CONSTRUCTION OF DAM 12-Jul-19

Activity ID Activity Name Original Duration Start Finish Physical % Total Float Q Q Q Q Q Q Q Q Q Q Q Q
Complete
J A S O ND J F M A M J J A S O N D J FM A M J J A S ON D J F M A M J
CONSTRUCTION OF DAM 1037 09-Jul-19 15-Mar-22 0 15-Mar-22, CONSTRUCTIO

PRELIMINARY PLANNING 260 09-Jul-19 27-Jul-20 0 27-Jul-20, PRELIMINARY PLANNING


A1000 Stakeholder Engagement 70 09-Jul-19* 14-Oct-19 0% 0 Stakeholder Engagement

A1010 Conceptual Design 65 30-Jul-19 28-Oct-19 0% 0 Conceptual Design

A1020 Obtain Approvals 180 29-Oct-19 27-Jul-20 0% 0 Obtain Approvals

DESIGN 80 29-Oct-19 03-Mar-20 10 03-Mar-20, DESIGN


A1030 Detailed Design 80 29-Oct-19 03-Mar-20 0% 10 Detailed Design

PRIME CONTRACTOR TENDER PROCESS 90 04-Mar-20 13-Jul-20 10 13-Jul-20, PRIME CONTRACTOR TENDER PROCESS
A1050 Two Stage Tendeing (Fixed Price Contract) 90 04-Mar-20 13-Jul-20 0% 10 Two Stage Tendeing (Fixed Price Contract)

A1040 Contract Award 0 13-Jul-20 0% 10 Contract Award,

CONSTRUCTION PHASE 385 28-Jul-20 01-Feb-22 30 01-Feb-22, CONSTRUCTION


A1060 Site Mobilization and Induction 10 28-Jul-20 10-Aug-20 0% 0 Site Mobilization and Induction

CIVIL & EARTHWORKS 335 11-Aug-20 07-Dec-21 0 07-Dec-21, CIVIL & EARTHWORK
A1070 Diversion Works 100 11-Aug-20 12-Jan-21 0% 0 Diversion Works

A1080 Survey, Site Clearing & Foundation Works 80 13-Jan-21 04-May-21 0% 0 Survey, Site Clearing & Foundation Works

A1090 Aggregate Stockpiling & Production 60 05-May-21 27-Jul-21 0% 0 Aggregate Stockpiling & Production

A1100 RCC Batching Works 50 09-Jun-21 17-Aug-21 0% 0 RCC Batching Works

A1110 RCC Placement Works 90 21-Jul-21 23-Nov-21 0% 0 RCC Placement Works

A1120 Construction of the Spillway 70 01-Sep-21 07-Dec-21 0% 0 Construction of the Spillway

MECHANICAL 40 05-May-21 29-Jun-21 115 29-Jun-21, MECHANICAL


A1130 Install Structural Platforms, Pumps & Valves 40 05-May-21 29-Jun-21 0% 115 Install Structural Platforms, Pumps & Valves

ELECTRICAL 50 05-May-21 13-Jul-21 85 13-Jul-21, ELECTRICAL


A1140 Install Transformers, Switchgears & Cable 50 05-May-21 13-Jul-21 0% 85 Install Transformers, Switchgears & Cable

INSTRUMENTATION 20 14-Jul-21 10-Aug-21 85 10-Aug-21, INSTRUMENTATION


A1150 Install Gauges, Pressure Cells & Control Cables 20 14-Jul-21 10-Aug-21 0% 85 Install Gauges, Pressure Cells & Control Ca

COMMISSIONING & TESTING 40 08-Dec-21 01-Feb-22 0 01-Feb-22, COMMISSIONING


A1160 Commissioning 40 08-Dec-21 01-Feb-22 0% 0 Commissioning

ADMIN BUILDING 250 11-Aug-20 10-Aug-21 155 10-Aug-21, ADMIN BUILDING


A1170 Auxilliary Works (Admin Building, Control Room) 250 11-Aug-20 10-Aug-21 0% 155 Auxilliary Works (Admin Building, Control Ro

PROJECT CLOSEOUT 45 02-Feb-22 15-Mar-22 0 15-Mar-22, PROJECT CLO


A1180 Submit As-Built Documents, Lessons Learned and Archiving 30 02-Feb-22 15-Mar-22 0% 0 Submit As-Built Documents,

A1190 Project Completion 0 15-Mar-22 0% 0 Project Completion,

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation