WO#40 SEPARATE DEDICATED NITROGEN HEADER AT MAA REFINERY

Activity ID Activity Name Original Start Finish 2019


Duration
A M J Jul A S O N

WO#40 SEPARATE
SEPARA DEDICATED NITROGEN HEADER AT MAA REFINERY 91 29-Jul-19 11-Nov-19

MILESTONES 0 11-Nov-19 11-Nov-19

MS155 Work Order Completion 0 11-Nov-19

GENERAL ACTIVTIES
AC 0

INITIATION 0
MOBILIZATION 0
SUBMISSIONS OF DOCUMENT 0
METHOD STATEMENTS
STAT & PROCEDURES 0
PAINTING & B
BLASTING PROCEDURE 0
WPS 0
ITP 0
HYDROTEST P PROCEDURE 0
PROCUREMENT
PROCUREME 20 09-Sep-19 01-Oct-19

MECHANICAL ITEMS
I 0
PIPE & FITTINGS
FITTIN 0
CS LINE 4"
4",SCH 40 (2439 M) 0
CS LINE 3" SCH 40 (732 M) 0
CS LINE 2" SCH 40 (86 M) 0
CS LINE 1" SCH 80 ( 250 M) 0
INSTRUMENTATION MATERIAL
INSTRUMENTA 20 09-Sep-19 01-Oct-19
CONTROL CABLES
CAB 0
CONTROL VALVE
VAL ( 1 NO) 20 09-Sep-19 01-Oct-19
P3080 Delivery & Inspection at Site 20 09-Sep-19 01-Oct-19
PRESSURE TRANSMITTER
TR 0
CIVIL ITEMS 0
GENERAL CONSTRUCTION
CO MATERIAL 0
ELECTRICAL ITEMS
IT 0

CONSTRUCTION
CONSTRUCTI 73 29-Jul-19 21-Oct-19

MECHANICAL 73 29-Jul-19 21-Oct-19


U-71 GROUND LEVEL 0
TIE IN 0
U-71 64 08-Aug-19 21-Oct-19
Near Unit 80
8 24 08-Aug-19 04-Sep-19
A2270 Scaffolding 12 08-Aug-19 21-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 3
29-Jul-19 Revised schedule
Actual Work Critical Remainin...
WO#40 SEPARATE DEDICATED NITROGEN HEADER AT MAA REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
A M J Jul A S O N
A2280 Fit-up and Welding 12 22-Aug-19 04-Sep-19
Near Unit 56
5 21 28-Sep-19 21-Oct-19
A2290 Scaffolding 12 28-Sep-19 10-Oct-19
A2300 Fit-up and Welding 12 08-Oct-19 21-Oct-19
U-26 0
U-25 29 29-Jul-19 31-Aug-19
A1590 Erection of scaffolding 9 29-Jul-19 07-Aug-19
A1620 Fit-up & welding of field joints 20 08-Aug-19 31-Aug-19
U-05 19 22-Aug-19 12-Sep-19
A1880 Erection of scaffolding 7 22-Aug-19 29-Aug-19
A1910 Fit-up & welding of field joints 12 31-Aug-19 12-Sep-19
U-98 21 31-Aug-19 23-Sep-19
A1400 Erection of scaffolding 3 31-Aug-19 02-Sep-19
A1430 Fit-up & welding of field joints 9 14-Sep-19 23-Sep-19
U-58 23 11-Sep-19 07-Oct-19
A1210 Erection of scaffolding 14 11-Sep-19 26-Sep-19
A1240 Fit-up & welding of field joints 12 24-Sep-19 07-Oct-19
E&I 32 03-Sep-19 09-Oct-19
A2310 Scaffolding 7 03-Sep-19 10-Sep-19
A2320 Tube bending & cable pulling 14 11-Sep-19 26-Sep-19
A2060 Installation of control valve 2 02-Oct-19 03-Oct-19
A2070 Testing & commissioning of Instruments 5 05-Oct-19 09-Oct-19
MECHANICAL ( Tie In ) ( Shutdown required ) 64 29-Jul-19 10-Oct-19
U-71 3 28-Sep-19 30-Sep-19
A1160 Tie in ( depends on Shut down date confirmation ) 3 28-Sep-19 30-Sep-19
U-26 12 29-Jul-19 11-Aug-19
A2170 Tie in ( depends on Shut down date confirmation ) 12 29-Jul-19 11-Aug-19
U-25 12 01-Sep-19 14-Sep-19
A1730 Tie in ( depends on Shut down date confirmation ) 12 01-Sep-19 14-Sep-19
U-05 5 14-Sep-19 18-Sep-19
A2020 Tie in ( depends on Shut down date confirmation ) 5 14-Sep-19 18-Sep-19
U-98 3 24-Sep-19 26-Sep-19
A1540 Tie in ( depends on Shut down date confirmation ) 3 24-Sep-19 26-Sep-19
U-58 3 08-Oct-19 10-Oct-19
A1350 Tie in ( depends on Shut down date confirmation ) 3 08-Oct-19 10-Oct-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 3
29-Jul-19 Revised schedule
Actual Work Critical Remainin...
WO#40 SEPARATE DEDICATED NITROGEN HEADER AT MAA REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
A M J Jul A S O N
COMPLETION & HANDOVER 43 22-Sep-19 11-Nov-19

A2330 Radiography Testing 5 22-Oct-19 27-Oct-19


A2340 Hydrotest 6 28-Oct-19 03-Nov-19
H100 Closure of Punch Points 45 22-Sep-19 06-Nov-19
H110 As built and finals issue of documents 5 06-Nov-19 11-Nov-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 3 of 3
29-Jul-19 Revised schedule
Actual Work Critical Remainin...