HANN LUX MASTER

PROGRAMME UPDATE
Activity Name Original Start Finish 2019 2020
Duration
Nov Dec Jan Feb Mar
WIDUS HOTEL & CASINO REFURBISHMENT 262 08-Aug-19 A 01-Apr-20

Casino Conversion to Ballroom 255 08-Aug-19 A 01-Apr-20

Design Consultant Procurement (RFP Process) 30 08-Aug-19 A 25-Dec-19


Recommendation,Sign-off & Award 30 08-Aug-19 A 25-Dec-19
Design Period 98 26-Dec-19 01-Apr-20
Design Review of existing Building Structure 8 26-Dec-19 02-Jan-20
Concept Design 90 03-Jan-20 01-Apr-20
Tower-1 Refurbishment 112 08-Aug-19 A 17-Mar-20

Consultant Procurement (RFP Process) 30 08-Aug-19 A 18-Dec-19


Recommendation,Sign-off & Award 30 08-Aug-19 A 18-Dec-19
Design Period (T1&T2) 90 19-Dec-19 17-Mar-20
Concept Design 90 19-Dec-19 17-Mar-20

Pre-Con Works Procurement Compl... PROGRAMME UPDATE Page 1 of 1 Date Revision Checked Approved
24-Apr-19 Widus Golf Course & Resort Dev't Master Programme
Design Construction Milesto... AS OF 22-NOV-2019 15-Nov-19 Widus Golf Course & Resort Dev't Master Programme Rev.01