[Arch.

] 4 Weeks Look-Ahead Construction Detail Schedule


Cirebon 2, 1x1000MW Coal Fired Power Plant Project, Indonesia cut off date: 5/10/2020
Progress (As of: 2020/05/10) May June
Plan/
Design
System Subsystem Description Actual or Dur. Start Finish Last Week 1 Week Look-Ahead 2 Weeks Look-Ahead 3 Weeks Look-Ahead 4 Weeks Look-Ahead Remarks
Q'ty Forecast Q'ty % Comp. Status
04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
Plan 250 2019-08-25 2020-04-30 4,000.00 100.0%
Masonry Wall Exterior & Interior 4,000.0 Delay
Actual 204 10/10/2019 4/30/2020 3,965.00 99.1% 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0
Plan 264 9/10/2019 5/30/2020 10,630.00 97.9% 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
CENTRAL Paint Interior Paint 10,860.0 Delay
Actual 215 10/29/2019 5/30/2020 7,276.75 67.0% 20.0 20.0 20.0 20.0 20.0 20.0 20.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
1 CONTROL
Plan 34 2020-03-09 2020-04-11 1,150.00 100.0%
BLDG Membrane waterproofing 1,150.0 Delay
Actual 63 2020-03-09 5/10/2020 1,146.00 99.7% 3.0 3.0 3.0 3.0 3.0 3.0 3.0 2.0 2.0 2.0
Roofing Work
Plan 24 2020-04-12 2020-05-05 1,000.00 100.0% 500.0
Protection Concrete 1,000.0 Delay
Actual 37 2020-04-12 2020-05-18 - 0.0% 500.0 500.0
Plan 136 2019-09-02 2020-01-15 1,900.00 100.0%
Masonry Wall Exterior & Interior 1,900.0 on progress
Actual 190 9/14/2019 3/21/2020 1,900.00 100.0%
Plan 178 2019-09-20 2020-03-15 6,700.00 100.0%
Water Paint Interior Paint 6,700.0 on progress
Actual 189 10/30/2019 5/5/2020 6,700.00 100.0% 0.0
2 Treatment
Plan 93 2019-12-20 2020-03-21 1,521.00 100.0%
Building Membrane waterproofing 1,521.0 on progress
Actual 93 2019-12-20 2020-03-21 1,521.00 100.0%
Roofing Work
Plan 34 2020-03-23 2020-04-25 955.00 100.0%
Protection Concrete 955.0 on progress
Actual 34 3/23/2020 4/25/2020 955.00 100.0%
Plan 78 2019-07-06 2019-09-21 440.00 100.0%
500kV SWYD Masonry Wall Exterior & Interior 440.0 on progress
Actual 74 8/8/2019 10/20/2019 440.00 100.0%
3 CONTROL
Plan 96 2019-08-22 2019-11-25 1,200.00 100.0%
BLDG Paint Interior Paint 1,200.0 on progress
Actual 29 11/2/2019 11/30/2019 1,200.00 100.0%
Plan 30 2019-11-01 2019-11-30 390.00 100.0%
Masonry Wall Exterior & Interior 390.0 on progress
Actual 62 11/15/2019 1/15/2020 390.00 100.0%
Plan 69 2019-12-09 2020-02-15 1,000.00 100.0%
Paint Interior Paint 1,000.0 on progress
AIR COMP. Actual 51 12/27/2019 2020-02-15 1,000.00 100.0%
4
BLDG Plan 27 2020-01-20 2020-02-15 330.00 100.0%
Membrane waterproofing 330.0 on progress
Actual 27 2020-01-20 2020-02-15 330.00 100.0%
Roofing Work
Plan 18 2020-03-02 2020-03-19 30.00 100.0%
Protection Concrete 30.0 on progress
Actual 18 2020-03-02 3/19/2020 30.00 100.0%
Plan 97 2019-12-15 2020-03-20 870.00 100.0%
Masonry Wall Exterior & Interior 870.0 on progress
Actual 129 12/16/2019 4/22/2020 870.00 100.0%
Plan 84 2020-02-07 2020-04-30 4,500.00 100.0%
Paint Interior Paint 4,500.0 on progress
COOLING Actual 99 2/7/2020 2020-05-15 4,500.00 100.0% 30.0 30.0 30.0 20.0 20.0 20.0
TOWER Plan 15 2020-01-24 2020-02-7 1.50 100.0%
5 rebar install 1.5 on progress
ELECTRICAL Actual 15 2020-01-24 2020-02-7 1.50 100.0%
BLDG Parapet & Dog Plan 31 2020-01-27 2020-02-26 500.00 100.0%
house Con'c (FL form install 500.0 on progress
Actual 31 2020-01-27 2020-02-26 500.00 100.0%
+11,300)
Plan 23 2020-02-10 2020-03-03 39.00 100.0%
con'c pouring(25 MPa) 39.0 on progress
Actual 33 2020-02-10 2020-03-13 39.00 100.0%
Plan 20 12/27/2019 1/15/2020 8.00 100.0%
rebar install 8.0 on progress
Actual 11 2/25/2020 3/6/2020 8.00 100.0%
1st FL Col/Wall Plan 18 12/29/2019 1/15/2020 470.00 100.0%
form install 470.0 on progress
Con'c (FL +8,400) Actual 21 3/2/2020 2020-03-22 470.00 100.0%
Plan 14 1/3/2020 1/16/2020 53.00 100.0%
con'c pouring(25 MPa) 53.0 on progress
Actual 21 3/5/2020 3/25/2020 53.00 100.0%
COAL Plan 19 3/16/2020 4/3/2020 19.30 100.0%
rebar install 19.3 on progress
HANDLING Actual 23 3/16/2020 4/7/2020 19.30 100.0%
6
CONTROL Roof FL Slab Plan 22 3/13/2020 4/3/2020 720.00 100.0%
BUILDING form install 720.0 on progress
Con'c (FL +8,500) Actual 27 3/13/2020 4/8/2020 720.00 100.0%
Plan 1 4/4/2020 4/4/2020 128.00 100.0%
con'c pouring(25 MPa) 128.0 on progress
Actual 6 4/4/2020 4/9/2020 128.00 100.0%
Plan 91 4/1/2020 6/30/2020 240.00 29.3% 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
Masonry Wall Exterior & Interior 820.0 Ahead
Actual 91 4/1/2020 6/30/2020 296.00 36.1% 18.0 18.0 18.0 18.0 18.0 18.0 18.0 15.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
Plan 76 6/1/2020 8/15/2020 - 0.0%
Paint Interior Paint 3,500.0 on progress
Actual 1 - 0.0%
Plan 36 2019-12-17 2020-01-21 34.00 100.0%
rebar install 34.0 on progress
Actual 32 2/20/2020 3/22/2020 34.00 100.0%
1st FL Col/Wall Plan 33 2019-12-20 2020-01-21 301.00 100.0%
Con'c form install 301.0 on progress
Actual 44 3/2/2020 4/14/2020 301.00 100.0%
(FL+11,300)
Plan 29 2019-12-25 2020-01-22 105.00 100.0%
FGD ELEC & con'c pouring(25 MPa) 105.0 on progress
Actual 43 3/4/2020 4/15/2020 105.00 100.0%
7 CONTROL
Plan 15 2020-3-21 2020-04-04 28.20 100.0%
BUILDING rebar install 28.2 on progress
Actual 47 2020-3-21 5/6/2020 28.20 100.0% 1.2 1.0 1.0 1.0 1.0 1.0 1.0
2nd FL Slab Con'c Plan 22 2020-03-14 2020-04-04 925.00 100.0%
form install 925.0 on progress
(FL+11,300) Actual 55 2020-03-14 5/7/2020 925.00 100.0% 10.0 10.0 10.0 10.0 10.0 10.0 10.0
Plan 1 2020-04-5 2020-04-05 200.00 100.0%
con'c pouring(25 MPa) 200.0 Delay
Actual 35 2020-04-5 5/9/2020 - 0.0% 200.0
Plan 15 2020-3-13 2020-3-27 22.10 100.0%
rebar install 22.1 on progress
Actual 29 2020-3-13 2020-04-10 22.10 100.0%
1st FL Slab Con'c Plan 19 2020-3-9 2020-3-27 770.00 100.0%
form install 770.0 on progress
(FL+4,000) Actual 33 2020-3-9 2020-04-10 770.00 100.0%
Plan 1 2020-03-28 2020-03-28 125.00 100.0%
ASH & ESP con'c pouring(25 MPa) 125.0 on progress
Actual 58 2020-02-17 2020-04-14 125.00 100.0%
9 CONTROL
BUILDING Plan 26 2020-04-05 2020-04-30 6.00 100.0%
rebar install 6.0 on progress
Actual 19 2020-04-17 2020-05-05 6.00 100.0% 0.1 0.1 0.1 0.1 0.1 0.1
1st FL Col/Wall
Plan 31 2020-04-10 2020-05-10 400.00 100.0% 5.0 5.0 5.0 5.0 5.0 5.0 1.0
Con'c form install 400.0 Delay
Actual 19 2020-04-22 2020-05-10 370.00 92.5% 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 10.0 10.0
(FL+9,400)
Plan 21 2020-04-25 2020-05-15 25.00 62.5% 5.0 5.0 10.0
con'c pouring(25 MPa) 40.0 Delay
Actual 21 2020-04-25 2020-05-15 20.00 50.0% 5.0 5.0 10.0
Plan 11 11/5/2019 11/15/2019 500.00 100.0%
backfill 500.0 on progress
Actual 89 11/5/2019 2/1/2020 500.00 100.0%
Plan 1 11/16/2019 11/16/2019 3.00 100.0%
lean con'c(15 MPa) 3.0 on progress
Actual 22 2020-02-6 2020-02-27 3.00 100.0%
GR FL Slab Con'c Plan 13 11/17/2019 11/29/2019 3.00 100.0%
LIMESTONE rebar install 3.0 on progress
(FL+0) Actual 25 2020-02-7 2020-03-02 3.00 100.0%
10 UNLOADING
Plan 11 11/19/2019 11/29/2019 150.00 100.0%
BUILDING form install 150.0 on progress
Actual 25 2020-02-9 2020-03-04 150.00 100.0%
Plan 1 11/30/2019 11/30/2019 25.00 100.0%
con'c pouring(25 MPa) 25.0 on progress
Actual 20 2/15/2020 3/5/2020 25.00 100.0%
Steel Plan 25 2020-01-30 2020-02-23 23.00 100.0%
Col/Girder/Beam/Bracing 23.0 Delay
Structure Actual 21 4/25/2020 5/15/2020 2.00 8.7% 3.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0
Plan 143 8/10/2019 12/30/2019 82.00 100.0%
form install 82.0 on progress
Actual 227 9/13/2019 4/26/2020 82.00 100.0%
FDN Plan 139 8/14/2019 12/30/2019 360.00 100.0%
LIMESTONE & rebar install 360.0 on progress
Con'c Actual 251 8/20/2019 4/26/2020 360.00 100.0%
11 GYPSUM
BUILDING Plan 88 10/5/2019 12/31/2019 628.00 100.0%
con'c pouring(25 MPa) 628.0 on progress
Actual 202 10/9/2019 4/27/2020 628.00 100.0%
Steel Plan 98 2020-04-01 2020-07-7 145.80 44.9% 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2
Col/Girder/Beam/Bracing 324.5 Delay
Structure Actual 84 4/15/2020 2020-07-7 21.00 6.5% 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0
Plan 87 2019-10-16 1/10/2020 7.00 100.0%
rebar install 7.0 on progress
Actual 141 10/16/2019 3/4/2020 7.00 100.0%
GR FL Col/Wall
Plan 88 2019-10-16 1/11/2020 420.00 100.0%
Con'c form install 420.0 on progress
(FL+5000) Actual 26 2/28/2020 3/24/2020 420.00 100.0%
Plan 46 2019-11-10 2019-12-25 45.00 100.0%
con'c pouring(25 MPa) 45.0 on progress
HYDROGEN Actual 27 3/4/2020 3/30/2020 45.00 100.0%
12
BUILDING Plan 14 2020-3-16 2020-3-29 9.70 100.0%
rebar install 9.7 on progress
Actual 26 2020-3-16 4/10/2020 9.70 100.0%
Roof FL Col/Wall
Plan 20 2020-3-10 2020-3-29 677.00 100.0%
Con'c form install 677.0 on progress
(FL+5000) Actual 32 2020-3-10 4/10/2020 677.00 100.0%
Plan 1 2020-03-30 2020-03-30 81.00 100.0%
con'c pouring(25 MPa) 81.0 on progress
Actual 13 2020-03-30 4/11/2020 81.00 100.0%
Plan 23 2020-02-12 2020-03-05 25.60 100.0%
rebar install 25.6 on progress
Actual 32 2020-01-17 2020-02-17 25.60 100.0%
Roof Slab Con'c Plan 56 2020-01-6 2020-03-1 1,120.00 100.0%
form install 1,120.0 on progress
(FL +9,000) Actual 36 2020-01-13 2020-02-17 1,120.00 100.0%
13
Plan 1 2020-03-06 2020-03-06 180.00 100.0%
con'c pouring(25 MPa) 180.0 on progress
Actual 4 2020-02-18 2020-02-21 180.00 100.0%
[Arch.] 4 Weeks Look-Ahead Construction Detail Schedule
Cirebon 2, 1x1000MW Coal Fired Power Plant Project, Indonesia cut off date: 5/10/2020
Progress (As of: 2020/05/10) May June
Plan/
Design
System
ADMIN Subsystem Description Actual or Dur. Start Finish Last Week 1 Week Look-Ahead 2 Weeks Look-Ahead 3 Weeks Look-Ahead 4 Weeks Look-Ahead Remarks
13 Q'ty Forecast
BUILDING Q'ty % Comp. Status
04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
Plan 92 3/7/2020 6/6/2020 1,040.00 67.9% 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0
Masonry Wall Exterior & Interior 1,532.0 Delay
Actual 129 1/30/2020 6/6/2020 830.00 54.2% 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
Plan 10 2020-02-20 2020-02-29 19.00 100.0%
lean con'c(15 MPa) 19.0 Delay
Actual 45 4/1/2020 5/15/2020 5.00 26.3%
Plan 35 2020-03-01 2020-04-04 11.00 100.0%
rebar install 11.0 Delay
CHLORINATIO Actual 51 4/11/2020 5/31/2020 7.00 63.6% 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
14 FDN Con'c
N BUILDING Plan 31 2020-03-05 2020-04-04 150.00 100.0%
form install 150.0 Delay
Actual 47 4/15/2020 5/31/2020 28.00 18.7% 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0
Plan 22 2020-03-15 2020-04-05 160.00 100.0%
con'c pouring(25 MPa) 160.0 Delay
Actual 38 4/25/2020 6/1/2020 17.00 10.6% 17.0 15.0
Plan 6 2019-07-28 2019-08-02 70.00 100.0%
lean con'c(15 MPa) 70.0 on progress
Actual 23 7/19/2019 8/10/2019 70.00 100.0%
Plan 79 2019-08-03 2019-10-20 82.00 100.0%
FDN & rebar install 82.0 on progress
Actual 35 7/22/2019 8/25/2019 82.00 100.0%
Cable Pit
WORKSHOP& Plan 85 2019-08-03 2019-10-26 430.00 100.0%
15 Con'c form install 430.0 on progress
WAREHOUSE Actual 46 7/11/2019 8/25/2019 430.00 100.0%
Plan 24 2019-10-05 2019-10-28 560.00 100.0%
con'c pouring(25 MPa) 560.0 on progress
Actual 33 7/25/2019 8/26/2019 560.00 100.0%
Steel Plan 95 2020-01-05 2020-04-08 181.00 100.0%
Col/Girder/Beam/Bracing 181.0 on progress
Structure Actual 78 1/22/2020 2020-04-08 181.00 100.0%
[Arch.] 4 Weeks Look-Ahead Construction Detail Schedule
Cirebon 2, 1x1000MW Coal Fired Power Plant Project, Indonesia cut off date: 5/10/2020
Progress (As of: 2020/05/10) May June
Plan/
Design
System Subsystem Description Actual or Dur. Start Finish Last Week 1 Week Look-Ahead 2 Weeks Look-Ahead 3 Weeks Look-Ahead 4 Weeks Look-Ahead Remarks
Q'ty Forecast Q'ty % Comp. Status
04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
Plan 20 2020-07-06 2020-07-25 - 0.0%
rebar install 14.0 Ahead
Actual 15 2020-05-01 2020-05-15 13.50 96.4% 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
Roof Slab Con'c Plan 27 2020-07-01 2020-07-27 - 0.0%
16 MOSQUE form install 60.0 Ahead
(FL +3,300) Actual 16 2020-05-01 2020-05-16 55.00 91.7% 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Plan 1 2020-07-28 2020-07-28 - 0.0%
con'c pouring(25 MPa) 65.0 on progress
Actual 1 2020-05-17 2020-05-17 - 0.0% 65.0
Plan 37 2019-07-25 2019-08-30 11.00 100.0%
rebar install 11.0 on progress
Actual 15 2019-07-01 2019-07-15 11.00 100.0%
FDN Plan 39 2019-07-26 2019-09-02 90.00 100.0%
FUEL OIL form install 90.0 on progress
Con'c Actual 12 2019-07-05 2019-07-16 90.00 100.0%
17 PUMP
Plan 10 2019-08-25 2019-09-03 105.00 100.0%
SHELTER con'c pouring(25 MPa) 105.0 on progress
Actual 1 7/19/2019 7/19/2019 105.00 100.0%
Steel Plan 7 2019-12-16 2019-12-22 11.00 100.0%
Col/Girder/Beam/Bracing 11.0 on progress
Structure Actual 8 2020-01-03 2020-01-10 11.00 100.0%
Plan 25 2019-08-01 2019-08-25 14.50 100.0%
rebar install 14.5 on progress
Actual 16 6/10/2019 6/25/2019 14.50 100.0%
Plan 22 2019-08-05 2019-08-26 95.00 100.0%
FIRE FDN Con'c form install 95.0 on progress
Actual 15 6/12/2019 6/26/2019 95.00 100.0%
18 FIGHTING
Plan 1 2019-08-27 2019-08-27 145.00 100.0%
SHELTER con'c pouring(25 MPa) 145.0 on progress
Actual 1 7/5/2019 7/5/2019 145.00 100.0%
Steel Plan 15 2019-12-16 2019-12-30 24.00 100.0%
Col/Girder/Beam/Bracing 24.0 on progress
Structure Actual 9 12/28/2019 1/5/2020 24.00 100.0%
Plan 1 2020-04-05 2020-04-05 160.00 100.0%
SERVICE GAS FDN Con'c con'c pouring(25 MPa) 160.0 on progress
Actual 1 6/15/2019 6/15/2019 160.00 100.0%
19 STORAGE
Steel Plan 30 2020-04-06 2020-05-05 21.00 100.0%
SHELTER Col/Girder/Beam/Bracing 21.0 Delay
Structure Actual 1 - 0.0%
Steel Plan 31 2020-05-01 2020-05-31 9.50 40.4% 1.0 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
20 PIPERACK#1 Col/Girder/Beam/Bracing 23.5 Delay
Structure Actual 18 5/14/2020 5/31/2020 - 0.0% 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

Plan 14 2020-02-12 2020-02-25 8.00 100.0%


lean con'c(15 MPa) 8.0 Delay
Actual 1 5.00 62.5%
Plan 24 2020-02-13 2020-03-7 5.76 100.0%
FGD WWT rebar install 5.8 Delay
EQUIP Actual 1 - 0.0%
21 FDN Con'c
SHELTER Plan 23 2020-02-14 2020-03-7 116.00 100.0%
(#1-#2-#3) form install 116.0 Delay
Actual 1 - 0.0%
Plan 13 2020-02-25 2020-03-8 55.00 100.0%
con'c pouring(25 MPa) 55.0 Delay
Actual 1 - 0.0%
7.777778
290