COMPUTATIONS
(Earthworks, Concrete & Masonry Works)
For CF1 :
V1 = 1000 x 1000 x 400 = 4x108 x 17
= 6.8x109 mm3 = 6.8 m3
For CF2:
V2 = 1600 x 1600 x 400 = 1.024x109 x 2
= 2.048x109 mm3 = 2.048 m3
For WF1 :
V = 600 x 300 x 97000 = 1.746x1010 = 17.46 m3
For CF1 :
V = 1000 x 1000 x 400 = 4x108 x 17
= 6.8x109 mm3 = 6.8 m3
For CF2:
V = 1600 x 1600 x 400 = 1.024x109 x 2
= 2.048x109 mm3 = 2.048 m3
V = V1 + V2 = 6.8 m3 + 2.048 m3 = 8.848 m3
*We use Class A mixture (1: 2: 4); Sum of ratio: 1+2+4 = 7
No. of cement = 8.848 x (1/7) = 1.264 m3 = 37 bags
No. of sand = 8.848 x (2/7) = 2.528 m3
No. of gravel = 8.848 x (4/7) = 5.056 m3
CONCRETE WORKS –
NICOLE JADE DAYO COLUMN & WALL
FOOTING
B. WALL FOOTING
WF1 = 1 set
Details of Wall Footing
For WF1 :
V = 600 x 300 x 97000 = 1.746x1010 = 17.46 m3
*We use Class A mixture (1: 2: 4); Sum of ratio: 1+2+4 = 7
No. of cement = 17.46 x (1/7) = 2.4943 m3 = 72 bags
No. of sand = 17.46 x (2/7) = 4.9886 m3
No. of gravel = 17.46 x (4/7) = 9.9771 m3
CONCRETE WORKS –
NICOLE JADE DAYO COLUMN & WALL
FOOTING
I. COLUMN
C1 = 15 columns
Column Details
400
400
For C1 :
V = 400 x 400 x 3900 x 15 = 9.36x109
= 9.36 m3
No. of cement = 9.36 x (1/7) = 1.3371 m3 = 39 bags
No. of sand = 9.36 x (2/7) = 2.6743 m3
No. of gravel = 9.36 x (4/7) = 5.3486 m3
CONCRETE WORKS –
NICOLE JADE DAYO
Column, Beams & Floors
II. BEAMS
50
60
50 50
CONCRETE WORKS –
NICOLE JADE DAYO
Column, Beams & Floors
III. FLOORING
TOTAL AREA
A = 1.565x108 mm2 = 156.5 m2
TOTAL VOLUME
V = 156.5 x 0.1 = 15.65 m3
*We use Class A mixture (1: 2: 4); Sum of ratio: 1+2+4 = 7
No. of cement = 15.65 x (1/7) = 2.2357 m3 = 64.4 bags
No. of sand = 15.65 x (2/7) = 4.4714 m3
No. of gravel = 15.65 x (4/7) = 8.9428m3
CONCRETE WORKS –
NICOLE JADE DAYO
Column, Beams & Floors
I. CONCRETE HOLLOW BLOCKS (CHB)
TOTAL QUANTITY
Cement = 54 bags
Sand = 29.65m2
I. REINFORCEMENT OF CHB
Length of bars
139.86x1.60 = 223.776m
Horizontal Reinforcement @particular layer = 3
(Using Area method we can get 2.15 multiplier for 3 layer)
Length of bars
139.86x2.15 = 300.699m
TOTAL LENGTH OF BARS
223.776 + 300.699 = 524.475m
Number of Steel Bars (6.00m)
524.475/6 = 88 steel bars
II. REINFORCEMENT OF WALL FOOTING
LONGITUDINAL REINFORCEMENT
No. of Columns = 15
Length of Bars (w/ allowances) = 4500mm = 4.5m
Total Length of Bars per Columns = 4.5 x 8 = 36m
Total Length of Bars for all Columns = 36 x 15 = 540m
No. of Steel Bars (Commercial-6.0m) = 540 / 6 = 90 pcs steel bars
LATERAL TIES
Length of Ties = 2000mm = 2m
Spacing = 2@75MM, 3@10MM, REST @200MM O.C. SYMMETRICAL
TOCENTER
2 x 75 = 150
3 x 10 = 300
(150 + 300) x 2 = 900mm
4500 – 900 = 3600mm
3600 / 200 = 18
Total No. Ties per column = 2 + 3 + 18 = 23 ties
Total length of Steel Bar per column = 2 x 23 = 46m
Total Length of Bars for all Columns = 46 x 15 = 690m
No. of Steel Bars (Commercial-6.0m) = 690 / 6 = 19pcs steel bars
II. TIE WIRES FOR COLUMN REINFORCEMENT