SCHEDULE PENYELESAIAN SISA PEKERJAAN

PROYEK PEMBANGUNAN WH UNIT - PART DAN FASILITAS PENDUKUNG ASTRA CANDI SEMARANG
KHUSUS BANGUNAN WH PART (INDOOR S/D TGL 30 JUNI)
SISA BOBOT (%) LEAD INDIKATOR KONDISI MATRIAL PELAKSANAAN PERKJAAN WAKTU
No. SISA PEKERJAAN VOLUME SAT Bobot PIC KETERANGAN
FISIK MATERIAL MATRIAL MAN POWER RENCANA PENDATANGAN STATUS MULAI TGL SELESAI TGL 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul

PEKERJAAN SIPIL

1 Atap canopi 237,95 m2 0,07% 0,069% 0,000% READY READY 24/06/2022 28/06/2022 47,59 47,59 47,59 47,59 47,59 Zamroni

2 Capping horisontal & vertikal untuk opening jendela 44,00 unit 0,03% 0,014% 0,014% READY READY PABRIKASI 24/06/2022 05/07/2022 3,67 3,67 3,67 3,67 3,67 3,67 3,67 3,67 3,67 3,67 3,67 3,67 Sugeng

3 Tangga office 905,59 kg 0,04% 0,039% READY READY - PABRIKASI 23/06/2022 30/06/2022 113 113 113 113 113 113 113 113 Zamroni

4 Steel Flashing zincalume t = 0.45 mm 199,20 m' 0,05% 0,023% 0,023% NOT READY READY 24/06/2022 25/06/2022 29/06/2022 MOS 39,8 39,8 39,8 39,8 39,8 Sugeng

5 Plafon clading dan Canopi 862,44 m2 0,42% 0,417% 0,000% NOT READY READY 28/06/2022 29/06/2022 05/07/2022 MOS 123,2 123,2 123,2 123,2 123,2 123,2 123,2 Sugeng

6 Talang Canopi 37,00 m' 0,02% 0,021% 0,000% READY READY 26/06/2022 28/06/2022 Zamroni
12,33 12,33 12,33
7 Pengecatan chequerplate tangga office 56,76 m2 0,01% 0,006% 0,006% NOT READY READY 24/06/2022 25/06/2022 30/06/2022 MOS 9,46 9,46 9,46 9,46 9,46 9,46 Zamroni

PEKERJAAN ARSITEK

1 Plesteran dan acian 66,00 m2 0,01% 0,010% 0,000% READY READY 20/06/2022 26/06/2022 Zamroni
9,43 9,43 9,43 9,43 9,43 9,43 9,43
2 Kamprotan 27,00 m2 0,00% 0,001% 0,000% READY READY 18/06/2022 24/06/2022 Zamroni
3,86 3,86 3,86 3,86 3,86 3,86 3,86
3 Pekerjaan border WH. Part lantai beton 1.283,00 m' 0,09% 0,087% 0,087% NOT READY READY 24/06/2022 25/06/2022 30/06/2022 Zamroni
MOS 214 214 214 214 214 214
4 Plint kramik 38,12 m2 0,01% 0,005% 0,000% READY READY 23/05/2022 30/06/2022 Zamroni
4,76 4,76 4,76 4,76 4,76 4,76 4,76 4,76
5 Pekerjaan lisplank fasacde ACP 749,36 m2 1,37% 1,371% 0,000% READY READY PABRIKASI 18/06/2022 05/07/2022 Sugeng
49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96 49,96
6 Roling door 6,00 unit 0,26% 0,130% 0,130% NOT READY READY 20/06/2022 21/06/2022 08/07/2022 MOS 0,60 0,60 0,60 0,60 0,60 0,60 0,60 0,60 0,60 0,60 Andri

7 Pintu besi darurat 4,00 unit 0,04% 0,041% 0,000% READY READY PABRIKASI 18/06/2022 28/06/2022 Andri
0,36 0,36 0,36 0,36 0,36 0,36 0,36 0,36 0,36 0,36 0,36
8 pekerjaan siku pada kolom pedestal 30,00 bh 0,01% 0,007% 0,000% READY READY 20/06/2022 29/06/2022 Zamroni
3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00
9 Pintu Office 4,00 unit 0,01% 0,004% 0,004% NOT READY READY 24/06/2022 PABRIKASI 25/06/2022 29/06/2022 MOS 0,80 0,80 0,80 0,80 0,80 Andri

10 Swadaya mesh 8,00 unit 0,25% 0,247% 0,000% READY READY PABRIKASI 18/06/2022 28/06/2022 Andri
0,73 0,73 0,73 0,73 0,73 0,73 0,73 0,73 0,73 0,73 0,73

BAST 1
11 Jendela Keliling 44,00 unit 0,10% 0,096% 0,000% READY READY PABRIKASI 18/06/2022 30/06/2022 Andri
3,38 3,38 3,38 3,38 3,38 3,38 3,38 3,38 3,38 3,38 3,38 3,38 3,38
12 Pekerjaan Pengecatan luar dan dalam 2.424,90 m2 0,17% 0,170% 0,000% READY READY 18/06/2022 30/06/2022 Zamroni
187 187 187 187 187 187 187 187 187 187 187 187 187
13 Pekerjaan railing tangga 12,98 m' 0,02% 0,016% 0,000% READY READY 22/06/2022 01/07/2022 Chamdun
1,30 1,30 1,30 1,30 1,30 1,30 1,30 1,30 1,30 1,30
14 Pekerjaan rubber protector 16,00 bh 0,03% 0,017% 0,017% NOT READY READY 05/07/2022 06/07/2022 10/07/2022 MOS 2,67 2,67 2,67 2,67 2,67 2,67 Chamdun

15 Penutup antar roling door 12,00 bh 0,01% 0,013% 0,000% READY READY 28/06/2022 30/06/2022 Andri
4,00 4,00 4,00
16 Proteksi rel roling door 7,00 bh 0,02% 0,010% 0,010% NOT READY READY 27/06/2022 28/06/2022 30/06/2022 MOS 2,33 2,33 2,33 Andri

17 Tangga monyet untuk maintanance ke roof tank 8,00 m 0,02% 0,023% 0,000% READY READY 28/06/2022 07/07/2022 Chamdun
0,80 0,80 0,80 0,80 0,80 0,80 0,80 0,80 0,80 0,80
18 Coner guard racking dan sudutan dinding 21,00 Unit 0,01% 0,012% 0,000% READY READY 20/06/2022 30/06/2022 Chamdun
1,91 1,91 1,91 1,91 1,91 1,91 1,91 1,91 1,91 1,91 1,91

PEKERJAAN MEP

1 Instalasi Alarm ,akeseosris dan perlengkapan

> Peralatan Utama MCP-FA Kap. 15 Zone 1,00 unit 0,02% 0,025% 0,000% READY READY 27/06/2022 29/06/2022 Sudarsono
0,33 0,33 0,33
> WH Part 144,00 unit 0,15% 0,150% 0,000% READY READY 20/06/2022 30/06/2022 Sudarsono
13,09 13,09 13,09 13,09 13,09 13,09 13,09 13,09 13,09 13,09 13,09
2 Instalasi CCTV

> Peralatan utama 1,00 unit 0,03% 0,033% 0,000% READY READY 18/06/2022 30/06/2022 Sudarsono
0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08
> Colour Camera Type Day / Night (INSTALASI ONLY) 27,00 ttk 0,07% 0,034% 0,034% NOT READY READY 24/06/2021 UNIT CCTV SUPLAI BY OWNER 18/06/2022 30/06/2022 Sudarsono
2,25 2,25 2,25 2,25 2,25 2,25 MOS 2,25 2,25 2,25 2,25 2,25 2,25
3 Instalasi tata suara 1,00 unit 0,05% 0,024% 0,024% NOT READY READY 22/06/2022 PROSES INSTALASI 18/06/2022 30/06/2022 Sudarsono
0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08
4 Instalasi telpon data

> Peralatan Utama PABX Kap. 8 PTT/ 24 1,00 unit 0,03% 0,014% 0,014% NOT READY READY 23/06/2022 24/06/2022 30/06/2022 MOS 0,13 0,13 0,13 0,13 0,13 0,13 0,13 Sudarsono

> intalasi tlp 105,00 m' 0,04% 0,021% 0,021% NOT READY READY 23/06/2022 24/06/2022 30/06/2022 MOS 13,13 13,13 13,13 13,13 13,13 13,13 13,13 Sudarsono

> Instalasi Telepon (ITC, 2 Pairs Dlm PVC Konduit) 5,00 ttk 0,00% 0,001% 0,001% NOT READY READY 23/06/2022 24/06/2022 30/06/2022 MOS 0,63 0,63 0,63 0,63 0,63 0,63 0,63 Sudarsono

5 Instalasi Data

> data 6,00 ttk 0,01% 0,005% 0,005% NOT READY READY 23/06/2022 24/06/2022 30/06/2022 MOS 0,75 0,75 0,75 0,75 0,75 0,75 0,75 Sudarsono

> outlet data 5,00 bh 0,01% 0,004% 0,004% NOT READY READY 23/06/2022 24/06/2022 30/06/2022 MOS 0,63 0,63 0,63 0,63 0,63 0,63 0,63 Sudarsono

6 Indoor Hydrant Box dan akeseosris 4,00 bh 0,23% 0,113% 0,113% NOT READY READY 25/06/2022 26/06/2022 30/06/2022 MOS 0,40 0,40 0,40 0,40 0,40 Arman

7 TEST COMMISIONING 0,01% 0,005% 0,000% 25/06/2022 15/07/2022


- - - - - - - - - - - - - - - - - - - - -
General Cleaning ls 0,000% 0,000% 18/06/2022 30/06/2022
- 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 9,00 10,00 11,00 12,00 13,00 14,00 15,00 16,00 17,00 18,00 19,00 20,00 21,00 22,00 23,00 24,00 25,00 26,00 27,00
3,69%

TOTAL BOBOT 3,278% 0,509%

Note urgent : Semarang, 20 Juni 2022 Semarang, 18 Juni 2022


1. Penyelesaian pekerjaan area indoor wh part komitmen selesai akhir bulan juni ( Tgl 30 juni 2022)
2. penyelesaian All pekerjaan area wh part komitmen selesai Tgl 15 juli 2022 Diperiksa oleh, Dibuat oleh,
PT. AESLER GROUP Internasional, Tbk PT Lestari Indahjaya Abadi
Manajemen Kontruksi Kontraktor

(Prayitno) (Hendy Setyadharma)


Construction Manajemen Site Manajer