You are on page 1of 2

PROJECT : PERIMETER FENCE

LOCATION : SAN VICENTE (EBUS), GUAGUA, PAMPANGA

OWNER : MR. TROY CHRISTENSEN

SUBJECT : BILL OF QUANTITIES

DATE : 11 September 2020

MATERIALS LABOR
NO. DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT
Unit Cost Amount Unit Cost Amount

I GENEREAL REQUIREMENTS
1. Mobilization 1.00 lot 5,000.00 5,000.00 5,000.00 5,000.00
2. Temporary Facilities
2.1. Temporary Site Warehouse/Barrocks 1.00 lot 10,000.00 10,000.00 5,000.00 5,000.00 15,000.00 15,000.00
SUBTOTAL 1 (GENERAL REQUIREMENTS ) 10,000.00 10,000.00 20,000.00

II CIVIL / EARTHWORKS
1. Excavation 32.73 cu. mtr. 440.00 14,402.96 207.00 6,775.94 647.00 21,178.90
2. Soil Backfill 23.56 cu. mtr. 412.50 9,716.85 194.06 4,571.34 606.56 14,288.19
3. Gravel Fill 4.59 cu. mtr. 1,936.00 8,884.30 910.80 4,179.66 2,846.80 13,063.97
SUBTOTAL II (CIVIL / EARTHWORKS ) 33,004.11 15,526.94 48,531.05

III STRUCTURAL WORKS


1. REBARS REINFORCEMENT
1.1. Column Footings
1.1.a. Deformed Bars 16mmø 113.78 kgs. 44.69 5,084.50 19.75 2,247.17 64.44 7,331.67
1.1.b. Deformed Bars 12mmø 213.33 kgs. 44.69 9,533.44 19.75 4,213.44 64.44 13,746.88
1.1.c. G.I. Wire #16 9.81 kgs. 79.93 784.42 35.33 346.69 115.26 1,131.11
1.2. Wall Footings
1.2.a. Deformed Bars 12mmø 149.33 kgs. 44.69 6,673.41 19.75 2,949.41 64.44 9,622.82
1.2.b. Deformed Bars 10mmø 14.81 kgs. 44.69 662.04 19.75 292.60 64.44 954.64
1.2.c. G.I. Wire #16 4.92 kgs. 79.93 393.63 35.33 173.97 115.26 567.60
1.3. Columns
1.3.a. Deformed Bars 16mmø 56.89 kgs. 44.69 2,542.25 19.75 1,123.58 64.44 3,665.83
1.3.b. Deformed Bars 12mmø 320.00 kgs. 44.69 14,300.16 19.75 6,320.16 64.44 20,620.32
1.3.c. Deformed Bars 10mmø 244.44 kgs. 44.69 10,923.73 19.75 4,827.90 64.44 15,751.63
1.3.d. G.I. Wire #16 18.64 kgs. 79.93 1,489.98 35.33 658.52 115.26 2,148.49
1.4. Grade Beams
1.3.a. Deformed Bars 12mmø 298.67 kgs. 44.69 13,346.82 19.75 5,898.82 64.44 19,245.63
1.3.b. Deformed Bars 10mmø 162.96 kgs. 44.69 7,282.49 19.75 3,218.60 64.44 10,501.09
1.3.c. G.I. Wire #16 13.85 kgs. 79.93 1,107.00 35.33 489.26 115.26 1,596.26
2. FORMWORKS
2.1. Column Footings 20.00 sqr. mtr. 414.40 8,288.00 191.48 3,829.50 605.88 12,117.50
2.2. Wall Footings 27.00 sqr. mtr. 414.40 11,188.80 191.48 5,169.83 605.88 16,358.63
2.3. Columns 37.44 sqr. mtr. 414.40 15,515.14 191.48 7,168.82 605.88 22,683.96
2.4. Grade Beams 19.89 sqr. mtr. 414.40 8,242.42 191.48 3,808.44 605.88 12,050.85
3. STRUCTURAL CONCRETE
3.1. Column Footings 5.20 cu. mtr. 4,816.00 25,043.20 2,225.25 11,571.30 7,041.25 36,614.50
3.2. Wall Footings 3.98 cu. mtr. 4,816.00 19,158.05 2,225.25 8,852.04 7,041.25 28,010.09
3.3. Columns 2.81 cu. mtr. 4,816.00 13,523.33 2,225.25 6,248.50 7,041.25 19,771.83
3.4. Grade Beams 2.98 cu. mtr. 4,816.00 14,368.54 2,225.25 6,639.03 7,041.25 21,007.57
SUBTOTAL III (STRUCTURAL WORKS) 189,451.34 86,047.57 275,498.92

IV MASONRY WORKS
1. CHB LAYING
1.1. CHB 6" 165.51 sqr. mtr. 564.93 93,503.08 261.03 43,203.43 825.95 136,706.51
1.2. Deformed Bars 10mmø 583.33 kgs. 44.69 26,068.00 20.65 12,044.81 65.34 38,112.81
1.3. G.I. Wire #16 17.50 kgs. 79.93 1,398.85 36.93 646.34 116.87 2,045.20
2. PLASTERING
2.1. Wall Perimeter 288.99 sqr. mtr. 156.49 45,224.94 72.31 20,896.34 228.80 66,121.28
SUBTOTAL IV (MASONRY WORKS) 166,194.87 76,790.93 242,985.80

TOTAL DIRECT COST: ₱ 587,015.77


PROFIT AND CONSTINGENCIES : ₱ 88,052.37

TOTAL PROJECT COST: ₱ 675,068.13

PREPARED BY: APPROVED BY:

JOHN CARL B. SALAS MR. TROY CHRISTENDEN

You might also like