A. COLUMN FOOTING
 CF-1 = 7 sets
CF 2 = 2 sets
 Details of Column Footing

 For CF1 :
V1 = 1000 x 1000 x 400 = 4x108 x 17
= 6.8x109 mm3 = 6.8 m3
For CF2:
V2 = 1600 x 1600 x 400 = 1.024x109 x 2
= 2.048x109 mm3 = 2.048 m3

PREPARED BY: TITLE OF THE ACTIVITY: SHEET NO.

NICOLE JADE DAYO EARTHWORKS


B. WALL FOOTING
 WF1 = 1 set
 Details of Wall Footing

 For WF1 :
V = 600 x 300 x 97000 = 1.746x1010 = 17.46 m3

PREPARED BY: TITLE OF THE ACTIVITY: SHEET NO.

NICOLE JADE DAYO EARTHWORKS


A. COLUMN FOOTING
 CF-1 = 7 sets
CF 2 = 2 sets
 Details of Column Footing

 For CF1 :
V = 1000 x 1000 x 400 = 4x108 x 17
= 6.8x109 mm3 = 6.8 m3
For CF2:
V = 1600 x 1600 x 400 = 1.024x109 x 2
= 2.048x109 mm3 = 2.048 m3
 V = V1 + V2 = 6.8 m3 + 2.048 m3 = 8.848 m3
*We use Class A mixture (1: 2: 4); Sum of ratio: 1+2+4 = 7
 No. of cement = 8.848 x (1/7) = 1.264 m3 = 37 bags
No. of sand = 8.848 x (2/7) = 2.528 m3
No. of gravel = 8.848 x (4/7) = 5.056 m3

PREPARED BY: TITLE OF THE ACTIVITY: SHEET NO.

CONCRETE WORKS –
NICOLE JADE DAYO COLUMN & WALL
FOOTING
B. WALL FOOTING
 WF1 = 1 set
 Details of Wall Footing

 For WF1 :
V = 600 x 300 x 97000 = 1.746x1010 = 17.46 m3
*We use Class A mixture (1: 2: 4); Sum of ratio: 1+2+4 = 7
 No. of cement = 17.46 x (1/7) = 2.4943 m3 = 72 bags
No. of sand = 17.46 x (2/7) = 4.9886 m3
No. of gravel = 17.46 x (4/7) = 9.9771 m3

PREPARED BY: TITLE OF THE ACTIVITY: SHEET NO.

CONCRETE WORKS –
NICOLE JADE DAYO COLUMN & WALL
FOOTING
I. COLUMN
 C1 = 15 columns
 Column Details

400

400

Total Height of columns= 3900mm

 For C1 :
V = 400 x 400 x 3900 x 15 = 9.36x109
= 9.36 m3
 No. of cement = 9.36 x (1/7) = 1.3371 m3 = 39 bags
No. of sand = 9.36 x (2/7) = 2.6743 m3
No. of gravel = 9.36 x (4/7) = 5.3486 m3

PREPARED BY: TITLE OF THE ACTIVITY: SHEET NO.

CONCRETE WORKS –
NICOLE JADE DAYO
Column, Beams & Floors
II. BEAMS

50

60

50 50

 Total length of the Beam


7(5000) + 2(6000) + 2(13500) + 12500 + 1500 = 88000mm
 Total volume of the Beam
 V = 300 x 200 x 88000 = 5.28x109
= 5.28 m3

 No. of cement = 5.28 x (1/7) = 0.7543 m3 = 22 bags


No. of sand = 5.28 x (2/7) = 1.5086 m3
No. of gravel = 5.28 x (4/7) = 3.0171 m3

PREPARED BY: TITLE OF THE ACTIVITY: SHEET NO.

CONCRETE WORKS –
NICOLE JADE DAYO
Column, Beams & Floors
III. FLOORING

 TOTAL AREA
A = 1.565x108 mm2 = 156.5 m2
 TOTAL VOLUME
V = 156.5 x 0.1 = 15.65 m3
*We use Class A mixture (1: 2: 4); Sum of ratio: 1+2+4 = 7
 No. of cement = 15.65 x (1/7) = 2.2357 m3 = 64.4 bags
No. of sand = 15.65 x (2/7) = 4.4714 m3
No. of gravel = 15.65 x (4/7) = 8.9428m3

PREPARED BY: TITLE OF THE ACTIVITY: SHEET NO.

CONCRETE WORKS –
NICOLE JADE DAYO
Column, Beams & Floors
I. CONCRETE HOLLOW BLOCKS (CHB)

 Area of Walls Window


Area Quantity
&Doors
OUTER WALLS
W1 4000x1800 1
Length = 57000mm = 57m
W2 1000x2000 4
Width = 2700mm = 2.7m
W3 1800x3000 1
Area = 57 x 2.7 = 153.9m2
W4 600x1000 1
INSIDE WALLS
W5 600x800 2
Length = 26000mm = 26m
D1 2100x1000 1
Width = 2700mm = 2.7m
Area = 26 x 2.7 = 70.2m2 D2 2100x1000 2
TOTAL AREA = 230.36m2 D3 2100x900 2
 Total Area of Columns, Doors & D4 2100x1000 1
Windows
COLUMNS
AW = 0.4 x 2.7 x 13 = 14.04m2
OUTER WALLS
AW = 6.428x107mm2 = 64.28m2
AD = 4200000mm2 = 4.2 m2
INSIDE WALLS
AW = 0
AD = 4980000mm2 = 7.98 m2
TOTAL AREA = 90.5 m2
 Total Area with CHB
AT = 230.36 – 90.5 = 139.86m2
 Number of CHB
No. of CHB = 153.9 x 12.5 = 1748.25 CHB’s
II. CEMENT AND SAND FOR BLOCK LAYING
Bags cement mixture
Size of CHB in cm Number Sand
per sq. m A B C D cu.m
10 x 20 x 40
(4”x8”x16”) 12.5 0.792 0.522 0.394 0.328 0.0435
15 x 20 x 40
(6”x8”x16”) 12.5 1.526 1.018 0.763 0.633 0.0844
20 x 20 x 40
(8”x8”x16”) 12.5 2.260 1.500 1.125 0.938 0.1250

 We are supposed to use Class B mixture of Cement, by Area method


we can get the multiplier for 4x8x16 CHB which is 0.522 and for
6x8x16 which 1.018 and for the sand which are 0.0435 and 0.0844
respectively.
 For 4x8x16
Area = 62.22m2
Cement = 62.22 x 0.522 = 33 bags
Sand = 62.22 x 0.0435 = 2.70657 m3
 For 6x8x16
Area = 107.86m2
Cement = 107.86 x 1.018 = 110 bags
Sand = 107.86 x 0.0844 = 9.103384 m3
 TOTAL QUANTITY
Cement = 143 bags
Sand = 11.809954 m3
III. CEMENT AND SAND FOR PLASTERING OF WALLS

 Total Area with Wall (2sides)


A = 139.86m2 x 2 = 279.72 m2
 Using a uniform thickness of 16mm for plaster and a Class B mixture
for cement we can get the multiplier of 0.192 for cement and 0.106
for sand.
Cement in bags
Mixture Thickness of Plaster
Class 8 mm 12 mm 16mm 20 mm 25 mm
A 0.144 0.216 0.288 0.360 0.450
B 0.096 0.144 0.192 0.240 0.300
C 0.072 0.108 0.144 0.180 0.225
D 0.060 0.090 0.120 0.150 0.188
Sand 0.008 0.012 0.106 0.120 0.025

 TOTAL QUANTITY
Cement = 54 bags
Sand = 29.65m2
I. REINFORCEMENT OF CHB

 Total Area with CHB = 139.26m2


 Vertical Reinforcement spacing = 80cm
(Using Area method we can get 1.60 multiplier for 80cm)
Vertical Reinforcement Horizontal
Spacing Spacing Reinforcement
cm Length of bars in meters Layer Length of bars in
meters
Per Block Per Sq. M. Per Block Per Sq. M
40 0.235 2.93 2 0.264 3.30
60 0.171 2.13 3 0.172 2.15
80 0.128 1.60 4 0.138 1.72

Length of bars
139.86x1.60 = 223.776m
 Horizontal Reinforcement @particular layer = 3
(Using Area method we can get 2.15 multiplier for 3 layer)
Length of bars
139.86x2.15 = 300.699m
 TOTAL LENGTH OF BARS
223.776 + 300.699 = 524.475m
 Number of Steel Bars (6.00m)
524.475/6 = 88 steel bars
II. REINFORCEMENT OF WALL FOOTING

 FOR TRANSVERSE BAR


Total Length of Wall Footing = 83000mm = 83m
Width = 600mm = 0.6m
Cut Length =0.6
Spacing = 0.2
83/0.2 = 415
415+1 = 416 pcs 9mmx0.6
6/0.6 = 10
416/10 = 41.6 or 42 pcs of 9mmx6m steel bars
 FOR TEMPERATURE BAR
Total Length of Wall Footing = 83000mm = 83m
83/5.5 = 15 pcs 9mmx6.0m
15 x 3 = 45 pcs 9mmx6.0m steel bars
III. TIE WIRES FOR CHB REINFORCEMENTS

 Total Area with CHB = 139.26m2


 Vertical Reinforcement spacing = 80cm
 Horizontal Reinforcement @particular layer = 3
 Length of tire wire = 30cm
(Using Area method we can get 0.024 multiplier)
Vertical Horizontal Kilograms per Square Meter
Spacing Layer Spacing 25 cm tie 30 cm tie 40 cm tie
40 2 0.054 0.065 0.066
40 3 0.039 0.047 0.063
40 4 0.024 0.029 0.039
60 2 0.036 0.044 0.057
60 3 0.028 0.032 0042
60 4 0.020 0.024 0.032
80 2 0.027 0.033 0.044
80 3 0.020 0.024 0.032
80 4 0.015 0.018 0.024
 Number of Kilograms of tire wires
139.26 x 0.024 = 3.34 Kilograms
I. COLUMN REINFORCEMENT

 LONGITUDINAL REINFORCEMENT
No. of Columns = 15
Length of Bars (w/ allowances) = 4500mm = 4.5m
Total Length of Bars per Columns = 4.5 x 8 = 36m
Total Length of Bars for all Columns = 36 x 15 = 540m
No. of Steel Bars (Commercial-6.0m) = 540 / 6 = 90 pcs steel bars

 LATERAL TIES
Length of Ties = 2000mm = 2m
Spacing = 2@75MM, 3@10MM, REST @200MM O.C. SYMMETRICAL
TOCENTER
2 x 75 = 150
3 x 10 = 300
(150 + 300) x 2 = 900mm
4500 – 900 = 3600mm
3600 / 200 = 18
Total No. Ties per column = 2 + 3 + 18 = 23 ties
Total length of Steel Bar per column = 2 x 23 = 46m
Total Length of Bars for all Columns = 46 x 15 = 690m
No. of Steel Bars (Commercial-6.0m) = 690 / 6 = 19pcs steel bars
II. TIE WIRES FOR COLUMN REINFORCEMENT

 No. of main reinforcement = 8


No. of intersections with the lateral ties = 23
23 x 8 = 184 intersections per column
 Total intersections
184 x 15 = 2760 intersections
 Total length in meters
2760 x 0.40 = 1104m
 Kilogram of tie wire
1104 / 53 = 20.83kg
I. REINFORCEMENT FOR BEAMS
Beams Length(m) No. of Stirrups
1 5 34
2 4.5 30
3 4 27
4 5 34
5 5 34
6 5 34
7 5 34
8 4.5 30
9 4 27
10 5 34
11 6 40
12 6 40
13 5 34
14 5 34
15 5 34
16 4 27
17 2 13
18 2 13
19 4.5 30
TOTAL 86.5 580
 Main Reinforcement for Beams and Girders
Beams are resisting in a center to center of columns
Total length of the Beam = 86.5
Total Length of main reinforcement
No. of main reinforcements = 4
86.5 x 4 = 346m
No. of commercial steel bars (6.0m) = 346 / 5.5 = 63 pcs
 Stirrups for beams and Girders
Total no. Stirrups = 580
Length per Stirrups = 60cm = 0.6m
Total Length of Stirrups = 580x0.6 = 348m
No. of commercial steel bars (6.0m) = 348 / 6= 58 pcs
II. TIE WIRES FOR COLUMN REINFORCEMENT

 No. of main reinforcement = 4


No. of intersections with the stirrups = 580
580 x 4 = 2320 intersections
 Total length in meters
2320 x 0.6 = 1392m
 Kilogram of tie wire
1392 / 53 = 26.26kg