Professional Documents
Culture Documents
ROAD BARRIER
1. Scope of Work and Work Description
This method statement describes work of installing road barrier. The stage of installing road barrier illustrated
by Figure 1.
START
Installation of reinforcement
and formwork
Casting Concrete
Loading formwork
Finishing Concrete
FINISH
2. Work Explanation
2.1 Material
Materials used for road barrier are as follows :
1. Concrete Class
2. Reinforcing Steel
2.2 Tools
Tools used for road barrier are as follows :
1. Bar Cutter
2. Bar Bender
3. Dump Truck
4. Tower Crane
5. Concrete Vibrator
6. Concrete Pump
7. Concrete Mixer
8. Geotextile (using when curing)
3. Quality Plan
Quality assurance works in this Project describes as follows:
The Contractor will carry out following actions to avoid mistakes and to secure the quality.
• Especially, the Contractor will explain the work procedure and materials to be used to the sub-contractor.
• All survey work will be checked by the Engineer’s surveyor.
• All material and shop drawing will be tested and approved prior to commence the work.
• Sampling and Test in the site will be done with attendance of the Engineer’s inspector.
4. Work Scheduling
Work schedule will be planned to follow description on Table 2 and Table 3 below