DATE December 15, 2021

TO Ar. AJ Nacario and Engr. Clifford Tapulayan


FROM Ar. Jhennel Evangelista and Wyllden Oliver T. Uy
PROJECT Proposed Interim Office
LOCATION Sct. Madriñan St., Diliman, Quezon City
OWNER Robomatrix Technologies Inc.
SUBJECT Construction Bulletin Architectural No. 3

ITEM NO. ITEM REMARKS

ARCHITECTURAL
Ground Floor Key Plan adjusted location of common toilets to clear bay
X5-X6 for sliding doors, use same structural
CBA 3.1 framing as in CBS - 3 but adjust locations as per
Ground Floor Blow-up Plan latest architectural plan, intermediate beam
W8X13 for toilet roof should now be from X3 to X6

Mezzanine Key Plan adjusted canopy location in relation to adjusted


common toilets location below, use same canopy
CBA 3.2 framing but adjust location as per latest
Mezzanine Blow-up Plan architectural plan

If you have further questions please call our office. Thank you.

Prepared by:

Wyllden Oliver T. Uy
Junior Architect

Noted by:

Ar. Jhennel Evangelistra


Supervising Architect
X1 X2 X3 X4 X5 X6 X7 X8 X9

Y1

11

Y2 1

SIDEWALK
3

Y3 4

SCT. MADRIÑAN STREET


5 4 3 2 1

Y4

SIDEWALK
7

Y5 8

11

Y6

2
1 KEY PLAN

X2 X3 X4 X5

Y5

Y6

2 BLOW-UP PLAN

CBA
3.1
X1 X2 X3 X4 X5 X6 X7 X8 X9

Y1

11

Y2

Y3

Y4

Y5

11

Y6

1 KEY PLAN

X3 X4 X5

Y5

Y6

2 BLOW-UP PLAN

CBA
3.2