Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019

Activity ID Activity Name Original Start Finish 2019


Duration
ar Apr M Jun Jul A S Oct N ec

Re-Design and A
Additional Works of Bait Al Wataniya Club at Messila B 285 17-Nov-18 A 04-Dec-19

General 0 04-Dec-19 04-Dec-19

A4020 Project Close Out 0 04-Dec-19

Milestones 42 07-Sep-19 05-Nov-19

A4050 Structure Assessment / Details & Lab Test Completion 0 07-Sep-19


A4035 Main Building with Substation & Guard Hose 2 &3 0 12-Sep-19
A4060 Loose Furniture Design Completion 0 26-Sep-19
A4230 General and External Works Completion 0 03-Oct-19
A4040 New Multipurpose Hall with Swimming Pool & Cafeteria Design Completion 0 08-Oct-19
A4070 Tender Documents Completion 0 05-Nov-19
A4080 Obtain Liscences from Different Authorities 0 05-Nov-19

Engineering W
Works 285 17-Nov-18 A 05-Nov-19

General / External
Exter Works 69 30-Jun-19 03-Oct-19
General 0
CIVIL 47 30-Jun-19 03-Sep-19
A3180 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION BASEMEN 27 30-Jun-19 30-Jul-19
A3200 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLTION BASEMENT 27 30-Jun-19 30-Jul-19
A3260 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION GROUND F 27 30-Jun-19 30-Jul-19
A3270 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLTION GROUND F 27 30-Jun-19 30-Jul-19
A3280 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLTION GROUND F 27 30-Jun-19 30-Jul-19
A3290 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION FIRST FLO 27 30-Jun-19 30-Jul-19
A3300 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION FIRST FLO 10 20-Jul-19 30-Jul-19
A3310 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION FIRST FLO 10 20-Jul-19 30-Jul-19
A3320 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION ROOF PLA 10 20-Jul-19 30-Jul-19
A3330 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION ROOF PLA 10 20-Jul-19 30-Jul-19
A3340 PREPARATION & SUBMISSION OF GENERAL CIVIL DEMOLITION ROOF PLA 10 20-Jul-19 30-Jul-19
A3350 PREPARATION & SUBMISSION OF SITE SURVEY PLAN 10 20-Jul-19 30-Jul-19
A3360 PREPARATION & SUBMISSION OF EXISTING BUILDINGS SECTIONS 10 20-Jul-19 30-Jul-19
A5643 KNPC Review / Comments (A2) 15 31-Jul-19 17-Aug-19
A5653 Incorporate KNPC Comments & KNPC Approval (A1) 15 18-Aug-19 03-Sep-19
ARCHITECTUR
ARCHITECTURAL 47 31-Jul-19 03-Oct-19
A3225 PREPARATION & SUBMISSION OF GENERAL NOTES ABBREVIATION & LEG 26 31-Jul-19 29-Aug-19
A3245 PREPARATION & SUBMISSION OF GENERAL PROPOSED LAYOUT AND SITE 26 31-Jul-19 29-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A3255 PREPARATION & SUBMISSION OF FENCE & GATE DETAILS 1 10 19-Aug-19 29-Aug-19
A3265 PREPARATION & SUBMISSION OF FENCE & GATE DETAILS 2 10 19-Aug-19 29-Aug-19
A3275 PREPARATION & SUBMISSION OF GENERAL TYPICAL DETAILS 1 10 19-Aug-19 29-Aug-19
A3285 PREPARATION & SUBMISSION OF GENERAL TYPICAL DETAILS 2 10 19-Aug-19 29-Aug-19
A3295 PREPARATION & SUBMISSION OF GENERAL TYPICAL DETAILS 3 10 19-Aug-19 29-Aug-19
A5663 KNPC Review / Comments (A2) 15 31-Aug-19 16-Sep-19
A5673 Incorporate KNPC Comments & KNPC Approval (A1) 15 17-Sep-19 03-Oct-19
STRUCTURAL 47 31-Jul-19 03-Oct-19
A32009 PREPARATION & SUBMISSION OF BORE HOLE PLAN 12 31-Jul-19 13-Aug-19
A3210 PREPARATION & SUBMISSION OF STRUCTURAL GENERAL NOTES - CONCR 14 14-Aug-19 29-Aug-19
A3380 PREPARATION & SUBMISSION OF STRUCTURAL GENERAL NOTES - STEEL 14 14-Aug-19 29-Aug-19
A3390 PREPARATION & SUBMISSION OF STRUCTURAL GENERAL NOTES - DEMO 14 14-Aug-19 29-Aug-19
A3400 PREPARATION & SUBMISSION OF STRUCTURAL GENERAL DETAILS - CONC 14 14-Aug-19 29-Aug-19
A3410 PREPARATION & SUBMISSION OF LANDSCAPE PLAN & RC DETAILS 14 14-Aug-19 29-Aug-19
A3420 PREPARATION & SUBMISSION OF LANDSCAPE PLAN & RC DETAILS 14 14-Aug-19 29-Aug-19
A5683 KNPC Review / Comments (A2) 15 31-Aug-19 16-Sep-19
A5693 Incorporate KNPC Comments & KNPC Approval (A1) 15 17-Sep-19 03-Oct-19
General Lands
Landscape Soft and Hard Plans 32 20-Jul-19 03-Sep-19
A3228 PREPARATION & SUBMISSION OF GENERAL LANDSCAPE DEMOLITION PL 10 20-Jul-19 30-Jul-19
A3248 PREPARATION & SUBMISSION OF GENERAL LANDSCAPE SOFT AND HARD 10 20-Jul-19 30-Jul-19
A3258 PREPARATION & SUBMISSION OF GENERAL LANDSCAPE SOFT AND HARD 10 20-Jul-19 30-Jul-19
A3268 PREPARATION & SUBMISSION OF GENERAL LANDSCAPE SOFT AND HARD 10 20-Jul-19 30-Jul-19
A3278 PREPARATION & SUBMISSION OF LANDSCAPING SITE CROSS SECTION 10 20-Jul-19 30-Jul-19
A3288 PREPARATION & SUBMISSION OF LANDSCAPE PLAN & DETAILS - PART A 10 20-Jul-19 30-Jul-19
A3298 PREPARATION & SUBMISSION OF LANDSCAPE PLAN & DETAILS - PART B 10 20-Jul-19 30-Jul-19
A5703 KNPC Review / Comments (A2) 15 31-Jul-19 17-Aug-19
A5713 Incorporate KNPC Comments & KNPC Approval (A1) 15 18-Aug-19 03-Sep-19
MECHANICAL 46 30-Jun-19 02-Sep-19
PLUMBING 46 30-Jun-19 02-Sep-19
A3230 PREPARATION & SUBMISSION OF GENERAL PLUMBING DEMOLITION BAS 16 30-Jun-19 17-Jul-19
A3460 PREPARATION & SUBMISSION OF GENERAL PLUMBING DEMOLITION GRO 16 30-Jun-19 17-Jul-19
A3470 PREPARATION & SUBMISSION OF GENERAL PLUMBING DEMOLITION FIRS 16 30-Jun-19 17-Jul-19
A3480 PREPARATION & SUBMISSION OF GENERAL PLUMBING DEMOLITION ROO 16 30-Jun-19 17-Jul-19
A3490 PREPARATION & SUBMISSION OF MECHANICAL GENERAL NOTES, ABBRIV 10 18-Jul-19 29-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A3500 PREPARATION & SUBMISSION OF GENERAL - COMBINED WATER SUPPLY 10 18-Jul-19 29-Jul-19
A3510 PREPARATION & SUBMISSION OF GENERAL - COMBINED DRAINAGE RISE 10 18-Jul-19 29-Jul-19
A3520 PREPARATION & SUBMISSION OF SITE PLAN - WATER SUPPLY LAYOUT 10 18-Jul-19 29-Jul-19
A3530 PREPARATION & SUBMISSION OF GENERAL - WATER SUPPLY SCHEMATIC 10 18-Jul-19 29-Jul-19
A3540 PREPARATION & SUBMISSION OF SITE PLAN - DRAINAGE LAYOUT 10 18-Jul-19 29-Jul-19
A3550 PREPARATION & SUBMISSION OF GENERAL - DRAINAGE SCHEMATIC LAYO 10 18-Jul-19 29-Jul-19
A3560 PREPARATION & SUBMISSION OF SITE PLAN - FIRE FIGHTING LAYOUT 10 18-Jul-19 29-Jul-19
A3570 PREPARATION & SUBMISSION OF SITE PLAN - FIRE FIGHTING SCHEMATIC 10 18-Jul-19 29-Jul-19
A3580 PREPARATION & SUBMISSION OF SITE PLAN - IRRIGATION LAYOUT 9 20-Jul-19 29-Jul-19
A3590 PREPARATION & SUBMISSION OF SITE PLAN - IRRIGATION SCHEMATIC LA 9 20-Jul-19 29-Jul-19
A3600 PREPARATION & SUBMISSION OF SITE PLAN - WATER + DRAINAGE TYPICA 9 20-Jul-19 29-Jul-19
A5723 KNPC Review / Comments (A2) 15 30-Jul-19 15-Aug-19
A5733 Incorporate KNPC Comments & KNPC Approval (A1) 15 17-Aug-19 02-Sep-19
HVAC 31 20-Jul-19 02-Sep-19
A4160 PREPARATION & SUBMISSION OF GENERAL HVAC DEMOLITION BASEME 9 20-Jul-19 29-Jul-19
A4240 PREPARATION & SUBMISSION OF GENERAL HVAC DEMOLITION GROUND 9 20-Jul-19 29-Jul-19
A4250 PREPARATION & SUBMISSION OF GENERAL HVAC DEMOLITION FIRST FLO 9 20-Jul-19 29-Jul-19
A4260 PREPARATION & SUBMISSION OF GENERAL HVAC DEMOLITION ROOF PLA 9 20-Jul-19 29-Jul-19
A4270 PREPARATION & SUBMISSION OF MECHANICAL GENERAL NOTE, ABBRIVIA 9 20-Jul-19 29-Jul-19
A4280 PREPARATION & SUBMISSION OF HVAC DETAILS - I 9 20-Jul-19 29-Jul-19
A4290 PREPARATION & SUBMISSION OF HVAC DETAILS - II 9 20-Jul-19 29-Jul-19
A4300 PREPARATION & SUBMISSION OF BAS DIAGRAM 9 20-Jul-19 29-Jul-19
A4310 PREPARATION & SUBMISSION OF EXTERNAL CHILLED WATER PIPING LAY 9 20-Jul-19 29-Jul-19
A4320 PREPARATION & SUBMISSION OF CHILLED WATER SCHEMATIC DIAGRAM 9 20-Jul-19 29-Jul-19
A4330 PREPARATION & SUBMISSION OF CHILLED WATER RISER DIAGRAM 9 20-Jul-19 29-Jul-19
A5743 KNPC Review / Comments (A2) 15 30-Jul-19 15-Aug-19
A5753 Incorporate KNPC Comments & KNPC Approval (A1) 15 17-Aug-19 02-Sep-19
ELECTRICAL 31 20-Jul-19 02-Sep-19
A3224 PREPARATION & SUBMISSION OF GENERAL ELECTRICAL DEMOLITION BA 9 20-Jul-19 29-Jul-19
A4170 PREPARATION & SUBMISSION OF GENERAL ELECTRICAL DEMOLITION GR 9 20-Jul-19 29-Jul-19
A4180 PREPARATION & SUBMISSION OF GENERAL ELECTRICAL DEMOLITION FIR 9 20-Jul-19 29-Jul-19
A4390 PREPARATION & SUBMISSION OF GENERAL ELECTRICAL DEMOLITION RO 9 20-Jul-19 29-Jul-19
A4400 PREPARATION & SUBMISSION OF ELECTRICAL GENERAL NOTE, ABBRIVIA 9 20-Jul-19 29-Jul-19
A4410 PREPARATION & SUBMISSION OF EXTERNAL LIGHTING LAYOUT 9 20-Jul-19 29-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 3 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A4420 PREPARATION & SUBMISSION OF ELECTRICAL CABLE ROUTE LAYOUT 9 20-Jul-19 29-Jul-19
A4421 KNPC Review / Comments (A2) 15 30-Jul-19 15-Aug-19
A4423 Incorporate KNPC Comments & KNPC Approval (A1) 15 17-Aug-19 02-Sep-19
Concept Design Alternatives 0
Main Building w
with Substation & Guard Hose 2 &3 125 23-May-19 A 12-Sep-19
ARCHITECTUR
ARCHITECTURAL 125 23-May-19 A 31-Jul-19
A2640 PREPARATION & SUBMISSION OF BASEMENT FLOORING LAYOUT 26 30-Jun-19 29-Jul-19
A2670 PREPARATION & SUBMISSION OF GRUND FLOOR FLOORING LAYOUT 26 30-Jun-19 29-Jul-19
A2680 PREPARATION & SUBMISSION OF FIRST FLOOR FLOORING LAYOUT 26 30-Jun-19 29-Jul-19
A2690 PREPARATION & SUBMISSION OF ROOF FLOORING LAYOUT 26 30-Jun-19 29-Jul-19
A2700 PREPARATION & SUBMISSION OF BASEMENT REFLECTED CEILING PLAN 26 30-Jun-19 29-Jul-19
A2710 PREPARATION & SUBMISSION OF GROUND FLOOR REFLECTED CEILING P 26 30-Jun-19 29-Jul-19
A2720 PREPARATION & SUBMISSION OF FIRST FLOOR REFLECTED CEILING PLA 26 30-Jun-19 29-Jul-19
A2730 PREPARATION & SUBMISSION OF ELEVATION 26 30-Jun-19 29-Jul-19
A2740 PREPARATION & SUBMISSION OF SECTION A & B 26 30-Jun-19 29-Jul-19
A2750 PREPARATION & SUBMISSION OF SECTIONS C & D 26 30-Jun-19 29-Jul-19
A2770 PREPARATION & SUBMISSION OF WALL SECTIONS 26 30-Jun-19 29-Jul-19
A2780 PREPARATION & SUBMISSION OF STAIR CASE & LIFT DETAILS 26 30-Jun-19 29-Jul-19
A2790 PREPARATION & SUBMISSION OF MISCELLENIOUS DETAILS - PART A 26 30-Jun-19 29-Jul-19
A2800 PREPARATION & SUBMISSION OF MISCELLENIOUS DETAILS - PART B 26 30-Jun-19 29-Jul-19
A2810 PREPARATION & SUBMISSION OF WET AREAS DETAILS IN BASEMENT FLO 26 30-Jun-19 29-Jul-19
A2820 PREPARATION & SUBMISSION OF WET AREAS DETAILS IN GROUND FLOO 26 30-Jun-19 29-Jul-19
A2830 PREPARATION & SUBMISSION OF DOOR SCHEDULE - DOOR HARDWARE S 26 30-Jun-19 29-Jul-19
A2840 PREPARATION & SUBMISSION OF WINDOW SCHEDULE - PART A 26 30-Jun-19 29-Jul-19
A2850 PREPARATION & SUBMISSION OF WINDOW SCHEDULE - PART B 26 30-Jun-19 29-Jul-19
A2860 PREPARATION & SUBMISSION OF FINISHING SCHEDULE 26 30-Jun-19 29-Jul-19
A4433 KNPC Review / Comments ( A2 ) 15 23-May-19 A 31-Jul-19
A4443 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 27-Jun-19 A 31-Jul-19
STRUCTURAL 38 23-Jul-19 12-Sep-19
A2565 PREPARATION & SUBMISSION OF FOUNDATION PLAN & DETAILS 15 23-Jul-19 08-Aug-19
A2585 PREPARATION & SUBMISSION OF GROUND FLOOR PLAN & DETAILS 15 23-Jul-19 08-Aug-19
A2595 PREPARATION & SUBMISSION OF FIRST FLOOR PLAN & DETAILS 15 23-Jul-19 08-Aug-19
A2605 PREPARATION & SUBMISSION OF ROOF PLAN & DETAILS 15 23-Jul-19 08-Aug-19
A2615 PREPARATION & SUBMISSION OF FOUNDATION PLAN & R.C DETAILS 8 31-Jul-19 08-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 4 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A2625 PREPARATION & SUBMISSION OF GROUND FLOOR PLAN & R.C DETAILS 8 31-Jul-19 08-Aug-19
A2635 PREPARATION & SUBMISSION OF FIRST FLOOR PLAN & R.C DETAILS 8 31-Jul-19 08-Aug-19
A2645 PREPARATION & SUBMISSION OF ROOF PLAN & R.C DETAILS 8 31-Jul-19 08-Aug-19
A2655 PREPARATION & SUBMISSION OF COLUMN & WALL R.C DETAILS 8 31-Jul-19 08-Aug-19
A2665 PREPARATION & SUBMISSION OF STAIR PLANS & R.C DETAILS 8 31-Jul-19 08-Aug-19
A2675 PREPARATION & SUBMISSION OF LIFT PLAN & R.C DETAILS 8 31-Jul-19 08-Aug-19
A4453 KNPC Review / Comments ( A2 ) 15 10-Aug-19 26-Aug-19
A4463 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 27-Aug-19 12-Sep-19
MECHANICAL 33 24-Jul-19 08-Sep-19
PLUMBING 33 24-Jul-19 08-Sep-19
A2570 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT,BASEMENT F 10 24-Jul-19 04-Aug-19
A2880 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT, GROUND FLO 10 24-Jul-19 04-Aug-19
A2890 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT, FIRST FLOOR 10 24-Jul-19 04-Aug-19
A2900 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT, ROOF 10 24-Jul-19 04-Aug-19
A2910 PREPARATION & SUBMISSION OF ENLARGED PLAN, POTABLE WATER 10 24-Jul-19 04-Aug-19
A2920 PREPARATION & SUBMISSION OF POTABLE WATER RISER DIAGRAM 10 24-Jul-19 04-Aug-19
A2930 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, BASEMENT FLOOR 10 24-Jul-19 04-Aug-19
A2940 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, GROUND FLOOR 10 24-Jul-19 04-Aug-19
A2950 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, FIRST FLOOR 10 24-Jul-19 04-Aug-19
A2960 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, ROOF 10 24-Jul-19 04-Aug-19
A2970 PREPARATION & SUBMISSION OF ENLARGED PLAN, DRAINAGE WATER 10 24-Jul-19 04-Aug-19
A2980 PREPARATION & SUBMISSION OF DRAINAGE RISER DIAGRAM 10 24-Jul-19 04-Aug-19
A2990 PREPARATION & SUBMISSION OF IRRIGATION LAYOUT, GROUND FLOOR 5 30-Jul-19 04-Aug-19
A3000 PREPARATION & SUBMISSION OF IRRIGATION TYPICAL DETAILS 5 30-Jul-19 04-Aug-19
A3010 PREPARATION & SUBMISSION OF FIRE FIGHTING LAYOUT,BASEMENT FLO 5 30-Jul-19 04-Aug-19
A3060 PREPARATION & SUBMISSION OF FIRE FIGHTING LAYOUT, GROUND FLOO 5 30-Jul-19 04-Aug-19
A3070 PREPARATION & SUBMISSION OF FIRE FIGHTING LAYOUT, FIRST FLOOR 5 30-Jul-19 04-Aug-19
A3080 PREPARATION & SUBMISSION OF FIRE FIGHTING TYPICAL DETAILS 5 30-Jul-19 04-Aug-19
A4473 KNPC Review / Comments ( A2 ) 15 05-Aug-19 21-Aug-19
A4483 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 22-Aug-19 08-Sep-19
HVAC 33 24-Jul-19 08-Sep-19
A2580 PREPARATION & SUBMISSION OF HVAC LAYOUT, BASEMENT FLOOR 10 24-Jul-19 04-Aug-19
A3090 PREPARATION & SUBMISSION OF HVAC LAYOUT, BASEMENT FLOOR 10 24-Jul-19 04-Aug-19
A3100 PREPARATION & SUBMISSION OF HVAC LAYOUT, GROUND FLOOR 10 24-Jul-19 04-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 5 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A3110 PREPARATION & SUBMISSION OF HVAC LAYOUT, FIRST FLOOR 10 24-Jul-19 04-Aug-19
A3120 PREPARATION & SUBMISSION OF HVAC LAYOUT, ROOF FLOOR 10 24-Jul-19 04-Aug-19
A3130 PREPARATION & SUBMISSION OF CHILLED WATER LAYOUT, BASEMENT F 10 24-Jul-19 04-Aug-19
A3140 PREPARATION & SUBMISSION OF CHILLED WATER LAYOUT, GROUND FLO 10 24-Jul-19 04-Aug-19
A3150 PREPARATION & SUBMISSION OF CHILLED WATER LAYOUT, FIRST FLOOR 10 24-Jul-19 04-Aug-19
A3620 PREPARATION & SUBMISSION OF CHILLED WATER LAYOUT, ROOF FLOOR 10 24-Jul-19 04-Aug-19
A3630 PREPARATION & SUBMISSION OF SMOKE CALCULATIONS 5 30-Jul-19 04-Aug-19
A3640 PREPARATION & SUBMISSION OF SMOKE LAYOUT, BASEMENT FLOOR 5 30-Jul-19 04-Aug-19
A3650 PREPARATION & SUBMISSION OF SMOKE LAYOUT, GROUND FLOOR 5 30-Jul-19 04-Aug-19
A3660 PREPARATION & SUBMISSION OF SMOKE LAYOUT, FIRST FLOOR 5 30-Jul-19 04-Aug-19
A3670 PREPARATION & SUBMISSION OF SMOKE LAYOUT, ROOF FLOOR 5 30-Jul-19 04-Aug-19
A3680 PREPARATION & SUBMISSION OF HVAC. EQUIPMENT SCHEDULE. 5 30-Jul-19 04-Aug-19
A4493 KNPC Review / Comments ( A2 ) 15 05-Aug-19 21-Aug-19
A4503 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 22-Aug-19 08-Sep-19
ELECTRICAL 33 24-Jul-19 08-Sep-19
A2590 PREPARATION & SUBMISSION OF LEGEND & GENERAL NOTES 10 24-Jul-19 04-Aug-19
A3700 PREPARATION & SUBMISSION OF BASEMENT - LIGHTING LAYOUT 10 24-Jul-19 04-Aug-19
A3710 PREPARATION & SUBMISSION OF GROUND FLOOR - LIGHTING LAYOUT 10 24-Jul-19 04-Aug-19
A3720 PREPARATION & SUBMISSION OF FIRST FLOOR - LIGHTING LAYOUT 10 24-Jul-19 04-Aug-19
A3730 PREPARATION & SUBMISSION OF ROOF - LIGHTING LAYOUT 10 24-Jul-19 04-Aug-19
A3740 PREPARATION & SUBMISSION OF BASEMENT - POWER LAYOUT 10 24-Jul-19 04-Aug-19
A3750 PREPARATION & SUBMISSION OF GROUND FLOOR - POWER LAYOUT 10 24-Jul-19 04-Aug-19
A3760 PREPARATION & SUBMISSION OF FIRST FLOOR - POWER LAYOUT 10 24-Jul-19 04-Aug-19
A3770 PREPARATION & SUBMISSION OF ROOF - POWER LAYOUT 10 24-Jul-19 04-Aug-19
A3780 PREPARATION & SUBMISSION OF SCHEDULE OF POINTS 10 24-Jul-19 04-Aug-19
A3790 PREPARATION & SUBMISSION OF SCHEMATIC DIAGRAM & SCHEDULE OF 10 24-Jul-19 04-Aug-19
A3800 PREPARATION & SUBMISSION OF TELEPHONE SYSTEM FOR FAX & DIREC 5 30-Jul-19 04-Aug-19
A3810 PREPARATION & SUBMISSION OF TELEPHONE SYSTEM FOR FAX & DIREC 5 30-Jul-19 04-Aug-19
A3820 PREPARATION & SUBMISSION OF TELEPHONE SYSTEM FOR FAX & DIREC 5 30-Jul-19 04-Aug-19
A3830 PREPARATION & SUBMISSION OF FIRE ALARM LAYOUT BASEMENT FLOO 5 30-Jul-19 04-Aug-19
A3840 PREPARATION & SUBMISSION OF FIRE ALARM LAYOUT GROUND FLOOR 5 30-Jul-19 04-Aug-19
A3850 PREPARATION & SUBMISSION OF FIRE ALARM LAYOUT FIRST FLOOR 5 30-Jul-19 04-Aug-19
A3860 PREPARATION & SUBMISSION OF SMART SYSTEM LAYOUT IN BASEMENT 5 30-Jul-19 04-Aug-19
A3870 PREPARATION & SUBMISSION OF SMART SYSTEM LAYOUT IN GROUND FL 5 30-Jul-19 04-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 6 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A3880 PREPARATION & SUBMISSION OF SMART SYSTEM LAYOUT IN FIRST FLOO 5 30-Jul-19 04-Aug-19
A3890 PREPARATION & SUBMISSION OF P.A & A.V SYSTEM LAYOUT IN BASEMEN 5 30-Jul-19 04-Aug-19
A3900 PREPARATION & SUBMISSION OF P.A & A.V SYSTEM LAYOUT IN GROUND 5 30-Jul-19 04-Aug-19
A3910 PREPARATION & SUBMISSION OF P.A & A.V SYSTEM LAYOUT IN FIRST FL 5 30-Jul-19 04-Aug-19
A3920 PREPARATION & SUBMISSION OF AUDIO VIDIO & PUBLIC ADDRESS SYSTE 5 30-Jul-19 04-Aug-19
A3930 PREPARATION & SUBMISSION OF SECURITY & TV SYSTEM BASEMENT PL 5 30-Jul-19 04-Aug-19
A3940 PREPARATION & SUBMISSION OF SECURITY & TV SYSTEM GROUND FLOO 5 30-Jul-19 04-Aug-19
A3950 PREPARATION & SUBMISSION OF SECURITY & TV SYSTEM FIRST FLOOR 5 30-Jul-19 04-Aug-19
A3960 PREPARATION & SUBMISSION OF EXTERNAL LOW VOLTAGE CABLE ROUT 5 30-Jul-19 04-Aug-19
A4513 KNPC Review / Comments ( A2 ) 15 05-Aug-19 21-Aug-19
A4523 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 22-Aug-19 08-Sep-19
New Multipurpo
Multipurpose Hall Design with Swimming Pool & Cafeteria 110 23-May-19 A 08-Oct-19
ARCHITECTUR
ARCHITECTURAL 110 23-May-19 A 24-Aug-19
A4623 PREPARATION & SUBMISSION OF BASEMENT FLOORING LAYOUT 30 20-Jul-19 22-Aug-19
A4633 PREPARATION & SUBMISSION OF GRUND FLOOR FLOORING LAYOUT 30 20-Jul-19 22-Aug-19
A4643 PREPARATION & SUBMISSION OF FIRST FLOOR FLOORING LAYOUT 30 20-Jul-19 22-Aug-19
A4653 PREPARATION & SUBMISSION OF ROOF FLOORING LAYOUT 30 20-Jul-19 22-Aug-19
A4663 PREPARATION & SUBMISSION OF BASEMENT REFLECTED CEILING PLAN 30 20-Jul-19 22-Aug-19
A4673 PREPARATION & SUBMISSION OF GROUND FLOOR REFLECTED CEILING P 27 23-Jul-19 22-Aug-19
A4683 PREPARATION & SUBMISSION OF FIRST FLOOR REFLECTED CEILING PLA 27 23-Jul-19 22-Aug-19
A4693 PREPARATION & SUBMISSION OF ELEVATION 27 23-Jul-19 22-Aug-19
A4703 PREPARATION & SUBMISSION OF SECTION A & B 27 23-Jul-19 22-Aug-19
A4713 PREPARATION & SUBMISSION OF SECTIONS C & D 27 23-Jul-19 22-Aug-19
A4733 PREPARATION & SUBMISSION OF WALL SECTIONS 30 20-Jul-19 22-Aug-19
A4743 PREPARATION & SUBMISSION OF STAIR CASE & WET AREAS DETAILS 30 20-Jul-19 22-Aug-19
A4793 PREPARATION & SUBMISSION OF DOOR SCHEDULE - DOOR HARDWARE S 30 20-Jul-19 22-Aug-19
A4823 PREPARATION & SUBMISSION OF FINISHING SCHEDULE 30 20-Jul-19 22-Aug-19
A4833 KNPC Review / Comments ( A2 ) 15 23-May-19 A 24-Aug-19
A4843 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 27-Jun-19 A 24-Aug-19
STRUCTURAL 37 18-Aug-19 08-Oct-19
A4563 PREPARATION & SUBMISSION OF FOUNDATION PLAN & DETAILS 15 18-Aug-19 03-Sep-19
A4863 PREPARATION & SUBMISSION OF GROUND FLOOR PLAN & DETAILS 15 18-Aug-19 03-Sep-19
A4873 PREPARATION & SUBMISSION OF FIRST FLOOR PLAN & DETAILS 15 18-Aug-19 03-Sep-19
A4883 PREPARATION & SUBMISSION OF ROOF PLAN & DETAILS 15 18-Aug-19 03-Sep-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 7 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A4893 PREPARATION & SUBMISSION OF FOUNDATION PLAN & R.C DETAILS 15 18-Aug-19 03-Sep-19
A4903 PREPARATION & SUBMISSION OF GROUND FLOOR PLAN & R.C DETAILS 15 18-Aug-19 03-Sep-19
A4913 PREPARATION & SUBMISSION OF FIRST FLOOR PLAN & R.C DETAILS 15 18-Aug-19 03-Sep-19
A4923 PREPARATION & SUBMISSION OF ROOF PLAN & R.C DETAILS 15 18-Aug-19 03-Sep-19
A4933 PREPARATION & SUBMISSION OF COLUMN & WALL R.C DETAILS 15 18-Aug-19 03-Sep-19
A4943 PREPARATION & SUBMISSION OF STAIR PLANS & R.C DETAILS 15 18-Aug-19 03-Sep-19
A4963 KNPC Review / Comments ( A2 ) 15 04-Sep-19 21-Sep-19
A4973 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 22-Sep-19 08-Oct-19
MECHANICAL 49 20-Jul-19 26-Sep-19
PLUMBING 49 20-Jul-19 26-Sep-19
A4543 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT,BASEMENT F 30 20-Jul-19 22-Aug-19
A4993 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT, GROUND FLO 30 20-Jul-19 22-Aug-19
A5003 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT, FIRST FLOOR 30 20-Jul-19 22-Aug-19
A5013 PREPARATION & SUBMISSION OF POTABLE WATER LAYOUT, ROOF 30 20-Jul-19 22-Aug-19
A5023 PREPARATION & SUBMISSIONE NLARGED PLAN, POTABLE WATER 30 20-Jul-19 22-Aug-19
A5033 PREPARATION & SUBMISSION OF POTABLE WATER RISER DIAGRAM 30 20-Jul-19 22-Aug-19
A5043 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, BASEMENT FLOOR 30 20-Jul-19 22-Aug-19
A5053 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, GROUND FLOOR 30 20-Jul-19 22-Aug-19
A5063 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, FIRST FLOOR 30 20-Jul-19 22-Aug-19
A5073 PREPARATION & SUBMISSION OF DRAINAGE LAYOUT, ROOF 30 20-Jul-19 22-Aug-19
A5083 PREPARATION & SUBMISSION OF WATER SUPPLY BASEMENT FLOOR PLA 30 20-Jul-19 22-Aug-19
A5093 PREPARATION & SUBMISSION OF WATER SUPPLY GROUND FLOOR PLAN 30 20-Jul-19 22-Aug-19
A5103 PREPARATION & SUBMISSION OF WATER SUPPLY FIRST FLOOR PLAN 30 20-Jul-19 22-Aug-19
A5113 PREPARATION & SUBMISSION OF WATER SUPPLY ROOF FLOOR PLAN 30 20-Jul-19 22-Aug-19
A5123 PREPARATION & SUBMISSION OF FIRE FIGHTING LAYOUT,BASEMENT FLO 30 20-Jul-19 22-Aug-19
A5133 PREPARATION & SUBMISSION OF FIRE FIGHTING LAYOUT, GROUND FLOO 30 20-Jul-19 22-Aug-19
A5143 PREPARATION & SUBMISSION OF FIRE FIGHTING LAYOUT, FIRST FLOOR 30 20-Jul-19 22-Aug-19
A5153 PREPARATION & SUBMISSION OF FIRE FIGHTING TYPICAL DETAILS 30 20-Jul-19 22-Aug-19
A5163 KNPC Review / Comments ( A2 ) 15 24-Aug-19 09-Sep-19
A5173 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 10-Sep-19 26-Sep-19
HVAC 49 20-Jul-19 26-Sep-19
A4553 PREPARATION & SUBMISSION OFHVAC LAYOUT, BASEMENT FLOOR 30 20-Jul-19 22-Aug-19
A5193 PREPARATION & SUBMISSION OFHVAC LAYOUT, GROUND FLOOR 30 20-Jul-19 22-Aug-19
A5203 PREPARATION & SUBMISSION OFHVAC LAYOUT, FIRST FLOOR 30 20-Jul-19 22-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 8 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A5213 PREPARATION & SUBMISSION OF HVAC LAYOUT, ROOF FLOOR 30 20-Jul-19 22-Aug-19
A5223 PREPARATION & SUBMISSION OFCHILLED WATER LAYOUT, BASEMENT FL 30 20-Jul-19 22-Aug-19
A5233 PREPARATION & SUBMISSION OFCHILLED WATER LAYOUT, GROUND FLOO 30 20-Jul-19 22-Aug-19
A5243 PREPARATION & SUBMISSION OFCHILLED WATER LAYOUT, FIRST FLOOR 30 20-Jul-19 22-Aug-19
A5253 PREPARATION & SUBMISSION OFCHILLED WATER LAYOUT, ROOF FLOOR 30 20-Jul-19 22-Aug-19
A5263 PREPARATION & SUBMISSION OFSMOKE CALCULATIONS 30 20-Jul-19 22-Aug-19
A5273 PREPARATION & SUBMISSION OFSMOKE LAYOUT, BASEMENT FLOOR 30 20-Jul-19 22-Aug-19
A5283 PREPARATION & SUBMISSION OFSMOKE LAYOUT, GROUND FLOOR 30 20-Jul-19 22-Aug-19
A5293 PREPARATION & SUBMISSION OFSMOKE LAYOUT, FIRST FLOOR 30 20-Jul-19 22-Aug-19
A5303 PREPARATION & SUBMISSION OFSMOKE LAYOUT, ROOF FLOOR 30 20-Jul-19 22-Aug-19
A5313 PREPARATION & SUBMISSION OF HVAC. EQUIPMENT SCHEDULE. 30 20-Jul-19 22-Aug-19
A5543 KNPC Review / Comments ( A2 ) 15 24-Aug-19 09-Sep-19
A5553 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 10-Sep-19 26-Sep-19
ELECTRICAL 38 12-Aug-19 02-Oct-19
A4573 PREPARATION & SUBMISSION OF LEGEND & GENERAL NOTES 10 12-Aug-19 22-Aug-19
A5333 PREPARATION & SUBMISSION OFBASEMENT - LIGHTING LAYOUT 10 12-Aug-19 22-Aug-19
A5343 PREPARATION & SUBMISSION OF GROUND FLOOR - LIGHTING LAYOUT 10 12-Aug-19 22-Aug-19
A5353 PREPARATION & SUBMISSION OF FIRST FLOOR - LIGHTING LAYOUT 10 12-Aug-19 22-Aug-19
A5363 PREPARATION & SUBMISSION OFROOF - LIGHTING LAYOUT 10 12-Aug-19 22-Aug-19
A5373 PREPARATION & SUBMISSION OF BASEMENT - POWER LAYOUT 10 12-Aug-19 22-Aug-19
A5383 PREPARATION & SUBMISSION OF GROUND FLOOR - POWER LAYOUT 10 12-Aug-19 22-Aug-19
A5393 PREPARATION & SUBMISSION OF FIRST FLOOR - POWER LAYOUT 10 12-Aug-19 22-Aug-19
A5403 PREPARATION & SUBMISSION OFROOF - POWER LAYOUT 10 12-Aug-19 22-Aug-19
A5413 PREPARATION & SUBMISSION OFSCHEDULE OF POINTS 15 12-Aug-19 28-Aug-19
A5423 PREPARATION & SUBMISSION OFSCHEMATIC DIAGRAM & SCHEDULE OF L 15 12-Aug-19 28-Aug-19
A5433 PREPARATION & SUBMISSION OFTELEPHONE SYSTEM FOR FAX & DIREC 15 12-Aug-19 28-Aug-19
A5443 PREPARATION & SUBMISSION OF TELEPHONE SYSTEM FOR FAX & DIREC 15 12-Aug-19 28-Aug-19
A5453 PREPARATION & SUBMISSION OFTELEPHONE SYSTEM FOR FAX & DIREC 15 12-Aug-19 28-Aug-19
A5463 PREPARATION & SUBMISSION OF FIRE ALARM LAYOUT BASEMENT FLOO 15 12-Aug-19 28-Aug-19
A5473 PREPARATION & SUBMISSION OF FIRE ALARM LAYOUT GROUND FLOOR 15 12-Aug-19 28-Aug-19
A5483 PREPARATION & SUBMISSION OF FIRE ALARM LAYOUT FIRST FLOOR 15 12-Aug-19 28-Aug-19
A5493 PREPARATION & SUBMISSION OF SMART SYSTEM LAYOUT IN BASEMENT 15 12-Aug-19 28-Aug-19
A5503 PREPARATION & SUBMISSION OF SMART SYSTEM LAYOUT IN GROUND FL 15 12-Aug-19 28-Aug-19
A5513 PREPARATION & SUBMISSION OF SMART SYSTEM LAYOUT IN FIRST FLOO 15 12-Aug-19 28-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 9 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A5523 PREPARATION & SUBMISSION OF P.A & A.V SYSTEM LAYOUT IN BASEMEN 15 12-Aug-19 28-Aug-19
A5533 PREPARATION & SUBMISSION OF P.A & A.V SYSTEM LAYOUT IN GROUND 15 12-Aug-19 28-Aug-19
A5583 PREPARATION & SUBMISSION OF P.A & A.V SYSTEM LAYOUT IN FIRST FL 15 12-Aug-19 28-Aug-19
A5593 PREPARATION & SUBMISSION OF AUDIO VIDIO & PUBLIC ADDRESS SYSTE 15 12-Aug-19 28-Aug-19
A5603 PREPARATION & SUBMISSION OF SECURITY & TV SYSTEM BASEMENT PL 15 12-Aug-19 28-Aug-19
A5613 PREPARATION & SUBMISSION OF SECURITY & TV SYSTEM GROUND FLOO 15 12-Aug-19 28-Aug-19
A5623 PREPARATION & SUBMISSION OF SECURITY & TV SYSTEM FIRST FLOOR 15 12-Aug-19 28-Aug-19
A5633 PREPARATION & SUBMISSION OF EXTERNAL LOW VOLTAGE CABLE ROUT 15 12-Aug-19 28-Aug-19
A5634 KNPC Review / Comments ( A2 ) 15 29-Aug-19 15-Sep-19
A5635 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 16-Sep-19 02-Oct-19
Structure Assessment
Asses / Details & Lab Test 210 17-Nov-18 A 07-Sep-19
A1245 Structure Analysis 15 17-Nov-18 A 16-Jul-19
A1260 Stiffening structure elements 15 17-Jul-19 03-Aug-19
A1270 KNPC Review / Comments ( A2 ) 15 04-Aug-19 20-Aug-19
A1280 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 21-Aug-19 07-Sep-19
Liscences from Different Authorities 70 31-Jul-19 05-Nov-19
A1300 KUWAIT FIRE DIRECTORATE APPROVAL 84 31-Jul-19 05-Nov-19
A1330 KUWAIT MUNICIPALITY-TANZEEM APPROVAL 84 31-Jul-19 05-Nov-19
A1340 KUWAIT MUNICPALITY-BUILDING PERMIT 84 31-Jul-19 05-Nov-19
A1350 MEW / CIVIL DEPARTMENT FOR SUBSTATION DRAWING APPROVAL 84 31-Jul-19 05-Nov-19
A1360 MEW / HVAC DRAWING APPROVAL 84 31-Jul-19 05-Nov-19
A1370 MPW + KNPC + ENVIRONMENT (IF NEEDED) 84 31-Jul-19 05-Nov-19
Loose Furniture Design 49 20-Jul-19 26-Sep-19
MAIN BUILDING
BUILDIN 31 20-Jul-19 02-Sep-19
A1540 PREPARATION & SUBMISSION OF FURNITURE LAYOUT - BASEMENT FLOO 9 20-Jul-19 29-Jul-19
A1600 PREPARATION & SUBMISSION OF FURNITURE LAYOUT - GROUND FLOOR P 9 20-Jul-19 29-Jul-19
A1610 PREPARATION & SUBMISSION OF FURNITURE LAYOUT - FIRST FLOOR PLA 9 20-Jul-19 29-Jul-19
A1620 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1630 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1640 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1650 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1660 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1670 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1680 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 10 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...
Re-Design and Additional Works of Bait Al Wataniya Club at Messila Beach update 3-07-2019
Activity ID Activity Name Original Start Finish 2019
Duration
ar Apr M Jun Jul A S Oct N ec
A1690 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL -S 9 20-Jul-19 29-Jul-19
A1700 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1710 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1720 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAIL - 9 20-Jul-19 29-Jul-19
A1730 PREPARATION & SUBMISSION OF INTERNAL 3D VIEWS 9 20-Jul-19 29-Jul-19
A1740 PREPARATION & SUBMISSION OFSIGNAGE LAYOUT - BASEMENT FLOR PL 9 20-Jul-19 29-Jul-19
A1750 PREPARATION & SUBMISSION OFSIGNAGE LAYOUT - GROUND FLOOR PLA 9 20-Jul-19 29-Jul-19
A1760 PREPARATION & SUBMISSION OF SIGNAGE LAYOUT - FIRST FLOOR PLAN 9 20-Jul-19 29-Jul-19
A1770 PREPARATION & SUBMISSION OF SIGNAGE MISCELLANEOUS DETAILS 9 20-Jul-19 29-Jul-19
A1771 KNPC Review / Comments ( A2 ) 15 30-Jul-19 15-Aug-19
A1772 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 17-Aug-19 02-Sep-19
MULTIPURPOS HALL
MULTIPURPOSE 43 30-Jul-19 26-Sep-19
A1830 PREPARATION & SUBMISSION OF FURNITURE MISCELLANEOUS DETAILS 21 30-Jul-19 22-Aug-19
A1850 PREPARATION & SUBMISSION OF INTERNAL 3D VIEWS 21 30-Jul-19 22-Aug-19
A1900 PREPARATION & SUBMISSION OF BASEMENT FLOOR SIGNAGE LAYOUT 21 30-Jul-19 22-Aug-19
A1910 PREPARATION & SUBMISSION OF GROUND FLOOR SIGNAGE LAYOUT 21 30-Jul-19 22-Aug-19
A1920 PREPARATION & SUBMISSION OF FIRST FLOOR SIGNAGE LAYOUT 21 30-Jul-19 22-Aug-19
A1930 PREPARATION & SUBMISSION OF SIGNAGE MISCELLANEOUS DETAILS 21 30-Jul-19 22-Aug-19
A1931 KNPC Review / Comments ( A2 ) 15 24-Aug-19 09-Sep-19
A1932 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 10-Sep-19 26-Sep-19
Tender Documents
Docume 37 16-Sep-19 05-Nov-19
A3020 PREPARATION & SUBMISSION OF PROJECT SPECIFICATION 14 16-Sep-19 01-Oct-19
A3035 PREPARATION & SUBMISSION OF PROJECT PRICED BOQ 14 16-Sep-19 01-Oct-19
A3030 PREPARATION & SUBMISSION OF PROJECT BOQ 14 16-Sep-19 01-Oct-19
A3970 PREPARATION & SUBMISSION OF SCOPE OF WORK 14 16-Sep-19 01-Oct-19
A3980 PREPARATION & SUBMISSION OF FEED DRAWINGS 14 16-Sep-19 01-Oct-19
A3990 PREPARATION & SUBMISSION OF PROJECT COST 14 16-Sep-19 01-Oct-19
A3991 KNPC Review / Comments ( A2 ) 15 02-Oct-19 19-Oct-19
A3992 Incorporate KNPC Comments & KNPC Approval ( A1 ) 15 20-Oct-19 05-Nov-19
A4002 PREPARATION & FINAL SUBMISSION OF TENDER DOCUMENTS 5 31-Oct-19 05-Nov-19

KCCEC Project
Projec Closeout 25 31-Oct-19 04-Dec-19

A4030 KCCEC Project Closeout 30 31-Oct-19 04-Dec-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 11 of 11
04-Jul-19 Revised schedule
Actual Work Critical Remainin...