MANUAL
CONSTRUCTION
ESTIMATE GUIDE
(A STEP BY STEP GUIDE FOR YOUR
CONSTRUCTION NEEDS)
1|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
TABLE OF CONTENTS
PART 1 ESTIMATES
• INTRODUCTION OF COST ESTIMATES
• 3 KEY TYPES OF ESTIMATE
• METHODS/TECHNIQUES IN ESTIMATE
• CREATING A SAMPLE BOM
• INTRODUCTION TO SAMPLE DESIGN PLANS
2|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
3|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
DEFINITION
Cost estimation in project management is the process of forecasting the cost and other resources
needed to complete a project within a defined scope. Cost estimation accounts for each element
required for the project and calculates a total amount that determines a project’s budget.
PRELIMINARY/ROUGH ESTIMATE
• Preliminary estimates are also called rough or approximate estimates,. This is because they
are not final—they give a ballpark idea of how much a project will cost.
• A preliminary estimate is made at the very beginning of a project when there’s limited
information available.
• A preliminary estimate allows a contractor to figure out the budget for a project and what to
charge the client.
• Used when the design plans is 35% to 50 % complete and is used to check if the proposed
project is on budget.
For example, a roofer is asked by a client to redo the roof of his house. The roofer did a very similar
project three months ago. He uses the estimate from his old project to make a preliminary estimate
for his new project.
• Once more information is available, a business can create a revised estimate, or detailed
estimate, from the preliminary estimate.
4|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
DETAILED/QUANTIFIED ESTIMATE
• Detailed estimates include incredibly detailed information on quantities, costs and rates—in
fact, all items necessary to complete the project. All the line items are added together to
reach the final cost.
• It includes a list of quantities for all materials needed to complete a project. Its purpose is to
give the client a complete list of all the quantities required for the project and what the cost
will be for each quantity. It is a key estimating method in construction.
• They are prepared from a complete or nearly complete set of drawings and are the most
accurate type of estimate.
• Information on the rates used to calculate costs (see quantity estimate below)
• Specifications
• Drawings for the areas included in the project (including an index and key)
• Detailed estimates are often used as a contractor’s budget estimate. This planning tool helps
him know how much cash flow he needs and whether he requires financing.
BID ESTIMATE
• A general contractor may only put a lot of work into this cost estimation method if she
believes her chance of winning the bid is high. Otherwise, it’s a waste of her time.
• A bid estimate can be drawn up based on plans provided by the client or on standard
industry costs. If the contractor wants more accurate amounts, she will need to calculate
specific labor, material and equipment costs for the project.
• For example, a landscaper is hired to redo the backyard of a client’s house. He uses his
hourly wage and material costs to arrive at a total for a bid estimate. The landscaper charges
his standard hourly rate (Php 80 per hour) for 25 hours of work. However, he decides to
mark up his material costs less than he usually does to outbid a competitor.
5|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
METHODS OF ESTIMATE
❑ KNOWING THE ACTUAL MARKET COST
❑ IMPLEMENTING QUALITY
ACTUAL CONSTRUCTION
FIGURE 1.1
6|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑ STEP 1
1. LIST DOWN ALL THE REQUIRED SCOPE OF WORKS (BE SPECIFIC AND DETAILED) SPECIFIED
WITH THE CONTRACT AND BUILDING SPECIFICATIONS OF THE PROJECT. LIST DOWN EVERY
REQUIREMENTS INTO SET OF CATEGORIES.
NOTE: ALSO BE AWARE OF DESIGN PLANS AND SPECIFICATION INDICATED BY THE PROJECT.
GENERAL REQUIREMENTS
❑ STRUCTURAL WORKS
❑ ARCHITECTURAL WORKS
❑ PLUMBING WORKS
❑ ELECTRICAL WORKS
❑ TINSMITHRY/ROOFING WORKS
❑ METAL WORKS
❑ CABINETRIES/WOOD WORKS
❑ AUXILLARY WORKS
I. GENERAL REQUIREMENTS
❑ DESIGN PLANS
❑ AS-BUILT PLANS
❑ BUILDING PERMITS
❑ TEMPORARY FACILITIES
❑ LOT RELOCATION
❑ MOBILIZATION/DEMOBILIZATION/SITE CLEARING
❑ TERMITES/SOIL POISONING
❑ EXCAVATION
❑ EMBANKMENT
❑ STAKING OUT/LAYOUT
7|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑ CONCRETING
▪ RC FOOTING
▪ RC COLUMNS (GF TO 2F)
▪ TIE BEAMS/WALL FOOTINGS
▪ SLAB ON GRADE
▪ SUSPENDED BEAMS
▪ SUSPENDED SLABS
▪ RC COLUMNS (2F TO RB)
▪ RC ROOFBEAMS
❑ MASONRY/ REINFORCEMENT
▪ MASONRY WORKS
▪ (INTERIORWALLS AND EXTERIOR WALLS)
▪ PLASTERING WORKS
▪ STAIRS
❑ FORMWORKS
▪ SCAFFOLDINGS
V. ELECTRICAL WORKS
8|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑ STEP 2
2. TRASFER THE LIST THAT YOU MADE INTO AN EXCEL SOFTWARE THAT YOU WILL USE
THEN LIST DOWN NECESSARY MATERIALS FOR EACH CATEGORIES. MAKE A TABLE
WITH HEADERS INDICATING THE FF:(ITEM NO., SCOPE OF WORKS, UNIT, UNIT PRICE
AND AMOUNT, LABOR, EQUIPMENT , TOTAL COST)
Example:
FORMAT I
FIGURE 1.2
FORMAT II
FIGURE 1.3
9|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑ STEP 3
3. TRY INPUTTING ALL THE INITIAL DATAS FOR COST/UNIT PRICE THAT YOU ALREADY HAVE
AND KNOW.
EXAMPLE:
❑ STEP 4
YOU MAY ALSO START TO GET A QUOTE FROM DIFFERENT SUPPLIERS MAINLY THE FOLLOWING:
HARDWARES
10 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑ STEP 5
5. ONCE DONE WITH ALL THE GATHERED DATAS.I NPUT THEM ONE BY ONE IN THE EXCEL FILE
AND CAREFULLY CHECK IT ALSO FROM TIME TO TIME.
EXAMPLE:
FIGURE 1.4
11 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑ STEP 6
6. “MARKING UP”
NOTE: MARKING UP OF THIS PERCENTAGE MAY VARIES FROM TIME TO TIME DUE TO THE
MARKET, SUPPLY AND DEMAND AND OTHER THINGS THAT MAY AFFECT THE COSTING.
I. MATERIAL COST
FROM THE BREAKDOWN OF MATERIALS MARK UP THE NUMBER OF QUANTITY OF
MATERIAL ITEMS INTO 5% TO 20% TO BE ABLE TO CONSIDER THE WASTAGE FACTOR.
EXAMPLE:
TOTAL QUANTITY OF PLYWOOD : 10 PCS (3/4 INCHES MARINE PLYWOOD)
X .20 (WASTAGE FACTOR PERCENTAGE)
ADDITIONAL MATERIALS + 2PCS OF PLYWOOD
TOTAL PLYWOOD : = 10+2 = 12 PCS NO. OF MARINE PLYWOOD
Example:
12 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE:
TOTAL MATERIAL COST : PHP 1,000,000
X .50
TOTAL LABOR COST = PHP 500,000
III. VATS/TAXES
WITH THE TOTAL OF MATERIAL COST MULTIPLY IT INTO 12% (MAY VARIES ON
WHAT KIND OF TAXES AND LOCATION OF THE PROJECT) .
EXAMPLE:
TOTAL MATERIAL COST : PHP 1,000,000
X .12
VATS/TAXES COST OF MATERIAL= PHP 120,000
13 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑ STEP 7
“Indicate at the final amount:
The ff:
❖ Discounted Cost(if any)
❖ Exclusions
❖ Total working or calendar days.
FIGURE 1.5
14 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
15 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
16 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
17 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
18 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
19 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
20 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
21 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
22 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
23 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
24 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
25 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
26 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
27 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
TYPES OF FOOTINGS
28 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
I. CONRETING OF FOOTINGS
AA 4000 PSI
A 3500 PSI
B 2500 PSI
C 2000 PSI
29 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE:
30 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
31 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SOLUTION
A. BY VOLUME METHOD
1. FIND THE VOLUME OF THE FOOTING (C1F1) (NO.1 PCS)
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
CEMENT = 0.50 X 9 (USING 40KG/BAG) = 4.5 BAGS = APPROX 5 BAGS
SAND = 0.5 X 0.50=0.25= APPROX 0.50 cu.m sand
GRAVEL=0.5 X 1.0= APPROX 0.50 cu.m gravel (3/4)
3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS DATA IS FOR ONLY ONE FOOTING THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE FOOTING YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).
32 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE:
GET THE TOTAL VOLUME
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
TOTAL VOLUME= 1.0 X 1.0 X 0.3 X (3 UNITS OF FOOTINGS) =0.9 CUBIC METERS
CEMENT = 0.90 X 9 (USING 40KG/BAG) = 8.1 BAGS = APPROX 9 BAGS
SAND = 0.9 X 0.50=0.45= APPROX 0.50 cu.m sand
GRAVEL=0.9 X 1.0= 0.90 cu.m gravel (3/4) X 11= 1 cu.m gravel (3/4)
ORDER:
CEMENT = 55+ 9 = 64 BAGS
SAND = 5.5+ .5 = 6 cu.m sand
GRAVEL= 0.5 + 5.5= 6.5= 7 cu.m sand
33 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
B. REINFORCEMENT
STEPS:
1. Know the actual dimensions of the footing as to it’s length and width.
2. Remember that the minimum underground protective covering of concrete to the
steel reinforcement is 7.5cm.
3. If the plan does not call for a hook or bend of the footing reinforcement, the length
of the bar is equal to the length or width of the footing minus the protecting
covering at both ends.
STEPS:
4. If the plan calls for a hook or bend of the reinforcement, the bar-cut should
include the allowances for hook and bend as presented in Figure 3-4 and 3-5.
5. Know the spacing distance of the steel bars both ways o determine the exact
number required. As much as possible, select the appropriate steel bar length which
is divisible by the cut length to avoid unwanted extra cuts.
34 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
ADDITIONAL INFORMATION:
35 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SOLUTION
FOR 1 FOOTING C1(F1)
A. CUTTING LIST-METHOD
INCLUDE THE CONCRETE COVERING FOR UNDERGROUND STRUCTURES= 75 MM
FOR ABOVE THE GROUND STRUCTURES = 40 MM
CUT LENGTH:
NOTE THAT THE COMMERCIAL LENGTH OF REBARS USED IN THIS FOOTING ARE
10MM WITH 6METERS LENGTH.
36 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
ALONG W:
ALONG L:
PCS REQUIRED = 1.2 M DIVIDE (BOTTOM BARS SPACING) + (1)
= 1.2 M DIVIDE 0.20M
= 6 PCS +1
= 7 PCS (1.5 m ALONG L)
THEREFORE:
TOTAL LENGTH: 7PCS (1.5) + 7PCS (1.5)= 21 M
COMMERCIAL LENGTH : 6M OF REBARS
21 METERS DIVIDE 6 = 3.5 =APPROX 4 PCS (16MM REBAR) FOR ONE FOOTING.
37 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
ILLUSTRATION:
SOLUTION:
FORMULA A
38 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SOLUTION :
FOR 4 PCS (16MM)
NOTE: ALWAYS CHECK THE VALUES AND ALSO THE WASTAGE FACTORS.
39 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
40 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
41 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
LAPPING LENGTHS
42 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE:
43 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
ISOMETRIC VIEW
APPROX HEIGHT FROM BOT OF FOOTING TO
ROOFBEAM= 8.86 METERS
FOR 1PC- C1
I. BY VOLUME METHOD
1. FIND THE VOLUME OF THE COLUMN (C1F1) (NO.1 PCS)
44 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS DATA IS FOR ONLY ONE COLUMN THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE COLUMN YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).
45 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
4. REINFORCEMENT
SECTION OF C1
46 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
47 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
Summary:
LENGTH OF A = 3.58 m + (16d= 0.256) =3.9m (6PCS)
LENGTH OF B = 6 Meters (4pcs)
LENGTH OF C = 0.8m + 0.8m + 3.7m =5.3 m (2pcs)
LENGTH OF D = 0.8+ 0.3 + 0.15= 1.25m (2pcs)
THEREFORE ORDER:
48 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
4 DB = 4 (10) = 40MM
6 DB = 6 (10) = 60 MM or 75mm
Therefor for
49 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
a. Compute for total perimeter of stirrups considering the concrete cover =40mm
Total Cutting Length = Perimeter of Rectangle + Total Hook Length -Total Bend length
Total Cutting Length = 880 + (3db + 75 mm) – 3db (2) -2db (3)
50 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SHORCUT METHOD
51 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
52 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
53 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SUMMARY:
FOR 12 PCS (16MM) -VERTICAL BARS
FOR 11 PCS (10MM) -STIRRUPS
g. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
54 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
55 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
56 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
57 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
LAP LENGTH
58 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
59 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
60 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
61 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
1. CONCRETING
BY VOLUME METHOD
FIND THE VOLUME OF THE BEAM FROM A TO D
62 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS DATA IS FOR ONLY ONE COLUMN THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE COLUMN YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).
63 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
4. Reinforcements
ACTUAL PLAN
64 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
Solution:
Lebd= Column size- Concrete cover- Column Main Bar- Lateral Ties dia.
= 0.2 m -0.040 m- 0.016m – 0.010 m
= 134 mm
ACTUAL
MIN LAP LENGTH 50D= 50(16)= 800MM
65 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
:by Theoretical:
FOR STIRRUPS
66 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
4 DB = 4 (10) = 40MM
6 DB = 6 (10) = 60 MM or 75mm
Therefor for
67 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
Total Cutting Length = Perimeter of Rectangle + Total Hook Length -Total Bend length
Total Cutting Length = 880 + (3db + 75 mm) – 3db (2) -2db (3)
68 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SUMMARY:
FOR 12 PCS (16MM) -MAIN BARS
FOR 16 PCS (10MM) -STIRRUPS
69 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
f. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS CONTINOUS BEAM IS JUST AN EXAMPLE ONLY THE WHOLE BEAM DETAILS ARE
NOT YET ESTIMATED.
70 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
71 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE:
1. CONCRETING
BY VOLUME METHOD
FIND THE VOLUME OF THE BEAM FROM A TO D
72 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS DATA IS FOR ONLY ONE COLUMN THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE COLUMN YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).
73 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
4. REINFORCEMENTS
PROPOSED CUTTING LIST
Solution:
Lebd= Column size- Concrete cover- Column Main Bar- Lateral Ties dia.
= 0.2 m -0.040 m- 0.016m – 0.010 m
= 134 mm
ACTUAL
MIN LAP LENGTH 50D= 50(16)= 800MM
74 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FOR STIRRUPS
MINIMUM INSIDE BEND DIAMETER
4 DB = 4 (10) = 40MM
6 DB = 6 (10) = 60 MM or 75mm
Therefor for
75 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
Total Cutting Length = Perimeter of Rectangle + Total Hook Length -Total Bend length
Total Cutting Length = 880 + (3db + 75 mm) – 3db (2) -2db (3)
76 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
USE:
6. KG OF GI WIRE
SUMMARY:
FOR 18 PCS (12MM) -MAIN BARS
FOR 14 PCS (10MM) -STIRRUPS
=1.91 KG OF GI.WIRE
= APPROX 2 KG OF GI WIRE.
=1.04 KG OF GI.WIRE
= APPROX 2 KG OF GI WIRE.
7. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS TIE CONTINOUS BEAM IS JUST AN EXAMPLE ONLY THE WHOLE BEAM DETAILS
ARE NOT YET ESTIMATED AND WASTAGE FACTOR ARE NOT INCLUDED.
78 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
79 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
80 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
81 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
82 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
83 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
1. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS DATA IS FOR ONLY ONE PORTION OF SLAB THEREFORE IN ORDER TO COMPUTE
THE TOTAL VOLUME OF ALL THE SLAB YOU MUST ESTIMATE IT ONE BY ONE AND
DETERMINE IF IT IS ONE WAY OR TWO WAY SLAB THEN ADD THE ADDITIONAL WASTAGE
FACTOR (5%-20%).
84 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
STEP 3 REINFORCEMENTS
85 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
86 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SUMMARY:
FOR 13 PCS (12MM) -BOTTOM BARS
FOR 12 + 6 PCS= 18 PCS (12MM) -TOP MAIN BARS
=3.27 KG OF GI.WIRE
= APPROX 4 KG OF GI WIRE.
87 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
88 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
STEP 1. CONCRETING
TOTAL VOLUME : 5.85 X 6.30 X .150 M(APPROX THICKNESS OF SLAB) = 5.53 CU.M
REFER TO THE TABLE:
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
89 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
STEP 2. REINFORCEMENTS
SUMMARY:
FOR 54 PCS (10MM)
90 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
=3.99 KG OF GI.WIRE
= APPROX 4 KG OF GI WIRE.
STEP 4 INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS DATA IS FOR ONLY ONE PORTION OF SLAB THEREFORE IN ORDER TO COMPUTE
THE TOTAL VOLUME OF ALL THE SLAB YOU MUST ESTIMATE IT ONE BY ONE THEN ADD THE
ADDITIONAL WASTAGE FACTOR (5%-20%).
91 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
92 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
GENERAL INFORMATION
93 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
94 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
95 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
96 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
97 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
5. KGS OF GI WIRE
SUMMARY:
FOR 3 PCS (12MM) -VERTICAL BARS
FOR 4 PCS (10MM) -HORIZONTAL BARS
98 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
=0.32
= APPROX 1 KG OF GI WIRE.
=0.30 KG OF GI.WIRE
= APPROX 1 KG OF GI WIRE.
6. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:
NOTE: THIS DATA IS FOR ONLY ONE PORTION OF WALL THEREFORE IN ORDER TO COMPUTE
THE TOTAL AREA OF ALL THE WALL YOU MUST ESTIMATE IT ONE BY ONE THEN ADD THE
ADDITIONAL WASTAGE FACTOR (5%-20%).
99 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
100 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
101 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
102 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE:
SPECIFICATION:
103 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
= 2(.200+.400) X 3M
= 3.6 sqm
104 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
105 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
= 2.75 sqm
106 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
STEP 3 SOLVE THE HORIZONTAL, VERTICAL AND DIAGONAL SUPPORT OF 1 SPAN BEAM
107 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
108 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
109 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
110 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SOLUTION:
A. CUTTING LIST ORDER FOR RIB TYPE LONG SPAN ROOF
BY DIRECT COUNTING :
THEREFORE ORDER CUT LENGTH :
111 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
112 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
113 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
THEREFORE: 9.2 M DIVIDE BY 2.2 =4.18 PCS = 5 PCS (24” CUT GUTTER)
OTHER ACCESSORIES
NOTE: FOR OTHER ROOFING ACCESSORIES ALWAYS LOOK FOR THE
MATERIALS REQUIRED IN THE SCOPE OF ROOFING WORKS
114 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
115 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
116 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FICEM BOARD
GYPSUM BOARD
117 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
118 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
119 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
120 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
121 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
122 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
123 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
DOOR HANDLES
124 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
125 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
127 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE ONLY:
128 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
ACTUAL PICTURES
OF TILE WORKS
129 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
130 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
❑TILE GROUT
❑CEMENT
❑SAND
❑TILE SPACER
131 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
132 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
133 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
134 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
135 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
136 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
137 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
MASONRY WALLS
138 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
METALS
EPOXY PRIMER
139 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
WOODS
140 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
DETERMINE:
❑GALLONS OF PAINT
❑BAGS OF SKIMCOATS
141 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SOLUTION:
142 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
ACTUAL CABINETRIES
143 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SPECIFICATIONS
144 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SPECIFICATIONS
145 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
146 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
147 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
148 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
149 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
PERSPECTIVE
150 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
151 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
152 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
153 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
154 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
155 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
156 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
157 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
158 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
159 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
160 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
161 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
162 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
163 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
164 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
165 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
166 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
167 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
168 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
STEP 1
DETERMINE THE TOTAL LENGTH OF ½ “ PIPE NEEDED IN THE SYSTEM
169 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
SO TO GET THE QTY. DIVIDE THE TOTAL LINEAR METER INTO 2.7M
(DEVELOPMENT LENGTH OF PIPE)
FOR FITTINGS
QUANTIFY EVERY INTERSECTIONS
170 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
171 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
STEP 1
DETERMINE THE TOTAL LENGTH OF PIPES NEEDED IN THE SYSTEM
USING THE FF:
FOR DOWNSPOUTS
3” ORANGE PVC PIPE
FOR FLOOR/SINK DRAINS
2” ORANGE PVC PIPE
2” PTRAPS
2” WYE
FOR MAIN SEWER PIPE
3” PIPE AND OTHER FITTINGS
172 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FOR DOWNSPOUTS
3” ORANGE PVC PIPE
NOTE:
THE OTHER FITTINGS
NOT INCLUDED IN HERE
SHOULD BE ADDED THIS IS
ONLY FOR EXAMPLE.
KNOW THE PROPER FITTINGS
AND ALLOWABLE SLOPING T0 2%.
INSERT QTY. IN THE BOM.
173 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
174 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
175 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
176 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
177 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
ELECTRICAL WIRES
1 BOX = 1 ROLL= 150METERS OF WIRE
178 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
179 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
180 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
181 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
182 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
EXAMPLE:
THE PANEL BOARD IS LOCATED AT KITCHEN AREA.
❑ STEP 1 MEASURE ALL THE WIRINGS FROM ALL CONNECTIONS: LIGHTS,
SWITCHES, OUTLES INTO PANEL BOARD.
IF CIRCUIT 1 HAS TOTAL LENGTH OF WIRE : 15 METERS
183 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
184 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
185 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
186 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
187 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
188 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
189 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
190 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
191 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE
FINAL STATEMENTS
This manual main purpose is to help students,
professionals, and contractors to somehow understood and
help them to manually estimate project scopes in each
different set of categories. If there are errors in computation
and everything the author of this manual is open for revising
this first manual in estimate.