YHP.1 Mobilisation Schedule 20-Aug-18 21-Nov-18 81.0 292.0 21-Nov-18, YHP.1 Mobilisation Schedule
A1100 Submission of 3rd party for testing 22-Nov-18 01-Dec-18 8.0 292.0 Submission of 3rd party for testing
A1110 Submission of Main Material Approval 02-Dec-18 10-Dec-18 8.0 292.0 Submission of Main Material Approval
A1120 Submission of Site Office Plan 11-Dec-18 23-Dec-18 11.0 292.0 Submission of Site Office Plan
YHP.3 Manpower Mobilisation 21-Aug-18 15-Nov-18 75.0 324.0 15-Nov-18, YHP.3 Manpower Mobilisation
A1130 Accomodation Arrangement Stage-1 21-Aug-18 12-Sep-18 20.0 324.0 Accomodation Arrangement Stage-1
A1140 Accomodation Arrangement Stage-2 13-Sep-18 11-Oct-18 25.0 324.0 Accomodation Arrangement Stage-2
A1150 Mobilisation Manpower 13-Oct-18 15-Nov-18 30.0 324.0 Mobilisation Manpower
YHP.4 Mobilisation of Key Personnels 20-Aug-18 25-Aug-18 5.0 0.0 25-Aug-18, YHP.4 Mobilisation of Key Personnels
A1160 Project Manager 20-Aug-18 22-Aug-18 3.0 0.0 Project Manager
A1170 Manager Construction 20-Aug-18 22-Aug-18 3.0 0.0 Manager Construction
A1180 Manager Technical Services 20-Aug-18 23-Aug-18 3.0 0.0 Manager Technical Services
A1190 Manager QA/QC 21-Aug-18 23-Aug-18 3.0 0.0 Manager QA/QC
A1200 Safety Officer 21-Aug-18 25-Aug-18 3.0 0.0 Safety Officer
A1210 Field Surveyor 21-Aug-18 25-Aug-18 3.0 0.0 Field Surveyor
A1220 Admin Staff 22-Aug-18 25-Aug-18 3.0 0.0 Admin Staff
YHP.5 Construction Civil (Phase 1) 26-Aug-18 01-Sep-18 6.0 236.0 01-Sep-18, YHP.5 Construction Civil (Phase 1)
A1230 Site Survey for building footing 26-Aug-18 28-Aug-18 3.0 236.0 Site Survey for building footing
A1240 Site Survey (Recording of existing levels) 29-Aug-18 01-Sep-18 3.0 236.0 Site Survey (Recording of existing levels)
YHP.6 Mobilisation of Construction Equipment 26-Aug-18 28-Oct-18 55.0 232.0 28-Oct-18, YHP.6 Mobilisation of Construction Equipment
A1250 Construction Equipment Mobilisation 26-Aug-18 30-Aug-18 5.0 0.0 Construction Equipment Mobilisation
A1260 Excavator-1 01-Sep-18 05-Sep-18 5.0 232.0 Excavator-1
A1270 Excavator-2 06-Sep-18 11-Sep-18 5.0 232.0 Excavator-2
A1280 Dump Truck-1 12-Sep-18 17-Sep-18 5.0 232.0 Dump Truck-1
A1290 Dump Truck-2 18-Sep-18 23-Sep-18 5.0 232.0 Dump Truck-2
A1300 Dump Truck-3 24-Sep-18 29-Sep-18 5.0 232.0 Dump Truck-3
A1310 Dump Truck-4 30-Sep-18 04-Oct-18 5.0 232.0 Dump Truck-4
A1320 Dump Truck-5 06-Oct-18 10-Oct-18 5.0 232.0 Dump Truck-5
A1330 Dump Truck-6 11-Oct-18 16-Oct-18 5.0 232.0 Dump Truck-6
A1340 Loader-1 17-Oct-18 22-Oct-18 5.0 232.0 Loader-1
A1350 Loader-2 23-Oct-18 28-Oct-18 5.0 232.0 Loader-2
YHP.7 Temporary Fence 26-Aug-18 03-Nov-18 60.0 123.0 03-Nov-18, YHP.7 Temporary Fence
A1360 Installation of Fence Post 26-Aug-18 03-Nov-18 60.0 123.0 Installation of Fence Post
A1370 Fixing of Fence Chain Link 29-Aug-18 14-Oct-18 40.0 123.0 Fixing of Fence Chain Link
A1380 Installation of Gate 03-Sep-18 18-Oct-18 40.0 123.0 Installation of Gate
YHP.8 Temporary Al badr Site Office 26-Aug-18 19-Jan-19 126.0 469.0 19-Jan-19, YHP.8 Temporary Al badr Site Office
A1390 Foundation Work 26-Aug-18 14-Nov-18 70.0 0.0 Foundation Work
A1400 Installation of Office 06-Sep-18 26-Nov-18 70.0 469.0 Installation of Office
Actual Work Critical Remaining Work Summary Date Revision Checked Approved Prepared By:
Remaining Work Milestone Muhammed Anshad K (Planning Engineer) 1 of 2
Ph: 0580356424, Email: anshadputtur@gmail.com
Yasref Housing Villa Project
Activity ID Activity Name Start Finish Original Total 2019 2020
Duration Float
g Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul g
A1410 Electrical Works 24-Sep-18 13-Dec-18 70.0 469.0 Electrical Works
A1420 IT Works 06-Oct-18 25-Dec-18 70.0 469.0 IT Works
A1430 Office Equipment Supply 20-Oct-18 08-Jan-19 70.0 469.0 Office Equipment Supply
A1440 Photocopy Machine Supply 25-Oct-18 14-Jan-19 70.0 469.0 Photocopy Machine Supply
A1450 Office Furniture Supply 28-Oct-18 16-Jan-19 70.0 469.0 Office Furniture Supply
A1460 Commissioning of Office Equipments 30-Oct-18 19-Jan-19 70.0 469.0 Commissioning of Office Equipments
YHP.9 First Aid Clinic 23-Oct-18 28-Jan-19 84.0 0.0 28-Jan-19, YHP.9 First Aid Clinic
A1470 First Aid Clinic 23-Oct-18 28-Jan-19 84.0 0.0 First Aid Clinic
YHP.11 Mosque
YHP.1 12-Mar-19 21-Aug-19 140.0 0.0 21-Aug-19, YHP.11 Mosque
A1490 Mosque 12-Mar-19 21-Aug-19 140.0 0.0 Mosque
Actual Work Critical Remaining Work Summary Date Revision Checked Approved Prepared By:
Remaining Work Milestone Muhammed Anshad K (Planning Engineer) 2 of 2
Ph: 0580356424, Email: anshadputtur@gmail.com