Industrial Training Weekly Diary

Weekly diary For

Industrial training

At

Name of industry: Swayam Construction

From: 29/06/2020 To 14/08/2020

Name of supervisor: Sachin Jaysing Koli

Designation of supervisor: Owner

Name of the student: Harish Gajanan Patil

Enrollment no: 1815520010

Branch of engineering: Civil Engineering

Name of polytechnic: Sanjay Bhokare Group Of Institute, Miraj.

.
Maharashtra state board Technical education
Industrial Training Weekly Diary

Week 1: From: 29 June 2020 To: 7 July 2020

Day Activities carried out


My first day on construction site. The lining and pit had been
removed earlier, PCC is doing today. There are a total of 10 columns
1 on the site, PCC of all that is almost complete today.workers started
steel framework for footing .

Today workers has been completed steel framework and steel


2 framework has been placed on the PCC.workers started work on
column steel framework for 10 columns.
Today column steel frame work has been completed. Workers started
next step to erecting columns in the pit. Workers were looking at the
3 level of each column, In this, they also let me see the level.
Also started formwok to column with appling oil to inside of the
formwork

Today workers filled concrete in the columns with tamping,these


4 columns filled with height 7ft. and used 1and half cement bag for
each column.
Workers are completing the ground level beam steel framework
today. I observed all the columns and saw if there was any problem,
5 there was no problem.

Today the column form form was opened. There were no cracks
6 anywhere and only one corner of the column was slightly damaged.
.

Weekly summarization of the above activities : In this week, the work of pcc,
footing and ground level column has been completed, which means that the
foundation is almost completed.

Signature of student : Signature of industrial supervisor :

.
Maharashtra state board Technical education
Industrial Training Weekly Diary

Week 2: From: 06 july 2020 To: 12 july 2020

Day Activities carried out

Foundation completed in last week then next work started on ground


1 floor beam and Workers have already started ground level beam steel
framework.

The Workers are started to formwork construction. Shuttering of


2 columns is made by plywood sheets .Today framework was
completed.

After completed formwork A thin film of oil should be applied in the


3 inner surface of shuttering. Then started the feeling of ground level
beam with concrete mix design.

Previous day half work is done. Today feeling is completed then set
4 the concrete for 3 days.

concrete is set perfectly and preparing to removing


after 2 days Formwork from concrete beam.started filling murum in
5 pit of column and beam.

Today workers started filling murum in plinth level


6 After removing formwork over the ground level beam. Workers are
doing curing the ground level beam .

Weekly summarization of the above activities: Ground level beam work was
completed and murum filling was started this week.

Signature of student : Signature of industrial supervisor :

.
Maharashtra state board Technical education
Industrial Training Weekly Diary

Week 3: From:13 july 2020 To:22 july 2020


Day Activities carried out
The machine filled it all up properly with mulch and mud up to the
plinth.
1

Today the plinth level bed was concreted by concreting and its
2 leveling was also checked

Today the bed concrete was watered and kept for 2 days to turn it
water from bed concrete.
3

the overall curing was completed. After this further work was started.

the superstructure construction was stared. Today workers are making


transverse reinforcement for column.
5

Today workers started work on superstructure columns.


6

Weekly summarization of the above activities : In this week flooring concrete


level is completed .and the superstructure construction was started.

Signature of student : Signature of industrial supervisor :

.
Maharashtra state board Technical education
Industrial Training Weekly Diary

Week 4: From: 25 july 2020 To: 31 july 2020

Day Activities carried out


Workers started work on steel reinforcement for superstructure 10
columns. They started this work in the last half and it will be
1
completed today
superstructure column formwork work was started. Today 10 columns
formwork is completed .
2

after completing formwork workers started to making concrete with


machine-mix concrete because it was small concrete volume .today 4
3 column are filled because rainy day.

today workers completed concrete filling in the columns ,


then set the concrete for 4 days.
4

columns are set perfectly and workers remove the formwork from
columns .there are no cracks are found on any column.column
5 looking was good.

workers marking the door frame location .for construct the door frame
6 and starting next brick masonry for outer wall.

Weekly summarization of the above activities: in this week superstructure


columns conrecting and reinforcement has been completed.workers started work
on brick masonry in next week.

Signature of student : Signature of industrial supervisor :

.
Maharashtra state board Technical education
Industrial Training Weekly Diary

Week 5: From: 01 aug 2020 To: 07 aug 2020


Day Activities carried out
columns are set perfectly and the masonry is begin in masonry work
these material are used bricks,cursh sand and cement
1 (cement name:birla Shakti cement and brick size as per standard
190x19x19 mm)

Workers soaking bricks today and Brick masonry work for external
walls started half work was done today. The door frame was erected
2
today to right place.
Brick masonry Still running,brick masonry still remaining for 2 walls
Bricks are Are over, So the next work has stopped.
3

Today bricks Are now brought, The next work began.brick masonry
is completed to sill level.
4

Outer wall brick masonry was done upto sill level then now workers
started inner wall brick masonry.
5

Today internal wall masonry is completed to the sill level.


6 The work has been stopped here as it is raining today.

Weekly summarization of the above activities : in this week inner wall and
outer wall brick masonry has been done,to the sill level.

Signature of student : Signature of industrial supervisor :

.
Maharashtra state board Technical education
Industrial Training Weekly Diary

Week 6: From: 06 aug 2020 To: 14 aug 2020


Day Activities carried out
To this day, Brick Masonry has fulfilled all fears to the seal
level.workers started brick masonry to the lintel level.
1

the masonry work is completed to lintel level. Formwork and steel


2 reinforcement Both of these are accomplished today.

Concrete was poured into the lintel,chajja and loft. It was left to dry
for 1 day
3

Formwork was removed from all places. Water was thrown at him.
Chajja ,loft and lintel slab are strength looking good.
4

Today all masonry work completed to the slab level.

Work on the slab will start from today. Today the workers brought the
6 plates for the slab and brought bamboo, they all began working on
slab.

Weekly summarization of the above activities : this is my last week in this week
lintel level was completed and brick masonry completed to the slab level.workers
will soon started work scaffolding of slab and beams.

Signature of student : Signature of industrial supervisor :

.