Professional Documents
Culture Documents
in PCS in KL'S
NO PARTICULAR CHB #5 CHB #4 CEMENT SAND RSB #16 RSB #12 RSB #10 RSB #7 RSB #16 RSB #12 RSB #10 RSB #7
1 Lorea 1475 pcs 150 pcs 230 bags 17.5 cu.m. - 63 140 61 - 335 518 189
2 Erica 1850 pcs 170 pcs 330 bags 28 cu.m. - 58 300 67 - 309 1110 207
3 Erica 45 2100 pcs 170 pcs 340 bags 30 cu.m. - 58 310 70 - 309 1145 216
4 Celina 2650 pcs 200 pcs 400 bags 31 cu.m. - 128 405 75 - 682 1497 232
5 Shana 220 2300 pcs 200 pcs 420 bags 33 cu.m. 71 61 415 75 670 325 1533 232
6 Shana 957 2500 pcs 200 pcs 450 bags 35 cu.m 75 66 460 75 710 352 1700 232
7 Amara 2800 pcs 250 pcs 580 bags 40 cu.m. 127 85 542 85 1200 453 2003 263
8 Bettina 3500 pcs 600 pcs 720 bags 60 cu.m 187 35 817 20 1775 187 3020 62
Prepared By:
PROJECT: Proposed Lorea
LOCATION: Kelsey Hills Subdivision, Muzon, San Jose Del Monte, Bulacan
SUBJECT: Estimates
I. EARTHWORKS
1 Excavation 12 m³ 150.00
2 Backfilling 10 m³ 120.00
3 Lay-out 1 lot 1,000.00
6 Concreting 10 m³
7 CHB Laying 140 m²
8 Plastering 280 m²
IV. FORMWORKS
1 Tie wire 8 kgs 50.00 400.00
2 C.W. Nail 4" 5 kgs 50.00 250.00
3 C.W. Nail 3" 4 kgs 48.00 192.00
4 C.W. Nail 2" 3 kgs 48.00 144.00
5 Cocolumber 2x2x10 25 pcs 105.00 2,625.00
6 Cocolumber 2x3x10 20 pcs 105.00 2,100.00
7 Plywood 1/4 thk. 8 pcs 315.00 2,520.00
8 Plywood 1/2 thk. 2 pcs 520.00 1,040.00
V DOORS & WINDOWS
1 Steel Door 2.1 x 0.8 1 sets
2 Steel Door 2.1 x 0.7 1 sets
3 PVC Door 2.1 x 0.6 2 sets 1,100.00 2,200.00
4 Steel Casement 1.2 x 1.2 4 sets 2,170.00 8,680.00
5 Steel Casement 0.9 x 0.8 -
6 Steel Casement 1.2 x 0.6 1 sets 1,440.00 1,440.00
7 Steel Casement 0.4 x 0.4 1 sets 241.00 241.00
vi.ii. Stair
1 C-Purlins 2x7x2mm 1 pcs 1,290.00 1,290.00
2 Angle Bar 2x2x4.5mm 2 pcs 960.00 1,920.00
3 G.I. Pipe 32mmØ x 6m 2 pcs 500.00 1,000.00
4 Square Bar 10x6mx10mm 1 pcs 170.00 170.00
5 Welding Rod 5 kgs 62.50 312.50
X. TILE WORKS
x.i. Ground Floor
1 Tiles 0.3 x 0.3 235 pcs 32.00 7,520.00
2 Tile Grout 3 kgs 60.00 180.00
1,800.00 1,800.00
1,200.00 1,200.00
1,000.00 1,000.00
-
-
12,168.75
1,125.00
47,150.00
8,750.00
7,400.00
-
-
-
-
-
-
37.00 12,395.00 12,395.00
37.00 19,166.00 19,166.00
- -
37.00 6,993.00 6,993.00
1,950.00 1,950.00 1,950.00
-
6,594.00 6,594.00
-
400.00
250.00
192.00
144.00
2,625.00
2,100.00
2,520.00
1,040.00
-
-
-
14,000.00 14,000.00 14,000.00
12,000.00 12,000.00 12,000.00
2,200.00
8,680.00
-
1,440.00
241.00
-
-
-
-
4,356.00
960.00
125.00
170.00 340.00 340.00
-
-
1,290.00
1,920.00
1,000.00
170.00
312.50
-
-
-
1,800.00 7,200.00 7,200.00
310.00 620.00 620.00
310.00 1,860.00 1,860.00
310.00 1,240.00 1,240.00
310.00 1,240.00 1,240.00
297.50
60.00
60.00
125.00
1,200.00
795.00
-
-
-
5,460.00
800.00
60.00
55.00
2,375.00
380.00
60.00
800.00
300.00
-
-
-
9,828.00
3,480.00
75.00
-
3,300.00
-
-
-
-
7,520.00
180.00
-
-
-
2,475.00
600.00
1,125.00
120.00
120.00
-
-
-
3,200.00
225.00
3,000.00
-
-
360.00
12,000.00 12,000.00 12,000.00
320.00
190.00
200.00 200.00 200.00
200.00 200.00 200.00
700.00 700.00 700.00
2,800.00 2,800.00 2,800.00
540.00 540.00 540.00
120.00 120.00 120.00
100.00 100.00 100.00
130.00
40.00
-
-
-
8,000.00 8,000.00
-
-
-
-
-
-
-
-
450.00 3,600.00 3,600.00
540.00 3,240.00 3,240.00
45.00
225.00
230.00
155.00
320.00
160.00
105.00
60.00
60.00
50.00
40.00
52.00
26.00
120.00
-
-
-
86.00 344.00 344.00
70.00 1,470.00 1,470.00
18.00 36.00 36.00
15.00 300.00 300.00
15.00 225.00 225.00
15.00 15.00 15.00
1,425.00
900.00
1,170.00
136.00
204.00
184.00
30.00
75.00
36.00
165.00
165.00
1,700.00
-
-
335.00 2,512.50 2,512.50
240.00 960.00 960.00
150.00 600.00 600.00
65.00 65.00 65.00
55.00 165.00 165.00
24.00 120.00 120.00
55.00 440.00 440.00
30.00 120.00 120.00
65.00 130.00 130.00
48.00 192.00 192.00
65.00 390.00 390.00
85.00 85.00 85.00
55.00 165.00 165.00
90.00
316.00 1,580.00 1,580.00
15.00 30.00 30.00
142.00 710.00 710.00
21.00 84.00 84.00
119.00 119.00 119.00
144.00 288.00 288.00
114.00 228.00 228.00
11.00 33.00 33.00
11.00 11.00 11.00
18.00 18.00 18.00
20.00 60.00 60.00
20.00 60.00 60.00
20.00 40.00 40.00
- - -
50,000.00 50,000.00
I. Earth Works
1 Excavation 12 m³ 150.00
2 Backfilling 7 m³ 120.00
3 Lay-out 1 lot 1,200.00
6 Concreting m³
7 CHB Laying m²
8 Plastering m²
IV. FORMWORKS
1 Tie wire 15 kgs 55.00 825.00
2 C.W. Nail 4" 3 kgs 55.00 165.00
3 C.W. Nail 3" 5 kgs 55.00 275.00
4 C.W. Nail 2" 5 kgs 55.00 275.00
5 Cocolumber 2x2x10 35 pcs 105.00 3,675.00
6 Cocolumber 2x3x10 30 pcs 105.00 3,150.00
7 Plywood 1/4 thk. 20 pcs 355.00 7,100.00
8 Plywood 1/2 thk. 5 pcs 630.00 3,150.00
vi.ii. Stair
1 Wood Handrail 2x3x10 1 pcs 600.00 600.00
2 Wood Handrail 2x3x7 1 pcs 520.00 520.00
3 Flat Bar 1x6mmx6m 2 pcs 150.00 300.00
4 Square Bar 1/2x1/2x6m 3 pcs 170.00 510.00
5 Angle Bar 2x2x6x3mm 1 pcs 900.00 900.00
6 Welding Rod 2 kgs 65.00 130.00
7 Hardiflex Screw 1 20 pcs 1.00 20.00
X. TILE WORKS
x.i. Ground Floor
1 Tiles 0.3 x 0.3 220 pcs 32.00 7,040.00
2 Tile Grout 4 kgs 60.00 240.00
-
-
x.ii. C.R. Tiles -
1 Wall Tiles Plain 0.2x0.2 165 pcs 15.00 2,475.00
2 Wall Tiles Accent 0.2x0.2 40 pcs 15.00 600.00
3 Floor Tiles 0.2x0.2 75 pcs 15.00 1,125.00
4 Tile Grout 3 kgs 60.00 180.00
5 Tile Trim 5 pcs 30.00 150.00
-
-
x.iii. 2nd Floor Tiles -
1 Tiles 0.3 x 0.3 230 pcs 32.00 7,360.00
2 Tile Grout 4 kgs 65.00 260.00
-
-
x.iv Stair Tiles -
1 Step tiles 0.3x0.28 43 pcs -
2 Riser tiles 0.3x0.18 42 pcs -
3 Tile Grout 2 kgs 65.00 130.00
-
-
XI. CARPENTRY WORKS -
1 Door Knob 2 sets 180.00 360.00
2 Modular Kitchen 1 sets
3 Shower Valve 1 sets 320.00 320.00
4 Shower Head 1 sets 190.00 190.00
5 Tissue Holder 1 sets
6 Soap Holder 1 sets
7 Lavatory 1 sets
8 Water Closet 1 sets
9 Plumbing Accessories 1 sets
10 Kitchen Faucet 1 sets
11 Brass Faucet 1 sets
12 Floor Drain 2 sets 65.00 130.00
13 Faucet at Garage pcs
14 Teflon Tape 2 pcs 10.00 20.00
15 Artificial Stone (Canyon Stone) 4 box 1,500.00 6,000.00
1,800.00 1,800.00
840.00 840.00
1,200.00 1,200.00
-
-
15,262.50
1,275.00
67,650.00
14,000.00
10,360.00
-
-
-
-
-
-
37.00 11,433.00 11,433.00
37.00 40,700.00 40,700.00
37.00 - -
37.00 7,659.00 7,659.00
1,950.00 1,950.00 1,950.00
-
11,550.00 11,550.00
-
-
825.00
165.00
275.00
275.00
3,675.00
3,150.00
7,100.00
3,150.00 18,615.00
-
-
-
14,000.00 14,000.00 14,000.00
12,000.00 12,000.00 12,000.00
2,200.00
3,255.00
-
1,440.00
241.00
-
-
-
-
3,366.00
1,920.00
125.00
340.00
-
-
-
600.00
520.00
300.00
510.00
900.00
130.00
20.00
-
-
-
1,373.00 4,119.00 4,119.00
1,519.00 1,519.00 1,519.00
310.00 620.00 620.00
310.00 1,240.00 1,240.00
310.00 1,860.00 1,860.00
310.00 1,240.00 1,240.00
297.50
60.00
75.00
250.00
600.00
795.00
-
-
-
-
1,350.00
300.00
-
75.00
110.00
2,500.00
418.00
60.00
400.00
450.00
-
-
-
8,000.00 16,000.00 16,000.00
6,750.00
1,700.00
10,500.00
180.00
-
-
-
-
7,040.00
240.00
-
-
-
2,475.00
600.00
1,125.00
180.00
150.00
-
-
-
7,360.00
260.00
-
-
-
-
-
130.00
-
-
-
360.00
12,000.00 12,000.00 12,000.00
- 320.00
- 190.00
200.00 200.00 200.00
200.00 200.00 200.00
700.00 700.00 700.00
2,800.00 2,800.00 2,800.00
540.00 540.00 540.00
120.00 120.00 120.00
100.00 100.00 100.00
130.00
210.00 - -
20.00
6,000.00
-
-
-
8,000.00
-
4,500.00
4,500.00
-
-
-
-
-
-
-
450.00 6,750.00 6,750.00
540.00 4,860.00 4,860.00
90.00
225.00
57.50
155.00
160.00
2,940.00
160.00
105.00
96.00
96.00
75.00
60.00
78.00
39.00
90.00
-
-
-
86.00 344.00 344.00
70.00 1,330.00 1,330.00
18.00 54.00 54.00
15.00 150.00 150.00
15.00 75.00 75.00
15.00 45.00 45.00
1,800.00
1,200.00
1,350.00
272.00
306.00
207.00
105.00
135.00
100.00
36.00
225.00
270.00
1,700.00
-
-
-
335.00 2,512.50 2,512.50
240.00 960.00 960.00
150.00 600.00 600.00
65.00 65.00 65.00
55.00 275.00 275.00
24.00 120.00 120.00
55.00 440.00 440.00
30.00 90.00 90.00
65.00 130.00 130.00
48.00 192.00 192.00
65.00 325.00 325.00
85.00 85.00 85.00
55.00 165.00 165.00
40.00 - -
90.00
316.00 1,580.00 1,580.00
15.00 30.00 30.00
142.00 568.00 568.00
21.00 63.00 63.00
119.00 119.00 119.00
144.00 288.00 288.00
114.00 228.00 228.00
11.00 22.00 22.00
11.00 - -
18.00 18.00 18.00
20.00 80.00 80.00
20.00 60.00 60.00
20.00 40.00 40.00
- -
120,000.00 120,000.00
135,390.00 153,663.50 514,756.00
PROJECT: Proposed Celina
LOCATION: Kelsey Hills Subdivision, Muzon, San Jose Del Monte, Bulacan
SUBJECT: Estimates
I. Earth Works
1 Excavation 16 m³ 150.00
2 Backfilling 10 m³ 120.00
3 Lay-out 1 lot 1,000.00
6 Concreting 10 m³
7 CHB Laying 140 m²
8 Plastering 280 m²
IV. FORMWORKS
1 Tie wire 30 kgs 50.00 1,500.00
2 C.W. Nail 4" 10 kgs 50.00 500.00
3 C.W. Nail 3" 10 kgs 48.00 480.00
4 C.W. Nail 2" 10 kgs 48.00 480.00
5 Cocolumber 2x2x10 90 pcs 105.00 9,450.00
6 Cocolumber 2x3x10 60 pcs 105.00 6,300.00
7 Plywood 1/4 thk. 25 pcs 315.00 7,875.00
8 Plywood 1/2 thk. 20 pcs 520.00 10,400.00
vi.ii. Stair
1 Wood Handrail 2x3x10 1 pcs 600.00 600.00
2 Wood Handrail 2x3x8 1 pcs 520.00 520.00
3 Flat Bar 1x6mmx6m 3 pcs 150.00 450.00
4 Square Bar 1/2x1/2x6m 5 pcs 170.00 850.00
5 Angle Bar 2x2x6x3mm 2 pcs 900.00 1,800.00
6 Welding Rod 2 kgs 65.00 130.00
7 Hardiflex Screw 1 20 pcs 1.00 20.00
X. TILE WORKS
x.i. Ground Floor -
1 Tiles 0.3 x 0.3 260 pcs 32.00 8,320.00
2 Tile Grout 5 kgs 60.00 300.00
-
-
x.ii. C.R. Tiles -
1 Wall Tiles Plain 0.2x0.2 372 pcs 15.00 5,580.00
2 Wall Tiles Accent 0.2x0.2 520 pcs 15.00 7,800.00
3 Floor Tiles 0.2x0.2 120 pcs 15.00 1,800.00
4 Tile Grout 12 kgs 60.00 720.00
5 Tile Trim 12 pcs 30.00 360.00
-
-
x.iii. 2nd Floor Tiles -
1 Tiles 0.3 x 0.3 340 pcs 32.00 10,880.00
2 Tile Grout 7 bot 65.00 455.00
-
-
x.iv Stair Tiles -
1 Floor tiles 0.3x0.3 85 pcs 32.00 2,720.00
2 Rubber Nosing 2x2x3 6 pcs 215.00 1,290.00
3 Rugby 2 bot 70.00 140.00
4 Tile Grout 2 kgs 65.00 130.00
-
-
XI. CARPENTRY WORKS -
1 Door Knob 5 sets 180.00 900.00
2 Modular Kitchen 1 sets
3 Shower Valve 2 sets 320.00 640.00
4 Shower Head 2 sets 190.00 380.00
5 Tissue Holder 2 sets
6 Soap Holder 2 sets
7 Lavatory 2 sets
8 Water Closet 2 sets
9 Plumbing Accessories 2 sets
10 Kitchen Faucet 1 sets
11 Brass Faucet 2 sets
12 Floor Drain 2 sets
13 Faucet at Garage 1 pcs
14 Teflon Tape 4 pcs 10.00 40.00
15 Artificial Stone (Canyon Stone) 2 box 1,500.00 3,000.00
2,400.00 2,400.00
1,200.00 1,200.00
1,000.00 1,000.00
-
-
21,862.50
1,500.00
82,000.00
15,500.00
13,690.00
-
-
-
-
-
-
37.00 25,234.00 25,234.00
37.00 55,389.00 55,389.00
37.00 - -
37.00 8,584.00 8,584.00
1,950.00 2,925.00 2,925.00
-
16,877.00 16,877.00
-
-
1,500.00
500.00
480.00
480.00
9,450.00
6,300.00
7,875.00
10,400.00 36,985.00
-
-
-
14,000.00 14,000.00 14,000.00
12,000.00 12,000.00 12,000.00
2,200.00
5,425.00
1,440.00
241.00
-
-
-
-
9,240.00
3,840.00
125.00
340.00
-
-
-
600.00
520.00
450.00
850.00
1,800.00
130.00
20.00
-
-
-
1,800.00 5,400.00 5,400.00
1,800.00 1,800.00 1,800.00
310.00 620.00 620.00
310.00 2,170.00 2,170.00
310.00 2,170.00 2,170.00
310.00 1,860.00 1,860.00
350.00
60.00
75.00
250.00
1,200.00
1,590.00
-
-
-
7,980.00
400.00
75.00
110.00
4,375.00
1,140.00
150.00
800.00
150.00
-
-
-
8,000.00 24,000.00 24,000.00
8,250.00
800.00
11,760.00
180.00
-
-
-
-
8,320.00
300.00
-
-
-
5,580.00
7,800.00
1,800.00
720.00
360.00
-
-
-
10,880.00
455.00
-
-
-
2,720.00
1,290.00
140.00
130.00
-
-
-
900.00
12,000.00 12,000.00 12,000.00
- 640.00
- 380.00
200.00 400.00 400.00
200.00 400.00 400.00
700.00 1,400.00 1,400.00
2,800.00 5,600.00 5,600.00
540.00 1,080.00 1,080.00
120.00 120.00 120.00
100.00 200.00 200.00
65.00 130.00 130.00
210.00 210.00 210.00
40.00
3,000.00
-
-
-
8,000.00
-
4,500.00
4,500.00
-
-
-
-
-
-
450.00 9,450.00 9,450.00
540.00 8,100.00 8,100.00
22.50
225.00
57.50
155.00
160.00
490.00
160.00
105.00
60.00
60.00
50.00
40.00
52.00
26.00
120.00
-
-
-
86.00 430.00 430.00
70.00 1,820.00 1,820.00
18.00 54.00 54.00
15.00 225.00 225.00
15.00 90.00 90.00
15.00 45.00 45.00
2,400.00
1,600.00
1,440.00
204.00
374.00
253.00
90.00
75.00
100.00
36.00
240.00
240.00
1,700.00
-
-
-
335.00 3,350.00 3,350.00
240.00 840.00 840.00
150.00 675.00 675.00
65.00 195.00 195.00
55.00 165.00 165.00
24.00 240.00 240.00
55.00 330.00 330.00
30.00 120.00 120.00
65.00 195.00 195.00
48.00 144.00 144.00
65.00 520.00 520.00
85.00 255.00 255.00
55.00 165.00 165.00
40.00 80.00 80.00
90.00
316.00 2,528.00 2,528.00
15.00 120.00 120.00
142.00 994.00 994.00
21.00 126.00 126.00
119.00 238.00 238.00
144.00 576.00 576.00
114.00 456.00 456.00
11.00 33.00 33.00
11.00 11.00 11.00
18.00 18.00 18.00
20.00 80.00 80.00
20.00 60.00 60.00
20.00 40.00 40.00
- -
210,000.00 210,000.00
I. EARTHWORKS
1 Excavation 12 m³ 150.00
2 Backfilling 10 m³ 120.00
3 Lay-out 1 lot 2,500.00
6 Concreting m³
7 CHB Laying m²
8 Plastering m²
IV. FORMWORKS
1 Tie wire 30 kgs 50.00 1,500.00
2 C.W. Nail 4" 15 kgs 50.00 750.00
3 C.W. Nail 3" 10 kgs 48.00 480.00
4 C.W. Nail 2" 5 kgs 48.00 240.00
5 Cocolumber 2x2x10 70 pcs 105.00 7,350.00
6 Cocolumber 2x3x10 50 pcs 105.00 5,250.00
7 Plywood 1/4 thk. 50 pcs 315.00 15,750.00
8 Plywood 1/2 thk. 10 pcs 520.00 5,200.00
vi.ii. Stair
1 Flat Bar 6mx3mmx1in 2 pcs 1,290.00 2,580.00
2 Angle Bar 2x2x6m 2 pcs 960.00 1,920.00
3 Angle Bar1/ 2x1/2x6m 2 pcs 500.00 1,000.00
4 Square Bar 10x6mx10mm 3 pcs 170.00 510.00
5 Welding Rod 2 kgs 62.50 125.00
6 Metal Primer Gray 1 qrt 115.00 115.00
7 Wood Handrail 2x3x6 1 pcs 450.00 450.00
8 Wood Handrail 2x3x3 1 pcs 300.00 300.00
9 PAINT Brush 2" 3 pcs 25.00 75.00
10 Paint Thinner 1 bot 30.00 30.00
X. TILE WORKS
x.i. Ground Floor
1 Tiles 0.3 x 0.3 340 pcs 32.00 10,880.00
2 Tile Grout 8 kgs 60.00 480.00
-
-
x.ii. C.R. Tiles -
GF & 2F -
1 Wall Tiles Plain 0.2x0.2 800 pcs 15.00 12,000.00
2 Wall Tiles Accent 0.2x0.2 250 pcs 15.00 3,750.00
3 Floor Tiles 0.2x0.2 140 pcs 15.00 2,100.00
4 Tile Grout 5 kgs 60.00 300.00
5 Tile Trim 10 pcs 30.00 300.00
-
-
Vinyl Tiles @ 2f -
1 Vinyl Tiles 0.3x0.3 450 pcs 45.00 20,250.00
2 Plaster Bond 3 gals 500.00 1,500.00
-
-
Stair Tiles -
1 Tiles 0.3x0.3 85 pcs 35.00 2,975.00
2 Tile Grout 1.5 bag 60.00 90.00
3 Rubber Nozzing 2.4 Gray 6 pcs 215.00 1,290.00
4 Rugby 2 bot 45.00 90.00
-
-
XI. CARPENTRY WORKS -
1 Door Knob 5 sets 180.00 900.00
2 Modular Kitchen 1 sets
3 Shower Valve 2 sets 320.00 640.00
4 Shower Head 2 sets 190.00 380.00
5 Tissue Holder 2 sets
6 Soap Holder 2 sets
7 Lavatory 2 sets
8 Water Closet 2 sets
9 Plumbing Accessories 2 sets
10 Kitchen Faucet 1 sets
11 Brass Faucet 2 sets
12 Floor Drain 2 sets 65.00 130.00
13 Teflon Tape 10 pcs 10.00 100.00
14 Canyon Stone 14 box 1,500.00 21,000.00
1,800.00 1,800.00
1,200.00 1,200.00
2,500.00 2,500.00
-
-
18,975.00
1,500.00
86,100.00
16,500.00
16,650.00
-
-
-
-
-
-
37.00 24,790.00 24,790.00
37.00 12,025.00 12,025.00
37.00 56,721.00 56,721.00
37.00 8,584.00 8,584.00
1,950.00 3,900.00 3,900.00
-
17,430.00 17,430.00
-
-
1,500.00
750.00
480.00
240.00
7,350.00
5,250.00
15,750.00
5,200.00 36,520.00
-
-
-
14,000.00 14,000.00 14,000.00
12,000.00 12,000.00 12,000.00
8,000.00 24,000.00 24,000.00
2,200.00
4,340.00
1,300.00
241.00
-
-
-
-
4,950.00
125.00
680.00
230.00
600.00
70.00
-
-
-
2,580.00
1,920.00
1,000.00
510.00
125.00
115.00
450.00
300.00
75.00
30.00
-
-
-
850.00 10,200.00 10,200.00
580.00 3,770.00 3,770.00
310.00 1,395.00 1,395.00
310.00 1,550.00 1,550.00
310.00 1,860.00 1,860.00
580.00 1,740.00 1,740.00
580.00 1,160.00 1,160.00
490.00
138.00
60.00
250.00
1,200.00
1,590.00
-
-
-
7,980.00
800.00
300.00
110.00
4,375.00
950.00
1,500.00
180.00
800.00
300.00
-
-
-
6,000.00
5,040.00
90.00
250.00
150.00
-
-
-
-
10,880.00
480.00
-
-
-
-
12,000.00
3,750.00
2,100.00
300.00
300.00
-
-
-
20,250.00
1,500.00
-
-
-
2,975.00
90.00
1,290.00
90.00
-
-
-
900.00
12,000.00 12,000.00 12,000.00
640.00
380.00
-
-
-
-
-
-
-
130.00
100.00
21,000.00
-
-
-
-
-
-
20,000.00
-
-
-
-
-
-
-
-
-
450.00 10,350.00 10,350.00
540.00 10,260.00 10,260.00
45.00
450.00
115.00
155.00
160.00
105.00
120.00
120.00
50.00
40.00
52.00
39.00
150.00
-
-
-
86.00 430.00 430.00
70.00 1,610.00 1,610.00
18.00 54.00 54.00
15.00 300.00 300.00
15.00 150.00 150.00
15.00 30.00 30.00
3,000.00
1,700.00
1,440.00
272.00
374.00
368.00
90.00
105.00
54.00
300.00
345.00
1,700.00
160.00
90.00
-
-
-
335.00 3,182.50 3,182.50
240.00 1,680.00 1,680.00
150.00 900.00 900.00
65.00 195.00 195.00
55.00 275.00 275.00
24.00 288.00 288.00
55.00 605.00 605.00
30.00 180.00 180.00
65.00 130.00 130.00
48.00 240.00 240.00
65.00 390.00 390.00
85.00 255.00 255.00
55.00 165.00 165.00
180.00
316.00 2,212.00 2,212.00
15.00 120.00 120.00
142.00 1,278.00 1,278.00
21.00 168.00 168.00
119.00 238.00 238.00
144.00 576.00 576.00
114.00 456.00 456.00
11.00 55.00 55.00
11.00 11.00 11.00
18.00 -
20.00 60.00 60.00
20.00 60.00 60.00
20.00 60.00 60.00
-
210,000.00 210,000.00
I. EARTHWORKS
1 Excavation 14 m³ 150.00
2 Backfilling 8 m³ 120.00
3 Lay-out 1 lot 2,500.00
6 Concreting m³
7 CHB Laying m²
8 Plastering m²
IV. FORMWORKS
1 Tie wire 30 kgs 50.00 1,500.00
2 C.W. Nail 4" 15 kgs 50.00 750.00
3 C.W. Nail 3" 10 kgs 48.00 480.00
4 C.W. Nail 2" 5 kgs 48.00 240.00
5 Cocolumber 2x2x10 70 pcs 105.00 7,350.00
6 Cocolumber 2x3x10 50 pcs 105.00 5,250.00
7 Plywood 1/4 thk. 50 pcs 315.00 15,750.00
8 Plywood 1/2 thk. 10 pcs 520.00 5,200.00
vi.ii. Stair
1 Flat Bar 6mx3mmx1in 2 pcs 1,290.00 2,580.00
2 Angle Bar 2x2x6m 2 pcs 960.00 1,920.00
3 Angle Bar1/ 2x1/2x6m 2 pcs 500.00 1,000.00
4 Square Bar 10x6mx10mm 3 pcs 170.00 510.00
5 Welding Rod 2 kgs 62.50 125.00
6 Metal Primer Gray 1 qrt 115.00 115.00
7 Wood Handrail 2x3x6 1 pcs 450.00 450.00
8 Wood Handrail 2x3x3 1 pcs 300.00 300.00
9 PAINT Brush 2" 3 pcs 25.00 75.00
10 Paint Thinner 1 bot 30.00 30.00
-
-
VII. ROOFING WORKS -
1 Roof Sheet 4.2m 12 pcs
2 Box Gutter 2.4m 6 pcs
3 End Flashing 3.5 pcs
4 Wall Flashing 3.5 pcs
5 Wall Capping 0.2 5 pcs
6 Ridge Roll 3 pcs
7 Valley Gutter 2 pcs
8 Tekscrew 280 pcs 1.75 490.00
9 Blind Revits 230 pcs 0.60 138.00
10 Hardiflex Screw 1 1/2" 40 pcs 1.50 60.00
11 Sealant 2 pcs 125.00 250.00
12 Fascia Board 1/4" 2 pcs 600.00 1,200.00
13 Insulation 1 roll 1,590.00 1,590.00
X. TILE WORKS
x.i. Ground Floor
1 Tiles 0.3 x 0.3 340 pcs 32.00 10,880.00
2 Tile Grout 8 kgs 60.00 480.00
2,100.00 2,100.00
960.00 960.00
2,500.00 2,500.00
-
-
20,625.00
1,500.00
92,250.00
17,500.00
18,500.00
-
-
-
-
-
-
37.00 26,270.00 26,270.00
37.00 13,024.00 13,024.00
37.00 62,900.00 62,900.00
37.00 8,584.00 8,584.00
1,950.00 3,900.00 3,900.00
-
17,430.00 17,430.00
-
-
1,500.00
750.00
480.00
240.00
7,350.00
5,250.00
15,750.00
5,200.00 36,520.00
-
-
-
14,000.00 14,000.00 14,000.00
12,000.00 12,000.00 12,000.00
8,000.00 24,000.00 24,000.00
2,200.00
4,340.00
1,300.00
241.00
-
-
-
-
3,960.00
125.00
340.00
230.00
-
35.00
-
-
-
2,580.00
1,920.00
1,000.00
510.00
125.00
115.00
450.00
300.00
75.00
30.00
-
-
-
850.00 10,200.00 10,200.00
580.00 3,480.00 3,480.00
310.00 1,085.00 1,085.00
310.00 1,085.00 1,085.00
310.00 1,550.00 1,550.00
580.00 1,740.00 1,740.00
580.00 1,160.00 1,160.00
490.00
138.00
60.00
250.00
1,200.00
1,590.00
-
-
-
7,980.00
350.00
300.00
110.00
4,375.00
950.00
1,500.00
120.00
800.00
300.00
-
-
-
6,000.00
8,400.00
300.00
1,500.00
150.00
-
-
-
-
-
10,880.00
480.00
-
-
-
-
12,000.00
3,750.00
2,100.00
300.00
300.00
-
-
-
20,250.00
1,500.00
-
-
-
2,975.00
90.00
1,290.00
90.00
-
-
-
540.00
12,000.00 12,000.00 12,000.00
- 640.00
- 380.00
200.00 400.00 400.00
200.00 400.00 400.00
700.00 1,400.00 1,400.00
2,800.00 5,600.00 5,600.00
540.00 1,080.00 1,080.00
120.00 120.00 120.00
100.00 200.00 200.00
130.00
100.00
21,000.00
-
-
-
-
-
-
20,000.00
-
-
-
-
-
-
-
-
-
450.00 10,350.00 10,350.00
540.00 10,260.00 10,260.00
45.00
450.00
115.00
155.00
160.00
105.00
120.00
120.00
50.00
40.00
52.00
39.00
150.00
-
-
-
86.00 344.00 344.00
70.00 1,750.00 1,750.00
18.00 54.00 54.00
15.00 300.00 300.00
15.00 150.00 150.00
15.00 30.00 30.00
3,000.00
1,700.00
1,440.00
408.00
476.00
368.00
75.00
150.00
54.00
300.00
345.00
1,700.00
200.00
90.00
-
-
-
335.00 4,020.00 4,020.00
240.00 1,200.00 1,200.00
150.00 750.00 750.00
65.00 195.00 195.00
55.00 330.00 330.00
24.00 288.00 288.00
55.00 550.00 550.00
30.00 180.00 180.00
65.00 130.00 130.00
48.00 240.00 240.00
65.00 455.00 455.00
85.00 255.00 255.00
55.00 165.00 165.00
180.00
316.00 2,528.00 2,528.00
15.00 105.00 105.00
142.00 1,278.00 1,278.00
21.00 168.00 168.00
119.00 238.00 238.00
144.00 576.00 576.00
114.00 456.00 456.00
11.00 55.00 55.00
11.00 11.00 11.00
18.00 - -
20.00 60.00 60.00
20.00 60.00 60.00
20.00 60.00 60.00
-
230,000.00 230,000.00
I. EARTHWORKS
1 Excavation 827.7494 m³
2 Backfilling
2.1 ordinary soil 302.1867 m³
2.2 S1 sand m³ 45.00
I. EARTHWORKS
a. Excavation m³ 102.28 500.00 51,140.00 51,140.00
b. Backfilling m³ 189.11 150.00 28,366.50 28,366.50
I. EARTHWORKS
1 Excavation 23 m³ 150.00
2 Backfilling 18 m³ 120.00
3 Lay-out 1 lot 2,000.00
6 Concreting m³
7 CHB Laying m²
8 Plastering m²
IV. FORMWORKS
1 Tie wire 30 kgs 50.00 1,500.00
2 C.W. Nail 4" 15 kgs 50.00 750.00
3 C.W. Nail 3" 10 kgs 48.00 480.00
4 C.W. Nail 2" 5 kgs 48.00 240.00
5 Cocolumber 2x2x10 100 pcs 105.00 10,500.00
6 Cocolumber 2x3x10 60 pcs 105.00 6,300.00
7 Plywood 1/4 thk. 50 pcs 315.00 15,750.00
8 Plywood 1/2 thk. 10 pcs 520.00 5,200.00
9 Labor Cost m²
vi.ii. Stair
1 Flat Bar 6mx3mmx1in 1 pcs 1,290.00 1,290.00
2 Angle Bar 2x2x6m 2 pcs 960.00 1,920.00
3 Angle Bar1/ 2x1/2x6m 2 pcs 500.00 1,000.00
4 Square Bar 10x6mx10mm 1 pcs 170.00 170.00
5 Welding Rod 5 kgs 62.50 312.50
6 Metal Primer Gray 1 qrt 115.00 115.00
7 Wood Handrail 2x3x6 1 pcs 450.00 450.00
8 Wood Handrail 2x3x3 1 pcs 300.00 300.00
9 PAINT Brush 2" 3 pcs 25.00 75.00
10 Paint Thinner 1 bot 30.00 30.00
14 Labor Cost m²
13 Labor Cost m²
3,450.00 3,450.00
2,160.00 2,160.00
2,000.00 2,000.00
-
-
23,100.00
1,875.00
118,900.00
20,000.00
21,460.00
-
-
-
-
-
-
44,400.00
16,761.00
74,111.00
-
9,731.00
1,950.00
-
27,433.00 27,433.00
-
-
1,500.00
750.00
480.00
240.00
10,500.00
6,300.00
15,750.00
5,200.00 40,720.00
-
-
-
-
14,000.00 14,000.00 14,000.00
12,000.00 12,000.00 12,000.00
8,000.00 24,000.00 24,000.00
- 1,000.00
- 3,300.00
- 6,510.00
- 1,300.00
- 482.00
- -
- -
- -
- -
- -
198.00 792.00 1,386.00
3,630.00
960.00
125.00
510.00
230.00
35.00
-
-
-
-
1,290.00
1,920.00
1,000.00
170.00
312.50
115.00
450.00
300.00
75.00
30.00
-
-
-
-
450.00 1,350.00 1,350.00
850.00 13,600.00 13,600.00
580.00 3,770.00 3,770.00
310.00 1,705.00 1,705.00
310.00 2,480.00 2,480.00
310.00 1,860.00 1,860.00
580.00 2,320.00 2,320.00
580.00 1,160.00 1,160.00
490.00
120.00
225.00
250.00
1,200.00
2,385.00
-
-
-
-
2,100.00
400.00
300.00
110.00
4,375.00
950.00
1,500.00
240.00
800.00
300.00
-
-
-
-
6,000.00
8,400.00
360.00
900.00
150.00
-
-
-
-
-
11,200.00
480.00
-
-
-
-
-
2,400.00
600.00
900.00
120.00
120.00
-
12,600.00
2,100.00
2,100.00
240.00
300.00
-
-
-
-
11,925.00
1,500.00
-
-
-
-
3,500.00
120.00
1,505.00
90.00
-
-
-
-
1,260.00
12,000.00 12,000.00 12,000.00
960.00
570.00
200.00 600.00 600.00
200.00 600.00 600.00
700.00 1,400.00 1,400.00
2,800.00 8,400.00 8,400.00
540.00 1,620.00 1,620.00
120.00 120.00 120.00
100.00 300.00 300.00
65.00
100.00
4,500.00
-
-
-
-
-
-
-
20,000.00
-
-
-
-
-
-
-
-
-
-
12,150.00
11,880.00
45.00
450.00
115.00
155.00
160.00
105.00
120.00
120.00
50.00
40.00
52.00
39.00
180.00
-
-
-
-
86.00 344.00 344.00
70.00 2,240.00 2,240.00
18.00 54.00 54.00
15.00 300.00 300.00
15.00 150.00 150.00
15.00 30.00 30.00
4,725.00
2,200.00
1,575.00
408.00
510.00
368.00
150.00
120.00
54.00
300.00
345.00
1,700.00
240.00
90.00
2,000.00
-
-
-
-
335.00 4,690.00 4,690.00
240.00 1,440.00 1,440.00
150.00 750.00 750.00
65.00 325.00 325.00
55.00 550.00 550.00
24.00 216.00 216.00
55.00 550.00 550.00
30.00 90.00 90.00
65.00 195.00 195.00
48.00 288.00 288.00
65.00 455.00 455.00
85.00 255.00 255.00
55.00 220.00 220.00
180.00
316.00 2,844.00 2,844.00
15.00 120.00 120.00
142.00 1,420.00 1,420.00
21.00 168.00 168.00
119.00 357.00 357.00
144.00 864.00 864.00
114.00 684.00 684.00
11.00 44.00 44.00
11.00 11.00 11.00
18.00 - -
20.00 80.00 80.00
20.00 60.00 60.00
20.00 40.00 40.00
- -
260,000.00 260,000.00
1 EARTH WORKS:
1 EXCAVATION 24.65 m³ 250.00
2 BACKFILLING 17.35 m³ 200.00
3 LAY-OUT 1.00 LOT 12,952.00
2 STEEL WORKS
1 16mmØ X 6.0m 1,775.00 kls
2 12mmØ X 6.0m 187.00 kls
3 10mmØ X 6.0m 3,020.00 kls
4 7mmØ x 6m 62 kgs 37.00 2,294.00
3 MASONRY WORKS
1 CHB #5 3,500.00 pcs 9.00 31,500.00
2 CHB #4 600.00 pcs 8.00 4,800.00
3 CEMENT 720.00 bags 205.00 147,600.00
4 WHITE SAND 60.00 m³ 500.00 30,000.00
5 GRAVEL 38.00 m³ 740.00 28,120.00
6 Labor Cost
Mason 154.00 days 380.00
Skill 40.00 days 380.00
Labor Cost 154.00 days 280.00
Foreman 40.00 days 450.00
4 FORMWORKS
9 Labor Cost
Carpenter 56.00 days 400.00
Skill 28.00 days 380.00
Labor 56.00 days 280.00
Foreman 28.00 days 450.00
5 PLUMBING WORKS
1 PVC Pipe 4" 15 pcs
2 PVC Pipe 3" 7.5 pcs
3 PVC Pipe 2" 7 pcs
4 PVC Elbow 90°x4" 5 pcs
5 PVC Elbow 45°x4" 6 pcs
6 PVC Elbow 90°x2" 10 pcs
7 PVC Elbow 90°x3" 9 pcs
8 PVC Elbow 45°x2" 4 pcs
9 PVC P-trap 2" 5 pcs
10 PVC Clean out with Cover 5 pcs
11 PVC Wye 2x4 9 pcs
12 PVC Wye 4x4 4 pcs
13 PVC Tee 2x2 4 pcs
14 Solvent Cement 200cc 3 can 90.00 270.00
15 PP-R Pipe 20mmX4m 10.5 pcs
16 PP-R Elbow 90° Plain 7 pcs
17 PP-R Elbow 90° Tread 9 pcs
18 PP-R Tee Plain 10 pcs
19 PP-R Tee with Tread 3 pcs
20 PP-R Male Adaptor 6 pcs
21 PP-R Female Adaptor 6 pcs
22 PP-R Coupling 6 pcs
23 PP-R End Plug 1 pcs
24 PP-R End Cap 2 pcs
25 Coupling 4" 7 pcs
26 Coupling 3" 4 pcs
27 Coupling 2" 4 pcs
28 Labor Cost
Plumber 8.5 days 400.00
Labor 8.5 days 300.00
6 ELECTRICAL WORKS
1 PVC Pipe 3/4 4.5 pcs
2 PVC Pipe 1/2 39 pcs
3 PVC Elbow 3/4 4 pcs
4 PVC Elbow 1/2 25 pcs
5 Coupling 1/2 13 pcs
6 Coupling 3/4 2 pcs
7 T.W. Wire #14 275 m 15.00 4,125.00
8 T.W. Wire #12 100 m 20.00 2,000.00
9 T.W. Wire #8 35 m 45.00 1,575.00
10 Outlet 16 pcs 34.00 544.00
11 Switch 15 pcs 34.00 510.00
12 Receptacle 16 pcs 23.00 368.00
13 One-gang Plate 9 pcs 15.00 135.00
14 Two-gang Plate 12 pcs 15.00 180.00
15 Electrical Tape 3 pcs 18.00 54.00
16 Junction Box 20 pcs 15.00 300.00
17 Utility Box 21 pcs 15.00 315.00
18 Panel Box with circuit breaker 1 set 1,700.00 1,700.00
19 3-gang plate 1 pcs 40.00 40.00
20 3-way switch 2 pcs 45.00 90.00
21 Labor Cost
Electrician 6.50 days 400.00
Labor 6.50 days 300.00
7 STRUCTURAL STEEL
Roof Framing
1 C-Purlins 2x4x2.4x1mm 39 pcs
2 Welding Rod 5 kgs 62.50 312.50
3 12mmØ x 6m Sag Rod 4 pcs 170.00 680.00
4 Labor Cost
Welder 4 days 400.00
Labor 4 days 280.00
Stair
1 Flat Bar 6mx1/2x1/2 6 pcs 150.00 900.00
2 Angle Bar 6mx2x2x3mm 4 pcs 900.00 3,600.00
3 Square Bar 6mx6mmx25mm 6 pcs 170.00 1,020.00
4 Welding Rod 5 kgs 62.50 312.50
5 Wood Handrail 2x3x10 2 pcs 600.00 1,200.00
6 Wood Handrail 2x3x12 2 pcs 700.00 1,400.00
7 Labor Cost
Welder 2 days 400.00
Labor 3 days 280.00
Carpenter 1 days 400.00
6 CEILING WORKS
1 METAL FURRING 5m 15.00 pcs 125.00 1,875.00
2 CARRYING CHANNEL 6m 10.00 pcs 125.00 1,250.00
3 WALL ANGLE 3m 34.00 pcs 45.00 1,530.00
4 PVC GLOSSY 4m 48.00 pcs
5 CORNER MOULDING 18.00 pcs
6 HARDIFLEX BOARD 1/8 5.00 pcs 420.00 2,100.00
7 HARDIFLEX SCREW 1" 350.00 pcs 1.00 350.00
8 HARDIFLEX SCREW 1 ½" 100.00 pcs 1.50 150.00
9 BLIND REVITS 150.00 pcs 0.60 90.00
10 CONCRETE NAIL 1.00 kls 110.00 110.00
11 CORNER EAVES 1.00 sets 200.00 200.00
12 END EAVES with Screen 1.00 sets 150.00 150.00
-
13 Labor Cost
Installer 7.00 days 400.00
Helper 7.00 days 350.00
7 ROOFING WORKS -
1 ROOF SHEET 1.1 x 10.45m 5.00 pcs
2 BOX GUTTER 3.00 pcs
3 WALL FLASHING 9.00 pcs
4 WALL CAPPING 0.25m pcs
5 WALL CAPPING 0.2m 5.00 pcs
6 INSULATION 1.00 roll 2,200.00 2,200.00
7 SEALANT 2.00 pcs 125.00 250.00
8 TEKSCREW 300.00 pcs 1.75 525.00
9 BLIND REVITS 320.00 pcs 0.60 192.00
10 HARDIFLEX 12mm 1.50 pcs 600.00 900.00
11 HARDIFLEX SCREW 1 ½ 100.00 pcs 1.50 150.00
12 Labor Cost
Tin Smith 3.00 days 400.00
Labor 3.00 days 280.00
Helper 3.00 days 320.00
8 CARPENTRY WORKS
1 DOORS & WINDOWS
2 STEEL CASEMENT (0.4X0.4) 2.00 sets 500.00 1,000.00
3 STEEL CASEMENT (0.8X0.9) 1.00 sets 1,170.00 1,170.00
4 STEEL CASEMENT (1.2X1.2) 1.00 sets 2,350.00 2,350.00
5 STEEL CASEMENT (1.6X0.4) 1.00 sets 1,050.00 1,050.00
6 SLIDING WINDOW (1.5 X2.0) 1.00 sets 7,500.00 7,500.00
7 SLIDING WINDOW (1.2X1.2) 2.00 sets 3,000.00 6,000.00
8 SLIDING WINDOW (1.0 X 1.2) 2.00 sets 2,700.00 5,400.00
9 FIXED WINDOW 1.2 X 0.4 2.00 sets 2,500.00 5,000.00
10 Window Grills 1.5 x 2 1.00 sets 1,500.00 1,500.00
11 Window Grills 1.2 x 1.2 2.00 sets 1,200.00 2,400.00
12 Window Grills 1.2 x 1.0 2.00 sets 1,000.00 2,000.00
13 Window Grills 0.9 x 0.8 1.00 sets 1,440.00 1,440.00
14 Awning Window 0.4 x 1.2 2.00 sets 750.00 1,500.00
15 Awning Window 0.4 x 0.4 3.00 sets 250.00 750.00
16 PVC DOOR W/ JAMB (2.1X0.6) 3.00 sets 1,200.00 3,600.00
17 MAIN DOOR& ACCESSORIES (2.1X0.9) 1.00 sets
18 BACK DOOR & ACCESSORIES (2.1X0.8) 1.00 sets
19 Labor Cost
Carpenter 5.50 days 380.00
Labor 5.50 days 280.00
8 Labor Cost
Installer 6.00 days 400.00
Helper 12.00 days 350.00
Plumbing Rough-ins
1 MODULAR KITCHEN CABINET 1.00 sets
2 KITCHEN FAUCET 1.00 pcs
3 TEFLON TAPE 6.00 roll
4 WATER CLOSET 3.00 sets
5 LAVATORY 3.00 sets
6 FLOOR DRAIN 3.00 pcs 65.00 195.00
7 PLUMBING ACCESSORIES 3.00 boxes
8 TISSUE HOLDER 3.00 pcs
9 SOAP HOLDER 3.00 pcs
10 SHOWER VALVE 3.00 sets 320.00 960.00
11 SHOWER HEAD 3.00 sets 190.00 570.00
12 GARAGE FAUCET
13 CR FAUCET 3.00 sets 200.00 600.00
14 DOOR KNOB 3.00 sets 180.00 540.00
15 Labor Cost
Plumber 4.00 days 400.00
Helper 4.00 days 300.00
Carpenter 1.50 days 400.00
Window Glass
1 Putty Gray 1.00 bags
2 Silicon 2.00 pcs
3 Glass 0.9 x 0.8 1.00 pcs 5,700.00 5,700.00 3,800.00
4 Glass 0.4 x 1.2 2.00 pcs
5 Glass 0.4 x 0.4 3.00 pcs
9 TILE WORKS
1 GROUND, 0.3X0.3 TILES 300.00 pcs 32.00 9,600.00
3 3rd FLOOR, 0.3X0.3 TILES 410.00 pcs 32.00 13,120.00
4 STAIR, 0.3X0.3 TILES 150.00 pcs 40.00 6,000.00
5 TILE GROUT 32.00 kls 65.00 2,080.00
6 CR FLOOR, 0.2X0.2 TILES 240.00 pcs 15.00 3,600.00
7 CR WALL, 0.2X0.2 PLAIN 450.00 pcs 15.00 6,750.00
8 CR WALL, 0.2X0.2 ACCENT 105.00 pcs 15.00 1,575.00
9 RUBBER NOZZING GRAY 2.4 10.00 pcs 215.00 2,150.00
10 TILE TRIM 7.50 pcs 30.00 225.00
11 Labor Cost
Installer 23.00 days 400.00
Labor 23.00 days 320.00
-
10 PAINTING WORKS -
1 FLAT LATEX 27.00 gal
2 SEMI-GLOSS 20.00 gal
3 CONCRETE NEUTRALIZER 3.50 qrt 45.00 157.50
4 QDE WHITE 2.50 qrt 155.00 387.50
5 PATCHING COMPOUND 10.50 bags 300.00 3,150.00
6 FLAT WALL ENAMEL WHITE 1.00 gal 490.00 490.00
7 LACQUER THINNER 4.00 btls 20.00 80.00
8 PAINT THINNER 3.00 btls 25.00 75.00
9 PAINT BRUSH 2 3.00 pcs 13.00 39.00
10 PAINT BRUSH 4 4.00 pcs 26.00 104.00
11 ROLLER BRUSH 8.00 pcs 45.00 360.00
12 SAND PAPER #100 20.00 pcs 12.00 240.00
13 SAND PAPER #80 20.00 pcs 12.00 240.00
15 TAINTING COLOR 2.00 qrt 160.00 320.00
-
16 Labor Cost
Painter 18.50 days 400.00
Labor 18.50 days 300.00
6,162.50 6,162.50
3,470.00 3,470.00
12,952.00 12,952.00
-
-
37.00 65,675.00 65,675.00
37.00 6,919.00 6,919.00
37.00 111,740.00 111,740.00
2,294.00
-
35,308.00 35,308.00
-
-
31,500.00
4,800.00
147,600.00
30,000.00
28,120.00
-
-
58,520.00 58,520.00
15,200.00 15,200.00
43,120.00 43,120.00
18,000.00 18,000.00
19,950.00
29,400.00
12,025.00
17,280.00
3,500.00
700.00
1,250.00
900.00
-
-
22,400.00 22,400.00
10,640.00 10,640.00
15,680.00 15,680.00
12,600.00 12,600.00
-
-
335.00 5,025.00 5,025.00
240.00 1,800.00 1,800.00
150.00 1,050.00 1,050.00
65.00 325.00 325.00
55.00 330.00 330.00
24.00 240.00 240.00
55.00 495.00 495.00
30.00 120.00 120.00
65.00 325.00 325.00
48.00 240.00 240.00
65.00 585.00 585.00
85.00 340.00 340.00
55.00 220.00 220.00
270.00
316.00 3,318.00 3,318.00
15.00 105.00 105.00
142.00 1,278.00 1,278.00
21.00 210.00 210.00
119.00 357.00 357.00
144.00 864.00 864.00
114.00 684.00 684.00
11.00 66.00 66.00
11.00 11.00 11.00
18.00 36.00 36.00
20.00 140.00 140.00
20.00 80.00 80.00
20.00 80.00 80.00
-
-
3,400.00 3,400.00
2,550.00 2,550.00
-
86.00 387.00 387.00
70.00 2,730.00 2,730.00
18.00 72.00 72.00
15.00 375.00 375.00
15.00 195.00 195.00
15.00 30.00 30.00
4,125.00
2,000.00
1,575.00
544.00
510.00
368.00
135.00
180.00
54.00
300.00
315.00
1,700.00
40.00
90.00
-
-
2,600.00 2,600.00
1,950.00 1,950.00
-
-
300.00 11,700.00 11,700.00
312.50
680.00
-
-
1,600.00 1,600.00
1,120.00 1,120.00
-
-
900.00
3,600.00
1,020.00
312.50
1,200.00
1,400.00
-
-
800.00 800.00
840.00 840.00
400.00 400.00
-
1,875.00
1,250.00
1,530.00
300.00 14,400.00 14,400.00
80.00 1,440.00 1,440.00
2,100.00
350.00
150.00
90.00
110.00
200.00
150.00
-
-
2,800.00 2,800.00
2,450.00 2,450.00
-
-
2,354.00 11,770.00 11,770.00
310.00 930.00 930.00
310.00 2,790.00 2,790.00
310.00 - -
310.00 1,550.00 1,550.00
2,200.00
250.00
525.00
192.00
900.00
150.00
1,200.00 1,200.00
840.00 840.00
960.00 960.00
1,000.00
1,170.00
2,350.00
1,050.00
7,500.00
6,000.00
5,400.00
5,000.00
1,500.00
2,400.00
2,000.00
1,440.00
1,500.00
750.00
3,600.00
14,000.00 14,000.00 14,000.00
12,000.00 12,000.00 12,000.00
-
-
2,090.00 2,090.00
1,540.00 1,540.00
- -
- -
- 9,000.00
- 12,180.00
- 720.00
- 1,500.00
- 150.00
8,000.00 24,000.00 24,000.00
-
-
2,400.00 2,400.00
4,200.00 4,200.00
7,400.00
5,550.00
LOREA MODEL
Material Cost Labor Cost
NO PARTICULAR End UNITS U/P TOTAL AMOUNT U/P TOTAL AMOUNT
FORMWORKS
1 Tie wire 8 kgs 50.00 400.00
2 C.W. Nail 4" 5 kgs 50.00 250.00
3 C.W. Nail 3" 4 kgs 48.00 192.00
4 C.W. Nail 2" 3 kgs 48.00 144.00
5 Cocolumber 2x2x10 25 pcs 105.00 2,625.00
6 Cocolumber 2x3x10 20 pcs 105.00 2,100.00
7 Plywood 1/4 thk. 8 pcs 315.00 2,520.00
8 Plywood 1/2 thk. 2 pcs 520.00 1,040.00
ERICA MODEL
Material Cost Labor Cost
NO PARTICULAR End UNITS U/P TOTAL AMOUNT U/P TOTAL AMOUNT
FORMWORKS
1 Tie wire 15 kgs 50.00 750.00
2 C.W. Nail 4" 3 kgs 50.00 150.00
3 C.W. Nail 3" 5 kgs 48.00 240.00
4 C.W. Nail 2" 5 kgs 48.00 240.00
5 Cocolumber 2x2x10 35 pcs 105.00 3,675.00
6 Cocolumber 2x3x10 30 pcs 105.00 3,150.00
7 Plywood 1/4 thk. 20 pcs 315.00 6,300.00
8 Plywood 1/2 thk. 5 pcs 520.00 2,600.00
ERICA MODEL
Material Cost Labor Cost
NO PARTICULAR End UNITS U/P TOTAL AMOUNT U/P TOTAL AMOUNT
FORMWORKS
1 Tie wire 1 kgs 50.00 50.00
2 C.W. Nail 4" kgs 50.00 -
3 C.W. Nail 3" kgs 48.00 -
4 C.W. Nail 2" 1 kgs 48.00 48.00
5 Cocolumber 2x2x10 24 pcs 105.00 2,520.00
6 Cocolumber 2x3x10 pcs 105.00 -
7 Plywood 1/4 thk. pcs 315.00 -
8 Plywood 1/2 thk. 3 pcs 520.00 1,560.00
CELINA MODEL
Material Cost Labor Cost
NO PARTICULAR End UNITS U/P TOTAL AMOUNT U/P TOTAL AMOUNT
FORMWORKS
1 Tie wire 30 kgs 50.00 1,500.00
2 C.W. Nail 4" 10 kgs 50.00 500.00
3 C.W. Nail 3" 8 kgs 48.00 384.00
4 C.W. Nail 2" 8 kgs 48.00 384.00
5 Cocolumber 2x2x10 40 pcs 105.00 4,200.00
6 Cocolumber 2x3x10 30 pcs 105.00 3,150.00
7 Plywood 1/4 thk. 20 pcs 315.00 6,300.00
8 Plywood 1/2 thk. 15 pcs 520.00 7,800.00
BETTINA MODEL
Material Cost Labor Cost
NO PARTICULAR End UNITS U/P TOTAL AMOUNT U/P TOTAL AMOUNT
1 COCO LUMBER 2X3X10 190.00 pcs 105.00 19,950.00
2 COCO LUMBER 2X2X10 280.00 pcs 105.00 29,400.00
3 PLYWOOD ¼ THK 37.00 pcs 325.00 12,025.00
4 PLYWOOD ½THK 32.00 pcs 540.00 17,280.00
5 TIE WIRE 70.00 kls 50.00 3,500.00
6 C.W. NAIL 2" 14.00 kls 50.00 700.00
7 C.W. NAIL 3" 25.00 kls 50.00 1,250.00
8 C.W. NAIL 4" 18.00 kls 50.00 900.00
Owner Supplied Material
U/P TOTAL AMOUNT TOTAL AMOUNT
-
400.00
250.00
192.00
144.00
2,625.00
2,100.00
2,520.00
1,040.00
ERICA MODEL
Material Cost Owner Supplied Material
NO PARTICULAR End UNITS U/P TOTAL AMOUNT U/P TOTAL AMOUNT TOTAL AMOUNT
FORMWORKS -
1 Tie wire 15 kgs 50.00 750.00 750.00
2 C.W. Nail 4" 3 kgs 50.00 150.00 150.00
3 C.W. Nail 3" 5 kgs 48.00 240.00 240.00
4 C.W. Nail 2" 5 kgs 48.00 240.00 240.00
5 Cocolumber 2x2x10 35 pcs 105.00 3,675.00 3,675.00
6 Cocolumber 2x3x10 30 pcs 105.00 3,150.00 3,150.00
7 Plywood 1/4 thk. 20 pcs 315.00 6,300.00 6,300.00
8 Plywood 1/2 thk. 5 pcs 520.00 2,600.00 2,600.00
17,105.00
ERICA MODEL
Material Cost Owner Supplied Material
NO PARTICULAR End UNITS U/P TOTAL AMOUNT U/P TOTAL AMOUNT TOTAL AMOUNT
FORMWORKS -
1 Tie wire 1 kgs 50.00 50.00 50.00
2 C.W. Nail 4" kgs 50.00 - -
3 C.W. Nail 3" kgs 48.00 - -
4 C.W. Nail 2" 1 kgs 48.00 48.00 48.00
5 Cocolumber 2x2x10 24 pcs 105.00 2,520.00 2,520.00
6 Cocolumber 2x3x10 pcs 105.00 - -
7 Plywood 1/4 thk. pcs 315.00 - -
8 Plywood 1/2 thk. 3 pcs 520.00 1,560.00 1,560.00
4,178.00
FORMWORKS
MODEL
MODEL
ORIG. COST NEW COST
ERICA 45 33,415.00 5,554.84
BEA 33,415.00 5,554.84
CELINA 36,985.00 6,456.91
SHANA 220 MODEL 36,520.00 5,697.27
SHANA 957 MODEL 36,520.00 5,697.27
AMARA MODEL 40,720.00 7,026.64
BETTINA 85,005.00 18,041.36
190 php/sqm
587.59 php/sqm diff. per sqm
PROJECT: PROPOSED BARBED WIRE PERIMETER FENCE
LOCATION: MAASIM, SAN ILDEFONZO, BULACAN
SUBJECT: QUOTATION
Labor Cost
NO PARTICULAR QTY UNITS
U/P TOTAL AMOUNT
I. EARTHWORKS
1 Excavation w/ ADOBE 226.8 m³ 300.00 68,040.00 68,040.00
2 Backfilling -
2.1 ordinary soil 100 m³ 120.00 12,000.00 12,000.00
2.2 S1 sand 126.8 m³ 45.00 5,706.00 120.00 15,216.00 20,922.00
I. EARTHWORKS
1 Excavation 5.916 m³ 150.00 887.40 887.40
2 Backfilling 1.963 m³ 120.00 235.56 235.56
2.1 lay-out 1 lot 1,000.00 1,000.00 1,000.00
I. EARTHWORKS
1 Excavation 15.4 m³ 250.00 3,850.00 3,850.00
2 Backfilling 3.93 m³ 200.00 786.00 786.00
2.1 lay-out 1 lot 1,000.00 1,000.00 1,000.00
IV REBAR WORKS
iv.i column footing
1 RSB 12mm x 6m 7 pcs 215 1,505.00 1,505.00
2 Tie wire 1 kgs 70 70.00 70.00
iv.ii column
1 RSB 10mm x 6m 24 pcs 145 3,480.00 3,480.00
2 RSB 12mm x 6m 12 pcs 215 2,580.00 2,580.00
3 RSB 16mm x 6m 12 pcs 310 3,720.00 3,720.00
4 Tie wire 2.2 kgs 70 154.00 154.00
iv.iv beam
1 RSB 10mm x 6m 5 pcs 145 725.00 725.00
2 RSB 12mm x 6m 6 pcs 215 1,290.00 1,290.00
3 Tie wire 1.7 kgs 70 119.00 119.00
iv.v pavement/parking
1 RSB 10mm x 6m 104 pcs 145 15,080.00 15,080.00
2 Tie wire 14 kgs 70 980.00 980.00
Prepared by:
I. EARTHWORKS
1 Excavation w/ ADOBE 517.47 m³ 300.00 155,241.00 155,241.00
2 Backfilling -
2.1 ordinary soil 178.74 m³ 120.00 21,448.80 21,448.80
2.2 S1 sand 325.29 m³ 45.00 14,638.05 120.00 39,034.80 53,672.85
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot 1,400.00 1,400.00 1,400.00
VI STRUCTURAL STEEL
1 Installation of C-purlins framming 1 lot 700.00 700.00 700.00
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot
V FORMWORKS 5.76 m²
1 C.W. Nail 3" 0.5 pcs 48.00
2 Plywood 1/2 x 4 x 8 2 pcs 520.00
VI ROOFING WORKS
1 Reinstallation of Roof sheet & C-purlins 31.96 m²
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot
V FORMWORKS 2.88 m²
1 C.W. Nail 3" 0.5 pcs 48.00
2 Plywood 1/2 x 4 x 8 1 pcs 520.00
VI ROOFING WORKS
1 Reinstallation of Roof sheet & C-purlins 27.2 m²
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot 1,050.00 1,050.00 1,050.00
VI STRUCTURAL STEEL
1 Installation of C-purlins framming 1 lot 700.00 700.00 700.00
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot 1,400.00 1,400.00 1,400.00
VI STRUCTURAL STEEL
1 Installation of C-purlins framming 1 lot 700.00 700.00 700.00
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot 1,050.00 1,050.00 1,050.00
VI STRUCTURAL STEEL
1 Installation of C-purlins framming 1 lot 700.00 700.00 700.00
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot 1,050.00 1,050.00 1,050.00
VI STRUCTURAL STEEL
1 Installation of C-purlins framming 1 lot 700.00 700.00 700.00
I DEMOLITION WORKS
i.i Cheaping of existing tiles
II PLUMBING WORKS
ii.i Water line
1 PP-R pipe 1/2 x 4m 4 pcs 222.00 888.00 888.00
2 PP-R Elbow plain 2 pcs 11.00 22.00 22.00
3 PP-R Elbow w/ tread 2 pcs 83.00 166.00 166.00
4 PP-R coupling 4 pcs 8.00 32.00 32.00
IV STEEL WORKS
iv.i Stair railings
1 Tubular 2" x 2" x 2mm x 6m 1 pc 700.00 700.00 700.00
2 Flat bar 1" x 6mm x 6m 7 pcs 280.00 1,960.00 1,960.00
3 Welding rod (ordinary) 1 kgs 90.00 90.00 90.00
4 Cutting Disc 3 pcs 45.00 135.00 135.00
VI CARPENTRY WORKS
vi.i Ceiling
1 Gypsum Board 4 x 8 3 pcs 380.00 1,140.00 1,140.00
2 Gypsum pathy 3 gal 230.00 690.00 690.00
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot
V FORMWORKS 5.76 m²
1 C.W. Nail 3" 1 pcs 48.00
2 Plywood 1/2 x 4 x 8 3 pcs 520.00
VI STRUCTURAL STEEL
1 Installation of C-purlins framming 1 lot
Prepared by:
I. DEMOLITION WORKS
1 Dismantling of roofing and framming 1 lot
V FORMWORKS 2.88 m²
1 C.W. Nail 3" 1 pcs 48.00
2 Plywood 1/2 x 4 x 8 3 pcs 520.00
VI STRUCTURAL STEEL
1 Installation of C-purlins framming 1 lot
Prepared by:
Approved by:
I. EARTHWORKS
1 Excavation 32.87 m³ 150.00 4,930.50 4,930.50
2 Backfilling 15.294 m³ 120.00 1,835.28 1,835.28
2.1 lay-out 1 lot 1,000.00 1,000.00 1,000.00
Prepared by:
I. EARTHWORKS