11127 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11128 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11129 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11130 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11131 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11132 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11133 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11134 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 286
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11135 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11136 Room 21-012-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-012-S1
11137 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
11138 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11139 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11140 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
11141 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11142 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11143 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11144 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11145 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11146 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11147 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11148 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11149 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11150 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11151 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11152 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11153 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统
11154 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11155 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11156 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11157 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11158 Room 21-013-S1 114 days12/6/2021 3/29/2022 12/6 Room 21-013-S1
11159 Plumbing system piping installation水管系统 114 days12/6/2021 3/29/2022 12/6 Plumbing system piping installation水
11160 Sanitary ware Piping installation 排水安装 3 days 12/6/2021 12/8/2021 12/6
11161 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/9/2021 12/13/2021 12/9
11162 Cold water piping installation冷水安装 16 days 2/17/2022 3/4/2022 2/17
11163 Hot water piping installation热水管安装 16 days 3/9/2022 3/24/2022 3/9
11164 Pre-Testing 测试 5 days 3/25/2022 3/29/2022 3/25
11165 Fire fighting piping installation消防系统安装 15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11166 Fire fighting pipe installation消防管安装 11 days 1/4/2022 1/14/2022 1/4
11167 Pre-Testing 测试 4 days 1/15/2022 1/18/2022 1/15
11168 MVAC System installation空调系统 33 days 2/3/2022 3/7/2022 2/3 MVAC System installation空调系统
11169 FCU installation风机盘安装 10 days 2/14/2022 2/23/2022 2/14
11170 15 days 2/14/2022 2/28/2022
Chiller Water Piping installation冷冻水管安装 2/14
11171 Valve Installation 空调阀门安装 15 days 2/14/2022 2/28/2022 2/14
11172 Ducting installation风管安装 15 days 2/3/2022 2/17/2022 2/3
11173 Pre-Testing 测试 4 days 3/1/2022 3/4/2022 3/1
11174 AC duct/pipe insulation 保温安装 7 days 3/1/2022 3/7/2022 3/1
11175 Electrical System installation电气系统 13 days 1/8/2022 1/20/2022 1/8 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 287
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11176 EMT Conduit Installation EMT导管安装 7 days 1/8/2022 1/14/2022 1/8
11177 Electrical Tray Installation 桥架安装 7 days 1/8/2022 1/14/2022 1/8
11178 LV cable installation 强电电缆安装 7 days 1/8/2022 1/14/2022 1/8
11179 Circuit & Mega Testing 电路,回路测试 6 days 1/15/2022 1/20/2022 1/15
11180 MEP Corridor机电走廊安装 33 days 12/11/2021 1/12/2022 12/11 MEP Corridor机电走廊安装
11181 Electrical System installation 15 days 12/11/2021 12/25/2021 12/11 Electrical System installation
11182 Cable tray installation 桥架安装 4 days 12/11/2021 12/14/2021 12/11
11183 LV cable installation 强电电缆安装 4 days 12/22/202112/25/2021 12/22
11184 ELV cable installation 弱电电缆安装 4 days 12/22/202112/25/2021 12/22
11185 Fire fighting piping installation消防系统 14 days 12/30/2021 1/12/2022 12/30 Fire fighting piping installation消防系统
11186 Fire fighting pipe installation消防管安装 10 days 12/30/2021 1/8/2022 12/30
11187 Testing 测试 4 days 1/9/2022 1/12/2022 1/9
11188 MVAC System installation空调系统 20 days 12/18/2021 1/6/2022 12/18 MVAC System installation空调系统
11189 Ducting for AC installation风管安装 7 days 12/18/2021 12/24/2021 12/18
11190 Chiller water pipe installation冷冻水管安装 14 days 12/18/2021 12/31/2021 12/18
11191 AC drain pipe installation空调排水管安装 5 days 12/23/2021 12/27/2021 12/23
11192 Testing 测试 3 days 1/1/2022 1/3/2022 1/1
11193 Duct/pipe insulation保温安装 3 days 1/4/2022 1/6/2022 1/4
11194 MEP Final Fix机电末端安装 32 days 4/24/2022 5/25/2022 4/24 MEP Final Fix机电末端
11195 Electrical Installation电气系统末端安装 30 days 4/24/2022 5/23/2022 4/24 Electrical Installation电
11196 Fire alarm system 火警系统安装 7 days 5/14/2022 5/20/2022 5/14
11197 Public address system 公共广播系统 5 days 5/16/2022 5/20/2022 5/16
11198 Access control system 门禁系统 5 days 5/19/2022 5/23/2022 5/19
11199 Sockets and Switches Installation 开关插座 4 days 4/24/2022 4/27/2022 4/24
11200 Normal & Emergency Luminaires installation 普 5 days 4/28/2022 5/2/2022 4/28
通和应急照明安装
11201 MVAC Installation空调系统末端安装 12 days 5/14/2022 5/25/2022 5/14 MVAC Installation空调
11202 Air grille/louver installation 通风格棚、百叶窗安装 7 days 5/14/2022 5/20/2022 5/14
11203 Wall controller units installation墙壁控制器 5 days 5/21/2022 5/25/2022 5/21
11204 Fire Protection Installation消防系统末端安装 6 days 4/29/2022 5/4/2022 4/29 Fire Protection Installation消
11205 Sprinkler Installation 喷淋头安装 5 days 4/30/2022 5/4/2022 4/30
11206 Fire hose reel cabinet消防箱带卷盘 4 days 4/29/2022 5/2/2022 4/29
11207 MEP Level 22 机电22层 175 days12/9/2021 6/1/2022 12/9 MEP Level 22 机电2
11208 Guest Room MEP Installation(1&2 Fix)客房机电安装127 days12/9/2021 4/14/2022 12/9 Guest Room MEP Installation(1&2
11209 Room 22-001-S3 127 days12/9/2021 4/14/2022 12/9 Room 22-001-S3
11210 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11211 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11212 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11213 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11214 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11215 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11216 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 288
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11217 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11218 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11219 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11220 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11221 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11222 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11223 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11224 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11225 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11226 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11227 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11228 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11229 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11230 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11231 Room 22-002-S3 127 days12/9/2021 4/14/2022 12/9 Room 22-002-S3
11232 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11233 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11234 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11235 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11236 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11237 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11238 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11239 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11240 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11241 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11242 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11243 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11244 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11245 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11246 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11247 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11248 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11249 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11250 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11251 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11252 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11253 Room 22-003-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-003-S1
11254 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11255 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11256 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11257 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 289
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11258 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11259 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11260 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11261 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11262 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11263 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11264 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11265 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11266 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11267 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11268 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11269 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11270 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11271 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11272 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11273 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11274 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11275 Room 22-004-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-004-S1
11276 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11277 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11278 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11279 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11280 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11281 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11282 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11283 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11284 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11285 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11286 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11287 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11288 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11289 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11290 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11291 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11292 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11293 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11294 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11295 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11296 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11297 Room 22-005-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-005-S1
11298 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 290
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11299 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11300 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11301 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11302 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11303 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11304 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11305 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11306 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11307 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11308 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11309 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11310 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11311 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11312 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11313 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11314 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11315 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11316 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11317 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11318 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11319 Room 22-006-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-006-S1
11320 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11321 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11322 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11323 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11324 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11325 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11326 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11327 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11328 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11329 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11330 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11331 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11332 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11333 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11334 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11335 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11336 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11337 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11338 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11339 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 291
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11340 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11341 Room 22-007-SUITE B 127 days12/9/2021 4/14/2022 12/9 Room 22-007-SUITE B
11342 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11343 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11344 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11345 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11346 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11347 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11348 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11349 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11350 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11351 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11352 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11353 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11354 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11355 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11356 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11357 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11358 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11359 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11360 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11361 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11362 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11363 Room 22-008-SUITE A 127 days12/9/2021 4/14/2022 12/9 Room 22-008-SUITE A
11364 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11365 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11366 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11367 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11368 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11369 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11370 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11371 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11372 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11373 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11374 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11375 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11376 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11377 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11378 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11379 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11380 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 292
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11381 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11382 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11383 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11384 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11385 Room 22-009-SUITE B 127 days12/9/2021 4/14/2022 12/9 Room 22-009-SUITE B
11386 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11387 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11388 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11389 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11390 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11391 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11392 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11393 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11394 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11395 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11396 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11397 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11398 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11399 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11400 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11401 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11402 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11403 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11404 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11405 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11406 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11407 Room 22-010-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-010-S1
11408 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11409 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11410 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11411 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11412 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11413 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11414 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11415 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11416 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11417 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11418 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11419 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11420 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11421 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 293
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11422 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11423 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11424 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11425 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11426 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11427 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11428 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11429 Room 22-011-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-011-S1
11430 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11431 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11432 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11433 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11434 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11435 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11436 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11437 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11438 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11439 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11440 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11441 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11442 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11443 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11444 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11445 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11446 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11447 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11448 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11449 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11450 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11451 Room 22-012-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-012-S1
11452 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11453 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11454 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11455 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11456 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11457 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11458 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11459 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11460 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11461 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11462 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 294
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11463 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11464 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11465 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11466 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11467 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11468 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11469 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11470 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11471 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11472 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11473 Room 22-013-S1 127 days12/9/2021 4/14/2022 12/9 Room 22-013-S1
11474 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11475 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11476 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11477 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11478 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11479 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11480 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11481 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11482 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11483 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11484 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11485 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11486 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11487 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11488 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11489 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11490 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11491 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11492 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11493 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11494 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11495 MEP Corridor机电走廊安装 39 days 12/15/2021 1/22/2022 12/15 MEP Corridor机电走廊安装
11496 Electrical System installation 29 days 12/15/2021 1/12/2022 12/15 Electrical System installation
11497 Cable tray installation 桥架安装 4 days 12/15/2021 12/18/2021 12/15
11498 LV cable installation 强电电缆安装 4 days 12/26/202112/29/2021 12/26
11499 ELV cable installation 弱电电缆安装 4 days 1/9/2022 1/12/2022 1/9
11500 Fire fighting piping installation消防系统 14 days 1/9/2022 1/22/2022 1/9 Fire fighting piping installation消防系统
11501 Fire fighting pipe installation消防管安装 10 days 1/9/2022 1/18/2022 1/9
11502 Testing 测试 4 days 1/19/2022 1/22/2022 1/19
11503 MVAC System installation空调系统 20 days 12/25/2021 1/13/2022 12/25 MVAC System installation空调系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 295
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11504 Ducting for AC installation风管安装 7 days 12/25/2021 12/31/2021 12/25
11505 Chiller water pipe installation冷冻水管安装 14 days 12/25/2021 1/7/2022 12/25
11506 AC drain pipe installation空调排水管安装 5 days 12/30/2021 1/3/2022 12/30
11507 Testing 测试 3 days 1/8/2022 1/10/2022 1/8
11508 Duct/pipe insulation保温安装 3 days 1/11/2022 1/13/2022 1/11
11509 MEP Final Fix机电末端安装 35 days 4/28/2022 6/1/2022 4/28 MEP Final Fix机电末
11510 Electrical Installation电气系统末端安装 33 days 4/28/2022 5/30/2022 4/28 Electrical Installation
11511 Fire alarm system 火警系统安装 7 days 5/21/2022 5/27/2022 5/21
11512 Public address system 公共广播系统 5 days 5/23/2022 5/27/2022 5/23
11513 Access control system 门禁系统 5 days 5/26/2022 5/30/2022 5/26
11514 Sockets and Switches Installation 开关插座 4 days 4/28/2022 5/1/2022 4/28
11515 Normal & Emergency Luminaires installation 普 5 days 5/2/2022 5/6/2022 5/2
通和应急照明安装
11516 MVAC Installation空调系统末端安装 12 days 5/21/2022 6/1/2022 5/21 MVAC Installation空
11517 Air grille/louver installation 通风格棚、百叶窗安装 7 days 5/21/2022 5/27/2022 5/21
11518 Wall controller units installation墙壁控制器 5 days 5/28/2022 6/1/2022 5/28
11519 Fire Protection Installation消防系统末端安装 7 days 5/3/2022 5/9/2022 5/3 Fire Protection Installation
11520 Sprinkler Installation 喷淋头安装 5 days 5/5/2022 5/9/2022 5/5
11521 Fire hose reel cabinet消防箱带卷盘 4 days 5/3/2022 5/6/2022 5/3
11522 MEP Level 23 机电23层 175 days12/9/2021 6/1/2022 12/9 MEP Level 23 机电2
11523 Guest Room MEP Installation(1&2 Fix)客房机电安装127 days12/9/2021 4/14/2022 12/9 Guest Room MEP Installation(1&2
11524 Room 23-001-S3 127 days12/9/2021 4/14/2022 12/9 Room 23-001-S3
11525 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11526 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11527 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11528 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11529 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11530 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11531 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11532 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11533 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11534 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11535 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11536 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11537 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11538 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11539 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11540 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11541 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11542 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11543 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11544 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 296
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11545 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11546 Room 23-002-S3 127 days12/9/2021 4/14/2022 12/9 Room 23-002-S3
11547 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11548 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11549 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11550 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11551 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11552 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11553 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11554 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11555 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11556 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11557 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11558 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11559 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11560 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11561 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11562 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11563 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11564 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11565 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11566 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11567 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11568 Room 23-003-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-003-S1
11569 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11570 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11571 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11572 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11573 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11574 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11575 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11576 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11577 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11578 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11579 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11580 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11581 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11582 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11583 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11584 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11585 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 297
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11586 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11587 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11588 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11589 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11590 Room 23-004-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-004-S1
11591 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11592 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11593 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11594 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11595 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11596 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11597 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11598 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11599 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11600 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11601 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11602 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11603 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11604 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11605 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11606 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11607 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11608 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11609 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11610 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11611 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11612 Room 23-005-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-005-S1
11613 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11614 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11615 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11616 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11617 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11618 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11619 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11620 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11621 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11622 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11623 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11624 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11625 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11626 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 298
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11627 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11628 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11629 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11630 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11631 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11632 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11633 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11634 Room 23-006-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-006-S1
11635 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11636 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11637 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11638 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11639 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11640 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11641 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11642 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11643 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11644 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11645 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11646 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11647 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11648 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11649 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11650 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11651 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11652 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11653 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11654 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11655 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11656 Room 23-007-SUITE B 127 days12/9/2021 4/14/2022 12/9 Room 23-007-SUITE B
11657 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11658 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11659 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11660 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11661 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11662 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11663 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11664 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11665 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11666 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11667 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 299
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11668 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11669 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11670 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11671 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11672 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11673 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11674 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11675 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11676 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11677 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11678 Room 23-008-SUITE A 127 days12/9/2021 4/14/2022 12/9 Room 23-008-SUITE A
11679 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11680 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11681 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11682 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11683 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11684 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11685 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11686 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11687 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11688 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11689 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11690 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11691 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11692 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11693 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11694 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11695 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11696 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11697 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11698 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11699 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11700 Room 23-009-SUITE B 127 days12/9/2021 4/14/2022 12/9 Room 23-009-SUITE B
11701 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11702 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11703 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11704 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11705 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11706 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11707 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11708 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 300
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11709 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11710 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11711 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11712 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11713 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11714 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11715 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11716 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11717 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11718 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11719 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11720 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11721 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11722 Room 23-010-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-010-S1
11723 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11724 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11725 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11726 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11727 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11728 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11729 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11730 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11731 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11732 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11733 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11734 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11735 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11736 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11737 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11738 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11739 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11740 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11741 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11742 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11743 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11744 Room 23-011-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-011-S1
11745 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11746 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11747 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11748 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11749 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 301
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11750 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11751 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11752 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11753 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11754 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11755 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11756 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11757 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11758 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11759 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11760 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11761 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11762 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11763 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11764 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11765 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11766 Room 23-012-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-012-S1
11767 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11768 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9
11769 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11770 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11771 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11772 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11773 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11774 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11775 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11776 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11777 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11778 15 days 2/24/2022 3/10/2022
Chiller Water Piping installation冷冻水管安装 2/24
11779 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11780 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11781 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11782 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11783 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11784 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11785 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11786 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11787 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11788 Room 23-013-S1 127 days12/9/2021 4/14/2022 12/9 Room 23-013-S1
11789 Plumbing system piping installation水管系统 127 days12/9/2021 4/14/2022 12/9 Plumbing system piping installatio
11790 Sanitary ware Piping installation 排水安装 3 days 12/9/2021 12/11/2021 12/9

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 302
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11791 Pre-Testing(Sanitary Pipe) 排水测试 5 days 12/12/202112/16/2021 12/12
11792 Cold water piping installation冷水安装 16 days 3/5/2022 3/20/2022 3/5
11793 Hot water piping installation热水管安装 16 days 3/25/2022 4/9/2022 3/25
11794 Pre-Testing 测试 5 days 4/10/2022 4/14/2022 4/10
11795 Fire fighting piping installation消防系统安装 15 days 1/15/2022 1/29/2022 1/15 Fire fighting piping installation消防系统安装
11796 Fire fighting pipe installation消防管安装 11 days 1/15/2022 1/25/2022 1/15
11797 Pre-Testing 测试 4 days 1/26/2022 1/29/2022 1/26
11798 MVAC System installation空调系统 28 days 2/18/2022 3/17/2022 2/18 MVAC System installation空调系统
11799 FCU installation风机盘安装 10 days 2/24/2022 3/5/2022 2/24
11800 15 days
Chiller Water Piping installation冷冻水管安装 2/24/2022 3/10/2022 2/24
11801 Valve Installation 空调阀门安装 15 days 2/24/2022 3/10/2022 2/24
11802 Ducting installation风管安装 15 days 2/18/2022 3/4/2022 2/18
11803 Pre-Testing 测试 4 days 3/11/2022 3/14/2022 3/11
11804 AC duct/pipe insulation 保温安装 7 days 3/11/2022 3/17/2022 3/11
11805 Electrical System installation电气系统 13 days 1/15/2022 1/27/2022 1/15 Electrical System installation电气系统
11806 EMT Conduit Installation EMT导管安装 7 days 1/15/2022 1/21/2022 1/15
11807 Electrical Tray Installation 桥架安装 7 days 1/15/2022 1/21/2022 1/15
11808 LV cable installation 强电电缆安装 7 days 1/15/2022 1/21/2022 1/15
11809 Circuit & Mega Testing 电路,回路测试 6 days 1/22/2022 1/27/2022 1/22
11810 MEP Corridor机电走廊安装 39 days 12/15/2021 1/22/2022 12/15 MEP Corridor机电走廊安装
11811 Electrical System installation 29 days 12/15/2021 1/12/2022 12/15 Electrical System installation
11812 Cable tray installation 桥架安装 4 days 12/15/2021 12/18/2021 12/15
11813 LV cable installation 强电电缆安装 4 days 12/26/202112/29/2021 12/26
11814 ELV cable installation 弱电电缆安装 4 days 1/9/2022 1/12/2022 1/9
11815 Fire fighting piping installation消防系统 14 days 1/9/2022 1/22/2022 1/9 Fire fighting piping installation消防系统
11816 Fire fighting pipe installation消防管安装 10 days 1/9/2022 1/18/2022 1/9
11817 Testing 测试 4 days 1/19/2022 1/22/2022 1/19
11818 MVAC System installation空调系统 20 days 12/25/2021 1/13/2022 12/25 MVAC System installation空调系统
11819 Ducting for AC installation风管安装 7 days 12/25/2021 12/31/2021 12/25
11820 Chiller water pipe installation冷冻水管安装 14 days 12/25/2021 1/7/2022 12/25
11821 AC drain pipe installation空调排水管安装 5 days 12/30/2021 1/3/2022 12/30
11822 Testing 测试 3 days 1/8/2022 1/10/2022 1/8
11823 Duct/pipe insulation保温安装 3 days 1/11/2022 1/13/2022 1/11
11824 MEP Final Fix机电末端安装 35 days 4/28/2022 6/1/2022 4/28 MEP Final Fix机电末
11825 Electrical Installation电气系统末端安装 33 days 4/28/2022 5/30/2022 4/28 Electrical Installation
11826 Fire alarm system 火警系统安装 7 days 5/21/2022 5/27/2022 5/21
11827 Public address system 公共广播系统 5 days 5/23/2022 5/27/2022 5/23
11828 Access control system 门禁系统 5 days 5/26/2022 5/30/2022 5/26
11829 Sockets and Switches Installation 开关插座 4 days 4/28/2022 5/1/2022 4/28
11830 Normal & Emergency Luminaires installation 普 5 days 5/2/2022 5/6/2022 5/2
通和应急照明安装
11831 MVAC Installation空调系统末端安装 12 days 5/21/2022 6/1/2022 5/21 MVAC Installation空

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 303
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E BM E M B E
11832 Air grille/louver installation 通风格棚、百叶窗安装 7 days 5/21/2022 5/27/2022 5/21
11833 Wall controller units installation墙壁控制器 5 days 5/28/2022 6/1/2022 5/28
11834 Fire Protection Installation消防系统末端安装 7 days 5/3/2022 5/9/2022 5/3 Fire Protection Installation
11835 Sprinkler Installation 喷淋头安装 5 days 5/5/2022 5/9/2022 5/5
11836 Fire hose reel cabinet消防箱带卷盘 4 days 5/3/2022 5/6/2022 5/3
11837 Riser MEP Work 管井机电立管安装 74 days 11/18/20211/30/2022 11/18 Riser MEP Work 管井机电立管安装
11838 Riser 管井(1,4,7,8 ,5A, 5B,9) 46 days 11/18/20211/2/2022 11/18 Riser 管井(1,4,7,8 ,5A, 5B,9)
11839 AC Ducting 风管安装 18 days 11/18/202112/5/2021 11/18
11840 Piping Work 水管(冷热水管,冷凝水管,通气管 28 days 12/6/2021 1/2/2022 12/6
,污水管,废水管)
11841 Riser 管井(2,3,6 ) 56 days 12/6/2021 1/30/2022 12/6 Riser 管井(2,3,6 )
11842 AC Ducting 风管安装 15 days 12/6/2021 12/20/2021 12/6
11843 Piping Work 水管(冷热水管,冷凝水管,通气管 28 days 1/3/2022 1/30/2022 1/3
,污水管,废水管)
11844 Fire Fighting Riser 消防立管安装 24 days 12/20/20211/12/2022 12/20
11845 Chiller Water Pipe Riser 冷冻水管 24 days 12/20/20211/12/2022 12/20
11846 MEP Work B3-5F地下室及裙楼机电 176 days 12/10/2021 6/3/2022 12/10 MEP Work B3-5F地
11847 MEP First Fix Installation For B1~5F地下室计划裙楼 166 days 12/10/2021 5/24/2022 12/10 MEP First Fix Installati
机电安装
11848 3B to 1B地下机电安装 78 days 12/10/2021 2/25/2022 12/10 3B to 1B地下机电安装
11849 B2Floor 64 days 12/10/20212/11/2022 12/10 B2Floor
11850 MEP conduit and pipe on brick wall墙上管预埋16 days 12/10/202112/25/2021 12/10 MEP conduit and pipe on brick wall墙上管预埋
11851 Setting out 放线 2 days 12/10/202112/11/2021 12/10
11852 Chipping gloove 5 days 12/12/202112/16/2021 12/12
11853 conduit/bottom box of switch&socket installation
7 days 12/17/202112/23/2021 12/17
11854 MEP conduit and pipe first inspection 2 days 12/24/202112/25/2021 12/24
11855 MEP First Fix Installation 54 days 12/20/20212/11/2022 12/20 MEP First Fix Installation
11856 Fire fighting piping installation消防系统安装15 days 12/20/20211/3/2022 12/20 Fire fighting piping installation消防系统安装
11857 Fire fighting pipe installation消防管安装 15 days 12/20/20211/3/2022 12/20
11858 Plumbing system piping installation 10 days 12/20/202112/29/2021 12/20 Plumbing system piping installation
11859 Sanitary ware piping installation排水管安装7 days 12/20/202112/26/2021 12/20
11860 Cold water piping installation冷水给水 4 days 12/20/202112/23/2021 12/20
11861 Rain water piping installation 雨水管 6 days 12/24/202112/29/2021 12/24
11862 Electrical System installation 12 days 1/28/2022 2/8/2022 1/28 Electrical System installation
11863 LV/ELV Cable ladder/tray installation桥架 7 days 1/28/2022 2/3/2022 1/28
11864 LV/ELV Cable installation强弱电电缆安装 9 days 1/31/2022 2/8/2022 1/31
11865 MVAC System installation空调系统 12 days 1/28/2022 2/8/2022 1/28 MVAC System installation空调系统
11866 ventilation installation风机 7 days 1/28/2022 2/3/2022 1/28
11867 Ducting for AC installation空调风管 5 days 1/28/2022 2/1/2022 1/28
11868 AC drain pipe installation空调排水管 5 days 1/28/2022 2/1/2022 1/28
11869 MVAC duct/pipe insulation保温 7 days 2/2/2022 2/8/2022 2/2
11870 MEP Pre-Testing测试 44 days 12/30/20212/11/2022 12/30 MEP Pre-Testing测试

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 304
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11871 MVAC System 空调测试 3 days 2/9/2022 2/11/2022 2/9
11872 Electrical System电器测试 3 days 2/9/2022 2/11/2022 2/9
11873 Plumbing System水管测试 3 days 12/30/20211/1/2022 12/30
11874 Fire Fighting System消防测试 3 days 1/4/2022 1/6/2022 1/4
11875 B1Floor 69 days 12/12/20212/18/2022 12/12 B1Floor
11876 MEP conduit and pipe on brick wall墙上管预埋16 days 12/12/202112/27/2021 12/12 MEP conduit and pipe on brick wall墙上管预埋
11877 Setting out 放线 2 days 12/12/202112/13/2021 12/12
11878 Chipping gloove 5 days 12/14/202112/18/2021 12/14
11879 conduit/bottom box of switch&socket installation
7 days 12/19/202112/25/2021 12/19
11880 MEP conduit and pipe first inspection 2 days 12/26/202112/27/2021 12/26
11881 MEP First Fix Installation 54 days 12/27/20212/18/2022 12/27 MEP First Fix Installation
11882 Fire fighting piping installation消防系统安装15 days 1/4/2022 1/18/2022 1/4 Fire fighting piping installation消防系统安装
11883 Fire fighting pipe installation消防管安装 15 days 1/4/2022 1/18/2022 1/4
11884 Plumbing system piping installation 10 days 12/27/20211/5/2022 12/27 Plumbing system piping installation
11885 Sanitary ware piping installation排水管安装7 days 12/27/20211/2/2022 12/27
11886 Cold water piping installation冷水给水 4 days 12/27/202112/30/2021 12/27
11887 Rain water piping installation 雨水管 6 days 12/31/20211/5/2022 12/31
11888 Electrical System installation 12 days 2/4/2022 2/15/2022 2/4 Electrical System installation
11889 LV/ELV Cable ladder/tray installation桥架 7 days 2/4/2022 2/10/2022 2/4
11890 LV/ELV Cable installation强弱电电缆安装 9 days 2/7/2022 2/15/2022 2/7
11891 MVAC System installation空调系统 12 days 2/4/2022 2/15/2022 2/4 MVAC System installation空调系统
11892 ventilation installation风机 7 days 2/4/2022 2/10/2022 2/4
11893 Ducting for AC installation空调风管 5 days 2/4/2022 2/8/2022 2/4
11894 AC drain pipe installation空调排水管 5 days 2/4/2022 2/8/2022 2/4
11895 MVAC duct/pipe insulation保温 7 days 2/9/2022 2/15/2022 2/9
11896 MEP Pre-Testing测试 44 days 1/6/2022 2/18/2022 1/6 MEP Pre-Testing测试
11897 MVAC System 空调测试 3 days 2/16/2022 2/18/2022 2/16
11898 Electrical System电器测试 3 days 2/16/2022 2/18/2022 2/16
11899 Plumbing System水管测试 3 days 1/6/2022 1/8/2022 1/6
11900 Fire Fighting System消防测试 3 days 1/19/2022 1/21/2022 1/19
11901 B3Floor 74 days 12/14/20212/25/2022 12/14 B3Floor
11902 MEP conduit and pipe on brick wall墙上管预埋16 days 12/14/202112/29/2021 12/14 MEP conduit and pipe on brick wall墙上管预埋
11903 Setting out 放线 2 days 12/14/202112/15/2021 12/14
11904 Chipping gloove 5 days 12/16/202112/20/2021 12/16
11905 conduit/bottom box of switch&socket installation
7 days 12/21/202112/27/2021 12/21
11906 MEP conduit and pipe first inspection 2 days 12/28/202112/29/2021 12/28
11907 MEP First Fix Installation 54 days 1/3/2022 2/25/2022 1/3 MEP First Fix Installation
11908 Fire fighting piping installation消防系统安装15 days 1/19/2022 2/2/2022 1/19 Fire fighting piping installation消防系统安装
11909 Fire fighting pipe installation消防管安装 15 days 1/19/2022 2/2/2022 1/19
11910 Plumbing system piping installation 10 days 1/3/2022 1/12/2022 1/3 Plumbing system piping installation
11911 Sanitary ware piping installation排水管安装7 days 1/3/2022 1/9/2022 1/3

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 305
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11912 Cold water piping installation冷水给水 4 days 1/3/2022 1/6/2022 1/3
11913 Rain water piping installation 雨水管 6 days 1/7/2022 1/12/2022 1/7
11914 Electrical System installation 12 days 2/11/2022 2/22/2022 2/11 Electrical System installation
11915 LV/ELV Cable ladder/tray installation桥架 7 days 2/11/2022 2/17/2022 2/11
11916 LV/ELV Cable installation强弱电电缆安装 9 days 2/14/2022 2/22/2022 2/14
11917 MVAC System installation空调系统 12 days 2/11/2022 2/22/2022 2/11 MVAC System installation空调系统
11918 ventilation installation风机 7 days 2/11/2022 2/17/2022 2/11
11919 Ducting for AC installation空调风管 5 days 2/11/2022 2/15/2022 2/11
11920 AC drain pipe installation空调排水管 5 days 2/11/2022 2/15/2022 2/11
11921 MVAC duct/pipe insulation保温 7 days 2/16/2022 2/22/2022 2/16
11922 MEP Pre-Testing测试 44 days 1/13/2022 2/25/2022 1/13 MEP Pre-Testing测试
11923 MVAC System 空调测试 3 days 2/23/2022 2/25/2022 2/23
11924 Electrical System电器测试 3 days 2/23/2022 2/25/2022 2/23
11925 Plumbing System水管测试 3 days 1/13/2022 1/15/2022 1/13
11926 Fire Fighting System消防测试 3 days 2/3/2022 2/5/2022 2/3
11927 5th Floor机电安装5层 86 days 12/10/20213/5/2022 12/10 5th Floor机电安装5层
11928 MEP conduit and pipe on brick wall墙上管预埋 11 days 12/10/202112/20/2021 12/10 MEP conduit and pipe on brick wall墙上管预埋
11929 Setting out 3 days 12/10/202112/12/2021 12/10
11930 Chipping gloove 5 days 12/13/202112/17/2021 12/13
11931 conduit/bottom box of switch&socket installation5 days 12/16/202112/20/2021 12/16
11932 MEP First Fix Installation 86 days 12/10/20213/5/2022 12/10 MEP First Fix Installation
11933 Installation Work of Duct/Pipe/Trucking 82 days 12/10/20213/1/2022 12/10 Installation Work of Duct/Pipe/Trucking
11934 Plumbing system piping installation水系统安装 23 days 1/4/2022 1/26/2022 1/4 Plumbing system piping installation水系统安装
11935 Sanitary ware piping installation(缺深化图) 15 days 1/4/2022 1/18/2022 1/4
11936 Cold/hot water piping installation给水 7 days 1/20/2022 1/26/2022 1/20
11937 Rain water piping installation雨水管 5 days 1/4/2022 1/8/2022 1/4
11938 Electrical System installation电器系统 18 days 12/20/20211/6/2022 12/20 Electrical System installation电器系统
11939 LV/ELV Cable ladder/tray installation桥架安装 3 days 12/20/202112/22/2021 12/20
11940 LV/ELV Cable installation强弱电电缆安装 15 days 12/23/20211/6/2022 12/23
11941 MVAC System installation空调系统 82 days 12/10/20213/1/2022 12/10 MVAC System installation空调系统
11942 FCU installation 7 days 1/4/2022 1/10/2022 1/4
11943 Chiller Water Pipe Installation 冷冻水管安装 15 days 12/10/202112/24/2021 12/10
11944 Ducting for AC installation风管安装 20 days 1/11/2022 1/30/2022 1/11
11945 ventilation installation风机安装 20 days 2/10/2022 3/1/2022 2/10
11946 AC drain pipe installation空调排水管安装 5 days 2/13/2022 2/17/2022 2/13
11947 MVAC duct/pipe insulation风管、冷冻水 保温 10 days 2/18/2022 2/27/2022 2/18
11948 Fire fighting piping installation消防安装 15 days 12/10/202112/24/2021 12/10 Fire fighting piping installation消防安装
11949 Fire fighting pipe installation 15 days 12/10/202112/24/2021 12/10
11950 MEP Pre-Testing 71 days 12/25/20213/5/2022 12/25 MEP Pre-Testing
11951 MVAC System 4 days 1/27/2022 1/30/2022 1/27
11952 Electrical System 4 days 1/7/2022 1/10/2022 1/7

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 306
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11953 Plumbing System 4 days 3/2/2022 3/5/2022 3/2
11954 Fire Fighting System 4 days 12/25/202112/28/2021 12/25
11955 4th Floor机电安装4层 103 days12/13/20213/25/2022 12/13 4th Floor机电安装4层
11956 MEP conduit and pipe on brick wall墙上管预埋 11 days 12/13/202112/23/2021 12/13 MEP conduit and pipe on brick wall墙上管预埋
11957 Setting out 3 days 12/13/202112/15/2021 12/13
11958 Chipping gloove 5 days 12/16/202112/20/2021 12/16
11959 conduit/bottom box of switch&socket installation5 days 12/19/202112/23/2021 12/19
11960 MEP First Fix Installation 93 days 12/23/20213/25/2022 12/23 MEP First Fix Installation
11961 Installation Work of Duct/Pipe/Trucking 89 days 12/23/20213/21/2022 12/23 Installation Work of Duct/Pipe/Trucking
11962 Plumbing system piping installation水系统安装 15 days 1/19/2022 2/2/2022 1/19 Plumbing system piping installation水系统安装
11963 Sanitary ware piping installation 排水管安装 15 days 1/19/2022 2/2/2022 1/19
11964 Cold/hot water piping installation给水管 7 days 1/27/2022 2/2/2022 1/27
11965 Electrical System installation电器系统 30 days 12/23/20211/21/2022 12/23 Electrical System installation电器系统
11966 LV/ELV Cable ladder/tray installation桥架安装 3 days 12/23/202112/25/2021 12/23
11967 LV/ELV Cable installation强弱电电缆安装 15 days 1/7/2022 1/21/2022 1/7
11968 MVAC System installation空调系统 87 days 12/25/20213/21/2022 12/25 MVAC System installation空调系统
11969 FCU installation 7 days 1/11/2022 1/17/2022 1/11
11970 Chiller Water Pipe Installation 冷冻水管安装 15 days 12/25/20211/8/2022 12/25
11971 Ducting for AC installation风管安装 20 days 1/31/2022 2/19/2022 1/31
11972 ventilation installation风机安装 20 days 3/2/2022 3/21/2022 3/2
11973 AC drain pipe installation空调排水管安装 5 days 2/18/2022 2/22/2022 2/18
11974 MVAC duct/pipe insulation风管、冷冻水 保温 10 days 2/23/2022 3/4/2022 2/23
11975 Fire fighting piping installation消防安装 15 days 12/25/20211/8/2022 12/25 Fire fighting piping installation消防安装
11976 Fire fighting pipe installation 15 days 12/25/20211/8/2022 12/25
11977 MEP Pre-Testing 76 days 1/9/2022 3/25/2022 1/9 MEP Pre-Testing
11978 MVAC System 4 days 2/3/2022 2/6/2022 2/3
11979 Electrical System 4 days 1/22/2022 1/25/2022 1/22
11980 Plumbing System 4 days 3/22/2022 3/25/2022 3/22
11981 Fire Fighting System 4 days 1/9/2022 1/12/2022 1/9
11982 3rd Floor机电安装3层 120 days12/16/20214/14/2022 12/16 3rd Floor机电安装3层
11983 MEP conduit and pipe on brick wall墙上管预埋 11 days 12/16/202112/26/2021 12/16 MEP conduit and pipe on brick wall墙上管预埋
11984 Setting out 3 days 12/16/202112/18/2021 12/16
11985 Chipping gloove 5 days 12/19/202112/23/2021 12/19
11986 conduit/bottom box of switch&socket installation5 days 12/22/202112/26/2021 12/22
11987 MEP First Fix Installation 110 days12/26/20214/14/2022 12/26 MEP First Fix Installation
11988 Installation Work of Duct/Pipe/Trucking 106 days12/26/20214/10/2022 12/26 Installation Work of Duct/Pipe/Tru
11989 Plumbing system piping installation水系统安装 15 days 2/3/2022 2/17/2022 2/3 Plumbing system piping installation水系统安装
11990 Sanitary ware piping installation 排水管安装 15 days 2/3/2022 2/17/2022 2/3
11991 Cold/hot water piping installation给水管 7 days 2/3/2022 2/9/2022 2/3
11992 Electrical System installation电器系统 42 days 12/26/20212/5/2022 12/26 Electrical System installation电器系统
11993 LV/ELV Cable ladder/tray installation桥架安装 3 days 12/26/202112/28/2021 12/26

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 307
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
11994 LV/ELV Cable installation强弱电电缆安装 15 days 1/22/2022 2/5/2022 1/22
11995 MVAC System installation空调系统 92 days 1/9/2022 4/10/2022 1/9 MVAC System installation空调系统
11996 FCU installation 7 days 1/18/2022 1/24/2022 1/18
11997 Chiller Water Pipe Installation 冷冻水管安装 15 days 1/9/2022 1/23/2022 1/9
11998 Ducting for AC installation风管安装 20 days 2/20/2022 3/11/2022 2/20
11999 ventilation installation风机安装 20 days 3/22/2022 4/10/2022 3/22
12000 AC drain pipe installation空调排水管安装 5 days 2/23/2022 2/27/2022 2/23
12001 MVAC duct/pipe insulation风管、冷冻水 保温 10 days 3/12/2022 3/21/2022 3/12
12002 Fire fighting piping installation消防安装 15 days 1/9/2022 1/23/2022 1/9 Fire fighting piping installation消防安装
12003 Fire fighting pipe installation 15 days 1/9/2022 1/23/2022 1/9
12004 MEP Pre-Testing 81 days 1/24/2022 4/14/2022 1/24 MEP Pre-Testing
12005 MVAC System 4 days 2/18/2022 2/21/2022 2/18
12006 Electrical System 4 days 2/6/2022 2/9/2022 2/6
12007 Plumbing System 4 days 4/11/2022 4/14/2022 4/11
12008 Fire Fighting System 4 days 1/24/2022 1/27/2022 1/24
12009 2nd Floor 机电安装2层 137 days12/19/20215/4/2022 12/19 2nd Floor 机电安装2层
12010 MEP conduit and pipe on brick wall墙上管预埋 11 days 12/19/202112/29/2021 12/19 MEP conduit and pipe on brick wall墙上管预埋
12011 Setting out 3 days 12/19/202112/21/2021 12/19
12012 Chipping gloove 5 days 12/22/202112/26/2021 12/22
12013 conduit/bottom box of switch&socket installation5 days 12/25/202112/29/2021 12/25
12014 MEP First Fix Installation 127 days12/29/20215/4/2022 12/29 MEP First Fix Installation
12015 Installation Work of Duct/Pipe/Trucking 123 days12/29/20214/30/2022 12/29 Installation Work of Duct/Pip
12016 Plumbing system piping installation水系统安装 23 days 2/10/2022 3/4/2022 2/10 Plumbing system piping installation水系统安
12017 Sanitary ware piping installation 排水管安装 15 days 2/18/2022 3/4/2022 2/18
12018 Cold/hot water piping installation给水管 7 days 2/10/2022 2/16/2022 2/10
12019 Electrical System installation电器系统 54 days 12/29/20212/20/2022 12/29 Electrical System installation电器系统
12020 LV/ELV Cable ladder/tray installation桥架安装 3 days 12/29/202112/31/2021 12/29
12021 LV/ELV Cable installation强弱电电缆安装 15 days 2/6/2022 2/20/2022 2/6
12022 MVAC System installation空调系统 97 days 1/24/2022 4/30/2022 1/24 MVAC System installation空调
12023 FCU installation 7 days 1/25/2022 1/31/2022 1/25
12024 Chiller Water Pipe Installation 冷冻水管安装 15 days 1/24/2022 2/7/2022 1/24
12025 Ducting for AC installation风管安装 20 days 3/12/2022 3/31/2022 3/12
12026 ventilation installation风机安装 20 days 4/11/2022 4/30/2022 4/11
12027 AC drain pipe installation空调排水管安装 5 days 2/28/2022 3/4/2022 2/28
12028 MVAC duct/pipe insulation风管、冷冻水 保温 10 days 4/1/2022 4/10/2022 4/1
12029 Fire fighting piping installation消防安装 15 days 1/24/2022 2/7/2022 1/24 Fire fighting piping installation消防安装
12030 Fire fighting pipe installation 15 days 1/24/2022 2/7/2022 1/24
12031 MEP Pre-Testing 86 days 2/8/2022 5/4/2022 2/8 MEP Pre-Testing
12032 MVAC System 4 days 3/5/2022 3/8/2022 3/5
12033 Electrical System 4 days 2/21/2022 2/24/2022 2/21
12034 Plumbing System 4 days 5/1/2022 5/4/2022 5/1

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 308
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12035 Fire Fighting System 4 days 2/8/2022 2/11/2022 2/8
12036 MF机电安装夹层 144 days12/22/20215/14/2022 12/22 MF机电安装夹层
12037 MEP conduit and pipe on brick wall墙上管预埋 11 days 12/22/20211/1/2022 12/22 MEP conduit and pipe on brick wall墙上管预埋
12038 Setting out 3 days 12/22/202112/24/2021 12/22
12039 Chipping gloove 5 days 12/25/202112/29/2021 12/25
12040 conduit/bottom box of switch&socket installation5 days 12/28/20211/1/2022 12/28
12041 MEP First Fix Installation 134 days1/1/2022 5/14/2022 1/1 MEP First Fix Installation
12042 Installation Work of Duct/Pipe/Trucking 130 days1/1/2022 5/10/2022 1/1 Installation Work of Duct/
12043 Plumbing system piping installation水系统安装 31 days 2/17/2022 3/19/2022 2/17 Plumbing system piping installation水系统
12044 Sanitary ware piping installation 排水管安装 15 days 3/5/2022 3/19/2022 3/5
12045 Cold/hot water piping installation给水管 7 days 2/17/2022 2/23/2022 2/17
12046 Electrical System installation电器系统 66 days 1/1/2022 3/7/2022 1/1 Electrical System installation电器系统
12047 LV/ELV Cable ladder/tray installation桥架安装 3 days 1/1/2022 1/3/2022 1/1
12048 LV/ELV Cable installation强弱电电缆安装 15 days 2/21/2022 3/7/2022 2/21
12049 MVAC System installation空调系统 99 days 2/1/2022 5/10/2022 2/1 MVAC System installation
12050 FCU installation 7 days 2/1/2022 2/7/2022 2/1
12051 Chiller Water Pipe Installation 冷冻水管安装 15 days 2/8/2022 2/22/2022 2/8
12052 Ducting for AC installation风管安装 20 days 4/1/2022 4/20/2022 4/1
12053 ventilation installation风机安装 10 days 5/1/2022 5/10/2022 5/1
12054 AC drain pipe installation空调排水管安装 5 days 3/5/2022 3/9/2022 3/5
12055 MVAC duct/pipe insulation风管、冷冻水 保温 10 days 4/21/2022 4/30/2022 4/21
12056 Fire fighting piping installation消防安装 15 days 2/8/2022 2/22/2022 2/8 Fire fighting piping installation消防安装
12057 Fire fighting pipe installation 15 days 2/8/2022 2/22/2022 2/8
12058 MEP Pre-Testing 81 days 2/23/2022 5/14/2022 2/23 MEP Pre-Testing
12059 MVAC System 4 days 3/20/2022 3/23/2022 3/20
12060 Electrical System 4 days 3/8/2022 3/11/2022 3/8
12061 Plumbing System 4 days 5/11/2022 5/14/2022 5/11
12062 Fire Fighting System 4 days 2/23/2022 2/26/2022 2/23
12063 Ground Floor机电安装首层 101 days2/13/2022 5/24/2022 2/13 Ground Floor机电安装
12064 MEP conduit and pipe on brick wall墙上管预埋 11 days 3/7/2022 3/17/2022 3/7 MEP conduit and pipe on brick wall墙上管
12065 Setting out 3 days 3/7/2022 3/9/2022 3/7
12066 Chipping gloove 5 days 3/10/2022 3/14/2022 3/10
12067 conduit/bottom box of switch&socket installation5 days 3/13/2022 3/17/2022 3/13
12068 MEP First Fix Installation 101 days2/13/2022 5/24/2022 2/13 MEP First Fix Installati
12069 Installation Work of Duct/Pipe/Trucking 97 days 2/13/2022 5/20/2022 2/13 Installation Work of Du
12070 Plumbing system piping installation水系统安装 39 days 2/24/2022 4/3/2022 2/24 Plumbing system piping installation水
12071 Sanitary ware piping installation 排水管安装 15 days 3/20/2022 4/3/2022 3/20
12072 Cold/hot water piping installation给水管 7 days 2/24/2022 3/2/2022 2/24
12073 Electrical System installation电器系统 38 days 2/13/2022 3/22/2022 2/13 Electrical System installation电器系统
12074 LV/ELV Cable ladder/tray installation桥架安装 3 days 2/13/2022 2/15/2022 2/13
12075 LV/ELV Cable installation强弱电电缆安装 15 days 3/8/2022 3/22/2022 3/8

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 309
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12076 MVAC System installation空调系统 72 days 3/10/2022 5/20/2022 3/10 MVAC System installati
12077 FCU installation 7 days 3/10/2022 3/16/2022 3/10
12078 Chiller Water Pipe Installation 冷冻水管安装 15 days 3/15/2022 3/29/2022 3/15
12079 Ducting for AC installation风管安装 20 days 4/1/2022 4/20/2022 4/1
12080 ventilation installation风机安装 25 days 4/26/2022 5/20/2022 4/26
12081 AC drain pipe installation空调排水管安装 5 days 3/10/2022 3/14/2022 3/10
12082 MVAC duct/pipe insulation风管、冷冻水 保温 10 days 4/21/2022 4/30/2022 4/21
12083 Fire fighting piping installation消防安装 15 days 2/23/2022 3/9/2022 2/23 Fire fighting piping installation消防安装
12084 Fire fighting pipe installation 15 days 2/23/2022 3/9/2022 2/23
12085 MEP Pre-Testing 76 days 3/10/2022 5/24/2022 3/10 MEP Pre-Testing
12086 MVAC System 4 days 4/4/2022 4/7/2022 4/4
12087 Electrical System 4 days 3/23/2022 3/26/2022 3/23
12088 Plumbing System 4 days 5/21/2022 5/24/2022 5/21
12089 Fire Fighting System 4 days 3/10/2022 3/13/2022 3/10
12090 MEP Installation Work (Final Fix) For B1~5th地下及裙 98 days 2/26/2022 6/3/2022 2/26 MEP Installation W
楼机电末端安装
12091 3B to 1B 64 days 2/26/2022 4/30/2022 2/26 3B to 1B
12092 B3 Floor 36 days 2/26/2022 4/2/2022 2/26 B3 Floor
12093 Electrical Installation 27 days 3/1/2022 3/27/2022 3/1 Electrical Installation
12094 Lighting fixture installation 8 days 3/8/2022 3/15/2022 3/8
12095 LV wiring device installation 9 days 3/1/2022 3/9/2022 3/1
12096 Fire alarm system wiring device installation 10 days 3/18/2022 3/27/2022 3/18
12097 PA system wiring device installation 7 days 3/18/2022 3/24/2022 3/18
12098 Access control system wiring device installation7 days 3/18/2022 3/24/2022 3/18
12099 LV panel board installation 14 days 3/13/2022 3/26/2022 3/13
12100 MVAC Installation 30 days 2/26/2022 3/27/2022 2/26 MVAC Installation
12101 Air grille/louver installation 7 days 2/26/2022 3/4/2022 2/26
12102 Mechanical Fan installation 7 days 3/4/2022 3/10/2022 3/4
12103 Fresh Air Room Installation 30 days 2/26/2022 3/27/2022 2/26
12104 Vent Ventilation room Installation 30 days 2/26/2022 3/27/2022 2/26
12105 Plumbing/Sanitary Installation 30 days 2/26/2022 3/27/2022 2/26 Plumbing/Sanitary Installation
12106 Water Tank Installation 21 days 2/26/2022 3/18/2022 2/26
12107 Pump Room and Equipment Installation 7 days 3/1/2022 3/7/2022 3/1
12108 Water treatment plant Installation 30 days 2/26/2022 3/27/2022 2/26
12109 Waste water treatment plant Installation 30 days 2/26/2022 3/27/2022 2/26
12110 FD/RD/FCO/COInstallation 7 days 3/4/2022 3/10/2022 3/4
12111 Fire Protection Installation 36 days 2/26/2022 4/2/2022 2/26 Fire Protection Installation
12112 Fire Protection Tank Installation 9 days 2/26/2022 3/6/2022 2/26
12113 Fire Pump Room and Equipment Installation 8 days 3/4/2022 3/11/2022 3/4
12114 Installation fire hose reel cabinet 7 days 3/7/2022 3/13/2022 3/7
12115 Sprinkler Installation 7 days 3/10/2022 3/16/2022 3/10
12116 Extinguisher 7 days 3/27/2022 4/2/2022 3/27

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 310
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12117 B2 Floor 60 days 2/26/2022 4/26/2022 2/26 B2 Floor
12118 Electrical Installation 29 days 3/10/2022 4/7/2022 3/10 Electrical Installation
12119 Lighting fixture installation 8 days 3/31/2022 4/7/2022 3/31
12120 LV wiring device installation 8 days 3/10/2022 3/17/2022 3/10
12121 Fire alarm system wiring device installation 7 days 3/28/2022 4/3/2022 3/28
12122 PA system wiring device installation 7 days 3/28/2022 4/3/2022 3/28
12123 Access control system wiring device installation7 days 3/28/2022 4/3/2022 3/28
12124 MVAC Installation 60 days 2/26/2022 4/26/2022 2/26 MVAC Installation
12125 Air grille/louver installation 7 days 3/5/2022 3/11/2022 3/5
12126 FCU installation 7 days 2/26/2022 3/5/2022 2/26
12127 Mechanical Fan installation 14 days 3/11/2022 3/24/2022 3/11
12128 Fresh Air Room Installation 30 days 3/28/2022 4/26/2022 3/28
12129 Vent Ventilation room Installation 30 days 3/28/2022 4/26/2022 3/28
12130 Plumbing/Sanitary Installation 7 days 3/11/2022 3/17/2022 3/11 Plumbing/Sanitary Installation
12131 FD/RD/FCO/COInstallation 7 days 3/11/2022 3/17/2022 3/11
12132 Fire Protection Installation 27 days 3/14/2022 4/9/2022 3/14 Fire Protection Installation
12133 Installation fire hose reel cabinet 9 days 3/14/2022 3/22/2022 3/14
12134 Sprinkler Installation 8 days 3/17/2022 3/24/2022 3/17
12135 Extinguisher 7 days 4/3/2022 4/9/2022 4/3
12136 B1 Floor 57 days 3/5/2022 4/30/2022 3/5 B1 Floor
12137 Electrical Installation 44 days 3/18/2022 4/30/2022 3/18 Electrical Installation
12138 Lighting fixture installation 8 days 4/8/2022 4/15/2022 4/8
12139 LV wiring device installation 8 days 3/18/2022 3/25/2022 3/18
12140 Fire alarm system wiring device installation 7 days 4/24/2022 4/30/2022 4/24
12141 PA system wiring device installation 7 days 4/24/2022 4/30/2022 4/24
12142 Access control system wiring device installation7 days 4/24/2022 4/30/2022 4/24
12143 MVAC Installation 50 days 3/5/2022 4/23/2022 3/5 MVAC Installation
12144 Air grille/louver installation 7 days 3/12/2022 3/18/2022 3/12
12145 FCU installation 7 days 3/5/2022 3/12/2022 3/5
12146 Mechanical Fan installation 14 days 3/25/2022 4/7/2022 3/25
12147 Fresh Air Room Installation 30 days 3/25/2022 4/23/2022 3/25
12148 Vent Ventilation room Installation 30 days 3/25/2022 4/23/2022 3/25
12149 Plumbing/Sanitary Installation 7 days 3/18/2022 3/24/2022 3/18 Plumbing/Sanitary Installation
12150 FD/RD/FCO/COInstallation 7 days 3/18/2022 3/24/2022 3/18
12151 Fire Protection Installation 25 days 3/23/2022 4/16/2022 3/23 Fire Protection Installation
12152 Installation fire hose reel cabinet 9 days 3/23/2022 3/31/2022 3/23
12153 Sprinkler Installation 8 days 3/25/2022 4/1/2022 3/25
12154 Fire Extinguisher 7 days 4/10/2022 4/16/2022 4/10
12155 GF to 5F 89 days 3/7/2022 6/3/2022 3/7 GF to 5F
12156 5th Floor 79 days 3/17/2022 6/3/2022 3/17 5th Floor
12157 Electrical Installation 52 days 3/17/2022 5/7/2022 3/17 Electrical Installation

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 311
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12158 Lighting fixture installation 14 days 3/23/2022 4/5/2022 3/23
12159 LV wiring device installation 14 days 3/17/2022 3/30/2022 3/17
12160 Fire alarm system wiring device installation 14 days 3/27/2022 4/9/2022 3/27
12161 Public address system wiring device installation7 days 4/10/2022 4/16/2022 4/10
12162 Access control system wiring device installation7 days 4/17/2022 4/23/2022 4/17
12163 LV panel board installation 14 days 4/24/2022 5/7/2022 4/24
12164 Fire alarm system station installation 7 days 3/27/2022 4/2/2022 3/27
12165 Public address system station installation 7 days 3/27/2022 4/2/2022 3/27
12166 Access control system station installation 7 days 3/27/2022 4/2/2022 3/27
12167 MVAC Installation 24 days 3/18/2022 4/10/2022 3/18 MVAC Installation
12168 Air grille/louver installation 7 days 3/18/2022 3/24/2022 3/18
12169 FCU installation 9 days 3/25/2022 4/2/2022 3/25
12170 Mechanical Fan installation 8 days 4/3/2022 4/10/2022 4/3
12171 Plumbing/Sanitary Installation 19 days 5/5/2022 5/23/2022 5/5 Plumbing/Sanitary Ins
12172 FD/RD/FCO/COInstallation 7 days 5/5/2022 5/11/2022 5/5
12173 Valve installation 7 days 5/12/2022 5/18/2022 5/12
12174 LPG station installation 15 days 5/9/2022 5/23/2022 5/9
12175 Fire Protection Installation 25 days 5/10/2022 6/3/2022 5/10 Fire Protection Inst
12176 Installation fire hose reel cabinet 9 days 5/10/2022 5/18/2022 5/10
12177 Sprinkler Installation 9 days 5/19/2022 5/27/2022 5/19
12178 Fire Extinguisher 7 days 5/28/2022 6/3/2022 5/28
12179 4th Floor 51 days 3/7/2022 4/26/2022 3/7 4th Floor
12180 Electrical Installation 44 days 3/7/2022 4/19/2022 3/7 Electrical Installation
12181 Lighting fixture installation 7 days 3/7/2022 3/13/2022 3/7
12182 LV wiring device installation 7 days 3/9/2022 3/15/2022 3/9
12183 Fire alarm system wiring device installation 14 days 4/6/2022 4/19/2022 4/6
12184 PA system wiring device installation 7 days 4/6/2022 4/12/2022 4/6
12185 Access control system wiring device installation7 days 4/8/2022 4/14/2022 4/8
12186 LV panel board installation 14 days 3/14/2022 3/27/2022 3/14
12187 MVAC Installation 35 days 3/14/2022 4/17/2022 3/14 MVAC Installation
12188 Air grille/louver installation 7 days 3/14/2022 3/20/2022 3/14
12189 FCU installation 14 days 3/21/2022 4/3/2022 3/21
12190 Mechanical Fan installation 14 days 4/4/2022 4/17/2022 4/4
12191 Plumbing/Sanitary Installation 14 days 3/14/2022 3/27/2022 3/14 Plumbing/Sanitary Installation
12192 FD/RD/FCO/COInstallation 7 days 3/14/2022 3/20/2022 3/14
12193 Valve installation 7 days 3/21/2022 3/27/2022 3/21
12194 Fire Protection Installation 21 days 4/6/2022 4/26/2022 4/6 Fire Protection Installation
12195 Installation fire hose reel cabinet 7 days 4/6/2022 4/12/2022 4/6
12196 Sprinkler Installation 7 days 4/13/2022 4/19/2022 4/13
12197 Fire Extinguisher 7 days 4/20/2022 4/26/2022 4/20
12198 3rd Floor 56 days 3/9/2022 5/3/2022 3/9 3rd Floor

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 312
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12199 Electrical Installation 37 days 3/9/2022 4/14/2022 3/9 Electrical Installation
12200 Lighting fixture installation 7 days 4/3/2022 4/9/2022 4/3
12201 LV wiring device installation 7 days 4/7/2022 4/13/2022 4/7
12202 Bus duct installation 5 days 4/7/2022 4/11/2022 4/7
12203 Fire alarm system wiring device installation 9 days 4/6/2022 4/14/2022 4/6
12204 PA system wiring device installation 9 days 4/6/2022 4/14/2022 4/6
12205 Access control system wiring device installation8 days 4/6/2022 4/13/2022 4/6
12206 LV panel board installation 14 days 3/9/2022 3/22/2022 3/9
12207 MVAC Installation 21 days 3/21/2022 4/10/2022 3/21 MVAC Installation
12208 Air grille/louver installation 7 days 3/21/2022 3/27/2022 3/21
12209 FCU installation 10 days 3/28/2022 4/6/2022 3/28
12210 Mechanical Fan installation 10 days 3/28/2022 4/6/2022 3/28
12211 Fresh Air Room Installation 14 days 3/28/2022 4/10/2022 3/28
12212 Vent Ventilation room Installation 14 days 3/28/2022 4/10/2022 3/28
12213 Plumbing/Sanitary Installation 7 days 3/21/2022 3/27/2022 3/21 Plumbing/Sanitary Installation
12214 FD/RD/FCO/COInstallation 7 days 3/21/2022 3/27/2022 3/21
12215 Valve installation 7 days 3/21/2022 3/27/2022 3/21
12216 Fire Protection Installation 26 days 4/8/2022 5/3/2022 4/8 Fire Protection Installation
12217 Installation fire hose reel cabinet 6 days 4/8/2022 4/13/2022 4/8
12218 Sprinkler Installation 7 days 4/13/2022 4/19/2022 4/13
12219 Extinguisher 7 days 4/27/2022 5/3/2022 4/27
12220 2nd Floor 46 days 3/23/2022 5/7/2022 3/23 2nd Floor
12221 Electrical Installation 32 days 3/23/2022 4/23/2022 3/23 Electrical Installation
12222 Lighting fixture installation 7 days 4/10/2022 4/16/2022 4/10
12223 LV wiring device installation 7 days 4/14/2022 4/20/2022 4/14
12224 Bus duct installation 5 days 4/12/2022 4/16/2022 4/12
12225 Fire alarm system wiring device installation 9 days 4/13/2022 4/21/2022 4/13
12226 PA system wiring device installation 9 days 4/15/2022 4/23/2022 4/15
12227 Access control system wiring device installation8 days 4/14/2022 4/21/2022 4/14
12228 LV panel board installation 14 days 3/23/2022 4/5/2022 3/23
12229 MVAC Installation 28 days 3/28/2022 4/24/2022 3/28 MVAC Installation
12230 Air grille/louver installation 7 days 3/28/2022 4/3/2022 3/28
12231 FCU installation 10 days 4/2/2022 4/11/2022 4/2
12232 Mechanical Fan installation 10 days 4/2/2022 4/11/2022 4/2
12233 Fresh Air Room Installation 14 days 4/1/2022 4/14/2022 4/1
12234 Vent Ventilation room Installation 14 days 4/11/2022 4/24/2022 4/11
12235 Plumbing/Sanitary Installation 7 days 3/28/2022 4/3/2022 3/28 Plumbing/Sanitary Installation
12236 FD/RD/FCO/COInstallation 7 days 3/28/2022 4/3/2022 3/28
12237 Valve installation 7 days 3/28/2022 4/3/2022 3/28
12238 Fire Protection Installation 24 days 4/14/2022 5/7/2022 4/14 Fire Protection Installation
12239 Installation fire hose reel cabinet 6 days 4/14/2022 4/19/2022 4/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 313
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12240 Sprinkler Installation 7 days 4/20/2022 4/26/2022 4/20
12241 Extinguisher 7 days 5/1/2022 5/7/2022 5/1
12242 MF Floor 51 days 3/19/2022 5/8/2022 3/19 MF Floor
12243 Electrical Installation 32 days 3/27/2022 4/27/2022 3/27 Electrical Installation
12244 Lighting fixture installation 7 days 4/7/2022 4/13/2022 4/7
12245 LV wiring device installation 7 days 4/11/2022 4/17/2022 4/11
12246 Bus duct installation 5 days 4/7/2022 4/11/2022 4/7
12247 Fire alarm system wiring device installation 9 days 4/19/2022 4/27/2022 4/19
12248 PA system wiring device installation 9 days 4/19/2022 4/27/2022 4/19
12249 Access control system wiring device installation8 days 4/19/2022 4/26/2022 4/19
12250 LV panel board installation 14 days 3/27/2022 4/9/2022 3/27
12251 MVAC Installation 45 days 3/25/2022 5/8/2022 3/25 MVAC Installation
12252 Air grille/louver installation 7 days 3/25/2022 3/31/2022 3/25
12253 FCU installation 10 days 4/2/2022 4/11/2022 4/2
12254 Mechanical Fan installation 10 days 4/2/2022 4/11/2022 4/2
12255 Fresh Air Room Installation 14 days 4/5/2022 4/18/2022 4/5
12256 Ventilation room Installation 14 days 4/25/2022 5/8/2022 4/25
12257 Plumbing/Sanitary Installation 23 days 3/19/2022 4/10/2022 3/19 Plumbing/Sanitary Installation
12258 FD/RD/FCO/COInstallation 7 days 4/4/2022 4/10/2022 4/4
12259 Valve installation 7 days 3/25/2022 3/31/2022 3/25
12260 Swimming pool pump room and equipment 20 days 3/19/2022 4/7/2022 3/19
installation
12261 Fire Protection Installation 25 days 4/10/2022 5/4/2022 4/10 Fire Protection Installation
12262 Installation fire hose reel cabinet 6 days 4/10/2022 4/15/2022 4/10
12263 Sprinkler Installation 7 days 4/17/2022 4/23/2022 4/17
12264 Extinguisher 7 days 4/28/2022 5/4/2022 4/28
12265 Ground Floor 43 days 3/31/2022 5/12/2022 3/31 Ground Floor
12266 Electrical Installation 33 days 3/31/2022 5/2/2022 3/31 Electrical Installation
12267 Lighting fixture installation 7 days 4/14/2022 4/20/2022 4/14
12268 LV wiring device installation 7 days 4/18/2022 4/24/2022 4/18
12269 Bus duct installation 5 days 4/12/2022 4/16/2022 4/12
12270 Fire alarm system wiring device installation 9 days 4/24/2022 5/2/2022 4/24
12271 PA system wiring device installation 9 days 4/24/2022 5/2/2022 4/24
12272 Access control system wiring device installation8 days 4/24/2022 5/1/2022 4/24
12273 LV panel board installation 14 days 3/31/2022 4/13/2022 3/31
12274 MVAC Installation 42 days 4/1/2022 5/12/2022 4/1 MVAC Installation
12275 Air grille/louver installation 7 days 4/1/2022 4/7/2022 4/1
12276 FCU installation 10 days 4/2/2022 4/11/2022 4/2
12277 Mechanical Fan installation 10 days 4/2/2022 4/11/2022 4/2
12278 Fresh Air Room Installation 14 days 4/4/2022 4/17/2022 4/4
12279 Vent Ventilation room Installation 14 days 4/29/2022 5/12/2022 4/29
12280 Plumbing/Sanitary Installation 12 days 4/1/2022 4/12/2022 4/1 Plumbing/Sanitary Installation

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 314
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12281 FD/RD/FCO/COInstallation 7 days 4/6/2022 4/12/2022 4/6
12282 Valve installation 7 days 4/1/2022 4/7/2022 4/1
12283 Fire Protection Installation 16 days 4/16/2022 5/1/2022 4/16 Fire Protection Installation
12284 Installation fire hose reel cabinet 6 days 4/16/2022 4/21/2022 4/16
12285 Sprinkler Installation 7 days 4/24/2022 4/30/2022 4/24
12286 Extinguisher 7 days 4/25/2022 5/1/2022 4/25
12287 Machine Room and Equipment Installation 机房设备安装 138 days12/2/2021 4/18/2022 12/2 Machine Room and Equipment I
12288 MF (Diesel Generator-Set)发电机 61 days 1/7/2022 3/8/2022 1/7 MF (Diesel Generator-Set)发电机
12289 Wall Plastering 墙抹灰 4 days 1/7/2022 1/11/2022 1/7
12290 Wall Skim Coat and Painting 腻子和油漆 4 days 1/14/2022 1/17/2022 1/14
12291 Slab concrete ceiling Skim Coat and Painting 顶板腻子 7 days 1/17/2022 1/23/2022 1/17
和油漆
12292 Floor Water proofing 防水 5 days 1/17/2022 1/22/2022 1/17
12293 Floor Polish Screeding 地坪 4 days 1/25/2022 1/29/2022 1/25
12294 Sound Proofing 发电机房隔音安装 5 days 1/12/2022 1/17/2022 1/12
12295 Diesel Piping System 发电机管安装 7 days 1/17/2022 1/24/2022 1/17
12296 Diesel Generator (Gen-Set) Installation 发电机 16 days 1/29/2022 2/13/2022 1/29
12297 Pre-Testing 3 days 2/14/2022 2/16/2022 2/14
12298 Wall Finishing work ( After Machine is Installed) 墙补修 20 days 2/17/2022 3/8/2022 2/17
12299 Level 4( Swimming Pool Pumping Room)泳池 59 days 1/10/2022 3/9/2022 1/10 Level 4( Swimming Pool Pumping Room)泳池
12300 Wall Plastering 4 days 1/10/2022 1/14/2022 1/10
12301 Wall Skim Coat and Painting 7 days 1/17/2022 1/23/2022 1/17
12302 Slab concrete ceiling Skim Coat and Painting 7 days 1/20/2022 1/27/2022 1/20
12303 Floor Polish Screeding 4 days 1/26/2022 1/30/2022 1/26
12304 Swimming Pool Pump Installation 泳池泵安装 16 days 1/30/2022 2/14/2022 1/30
12305 Wall Finishing work ( After Equipments is Installed) 20 days 2/18/2022 3/9/2022 2/18
12306 Level 4(EE Room) 46 days 1/8/2022 2/22/2022 1/8 Level 4(EE Room)
12307 Wall Plastering 4 days 1/8/2022 1/12/2022 1/8
12308 Wall Skim Coat and Painting 7 days 1/12/2022 1/18/2022 1/12
12309 Slab concrete ceiling Skim Coat and Painting 7 days 1/8/2022 1/14/2022 1/8
12310 Floor Water proofing 5 days 1/8/2022 1/13/2022 1/8
12311 Floor Polish Screeding 4 days 1/16/2022 1/20/2022 1/16
12312 MV Switchgear and Transformer Installation 11 days 1/20/2022 1/30/2022 1/20
12313 Pre-Testing 3 days 1/31/2022 2/2/2022 1/31
12314 Wall Finishing work ( After Machine is Installed) 20 days 2/3/2022 2/22/2022 2/3
12315 Central Station Air Handling Units &PAU(4F,3F,MF,2F,25F)107 days12/14/20213/30/2022 12/14 Central Station Air Handling Units &PA
12316 Wall Plastering 4 days 12/14/202112/18/2021 12/14
12317 Wall Skim Coat and Painting 7 days 12/21/202112/27/2021 12/21
12318 Slab concrete ceiling Skim Coat and Painting 7 days 12/24/202112/30/2021 12/24
12319 Floor Water proofing 5 days 12/24/202112/29/2021 12/24
12320 Floor Polish Screeding 4 days 1/1/2022 1/5/2022 1/1
12321 AHU and PAU Installation 60 days 1/5/2022 3/5/2022 1/5

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 315
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12322 Pre-Testing 7 days 3/6/2022 3/12/2022 3/6
12323 Wall Finishing work ( After Machine is Installed) 25 days 3/6/2022 3/30/2022 3/6
12324 L25(Water-Cooled Rotary-Screw Water Chillers)冷冻机 57 days 12/16/20212/10/2022 12/16 L25(Water-Cooled Rotary-Screw Water Chillers)冷冻
12325 Wall Plastering 4 days 1/31/2022 2/4/2022 1/31
12326 Wall Skim Coat and Painting 4 days 2/4/2022 2/8/2022 2/4
12327 Floor Water proofing 5 days 12/16/202112/21/2021 12/16
12328 Floor Screeding 3 days 12/26/202112/29/2021 12/26
12329 Chiller Installation 30 days 1/5/2022 2/3/2022 1/5
12330 Pre-Testing 7 days 2/4/2022 2/10/2022 2/4
12331 L26 (Cooling Towers)冷却塔 70 days 2/8/2022 4/18/2022 2/8 L26 (Cooling Towers)冷却塔
12332 Wall Plastering 7 days 2/9/2022 2/16/2022 2/9
12333 Wall Skim Coat and Painting 7 days 2/16/2022 2/22/2022 2/16
12334 Floor Water proofing 5 days 2/8/2022 2/13/2022 2/8
12335 Floor Screeding 3 days 2/18/2022 2/21/2022 2/18
12336 Cooling Tower Installation 45 days 2/28/2022 4/13/2022 2/28
12337 Pre-Testing 5 days 4/14/2022 4/18/2022 4/14
12338 L25(Sanitary Pump Room)排水泵 52 days 12/2/2021 1/22/2022 12/2 L25(Sanitary Pump Room)排水泵
12339 Wall Plastering 7 days 12/2/2021 12/9/2021 12/2
12340 Wall Skim Coat and Painting 7 days 12/9/2021 12/16/2021 12/9
12341 Floor Water proofing 5 days 12/16/202112/21/2021 12/16
12342 Floor Screeding 3 days 12/26/202112/29/2021 12/26
12343 Pump Installation 15 days 1/5/2022 1/19/2022 1/5
12344 Pre-Testing 3 days 1/20/2022 1/22/2022 1/20
12345 L25(Pressurization Fan) 52 days 12/7/2021 1/27/2022 12/7 L25(Pressurization Fan)
12346 Wall Plastering 7 days 12/7/2021 12/14/2021 12/7
12347 Wall Skim Coat and Painting 7 days 12/14/202112/21/2021 12/14
12348 Floor Water proofing 5 days 12/21/202112/26/2021 12/21
12349 Floor Screeding 3 days 12/31/20211/3/2022 12/31
12350 Presurlization Fan 15 days 1/10/2022 1/24/2022 1/10
12351 Pre-Testing 3 days 1/25/2022 1/27/2022 1/25
12352 B3 (Waste Water Treatment Plant & Equipment)污水处理20 days 1/31/2022 2/19/2022 1/31
12353 B3 (Cold Water Pump) 冷水泵 30 days 3/5/2022 4/3/2022 3/5
12354 B3 (Diesel Engine Fire Pump)采油泵 19 days 1/24/2022 2/11/2022 1/24
12355 B3 (Jockey Pump)消防泵 19 days 1/24/2022 2/11/2022 1/24
12356 LPG SYSTEM Installation 燃气 30 days 1/5/2022 2/3/2022 1/5
12357 Mechanical Fan Room 风机房 27 days 2/21/2022 3/19/2022 2/21
12358 Busduct Installation 母线 30 days 1/15/2022 2/13/2022 1/15
12359 External/Landscape景观工程 91 days 3/7/2022 6/5/2022 3/7 External/Landscap
12360 External Landscape Work GF首层室外景观 72 days 3/7/2022 5/17/2022 3/7 External Landscape Wor
12361 Site Clearance 5 days 3/7/2022 3/11/2022 3/7
12362 Leveling Survey Setting Out 3 days 3/12/2022 3/14/2022 3/12

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 316
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12363 Bulk Excavation Reducing Existing Level 5 days 3/15/2022 3/19/2022 3/15
12364 Compacted Aggregate Base 7 days 3/20/2022 3/26/2022 3/20
12365 Reinforment Concrete Subslab 10 days 3/27/2022 4/5/2022 3/27
12366 Drainage Work(Concrete Gutter) 5 days 4/3/2022 4/7/2022 4/3
12367 Concrete Curb Work ( City Standard Curb) 4 days 4/6/2022 4/9/2022 4/6
12368 Wall Recessed Light 5 days 4/6/2022 4/10/2022 4/6
12369 Planter Box Construction 10 days 4/6/2022 4/15/2022 4/6
12370 Land Scap Stairs and Ramp 7 days 4/6/2022 4/12/2022 4/6
12371 Floor Finishing ( Stone Tile Installation) 20 days 4/16/2022 5/5/2022 4/16
12372 Slot Drain and Trench Drain Installation 7 days 4/18/2022 4/24/2022 4/18
12373 Signage Wall& Fountain Wall 5 days 5/6/2022 5/10/2022 5/6
12374 landscape Lighting Fixture &Lighting Control (By Owner) 7 days 5/11/2022 5/17/2022 5/11
12375 External Landscape Work 5F五层室外景观 71 days 3/27/2022 6/5/2022 3/27 External Landscape
12376 Site Clearance 3 days 3/27/2022 3/29/2022 3/27
12377 Setting Out 3 days 3/30/2022 4/1/2022 3/30
12378 Brick Wall 10 days 4/2/2022 4/11/2022 4/2
12379 Drainage Work(Gutter) 7 days 4/9/2022 4/15/2022 4/9
12380 Floor Finishing ( Stone Tile ,Natural Stone ..Installation) 20 days 4/12/2022 5/1/2022 4/12
12381 Wood Deck Installation 10 days 5/7/2022 5/16/2022 5/7
12382 Glass Rail 7 days 5/17/2022 5/23/2022 5/17
12383 Tree Planting (By Owner) 20 days 5/17/2022 6/5/2022 5/17
12384 External Landscape Work 19F19层室外景观 42 days 3/27/2022 5/7/2022 3/27 External Landscape Work 1
12385 Site Clearance 2 days 3/27/2022 3/28/2022 3/27
12386 Setting Out 3 days 3/29/2022 3/31/2022 3/29
12387 Floor Finishing 15 days 4/1/2022 4/15/2022 4/1
12388 Planter Wall 12 days 4/16/2022 4/27/2022 4/16
12389 Drainage Work(Gutter) 7 days 4/25/2022 5/1/2022 4/25
12390 Glass Rail 5 days 4/28/2022 5/2/2022 4/28
12391 Tree Planting (By Owner) 10 days 4/28/2022 5/7/2022 4/28
12392 Land Scape MEP Work 室外景观机电安装 25 days 3/20/2022 4/13/2022 3/20
12393 Scaffolding Removal 外架拆除 20 days 2/5/2022 2/24/2022 2/5 Scaffolding Removal 外架拆除
12394 13F- 6F 10 days 2/15/2022 2/24/2022 2/15
12395 RF-14F 10 days 2/5/2022 2/14/2022 2/5
12396 Construction Hoist Removal 施工电梯拆除 10 days 2/10/2022 2/19/2022 2/10
12397 Tower Crane Removal 塔吊拆除 10 days 2/25/2022 3/6/2022 2/25
12398 EDC Connecting (After MV Switch Gear , Transformer, 15 days 2/19/2022 3/5/2022 2/19
and Bus Duct Installation) 市政电链接
12399 MEP Testing and Commissioning Work机电调试及测试 60 days 6/2/2022 7/31/2022 6/2 M
12400 MV System MV系统 60 days 6/2/2022 7/31/2022 6/2 M
12401 MV System ready for power receiving 30 days 6/2/2022 7/1/2022 6/2
12402 Testing and Commissioning for MV System. 35 days 6/27/2022 7/31/2022 6/27
12403 Electrical System强电系统 35 days 6/12/2022 7/16/2022 6/12 Electric

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 317
PHNOM PENH NOVOTEL PROJECT MASTER SCHEDULE
ID Task Task Name Duration Start Finish March May July September November January March May July
Mode E M B E M B E M B E M B E M B E M B E M B E M B E
12404 Testing and Commissioning for LV System 35 days 6/12/2022 7/16/2022 6/12
12405 LV System ready for power receiving 30 days 6/17/2022 7/16/2022 6/17
12406 ELV System弱电系统 35 days 6/7/2022 7/11/2022 6/7 ELV Syst
12407 Testing and Commissioning for Fire alarm System 35 days 6/7/2022 7/11/2022 6/7
12408 Fire alarm System ready for power receiving 20 days 6/12/2022 7/1/2022 6/12
12409 Testing and Commissioning for Public address System 20 days 6/17/2022 7/6/2022 6/17
12410 Public address System ready for power receiving 20 days 6/17/2022 7/6/2022 6/17
12411 Testing and Commissioning for Access control System 20 days 6/17/2022 7/6/2022 6/17
12412 Access control System ready for power receiving 20 days 6/17/2022 7/6/2022 6/17
12413 Sanitary/Plumbing System 污水系统 60 days 6/2/2022 7/31/2022 6/2 Sa
12414 Tapping off 30 days 6/2/2022 7/1/2022 6/2
12415 Testing for water system 30 days 7/2/2022 7/31/2022 7/2
12416 AC System空调系统 50 days 6/10/2022 7/29/2022 6/10 AC
12417 Testing and commissioning for Chiller System 50 days 6/10/2022 7/29/2022 6/10
12418 Testing and commissioning for AHU 40 days 6/12/2022 7/21/2022 6/12
12419 Firefighting System消防系统 50 days 6/2/2022 7/21/2022 6/2 Firefi
12420 Fire Fighting system at pump station. 25 days 6/2/2022 6/26/2022 6/2
12421 Fire Fighting system 25 days 6/27/2022 7/21/2022 6/27
12422 Waste Water System 排水系统 30 days 6/12/2022 7/11/2022 6/12
12423 Defect and Hand Over 缺陷修正及移交 40 days 6/22/2022 7/31/2022 6/22
12424 START DATE FOR OWNER DIRECT SUB-CONSTRACTOR 甲子 188 11/15/20215/21/2022 11/15 START DATE FOR OWN
自己分包 days
12425 AV WORKS 0 days 4/2/2022 4/2/2022 4/2
12426 IT WORKS 0 days 4/2/2022 4/2/2022 4/2
12427 BMS SYSTEM /RCU 0 days 4/2/2022 4/2/2022 4/2
12428 ELEVATOR Installation 0 days 11/15/202111/15/2021 11/15
12429 KITCHEN EQUIPMENT INSTALLATION (After Painting work 0 days 5/21/2022 5/21/2022 5/21
completed)

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
NPP-RFA-G-S005R6-NOVOTEL MASTER SCHEDULE(Revise Base on S
Milestone Inactive Task Manual Summary Rollup Progress
Date: 19-November- 2021
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

NOTE: SHOP DRAWING, MATERIAL, METHOD STATEMENT TAKE MAXIMUM 7 DAYS TO GET APPROVAL FROM SUBMISSION DATE Page 318