You are on page 1of 192

MANUAL CONSTRUCTION ESTIMATE GUIDE

MANUAL
CONSTRUCTION
ESTIMATE GUIDE
(A STEP BY STEP GUIDE FOR YOUR
CONSTRUCTION NEEDS)

1|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

TABLE OF CONTENTS
PART 1 ESTIMATES
• INTRODUCTION OF COST ESTIMATES
• 3 KEY TYPES OF ESTIMATE
• METHODS/TECHNIQUES IN ESTIMATE
• CREATING A SAMPLE BOM
• INTRODUCTION TO SAMPLE DESIGN PLANS

PART 2 STRUCTURAL ESTIMATE


MANUAL CONSTUCTION ESTIMATE GUIDE

• CONCEPTS IN STRUCTURAL SCOPE FOR CONSTRUCTION


• CONCRETING
• MASONRY
• METAL REINFORCEMENT
• LUMBER
• FORM/SCAFFOLDINGS AND STAGING
• ROOFING WORKS

PART 3 ARCHITECTURAL ESTIMATE


MANUAL CONSTUCTION ESTIMATE GUIDE

• CONCEPTS IN ARCHITECTURAL SCOPE FOR CONSTRUCTION


• CEILING WORKS
• TILEWORKS
• HARDWARE
• PAINTING
• DOORS AND WINDOWS
• CABINETRIES
• METAL WORKS
• AUXILIARY TOPICS

2|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

PART 4 SANITARY AND ELECTRIAL


MANUAL CONSTUCTION ESTIMATE GUIDE

• CONCEPTS IN SANITARY SCOPE FOR CONSTRUCTION


• THE SEPTIC TANK
• WATERLINE
• SEWERLINE
• PLUMBING FITTINGS
• PLUMBING FIXTURES
• CONCEPTS IN ELECTRICAL SCOPE FOR CONSTRUCTION
• THE PANEL BOARD
• LIGHTING LAYOUT
• POWER LAYOUT
• SEWERLINE
• ELECTRICAL FITTINGS
• ELECTRICAL LIGHTS

3|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

DEFINITION

Cost estimation in project management is the process of forecasting the cost and other resources
needed to complete a project within a defined scope. Cost estimation accounts for each element
required for the project and calculates a total amount that determines a project’s budget.

“ESTIMATE HAS ALWAYS BEEN REGARDED AS A VALUATION BASED ON OPINION OR


ROUGHLY MADE FROM IMPERFECT OR INCOMPLETE DATA; A CALCULATION NOT
PROFESSEDLY EXACT, AN APPRAISEMENT; ALSO A STATEMENT , AS BY A BUILDER, IN
REGARD TO THE COST OF CERTAIN WORK” –MAX FAJARDO
THREE KEY TYPES OF ESTIMATES

PRELIMINARY/ROUGH ESTIMATE

• Preliminary estimates are also called rough or approximate estimates,. This is because they
are not final—they give a ballpark idea of how much a project will cost.

• A preliminary estimate is made at the very beginning of a project when there’s limited
information available.

• A preliminary estimate allows a contractor to figure out the budget for a project and what to
charge the client.

• Used to study the feasibility of the project also.

• Used when the design plans is 35% to 50 % complete and is used to check if the proposed
project is on budget.

For example, a roofer is asked by a client to redo the roof of his house. The roofer did a very similar
project three months ago. He uses the estimate from his old project to make a preliminary estimate
for his new project.

• Once more information is available, a business can create a revised estimate, or detailed
estimate, from the preliminary estimate.

4|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

DETAILED/QUANTIFIED ESTIMATE

• A business can convert a preliminary estimate to a detailed estimate. A detailed estimate is


drawn up when there’s more information available or the scope of the project is better
known.

• Detailed estimates include incredibly detailed information on quantities, costs and rates—in
fact, all items necessary to complete the project. All the line items are added together to
reach the final cost.

• It includes a list of quantities for all materials needed to complete a project. Its purpose is to
give the client a complete list of all the quantities required for the project and what the cost
will be for each quantity. It is a key estimating method in construction.

• They are prepared from a complete or nearly complete set of drawings and are the most
accurate type of estimate.

• Besides these line items, detailed estimates can also include:

• Information on the rates used to calculate costs (see quantity estimate below)

• Specifications

• Drawings for the areas included in the project (including an index and key)

• Detailed estimates are often used as a contractor’s budget estimate. This planning tool helps
him know how much cash flow he needs and whether he requires financing.

BID ESTIMATE

• A bid estimate is submitted to a potential client in hopes of winning a project. It is based on


both a contractor’s prior estimations as well as her desire to win the project i.e. to provide
the best price to hopefully outbid competitors.

• A general contractor may only put a lot of work into this cost estimation method if she
believes her chance of winning the bid is high. Otherwise, it’s a waste of her time.

• A bid estimate can be drawn up based on plans provided by the client or on standard
industry costs. If the contractor wants more accurate amounts, she will need to calculate
specific labor, material and equipment costs for the project.

• For example, a landscaper is hired to redo the backyard of a client’s house. He uses his
hourly wage and material costs to arrive at a total for a bid estimate. The landscaper charges
his standard hourly rate (Php 80 per hour) for 25 hours of work. However, he decides to
mark up his material costs less than he usually does to outbid a competitor.

5|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

METHODS OF ESTIMATE
❑ KNOWING THE ACTUAL MARKET COST

❑ PROJETING FEASIBLE TIMELINE

❑ DETAILED ORIENTED ON SCOPE OF WORKS

❑ KNOWING ALL THE CONSTRUCTION RISKS

❑ ALLOCATING AVAILABLE RESOURCES

❑ IMPLEMENTING QUALITY

❑ BASIC KNOWLEDGE IN CONSTRUCTION

❑ KNOWLEDGE IN RAW MATERIALS ,EQUIPMENT AND LABOR

ACTUAL CONSTRUCTION

FIGURE 1.1

6|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

CREATING A SAMPLE BOM


What Is a Bill of Materials (BOM)?
A bill of materials (BOM) is an extensive list of raw materials, components, and instructions required
to construct, manufacture, or repair a product or service. A bill of materials usually appears in a
hierarchical format, with the highest level displaying the finished product and the bottom level
showing individual components and materials.

❑ STEP 1
1. LIST DOWN ALL THE REQUIRED SCOPE OF WORKS (BE SPECIFIC AND DETAILED) SPECIFIED
WITH THE CONTRACT AND BUILDING SPECIFICATIONS OF THE PROJECT. LIST DOWN EVERY
REQUIREMENTS INTO SET OF CATEGORIES.

NOTE: ALSO BE AWARE OF DESIGN PLANS AND SPECIFICATION INDICATED BY THE PROJECT.

GENERAL REQUIREMENTS
❑ STRUCTURAL WORKS
❑ ARCHITECTURAL WORKS
❑ PLUMBING WORKS
❑ ELECTRICAL WORKS
❑ TINSMITHRY/ROOFING WORKS
❑ METAL WORKS
❑ CABINETRIES/WOOD WORKS
❑ AUXILLARY WORKS

I. GENERAL REQUIREMENTS

❑ DESIGN PLANS

❑ AS-BUILT PLANS

❑ BUILDING PERMITS

❑ PROVISION OF TEMPORARY BOARD UP, COVER AND SIGNAGES

❑ TEMPORARY FACILITIES

❑ LOT RELOCATION

❑ MOBILIZATION/DEMOBILIZATION/SITE CLEARING

❑ TERMITES/SOIL POISONING

❑ EXCAVATION

❑ EMBANKMENT

❑ STAKING OUT/LAYOUT

7|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

II. STRUCTURAL WORKS

❑ CONCRETING
▪ RC FOOTING
▪ RC COLUMNS (GF TO 2F)
▪ TIE BEAMS/WALL FOOTINGS
▪ SLAB ON GRADE
▪ SUSPENDED BEAMS
▪ SUSPENDED SLABS
▪ RC COLUMNS (2F TO RB)
▪ RC ROOFBEAMS

❑ MASONRY/ REINFORCEMENT
▪ MASONRY WORKS
▪ (INTERIORWALLS AND EXTERIOR WALLS)
▪ PLASTERING WORKS
▪ STAIRS

❑ FORMWORKS
▪ SCAFFOLDINGS

III. ARCHITECTURAL WORKS


❑ CEILING WORKS
❑ DOORS
❑ WINDOW/GLASS WORKS
❑ TILE WORKS
❑ PAINTING WORKS

IV. PLUMBING WORKS

V. ELECTRICAL WORKS

VI. TINSMITHRY/ROOFING WORKS

VII. METAL WORKS

VIII. CABINETRIES/WOOD WORKS

IX. AUXILLARY WORKS

8|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑ STEP 2
2. TRASFER THE LIST THAT YOU MADE INTO AN EXCEL SOFTWARE THAT YOU WILL USE
THEN LIST DOWN NECESSARY MATERIALS FOR EACH CATEGORIES. MAKE A TABLE
WITH HEADERS INDICATING THE FF:(ITEM NO., SCOPE OF WORKS, UNIT, UNIT PRICE
AND AMOUNT, LABOR, EQUIPMENT , TOTAL COST)

Example:
FORMAT I

FIGURE 1.2

FORMAT II

FIGURE 1.3

9|P age
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑ STEP 3

3. TRY INPUTTING ALL THE INITIAL DATAS FOR COST/UNIT PRICE THAT YOU ALREADY HAVE
AND KNOW.

EXAMPLE:

❑ STEP 4

4. ON A SEPARATE SCRATCH PAPERS PROCEED WITH THE PROJECT ESTIMATES IN EACH


CATEGORIES.

YOU MAY ALSO START TO GET A QUOTE FROM DIFFERENT SUPPLIERS MAINLY THE FOLLOWING:

HARDWARES

GRAVEL & SAND SUPPLIER

AND MORE (ROOF SUPPLIER, WINDOW SUPPLIER, DOORS FABRICATOR ETC).

10 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑ STEP 5

5. ONCE DONE WITH ALL THE GATHERED DATAS.I NPUT THEM ONE BY ONE IN THE EXCEL FILE
AND CAREFULLY CHECK IT ALSO FROM TIME TO TIME.

EXAMPLE:

FIGURE 1.4

11 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑ STEP 6

6. “MARKING UP”

INDICATING OTHER COSTS RELATED IN CONSTRUCTION MAINLY THE FOLLOWING.

NOTE: MARKING UP OF THIS PERCENTAGE MAY VARIES FROM TIME TO TIME DUE TO THE
MARKET, SUPPLY AND DEMAND AND OTHER THINGS THAT MAY AFFECT THE COSTING.

I. MATERIAL COST
FROM THE BREAKDOWN OF MATERIALS MARK UP THE NUMBER OF QUANTITY OF
MATERIAL ITEMS INTO 5% TO 20% TO BE ABLE TO CONSIDER THE WASTAGE FACTOR.
EXAMPLE:
TOTAL QUANTITY OF PLYWOOD : 10 PCS (3/4 INCHES MARINE PLYWOOD)
X .20 (WASTAGE FACTOR PERCENTAGE)
ADDITIONAL MATERIALS + 2PCS OF PLYWOOD
TOTAL PLYWOOD : = 10+2 = 12 PCS NO. OF MARINE PLYWOOD

II. LABOR COST


A. Can be estimated using the man/hour or
productivity rate of workers.

Example:

12 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

B. Can be estimated using the labor cost multiply bit


the estimated percentage of 35% to 50 %.

EXAMPLE:
TOTAL MATERIAL COST : PHP 1,000,000
X .50
TOTAL LABOR COST = PHP 500,000

III. VATS/TAXES
WITH THE TOTAL OF MATERIAL COST MULTIPLY IT INTO 12% (MAY VARIES ON
WHAT KIND OF TAXES AND LOCATION OF THE PROJECT) .

EXAMPLE:
TOTAL MATERIAL COST : PHP 1,000,000
X .12
VATS/TAXES COST OF MATERIAL= PHP 120,000

IV. MISCELLANEOUS COST/CONTINGENCY COST


WITH THE TOTAL OF LABOR AND MATERIAL COST MULTIPLY IT INTO 3%-
10%.(MAY VARIES)
EXAMPLE:
TOTAL LABOR&MATERIALS COST : PHP 1,000,000
X .03
CONTINGENCY COST = PHP 30,000

13 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

V. OVERHEAD & PROFIT


❑ WITH THE TOTAL OF LABOR AND MATERIAL COST GET A PERCENTAGE INTO 5%-30%.
(MAY VARIES)
EXAMPLE:

TOTAL LABOR&MATERIALS COST : PHP 1,000,000


X .08
OVERHEAD AND PROFIT = PHP 80,000

❑ STEP 7
“Indicate at the final amount:
The ff:
❖ Discounted Cost(if any)
❖ Exclusions
❖ Total working or calendar days.

FIGURE 1.5

14 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.6 (ARCHITECTURAL PLAN)

15 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.7 (ARCHITECTURAL PLAN)

16 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.8 (ARCHITECTURAL PLAN)

17 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.9 (ARCHITECTURAL PLAN)

18 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.10 (STRUCTURAL PLAN)

19 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.11 (STRUCTURAL PLAN)

20 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.12 (STRUCTURAL PLAN)

21 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.13 (PLUMBING PLAN)

22 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.14 (PLUMBING PLAN)

23 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.15 (ELECTRICAL PLAN)

24 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 1.16 (ELECTRICAL PLAN)

25 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

TYPICAL STRUCTURAL FORM OF RESIDENTIALS

26 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FIGURE 2.1 (STRUCTURAL SYSTEM OF SAMPLE WORKING DRAWING)

FIGURE 2.2 (STRUCTURAL SYSTEM OF SAMPLE WORKING DRAWING)

27 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

A. HOW TO ESTIMATE FOOTINGS


o CONCRETING
o REINFORCEMENT

TYPES OF FOOTINGS

28 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

I. CONRETING OF FOOTINGS

FROM MAX FAJARDO BOOK

CLASSES OF MIXTURE IN PSI

CLASS PSI EQUIVALENT

AA 4000 PSI

A 3500 PSI

B 2500 PSI

C 2000 PSI

29 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE:

30 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

31 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SOLUTION
A. BY VOLUME METHOD
1. FIND THE VOLUME OF THE FOOTING (C1F1) (NO.1 PCS)

VOLUME= LENGTH X WIDTH X THICKNESS OF FOOTING


(REFER TO FOOTING SCHEDULE)

VOLUME= 1.20 m x 1.20 m x 0.35 m


VOLUME= 0.50 cubic m.

2. REFER TO THE TABLE:

FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:
CEMENT = 0.50 X 9 (USING 40KG/BAG) = 4.5 BAGS = APPROX 5 BAGS
SAND = 0.5 X 0.50=0.25= APPROX 0.50 cu.m sand
GRAVEL=0.5 X 1.0= APPROX 0.50 cu.m gravel (3/4)

3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS DATA IS FOR ONLY ONE FOOTING THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE FOOTING YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).

32 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE:
GET THE TOTAL VOLUME
FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:

FOR C1/F1 (11 UNITS)

TOTAL VOLUME= 0.50 X 11 PCS =5.5 CUBIC METERS


CEMENT = 0.50 X 9 (USING 40KG/BAG) = 4.5 BAGS = APPROX 5 BAGS X 11=55 BAGS
SAND = 0.5 X 0.50=0.25= APPROX 0.50 cu.m sand X 11 = 5.5 cu.m sand
GRAVEL=0.5 X 1.0= APPROX 0.50 cu.m gravel (3/4) X 11= 5.5 cu.m sand

FOR C1/F2 (3 UNITS)

TOTAL VOLUME= 1.0 X 1.0 X 0.3 X (3 UNITS OF FOOTINGS) =0.9 CUBIC METERS
CEMENT = 0.90 X 9 (USING 40KG/BAG) = 8.1 BAGS = APPROX 9 BAGS
SAND = 0.9 X 0.50=0.45= APPROX 0.50 cu.m sand
GRAVEL=0.9 X 1.0= 0.90 cu.m gravel (3/4) X 11= 1 cu.m gravel (3/4)

INSERT THE TWO DATAS:

ORDER:
CEMENT = 55+ 9 = 64 BAGS
SAND = 5.5+ .5 = 6 cu.m sand
GRAVEL= 0.5 + 5.5= 6.5= 7 cu.m sand

33 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

INSERT INTO THE BOM FORMAT:


FINAL OUTPUT: (IF YOU WANT TO INCLUDE THE WASTAGE FACTOR ALREADY MARK UP
THE QUANTITY INTO 5-10 % INCREASE)

B. REINFORCEMENT
STEPS:
1. Know the actual dimensions of the footing as to it’s length and width.
2. Remember that the minimum underground protective covering of concrete to the
steel reinforcement is 7.5cm.
3. If the plan does not call for a hook or bend of the footing reinforcement, the length
of the bar is equal to the length or width of the footing minus the protecting
covering at both ends.

STEPS:
4. If the plan calls for a hook or bend of the reinforcement, the bar-cut should
include the allowances for hook and bend as presented in Figure 3-4 and 3-5.
5. Know the spacing distance of the steel bars both ways o determine the exact
number required. As much as possible, select the appropriate steel bar length which
is divisible by the cut length to avoid unwanted extra cuts.

34 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

ADDITIONAL INFORMATION:

35 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SOLUTION
FOR 1 FOOTING C1(F1)
A. CUTTING LIST-METHOD
INCLUDE THE CONCRETE COVERING FOR UNDERGROUND STRUCTURES= 75 MM
FOR ABOVE THE GROUND STRUCTURES = 40 MM

CUT LENGTH:

NOTE THAT THE COMMERCIAL LENGTH OF REBARS USED IN THIS FOOTING ARE
10MM WITH 6METERS LENGTH.

1. COMPUTE TOTAL LENGH FOR ONE PCS OF REBAR


1.05 M + 0.2 + 0.2 = 1.45 m = approx. 1.5 m

36 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

2. COMPUTE THE NO.PCS REQUIRED

ALONG W:

PCS REQUIRED = 1.2 M DIVIDE (BOTTOM BARS SPACING) + (1)


= 1.2 M DIVIDE 0.20M
= 6 PCS +1
= 7 PCS (1.5m ALONG W)

ALONG L:
PCS REQUIRED = 1.2 M DIVIDE (BOTTOM BARS SPACING) + (1)
= 1.2 M DIVIDE 0.20M
= 6 PCS +1
= 7 PCS (1.5 m ALONG L)

THEREFORE:
TOTAL LENGTH: 7PCS (1.5) + 7PCS (1.5)= 21 M
COMMERCIAL LENGTH : 6M OF REBARS
21 METERS DIVIDE 6 = 3.5 =APPROX 4 PCS (16MM REBAR) FOR ONE FOOTING.

37 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

ILLUSTRATION:

FOR G.I WIRES

SOLUTION:
FORMULA A

38 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SOLUTION :
FOR 4 PCS (16MM)

1. GET THE KG/M OF 16MM


USING THE FORMULA A.

KG/M= (16 X 16) DIVIDE (162.2)= 1.578 KG/M

2. GET THE KG OF GI WIRE @ 4PCS 6M LENGTH OF REBARS

GI WIRE(KG) = 1.578 (KG/M) X 6M X 4 PCS X 0.02 (% AS PER REBARS)


=0.78 KG OF GI.WIRE
= APPROX 1KG OF GI WIRE.

SUMMARY THEREFORE IN 1 COLUMN FOOTING:

NOTE: ALWAYS CHECK THE VALUES AND ALSO THE WASTAGE FACTORS.

39 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

B. HOW TO ESTIMATE COLUMNS


o CONCRETING
o REINFORCEMENT

(ACUAL COLUMN PICTURE)

40 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

COLUMNS GENERAL INFORMATION

41 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

LAPPING LENGTHS

42 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE:

FROM THE SAMPLE WORKING DRAWING:

43 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

ISOMETRIC VIEW
APPROX HEIGHT FROM BOT OF FOOTING TO
ROOFBEAM= 8.86 METERS

FOR 1PC- C1
I. BY VOLUME METHOD
1. FIND THE VOLUME OF THE COLUMN (C1F1) (NO.1 PCS)

VOLUME= LENGTH X WIDTH X HEIGHT OF COLUMN


(REFER TO COLUMN SCHEDULE)

VOLUME= 0.4 m x 0.2 m x 8.86 m


VOLUME= 0.71 cubic m. (FOR 1 COLUMN)

44 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

2. REFER TO THE TABLE:

FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:

CEMENT = 0.70 X 9 (USING 40KG/BAG) = 6.3 BAGS = APPROX 7 BAGS


SAND = 0.7 X 0.50=0.35= APPROX 0.50 cu.m sand
GRAVEL=0.7 X 1.0=0.7= APPROX 1 cu.m gravel (3/4)

3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS DATA IS FOR ONLY ONE COLUMN THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE COLUMN YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).

45 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

4. REINFORCEMENT

SECTION OF C1
46 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

1. MAKE/SKETCH A PROPOSED CUTTING LIST


USING ALL THE PROVISIONS NEEDED.

47 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

By following the staggered in splicing:

Summary:
LENGTH OF A = 3.58 m + (16d= 0.256) =3.9m (6PCS)
LENGTH OF B = 6 Meters (4pcs)
LENGTH OF C = 0.8m + 0.8m + 3.7m =5.3 m (2pcs)
LENGTH OF D = 0.8+ 0.3 + 0.15= 1.25m (2pcs)

THEREFORE ORDER:

TOTAL L= 3.9 (6) + 6 (4) + 5.3 (2)+ 1.2 (2)


L= 60.4

FOR VERTICAL BARS USING 16MM:


PCS OF VERTICAL BARS= 60.4 DIVIDE BY 6 METERS = 10.06 PCS
= APPROX 11PCS = MARK UP 12PCS (16MM)

48 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FOR TIES BARS USING 16MM:

FROM NATIONAL STRUCTURAL CODE OF THE PHILIPPINES

USING THE 135 DEGREE HOOK

MINIMUM INSIDE BEND DIAMETER

4 DB = 4 (10) = 40MM

6 DB = 6 (10) = 60 MM or 75mm

Therefor for

49 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

a. Compute for total perimeter of stirrups considering the concrete cover =40mm

P= 200 + 400 +200 +400 – 4(40)


P= 880mm

b. For Total Straight Extension (2 HOOKS) (total hook length)

o 6 DB = 6 (10) = 60 MM or 75mm (use 75mm as per code)

Total Hook= 3db + 75mm


Total Hook = 3(10) +75 mm
Total Hook = 105mm (use 2pcs for 2 hooks length)

c. For 5 bends (Total bend length)


3 pcs (90 degree bend = 2db) + 2pcs (135 degree bend= 3db)
3 (2db)+ 2 (3db)
3 (2)(10) + 2(3)(10)
=120mm

Total Cutting Length = Perimeter of Rectangle + Total Hook Length -Total Bend length

Total Cutting Length = 880 + (3db + 75 mm) – 3db (2) -2db (3)

= 880+ 2(3(10) + 75mm)- 3(10)(2) -2 (10)(3)

= 970 mm Approx 1000MM for easy cut.

50 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SHORCUT METHOD

Note: applicable for 2 storey -3 storey using 10mm for stirrups

TOTAL LENGTH = PERIMETER – 230 (FACTOR USE)


= 2(200)+2(100)-230
= 970 mm approx. 1000mm

Therefore same solution.


d. Get the number of pcs that can 1 pc of 10mm x 6m rebars
PCS= 6meters divide by 1000meters
PCS = 6 PCS FOR EVERY 1pcs of 10mm

51 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

e. For Total Column Stirrups in one column

FOLLOWING THE SPACING @ the column details

52 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

CUTTING LIST FOR STIRRUPS

TOTAL NUMBER OF PCS = 8PCS + 24PCS +30 PCS

= 62 PCS (1000mm length of stirrups)

THEREFORE ORDER: 62 DIVIDE 6 PCS(EVERY 1PC OF 10MM) = 10. 33

ORDER = 11 PCS OF 10MM (6M LENGTH)

53 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

f. Solve for G.I Wire

SUMMARY:
FOR 12 PCS (16MM) -VERTICAL BARS
FOR 11 PCS (10MM) -STIRRUPS

GET THE KG/M OF 10 AND 16MM


USING THE FORMULA A.

KG/M= (16 X 16) DIVIDE (162.2)= 1.578 KG/M

KG/M= (10 X 10) DIVIDE (162.2)= 0.617 KG/M

GET THE KG OF GI WIRE

@ 12PCS FOR 16MM


GI WIRE(KG) = 1.578 (KG/M) X 6M X 12 PCS X 0.02 (% AS PER REBARS)
=2.27 KG OF GI.WIRE
= APPROX 3 KG OF GI WIRE.

@11 PCS FOR 10MM


GI WIRE(KG) = 0.617 (KG/M) X 6M X 11 PCS X 0.02 (% AS PER REBARS)
=0.81 KG OF GI.WIRE
= APPROX 1KG OF GI WIRE.

THEREFORE ORDER: 4 KGS GI.WIRE #16

g. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

54 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

C. HOW TO ESTIMATE BEAMS, TIE BEAMS AND ROOF


BEAMS
o CONCRETING
o REINFORCEMENT

Actual Picture of Suspended Beams and Girders

55 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

GENERAL INFORMATION ON BEAMS

56 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

57 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

LAP LENGTH

58 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

59 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

60 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM WORKING DRAWING:


ESTIMATE MATERIALS AT BEAM A5 TO D5

61 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

1. CONCRETING

BY VOLUME METHOD
FIND THE VOLUME OF THE BEAM FROM A TO D

VOLUME= WIDTH BEAM X DEPTH BEAM X LENGTH OF BEAM


= (0.2M) X (0.4M) X (2.8M+2.55M + 5.65)
= 0.88 cu.m

62 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

2. REFER TO THE TABLE:

FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:

CEMENT = 0.88 X 9 (USING 40KG/BAG) = 7.92 BAGS = APPROX 8 BAGS


SAND = 0.88 X 0.50=0.44= APPROX 0.50 cu.m sand
GRAVEL=0.88 X 1.0=0.88= APPROX 1 cu.m gravel (3/4)

3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS DATA IS FOR ONLY ONE COLUMN THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE COLUMN YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).

63 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

4. Reinforcements

Using the cutting list method following the lapping splice


locations.

ACTUAL PLAN

64 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

PROPOSED CUTTING LIST

To get the total embedment length of beam


Through the column.

Solution:
Lebd= Column size- Concrete cover- Column Main Bar- Lateral Ties dia.
= 0.2 m -0.040 m- 0.016m – 0.010 m
= 134 mm

16db= 16 (16) = 246mm

Total bend = 134+246= 380 mm

ACTUAL
MIN LAP LENGTH 50D= 50(16)= 800MM

LENGTH LOCATION PCS

A 4.85+.380=5.23m TOP BAR (RIGHT) 2

B 5.13m TOP BAR (MID) 2

C 3.22+.380=3.6m TOP BAR (LEFT) 2

D 2.1m XTRA BAR 1


(RIGHT) BOT

65 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

E 1.92m XTRA BAR (MID) 1


BOT

F 4.24m XTRA BAR (LEFT) 1


BOT

G 3.52+.380= 3.9m BOT BAR (RIGHT) 2

H 4.21 m BOT BAR (MID) 2

I 5.62+.380 = 6m BOT BAR (LEFT) 2

:by Theoretical:

Total L= 2(5.23)+2 (5.13) + 2 (3.6)+


2.1+1.92+4.24+2(3.9)+2(4.21)+2(6)

L=64.4 =10.73 = 11 pcs

:by Cutting list:

APPROX via Cutting List = 12 pcs (16mm x 6meters )

FOR STIRRUPS

ACTUAL PCS: 25 +25 +41 =91PCS

66 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

MINIMUM INSIDE BEND DIAMETER

4 DB = 4 (10) = 40MM

6 DB = 6 (10) = 60 MM or 75mm

Therefor for

a. Compute for total perimeter of stirrups considering the concrete cover


=40mm

P= 200 + 400 +200 +400 – 4(40)


P= 880mm

b. For Total Straight Extension (2 HOOKS) (total hook length)

o 6 DB = 6 (10) = 60 MM or 75mm (use 75mm as per code)

Total Hook= 3db + 75mm


Total Hook = 3(10) +75 mm

67 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

Total Hook = 105mm (use 2pcs for 2 hooks length)

c. For 5 bends (Total bend length)


3 pcs (90 degree bend = 2db) + 2pcs (135 degree bend= 3db)
3 (2db)+ 2 (3db)
3 (2)(10) + 2(3)(10)
=120mm

Total Cutting Length = Perimeter of Rectangle + Total Hook Length -Total Bend length

Total Cutting Length = 880 + (3db + 75 mm) – 3db (2) -2db (3)

= 880+ 2(3(10) + 75mm)- 3(10)(2) -2 (10)(3)

= 970 mm Approx 1000MM for easy cut.

d. Get the number of pcs that can 1 pc of 10mm x 6m rebars


PCS= 6meters divide by 1000meters
PCS = 6 PCS FOR EVERY 1pcs of 10mm

TOTAL NUMBER OF PCS = 91 PCS (1000mm length of stirrups)

THEREFORE ORDER: 91 DIVIDE 6 PCS(EVERY 1PC OF 10MM) = 15.16

ORDER = 16 PCS OF 10MM (6M LENGTH)

68 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

e. Solve for G.I Wire

SUMMARY:
FOR 12 PCS (16MM) -MAIN BARS
FOR 16 PCS (10MM) -STIRRUPS

GET THE KG/M OF 10 AND 16MM


USING THE FORMULA A.

KG/M= (16 X 16) DIVIDE (162.2)= 1.578 KG/M

KG/M= (10 X 10) DIVIDE (162.2)= 0.617 KG/M

GET THE KG OF GI WIRE

@ 12PCS FOR 16MM


GI WIRE(KG) = 1.578 (KG/M) X 6M X 12 PCS X 0.02 (% AS PER REBARS)
=2.27 KG OF GI.WIRE
= APPROX 3 KG OF GI WIRE.

@16 PCS FOR 10MM


GI WIRE(KG) = 0.617 (KG/M) X 6M X 16 PCS X 0.02 (% AS PER REBARS)
=1.184 KG OF GI.WIRE
= APPROX 2 KG OF GI WIRE.

THEREFORE ORDER: 5 KGS GI.WIRE #16

69 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

f. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS CONTINOUS BEAM IS JUST AN EXAMPLE ONLY THE WHOLE BEAM DETAILS ARE
NOT YET ESTIMATED.

D. HOW TO ESTIMATE FOR ROOFBEAMS:

ACTUAL PICTURE OF ROOF BEAMS

“USE THE SAME METHOD IN ESTIMATING A SUSPENDED BEAMS.”

70 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

E. HOW TO ESTIMATE TIE BEAMS


o CONCRETING
o REINFORCEMENT

NOTE: APPROACH IN ESTIMATING THE CONCRETING AND


REINFORCEMENT IN TIE BEAMS JUST INTERCHANGE THE LAPPING
ZONE FOR TOP PARS AT L/8 NOT EXCEEDING L/4 FOR BOTTOM BARS
MIDDLE L/3 OF THE SPAN.

71 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE:

1. CONCRETING

BY VOLUME METHOD
FIND THE VOLUME OF THE BEAM FROM A TO D

VOLUME= WIDTH BEAM X DEPTH BEAM X LENGTH OF BEAM


= (0.2M) X (0.4M) X (2.8M+2.55M + 5.65)
= 0.88 cu.m

72 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

2. REFER TO THE TABLE:

FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:

CEMENT = 0.88 X 9 (USING 40KG/BAG) = 7.92 BAGS = APPROX 8 BAGS


SAND = 0.88 X 0.50=0.44= APPROX 0.50 cu.m sand
GRAVEL=0.88 X 1.0=0.88= APPROX 1 cu.m gravel (3/4)

3. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS DATA IS FOR ONLY ONE COLUMN THEREFORE IN ORDER TO COMPUTE THE
TOTAL VOLUME OF ALL THE COLUMN YOU MUST MULTIPLY IT ALL WITH THE
CORRESPONDING TOTAL UNITS OF FOOTING WITH RESPECT TO THEIR VOLUMES ALSO
ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%).

73 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

4. REINFORCEMENTS
PROPOSED CUTTING LIST

To get the total embedment length of beam


Through the column.

Solution:
Lebd= Column size- Concrete cover- Column Main Bar- Lateral Ties dia.
= 0.2 m -0.040 m- 0.016m – 0.010 m
= 134 mm

16db= 16 (16) = 246mm

Total bend = 134+246= 380 mm

ACTUAL
MIN LAP LENGTH 50D= 50(16)= 800MM

LENGTH LOCATION PCS

A 3.52+.380= 3.9m TOP BAR (RIGHT) 3

B 4.21 m TOP BAR (MID) 3

C 5.62+.380 = 6m TOP BAR (LEFT) 3

74 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

D 4.85+.380=5.23m BOT BAR (RIGHT) 3

E 5.13m BOT BAR (MID) 3

F 3.22+.380=3.6m BOTA BAR (LEFT) 3

:by Cutting list:

APPROX via Cutting List = 18 pcs (12mm x 6meters )

FOR STIRRUPS
MINIMUM INSIDE BEND DIAMETER

4 DB = 4 (10) = 40MM

6 DB = 6 (10) = 60 MM or 75mm

Therefor for

75 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

1. Compute for total perimeter of stirrups considering the concrete cover


=40mm

P= 200 + 400 +200 +400 – 4(40)


P= 880mm

2. For Total Straight Extension (2 HOOKS) (total hook length)

o 6 DB = 6 (10) = 60 MM or 75mm (use 75mm as per code)

Total Hook= 3db + 75mm


Total Hook = 3(10) +75 mm
Total Hook = 105mm (use 2pcs for 2 hooks length)

3. For 5 bends (Total bend length)


3 pcs (90 degree bend = 2db) + 2pcs (135 degree bend= 3db)
3 (2db)+ 2 (3db)
3 (2)(10) + 2(3)(10)
=120mm

Total Cutting Length = Perimeter of Rectangle + Total Hook Length -Total Bend length

Total Cutting Length = 880 + (3db + 75 mm) – 3db (2) -2db (3)

= 880+ 2(3(10) + 75mm)- 3(10)(2) -2 (10)(3)

= 970 mm Approx 1000MM for easy cut.

4. Get the number of pcs that can 1 pc of 10mm x 6m rebars


PCS= 6meters divide by 1000meters
PCS = 6 PCS FOR EVERY 1pcs of 10mm

5. For number of pcs


Total Length Perimeter of tie beams= 12meters divide spacing @ 150mm

= 80 pcs (1meter length)

76 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

USE:

TOTAL L= 80 PCS X 1 METER = 80 METER DIVIDE BY 6 METER = 13.33 =14 PCS

THEREFORE ORDER 14 PCS 10MM (6METER LENGTH)

6. KG OF GI WIRE
SUMMARY:
FOR 18 PCS (12MM) -MAIN BARS
FOR 14 PCS (10MM) -STIRRUPS

GET THE KG/M OF 12 AND 10MM

USING THE FORMULA A.

KG/M= (12 X 12) DIVIDE (162.2)= 0.888 KG/M

KG/M= (10 X 10) DIVIDE (162.2)= 0.617 KG/M

GET THE KG OF GI WIRE

@ 18PCS FOR 12MM

GI WIRE(KG) = 0.888 (KG/M) X 6M X 18 PCS X 0.02 (% AS PER REBARS)

=1.91 KG OF GI.WIRE

= APPROX 2 KG OF GI WIRE.

@14 PCS FOR 10MM

GI WIRE(KG) = 0.617 (KG/M) X 6M X 14 PCS X 0.02 (% AS PER REBARS)

=1.04 KG OF GI.WIRE

= APPROX 2 KG OF GI WIRE.

THEREFORE ORDER: 4 KGS GI.WIRE #16


77 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

7. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS TIE CONTINOUS BEAM IS JUST AN EXAMPLE ONLY THE WHOLE BEAM DETAILS
ARE NOT YET ESTIMATED AND WASTAGE FACTOR ARE NOT INCLUDED.

F. HOW TO ESTIMATE SUSPENDED SLABS


o CONCRETING
o REINFORCEMENT

78 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SUSPENDED SLABS GENERAL INFORMATION

ONE WAY SLAB

79 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

80 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

TWO WAY SLAB

81 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

82 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM SAMPLE WORKING DRAWING:

STEP 1 “ DETERMINE WHAT KING OF SLAB “

TO DETERMINE DIVIDE LX = 5650 INTO LY =2500 = 2.26>2

THEREFORE: ONE WAY SLAB

83 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 2 DETERMINE THE CONCRETING

TOTAL VOLUME : 5.65 X 2.5 X .125 M = 1.76 CU.M


REFER TO THE TABLE:

FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:

CEMENT = 1.76 X 9 (USING 40KG/BAG) = 15.84 BAGS = APPROX 16 BAGS


SAND = 1.76 X 0.50=0.88= APPROX 1 cu.m sand
GRAVEL=1.76 X 1.0=1.76= APPROX 2 cu.m gravel (3/4)

1. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS DATA IS FOR ONLY ONE PORTION OF SLAB THEREFORE IN ORDER TO COMPUTE
THE TOTAL VOLUME OF ALL THE SLAB YOU MUST ESTIMATE IT ONE BY ONE AND
DETERMINE IF IT IS ONE WAY OR TWO WAY SLAB THEN ADD THE ADDITIONAL WASTAGE
FACTOR (5%-20%).

84 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 3 REINFORCEMENTS

85 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

86 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 4 KGS OF G.I. WIRE

SUMMARY:
FOR 13 PCS (12MM) -BOTTOM BARS
FOR 12 + 6 PCS= 18 PCS (12MM) -TOP MAIN BARS

GET THE KG/M OF 12 MM

USING THE FORMULA A.

KG/M= (12 X 12) DIVIDE (162.2)= 0.888 KG/M

GET THE KG OF GI WIRE

@ 31 PCS FOR 12MM

GI WIRE(KG) = 0.888 (KG/M) X 6M X 31 PCS X 0.02 (% AS PER REBARS)

=3.27 KG OF GI.WIRE

= APPROX 4 KG OF GI WIRE.

THEREFORE ORDER: 4 KGS GI.WIRE #16


STEP 5 INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

87 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

G. HOW TO ESTIMATE SLAB ON GRADE


o CONCRETING
o REINFORCEMENT

ACTUAL SAMPLE OF SLAB ON GRADE

EXAMPLE FROM SAMPLE WORKING DRAWINGS

88 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 1. CONCRETING

TOTAL VOLUME : 5.85 X 6.30 X .150 M(APPROX THICKNESS OF SLAB) = 5.53 CU.M
REFER TO THE TABLE:

FOR CEMENT, SAND AND GRAVEL MULTIPLY IT WITH THE FACTOR USED:

CEMENT = 5.53 X 9 (USING 40KG/BAG) = 49.77 BAGS = APPROX 50 BAGS


SAND = 5.53 X 0.50=2.765= APPROX 3 cu.m sand
GRAVEL=5.53 X 1.0=5.53= APPROX 6 cu.m gravel (3/4)

89 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 2. REINFORCEMENTS

STEP 3 G.I. WIRE

SUMMARY:
FOR 54 PCS (10MM)

90 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

GET THE KG/M OF 10 MM

USING THE FORMULA A.

KG/M= (10 X 10) DIVIDE (162.2)= 0.617 KG/M

GET THE KG OF GI WIRE

@ 54 PCS FOR 10MM

GI WIRE(KG) = 0.617 (KG/M) X 6M X 54 PCS X 0.02 (% AS PER REBARS)

=3.99 KG OF GI.WIRE

= APPROX 4 KG OF GI WIRE.

THEREFORE ORDER: 4 KGS GI.WIRE #16

STEP 4 INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS DATA IS FOR ONLY ONE PORTION OF SLAB THEREFORE IN ORDER TO COMPUTE
THE TOTAL VOLUME OF ALL THE SLAB YOU MUST ESTIMATE IT ONE BY ONE THEN ADD THE
ADDITIONAL WASTAGE FACTOR (5%-20%).

91 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

H. HOW TO ESTIMATE MASONRY WORKS


o CONCRETE HOLLOW BLOCKS
o MORTAR FOR FILLER AND BLOCK LAYING
o REINFORCEMENT
o PLASTERING WORKS

ACTUAL MASONRY WORKS

92 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

GENERAL INFORMATION

93 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM SAMPLE WORKING DRAWINGS

94 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

95 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

USING .025 THICKNESS OF PLASTERING


FACTORS: 0.3 FOR CEMENT AND 0.025 FOR SAND

OTHERS IF 16MM IS USED

96 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

97 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

5. KGS OF GI WIRE
SUMMARY:
FOR 3 PCS (12MM) -VERTICAL BARS
FOR 4 PCS (10MM) -HORIZONTAL BARS

GET THE KG/M OF 12 AND 10MM

USING THE FORMULA A.

KG/M= (12 X 12) DIVIDE (162.2)= 0.888 KG/M

KG/M= (10 X 10) DIVIDE (162.2)= 0.617 KG/M

98 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

GET THE KG OF GI WIRE

@ 3PCS FOR 12MM

GI WIRE(KG) = 0.888 (KG/M) X 6M X 3 PCS X 0.02 (% AS PER REBARS)

=0.32

= APPROX 1 KG OF GI WIRE.

@4 PCS FOR 10MM

GI WIRE(KG) = 0.617 (KG/M) X 6M X 4 PCS X 0.02 (% AS PER REBARS)

=0.30 KG OF GI.WIRE

= APPROX 1 KG OF GI WIRE.

THEREFORE ORDER: 2 KGS GI.WIRE #16

6. INSERT THE DATA IN THE EXCEL FILE FORMAT YOU WANT TO USE:

NOTE: THIS DATA IS FOR ONLY ONE PORTION OF WALL THEREFORE IN ORDER TO COMPUTE
THE TOTAL AREA OF ALL THE WALL YOU MUST ESTIMATE IT ONE BY ONE THEN ADD THE
ADDITIONAL WASTAGE FACTOR (5%-20%).

99 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

I. HOW TO ESTIMATE FORMWORKS


o FORMWORKS FOR COLUMN
o FORMWORKS FOR BEAMS
o FORMWORKS FOR SLABS

ACTUAL PICTURE OF FORMWORKS

100 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

OTHER KINDS OF FORMWORKS

SHORINGS AND DIFFERENT FORMWORKS SUPPORT


SYSTEMS

101 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

GENERAL INFORMATION FOR COLUMN FORMWORKS

102 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE:

SPECIFICATION:

HEIGHT OF COLUMN = 3M USE 2X3 LUMBER FRAME

SIZE OF COLUMN = 200 X400

103 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 1. FIND THE LATERAL SURFACE AREA OF THE FORMWORKS

AREA= PERIMETER OF SURFACE X HEIGHT OF COLUMN

= 2(.200+.400) X 3M

= 3.6 sqm

STEP 2 USE THE DATA FROM TABLE 5-4

STEP 3 SOLVE THE HORIZONTAL, VERTICAL AND DIAGONAL SUPPORT OF 1 COLUMN

104 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

USING TABLE 5-5

USE 2” X 3” FOR VERT, HORIZONTAL, AND DIAGONAL BRACINGS

105 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FOR BEAMS (FORMS , FRAMES AND BRACINGS)

SOLVE THE FORMWORKS AT B1

STEP 1. FIND THE LATERAL SURFACE AREA OF THE FORMWORKS

AREA= PERIMETER OF SURFACE X length of beam

= 2(.400) + 0.2 X 2.75 M

= 2.75 sqm

STEP 2 USE THE DATA FROM TABLE 5-4

Frame= 2.75 x .42 =1.155 = 2 pcs (phenolic board)


Lumber Frame (2x3 wood) = 2.75 x 48 =132 bd.ft (2 x 3)

106 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 3 SOLVE THE HORIZONTAL, VERTICAL AND DIAGONAL SUPPORT OF 1 SPAN BEAM

USING TABLE 5-5

USE 2” X 3” FOR VERT, HORIZONTAL, BRACINGS

FOR BEAM VERTICAL BRACING


BDFT = 2.75 SQM X 6(FACTOR USED) = 16.5 BDFT= 17 BDFT

FOR BEAM HORIZONTAL BRACING


BDFT = 2.75 SQM X 7 (FACTOR USED) = 19.25 BDFT= 20 BDFT

THEREFORE USE : 37 BDFT (2”X3” LUMBER)

NOTE: FOR COMPUTATION FOR SLABS FORMWORKS FOLLOW THE SAME


PROCEDURE AND USED THE TABLE ABOVE. ALWAYS REMEMBER TO INCLUDE
ALL THE WASTAGE FACTOR OF 5% TO 20% FOR THE QUANTITIES. AND ALSO
ALWAYS CHECK WHAT KIND OF FORMWORKS SYSTEM YOU WILL USE.

107 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

J. HOW TO ESTIMATE ROOFING WORKS

108 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SAMPLE ROOF RAMING

FINISHED ROOFING WORKS WITH SPANDRELS

109 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM SAMPLE WORKING DRAWINGS


FIND THE FF:
A. CUTTING LIST ORDER FOR RIB TYPE LONG SPAN ROOF
B. PCS OF 2” X 6 “ STEEL TUBULAR (1.5MM) SPACED @ 1.2 0.C
C. PCS OF 2” X 3” CEE PURLINS (1.2MM) FOR FASCIA
D. PCS OF 2” X 3” CEE PURLINS SPACED @ 0.6 O.C
E. PCS OF GUTTER (24 CUT)

110 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SOLUTION:
A. CUTTING LIST ORDER FOR RIB TYPE LONG SPAN ROOF
BY DIRECT COUNTING :
THEREFORE ORDER CUT LENGTH :

9 PCS (7.9M X 1.050) DARK GRAY COLOR LONG SPAN

111 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

B. PCS OF 2” X 6 “ STEEL TUBULAR (1.5MM) SPACED @ 1.2 0.C

112 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

C. PCS OF 2” X 3” CEE PURLINS (1.2MM) FOR FASCIA

D. PCS OF 2” X 3” CEE PURLINS SPACED @ 0.6 O.C

113 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

E. PCS OF GUTTER (24 CUT)


GUTTER LENGTH AS PER PLAN = 9.2M
FOR 24” CUT APPROX LENGTH OF 1 PCS IS 2.2 M LENGTH

THEREFORE: 9.2 M DIVIDE BY 2.2 =4.18 PCS = 5 PCS (24” CUT GUTTER)

F. INSERT THE SCOPE IN THE B.O.M FORMAT IN EXCEL

OTHER ACCESSORIES
NOTE: FOR OTHER ROOFING ACCESSORIES ALWAYS LOOK FOR THE
MATERIALS REQUIRED IN THE SCOPE OF ROOFING WORKS

114 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

A. HOW TO ESTIMATE CEILING WORKS


THE CEILING MATERIALS:

115 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

116 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FICEM BOARD

GYPSUM BOARD

117 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM SAMPLE WORKING DRAWING

118 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 1 NUMBER OF PCS OF GYPSUM BOARD

STEP 2 NUMBER OF PCS OF WALL ANGLE

119 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 3 NUMBER OF PCS OF CARRYING CHANNEL SPACED @0.60

120 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 4 NUMBER OF PCS OF METAL FURRING SPACED @1.20M

121 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 5 NUMBER OF PCS OF DOUBLE U CLIP

STEP 6 INPUT ALL DATAS IN THE EXCEL FORMAT.

122 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

B. HOW TO ESTIMATE DOORS AND WINDOWS WORKS


PARTS OF THE DOORS:

123 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

DOOR HANDLES

124 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

MODERN TYPES OF DOORS

WINDOWS WORKS/GLASS WORKS

125 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

ACTUAL PICTURES OF SLIDING WINDOW

FRAMES OF CASEMENT WINDOWS


126 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

NOTE: GENERALLY IN ESTIMATING DOORS AND WINDOWS THERE ARE 2


WAYS, OPTION 1 YOU CAN ESTIMATE ALL THE MATERIALS NEEDED IN ONE
DOORS OR WINDOWS. OPTION 2 YOU WILL GET A QUOTATION FOR AN
INSTALLER OR FABRICATOR THEN QUANTIFIED ALL THE INPUT DATAS IN
YOUR EXCEL FORMAT DON’T FORGET TO INCLUDE ALL ACCESSORIES TO THE
QUOTE.

127 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE ONLY:

128 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

C. HOW TO ESTIMATE TILE WORKS

ACTUAL PICTURES
OF TILE WORKS

129 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

130 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

TILE WORKS MATERIALS


❑TILE ADHESIVE

❑TILE GROUT

❑CEMENT
❑SAND
❑TILE SPACER

131 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

OTHER ESTIMATE TABLE USED:

132 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM SAMPLE WORKING DRAWING

DETERMINE THE FF.


1.
2. NUMBER OF CEMENT, SAND, TILE ADHESIVE , TILE GROUTS AND TILE
SPACERS.

133 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 1 NUMBER OF 60X60 TILES

STEP 2 NUMBER OF CEMENT, SAND, TILE ADHESIVE


, TILE GROUTS AND TILE SPACERS.
NOTE: THE VALUES AT THE RED BOX ARE FACTORS USED

134 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 3 INSERT THE DATAS INTO THE EXCEL


FORMAT

NOTE: THIS DATA IS FOR ONLY ONE PORTION OF FLOORING


THEREFORE IN ORDER TO COMPUTE THE TOTAL MATERIALS OF ALL
THE FLOORINGS IN THE PLAN YOU MUST ESTIMATE IT ONE BY ONE
THEN ADD THE ADDITIONAL WASTAGE FACTOR (5%-20%) IN EACH
ITEM INCREASE.

135 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

D.HOW TO ESTIMATE PAINTING WORKS

136 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

137 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

MASONRY WALLS

138 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

METALS

EPOXY PRIMER

QUICK DRY ENAMEL

139 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

WOODS

140 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM WORKING DRAWINGS

DETERMINE:
❑GALLONS OF PAINT
❑BAGS OF SKIMCOATS

141 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SOLUTION:

INSERT DATAS INTO BOM EXCEL FORMAT

142 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

E. HOW TO ESTIMATE CABINETRIES/WOOD WORKS

ACTUAL CABINETRIES

143 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM SAMPLE WORKING DRAWINGS:

SPECIFICATIONS

144 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SPECIFICATIONS

145 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

146 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

: INSERT THE DATAS IN THE EXCEL BOM

147 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

F. HOW TO ESTIMATE METAL WORKS


FROM THE SAMPLE WORKING DRAWING

148 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

149 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SAMPLE FINISHED WORKS

PERSPECTIVE

150 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

A.HOW TO ESTIMATE SEPTIC TANK

OLD PLANS FOR SEPTIC VAULT

151 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

152 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

VOLUME OF SEPTIC TANK


TECHNICAL DATA IN DETERMINING THE VOLUME OF
SEPTIC TANK
MINIMUM WIDTH 90 CM
MINIMUM LENGTH 150 CM
MINIMUM DEPTH 120 CM

For residential buildings 0.14 TO 0.17 cu.m


to serve larger number of
people, allocate of liquid
per person
For small residential
house to serve up o 12
persons , the chamber
should have a liquid
content of not more than 2.0 cubic meters
For school , commercial
and industrial
establishments, the
volume of the septic tank
should not be less than.. .057 cu.m nor
More than……………….. .086 cu.m /person

153 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

ESTIMATE OF SEPTIC TANK FROM SAMPLE WORKING


DRAWINGS

154 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

PERIMETER = 2(3.5) + 4 (1.5) = 13 meters

155 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

156 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

For Plumbing Works:


1. Quantify all needed pipe fittings.

157 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

SOME PIPE FITTINGS

158 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

159 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

160 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

161 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

162 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

163 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

164 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

165 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

166 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

B. HOW TO ESTIMATE WATERLINE SYSTEM

167 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

168 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 1
DETERMINE THE TOTAL LENGTH OF ½ “ PIPE NEEDED IN THE SYSTEM

169 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑ MEASURE OR QUANTIFIED ALL THE LINEAR METER OF THE


PIPE

TOTAL LINEAR METER = 32.947


IN A ½ INCHES PIPE THEIR LENGTH IS 3M AVAILABLE.

SO TO GET THE QTY. DIVIDE THE TOTAL LINEAR METER INTO 2.7M
(DEVELOPMENT LENGTH OF PIPE)

32.947 DIVIDE 2.7M = 12.21 PCS = 13 PCS (BLUE PIPE ½ INCHES)

FOR FITTINGS
QUANTIFY EVERY INTERSECTIONS

½ INCHES COUPLING 26 PCS


½ INCHES TEE 8 PCS
½ INCHES ELBOW 90 DEG 16 PCS
WATER METER 1 PC
MAIN GATE VALVE 1 PC
CHECK VALVE 1 PC

Quantify the qty in the B.O.M excel Format

170 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

C. HOW TO ESTIMATE SEWERLINE AND DRAINAGE


SYSTEM

171 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

STEP 1
DETERMINE THE TOTAL LENGTH OF PIPES NEEDED IN THE SYSTEM
USING THE FF:

FOR DOWNSPOUTS
3” ORANGE PVC PIPE
FOR FLOOR/SINK DRAINS
2” ORANGE PVC PIPE
2” PTRAPS
2” WYE
FOR MAIN SEWER PIPE
3” PIPE AND OTHER FITTINGS

172 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FOR MAIN SEWER PIPE

TOTAL LINEAR METER = 23.591M


PCS= 23.591 DIVIDE 2.7M(DEVELOPMENT LENGTH OF PIPE)
= 8.73 = 9PCS (3” PVC PIPE ORANGE)

FOR FLOOR/SINK DRAINS


2” ORANGE PVC PIPE =2 PCS
2” PTRAPS = 6 PCS
3”X 2” WYE =2 PCS
3” CLEANOUT = 3 PCS

FOR DOWNSPOUTS
3” ORANGE PVC PIPE

LM= (6.796 +8.532)2= 30.656M


PCS= 30.656 DIVIDE BY 2.7 M =11.35= 12 PCS 3” ORANGE PIPE

NOTE:
THE OTHER FITTINGS
NOT INCLUDED IN HERE
SHOULD BE ADDED THIS IS
ONLY FOR EXAMPLE.
KNOW THE PROPER FITTINGS
AND ALLOWABLE SLOPING T0 2%.
INSERT QTY. IN THE BOM.

173 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

D.HOW TO ESTIMATE PLUMBING FIXTURES

174 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑IN ESTIMATING PLUMBING FIXTURE YOU NEED


ONLY TO KNOW THE FIXTURES ITSELF AND
ACCESSORIES THEN QUANTIFY EVERYTHING .

❑INSERT THE QUANTITIES ON B.O.M


AFTERWARDS YOU CAN MARK-UP THE PRICES

175 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

THE PANEL BOARD

PLUG-IN TYPE BREAKER

BOLT ON TYPE BREAKER

176 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

THE SERVICE ENTRANCE

177 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

ELECTRICAL WIRES
1 BOX = 1 ROLL= 150METERS OF WIRE

178 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FROM WORKING DRAWINGS.

179 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

180 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

181 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

IN ESTIMATING THE WIRES IN A ELECTRICAL PLAN


YOU JUST NEED THE INTERCONNECTION OF LIGHTS,
OUTLETS , SWITCHES INTO PANEL BOARD.

182 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE:
THE PANEL BOARD IS LOCATED AT KITCHEN AREA.
❑ STEP 1 MEASURE ALL THE WIRINGS FROM ALL CONNECTIONS: LIGHTS,
SWITCHES, OUTLES INTO PANEL BOARD.
IF CIRCUIT 1 HAS TOTAL LENGTH OF WIRE : 15 METERS

THEREFORE NEEDED ARE:


N-15 METERS – 3.5MM^2 ON A 20MM DIAMETER PVC PIPE
E-15 METERS – 3.5MM^2 ON A 20MM DIAMETER PVC PIPE
L-15 METERS – 3.5MM^2 ON A 20MM DIAMETER PVC PIPE

TOTAL PIPE: 15 METERS ELECTRICAL PIPE


❑STEP 2 TO GET THE TOTAL PIPELENGTH DIVIDE THE COMPUTED INTO
THE AVAILABLE LENGTH
L= 15METERS DIVIDE 3METERS= 5 PCS 2OMM DIAMETER PVC PIPE

183 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑STEP 3 REMEMBER THAT IN EVERY SWITCHES AND OUTLETS THERE


ARE UTILITY BOX.

Count the : Switches: 8 Outlets: 25


Therefore total utility 2 x4 = 33 pcs
❑STEP 4 In estimating the panel board refer to panel diagram then
quantify everything.

184 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑STEP 5 FOR THE SERVICE ENTRANCE COMPUTE THE MATERIALS


NEEDED MAINLY THE G.I. PIPE AND RECEPTICLE AND MAINWIRE, AND
BASE METER ETC.

185 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

❑STEP 6 FOR LIGHTS, SWITCHES AND OUTLETS LIKE IN PLUMBING


FIXTURES YOU JUST NEED TO QUANTIFY EACH ITEMS.

“Therefore generally in estimating plumbing and


electrical works you just need to know the raw
materials needed, their specifications , prices, and the
system how everything works in actual construction.”

186 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

EXAMPLE FINISHED B.O.M WITH MARKUP

187 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

188 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

189 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

190 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

191 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)
MANUAL CONSTRUCTION ESTIMATE GUIDE

FINAL STATEMENTS
This manual main purpose is to help students,
professionals, and contractors to somehow understood and
help them to manually estimate project scopes in each
different set of categories. If there are errors in computation
and everything the author of this manual is open for revising
this first manual in estimate.

This manual is also a compilations of other estimate


guides and not intended for own purpose. The purpose
of this manual is to help our fellow people in
understanding more about cost estimates.

As I said before estimates should not be 100%


accurate but it should be “precise”.

In behalf of MST Connect. We would like to thank


you for supporting our training. Goodluck and God
bless. Happy Learning!

-ENGR. JONATHAN CORTEZ

192 | P a g e
COPYRIGHTS RESERVED BY MST.CONNECT -ENGR.J.CORTEZ (2022)

You might also like