MATERIALS

JUNE

Temporary Facilities
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Coco Lumber
Plywood
Nails
Sheating
Rebar & Concreting
Foundation
Coco Lumber
Plywood
Cement
Gravel
Sand
Rebars/ Steel
Ground Floor/ Second Floor
Coco Lumber
Plywood
Cement
Gravel
Sand
Rebars/ Steel
Pipes (septic tank & etc.)
Masonry
Plaster
Bricks
Hollow Blocks
Cement
Gravel
Sand
Roofing
Purlins
Sag Rod
Down Spout
Ridges
Shingles
Electrical Layout
Electrical Wiring
Main circuit board
Lightning Fixtures
Drainage & Sewer line
Pipes (water & waste)
Pluming Fixtures
Finishes
Concrete
Tiles

Painting
Glass Works ( windows)
Carpentry Works

NE

JULY
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

MATERIALS SCHEDULES
JULY
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14

AUGU

S
AUGUST
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12

SEPTEMBER
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9

OCTOBE

OCTOBER
10 11 12 13 14 15 16 17 18