CLIENT IKPT

DATE PRINT 29/09/2022
PERIODE 29‐Sep‐22

DESCRIPTION AUGUST SEPTEMBER


Task Name DurationStart Finish 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
   Technical Approval 5 05/07/2022 11/07/2022 90,0
   Technical Datasheet 5 05/07/2022 11/07/2022
   Approval Drawing 5 05/07/2022 11/07/2022
   Inventory Process Non Stock 1 11/07/2022 11/07/2022
80,0
   Incomming Material 1 12/07/2022 12/07/2022
   Inspection Material & Dimension 1 13/07/2022 13/07/2022
      Pipe Production Process 10 13/07/2022 26/07/2022
      Fitting Production Process 10 21/07/2022 03/08/2022 70,0

      PTFE Solid Material Production Process 10 27/07/2022 09/08/2022


      Surface & Visual Inspection 4 10/08/2022 15/08/2022
      Material Processing 4 16/08/2022 19/08/2022 60,0
      Measure Length, Dia Inner and Outer 3 18/08/2022 22/08/2022
      Mold Making Process 3 23/08/2022 25/08/2022
      Mold Filling 3 24/08/2022 26/08/2022
50,0
      Finishing 2 27/08/2022 29/08/2022 0,83
      Hydro Pressure Test 2 30/08/2022 31/08/2022 0,83 0,83
      Positive Material Identification 2 31/08/2022 01/09/2022 0,83 0,83
      Spark Test 2 01/09/2022 02/09/2022 40,0 0,83 0,83
      Penetrant Test 2 02/09/2022 05/09/2022 0,83 0,83
      Temperature Test 2 06/09/2022 07/09/2022 0,83 0,83
      Cleaning Surface Preparation 2 08/09/2022 09/09/2022 30,0
0,83 0,83
      Checking Quantity & Final Inspection 2 08/09/2022 09/09/2022 0,83 0,83
      Packing Process 2 08/09/2022 09/09/2022 0,83 0,83
      Estimated Delivery to Port 3 09/09/2022 13/09/2022 0,83 0,83 0,83
20,0
   Estimated Arrived Jakarta 17 13/09/2022 05/10/2022 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83
   Customs Duty 5 05/10/2022 11/10/2022
   Visual & Dimension Check 1 11/10/2022 11/10/2022
   Document Check 1 11/10/2022 11/10/2022 10,0

   Pressure Test On Bueno Indonesia WS 2 12/10/2022 13/10/2022


   Preparation Product 2 14/10/2022 17/10/2022
   Packing and Marking 2 15/10/2022 17/10/2022 0,0
   Input Delivery Document 1 16/10/2022 16/10/2022 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

   Scheduling to Delivery 1 17/10/2022 17/10/2022 Plan Actual

   Delivery to Site 3 18/10/2022 20/10/2022

PLAN 0,00 0,83 0,83 1,65 1,65 1,65 0,00 0,00 0,83 0,83 0,83 2,48 3,31 0,00 0,00 0,83 1,65 0,83 0,83 0,83 0,00 0,00 0,83 0,83 0,83 0,83 0,83 0,00 0,00 0,83 0,83 0,83 0,83 0,83
ACCUMULATION 54,5 55,4 56,2 57,9 59,5 61,2 61,2 61,2 62,0 62,8 63,6 66,1 69,4 69,4 69,4 70,2 71,9 72,7 73,6 74,4 74,4 74,4 75,2 76,0 76,9 77,7 78,5 78,5 78,5 79,3 80,2 81,0 81,8 82,6

ACTUAL 0,2 0,2 0,2 0,2 0,2 0,2 0,3 0,3 0,3 0,5 0,5 0,3 0,5 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1
ACCUMULATION 44,9 45,1 45,3 45,5 45,7 45,9 45,9 45,9 46,2 46,5 46,8 47,3 47,8 47,8 47,8 48,1 48,6 48,7 48,8 48,9 48,9 48,9 49,0 49,1 49,2 49,3 49,4 49,4 49,4 49,5 49,6 49,7 49,8

* the date is posible to change according manufacturing process and approval the dimension