You are on page 1of 11

6/26/2021 Philippine construction productivity rates – PHILCON PRICES

Search


MENU

Philippine construction productivity rates

Philippine Manpower and Equipment Productivity Ratio


JANUARY 24, 2021 BY PHILCONPRICES

Shoring Contractor

Safe work methodology

TeamWork Engineering Open

PHILIPPINE PRODUCTIVITY RATIOS

DESCRIPTION MANHOUR/UNIT UNIT

1.STRUCTURAL EXCAVATION

Common excavation

Hand 6.00 MH/M3

Machine 0.50 MH/M3

Rock excavation 8.00 MH/M3

Hauling of spoils 1.00 MH/M3

2.STRUCTURAL BACKFILL

By hand 5.00 MH/M3

By machine 2.00 MH/M3

https://philconprices.com/tag/philippine-construction-productivity-rates/ 1/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

3.TRENCHING

By hand 6.00 MH/M3

By machine 0.50 MH/M3

EXCAVATION- MANUAL

Common earth 8.00 MH/M3

Loam of sand 1.31 MH/M3

Clay or heavy soil 1.64 MH/M3

Rock 2.63 MH/M3

EXCAVATION- MECHANICAL

Common earth 6.67 MH/M3

Rock with jack hammer 16.67 MH/M3

BACKFILLING

Common manual 0.82 MH/M3

Gravel fill manual 5.00 MH/M3

TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION MATLS MANUAL FROM:

0 – 2m Depth 1.25 MH/LM

2 – 3m Depth 1.67 MH/LM

3 – 4m Depth 2.50 MH/LM

4 – 5m Depth 3.33 MH/LM

Placing binder gravel 0.11 MH/M3

Escombro backfilling 0.21 MH/M3

Spreading,tamping & grading 0.48 MH/M2

Mechanical compaction, plate compaction 0.06 MH/M3

MANUAL CLEARING & GRUBBING

Clearing under growth & trees – 12″ 0.05 MH/M2

Clearing under growth & shrubs 0.03 MH/M2

Disposal of soil 1.69 MH/M3

https://philconprices.com/tag/philippine-construction-productivity-rates/ 2/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

Hauling of soil 1.00 MH/M3

Gravel fill 2.07 MH/M3

EXCAVATION – CRANE & CLAMPSHELL

With 8 men & 2 carpenters 1.07 MH/M3

5.ROOFING AND SIDING

Roofing

Metallic 0.97 MH/m2

Non-Metallic 1.51 MH/m2

Siding

Metallic 1.29 MH/m2

Non-Metallic 1.51 MH/m2

CONCRETE WORKS

4.CONCRETE WORKS

Grade members

Formworks 2.54 MH/M2

Concreting 8.54 MH/M3

Rebar 0.07 MH/kg

Finishing 0.40 MH/M2

Suspended members

Formworks 3.28 MH/M2

Concreting 16.70 MH/M3

Rebar 0.08 MH/kg

Finishing 0.80 MH/M2

Embeded metal 0.27 MH/kg

Water proofing 1.82 MH/M2

Joint filler 0.30 MH/lLm

PLACING CONCRETE

https://philconprices.com/tag/philippine-construction-productivity-rates/ 3/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

Slab on Fill 5.00 MH/M3

Slip Form 25.00 MH/M3

Floor Finish Unhardened 1.00 MH/M3

Concrete finished hardened 1.43 MH/M3

REBAR WORKS

Ground floor installation 0.07 MH/M3

Upper floor installation 0.08 MH/M3

Fabrication 0.10 MH/M3

Mixing manual 16.00 MH/M3

Mixing machine 1.80 MH/M3

MORE THAN  1.8 M3 POUR

Chute from truck 7.00 MH/M3

Crane & bucket 14.00 MH/M3

Wheeling 27.00 MH/M3

Finishing 2.80 MH/M3

FORMWORKS & CARPENTRY WORKS

FORM WORKS INSTALLATION

Wall on ground 2.00 MH/M2

Wall above ground 2.35 MH/M2

Beams 3.08 MH/M2

Columns 2.35 MH/M2

Suspended slab

Suspended slab 0 – 18″ 1.67 MH/M2

Suspended slab 10 – 36″ up 3.33 MH/M2

Elevated & shored slab forming

Forming only 8.60 MH/M2

Forming & Shoring 11.00 MH/M2

https://philconprices.com/tag/philippine-construction-productivity-rates/ 4/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

Wood wall & Partition 0.50 MH/M2

FORM WORKS FABRICATION

Form works fabrication 1.00 MH/M2

STRIPPING OF FORMS

Wall on ground 0.25 MH/M2

Wall above 10″ 1.29 MH/M2

Beams 1.03 MH/M2

Columns 0.85 MH/M2

Suspended slab

Suspended slab 0 – 18″ 0.83 MH/M2

Suspended slab 10 – 36″ up 1.08 MH/M2

Elevated & shored slab forming – strip of forms 3.50 MH/M2

Floor slab at grade – strip of forms 2.80 MH/M2

INSTALLATION OF CARPENTRY WORKS

Plywood partition 1.00 MH/PC

T & G Flooring and Siding 0.14 MH/B.F.

Ceiling & frame work 0.36 MH/B.F.

Siding frame work 0.27 MH/B.F.

Flooring framing 0.97 MH/B.F.

Wooden post errection 0.43 MH/B.F.

Truss Fabrication 0.35 MH/B.F.

Truss Installation 0.80 MH/B.F.

Girt Installation 0.21 MH/B.F.

Plates Installation 0.13 MH/B.F.

Purlins Installation 0.27 MH/B.F.

Fascia board Installation 0.46 MH/B.F.

1/4″ or 3/4″ thk. plywood

https://philconprices.com/tag/philippine-construction-productivity-rates/ 5/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

Cutting by manual 1.00 MH/PC

Assembly 0.42 MH/M2

ARCHITECTURAL SPECIALTIES

DOORS

Wooden 2.37 MH/M2

Steel 7.64 MH/M2

Aluminum 8.07 MH/M2

Cyclone wire 7.64 MH/M2

WINDOWS

Glass 3.23 MH/M2

Louver 4.63 MH/M2

Steel 32.29 MH/M2

PARTITIONS

single wall 2.48 MH/M2

Wooden wall 3.44 MH/M2

Wooden Louver 3.44 MH/M2

cyclone Louver 5.38 MH/M2

PAINTING ( 3 coats )

Equipment 0.24 MH/f2

Pipes 0.30 MH/f2

Miscillaneous 0.24 MH/f2

STRUCTURAL STEEL WORKS

7. STRUCTURAL STEEL

Fabrication

Light 110-130 MH/MT

Heavy 60-90 MH/MT

Errection

https://philconprices.com/tag/philippine-construction-productivity-rates/ 6/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

Light 70-100 MH/MT

Heavy 40-60 MH/MT

WELDING ( one pass only )

1- Welder and 1- Helper ( 16 total mh ) 40-50 Lf/day

G.1 STRUCTURAL STEEL

Fabrication

Heavy weight 50-90 MH/MT

Light weight 100-125 MH/MT

Grating 1 1/4″ x 3/16″ 3.0 – 3.5 MH/SF

Star threat grating 4.0 – 5.0 MH/SF

Errection

Heavy Structural teel 30 – 60 MH/MT

Light Structural steel 60- 90 MH/MT

Stacks ( Inc. full welding ) 250 – 300 MH/MT

Tanks ( Inc. full welding ) 200 – 275 MH/MT

FINISHING AND MASONRY WORKS

H. CHB

4” CHB

Laying 8.0 – 10 m2/day

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day

6” CHB

Laying 7.0 – 9.0 m2/day

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day

8” CHB

Laying 6.0 – 8.0 m2/day

https://philconprices.com/tag/philippine-construction-productivity-rates/ 7/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day

These are average productivity ratios of an average construction worker. Productivity ratios of manpower
and equipment are used in the construction industry to estimate how much time is needed to complete
a certain work.

Shoring Contractor

Safe work methodology

TeamWork Engineering Open

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

Mini Concrete Batch


Average Construction
Be a member for only
Average House

Plant Cost for Two-Story


P400 Construction Cost

Houses in the
Philippines
Philippines
Ad Haomei Machinery philconprices.com Ad Landers Superstore philconprices.com

Welding Carriage
Single Story House (w/
Bungalow Uno (36
Ceiling Construction

Manufacturer - For
two-story foundation
SQ.M.) Construction
Work Prices

different welding
provision) Materials
Price with Labor
Philippines
project Breakdown with… Estimates – Two…
Ad huawei-cutting.com philconprices.com philconprices.com philconprices.com

Share this:

https://philconprices.com/tag/philippine-construction-productivity-rates/ 8/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

       More

Like this:


Like

One blogger likes this.

 CONSTRUCTION PRODUCTIVITY RATIO, EQUIPMENT PRODUCTIVITY RATIO, PHILIPPINE CONSTRUCTION MATERIAL PRICES, PRODUCTIVITY
RATIO
 EQUIPMENT PRODUCTIVITY RATES, EQUIPMENT PRODUCTIVITY RATIO PHILIPPINES, MANPOWER PRODUCTIVITY RATES, MANPOWER
PRODUCTIVITY RATIO PHILIPPINES, PHILIPPINE CONSTRUCTION PRODUCTIVITY RATES, PRODUCTIVITY RATES
 25 COMMENTS

SUBSCRIBE TO BLOG VIA EMAIL

Enter your email address to subscribe to this blog and receive notifications of new posts by email.
Join 799 other subscribers

Email Address

SUBSCRIBE

Search …

Sort by Relevance

COLLABORATE WITH US!

https://philconprices.com/tag/philippine-construction-productivity-rates/ 9/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES

RECENT POSTS

https://philconprices.com/tag/philippine-construction-productivity-rates/ 10/11
6/26/2021 Philippine construction productivity rates – PHILCON PRICES
Region VII – Concreting Material Prices
June 26, 2021
Region VII – Painting Material Prices
May 27, 2021

RECENT COMMENTS

Nica on Average Construction Cost for…

Joy on Glazing and Curtain Wall Price…

John Hughes on Region XI – Reinforced C…

DAVE on Philippine Manpower and Equipm…

Ryan on Philippine Manpower and Equipm…

ADSENSE

https://philconprices.com/tag/philippine-construction-productivity-rates/ 11/11

You might also like