Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :

Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

MBBR AERATION POOL DEVELOPMENT WORK METHOD

&

CLARIFIER

Rev. Date Submission Purpose ready Checked Approved


00
Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

1. DESTINATION
Method implementation this explain about MBRR Aeration Pond Construction & Clarifier PT.
Angels Products , Implementation Work cover stages as following :
A. Preparation
B. Permission
C. Safety
D. Tools & Equipment
E. Implementation Work
1. Determine point coordinates that have been determined by PT. Angels Products
2. Preparation land
3. Method Erection
4. Method Casting A number of Stage
5. Install Reebar , Waterstop & Formwork
6. 3D Finishing

A. PREPARATION
Preparation profession include :
1. Coordination about the work plan this with Owner PT . Angels Products
2. Preparation (Joint Survey & QC)
3. Mobilization of materials and tools needed for profession to location work .
4. Make sure all areas in state clean and safe During activity profession take place .
B. PERMISSION
Before To do each stages implementation carried out by PT. GKM filed licensing and
coordination with PT. Related Angels Products each stages every profession that .

C. SAFETY
Before start work , all worker given briefing about safety briefing in the work area by the HSE
team of PT . GKM and PT. Angel Products.
Preparation prevention accident work on site include :
Work permit, JSA (Job Safety Analyst), Check PPE ( Protective Equipment self ).
Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

D. IMPLEMENTATION PROFESSION
1. Point Coordinate
Before it 's done for Step cleaning land point survey will be conducted location and
elevation in accordance with point coordinates and which points have been agreed by PT .
Angels Products and Consultants . With illustration below _ this :

Figure 1. Surveyor
 After doing _ point the coordinates already in accordance request PT. Angels
Products
 Can be done for Step next that is preparation land

2. Preparation Land
Se has been found point coordinate so Step next are :
 Cleaning land from trees and dirt that disturbs the work area
 To do stripping at the points certain height _ still not yet in accordance with the
required elevation .
 Ask to do _ checking to party owner and consultant is already appropriate , before
proceeding _ to Step next .
3. Erection
Steering on activities MBBR & Clarifier 's Aeration Pond Construction work use
 Preparation of the Sampling Site in accordance with picture work and coordinates .
 Preparation tool erection
 Erection using Hydraulic Static Pile Driver (HSPD)
With illustration as following :
Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

Figure 2. Piling With Hydraulics

4. Installation Reebar and Formwork


 Before rebar installed make sure iron rebar clean from dirt land , mud or other .
 Measuring distance iron , mark with marker and for Suite rebar in accordance
with picture work .
 Install concrete decking in accordance with needs which hinted .
 Check return distance , bond and concrete decking her .
 Make sure bond enough strong ( until on strength max )
 Check slime concrete is already installed and in accordance with which hinted .
 Check is diameter, position , distance and amount rebar which installed
already in accordance with picture and bar schedule appeal.
 Check overlapping is already in accordance with which hinted .
 Check cleanliness iron rebar from dirt land , and remnants wire bendrat .
 Check Installation Waterstop

On casting wall wall done strengthening the formwork so as not to there is movement
moment casting with design strengthening support below this . As for other than to
strengthen our support, we add tie rods to the formwork so it doesn't occur side change _
inside and outside walls. Following for illustration tie rod point
Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

Figure 3. Tie-Rod . Installation

5. Casting
Moment casting profession development pool MBBR & Clarifier aeration done with multiple
stages of casting for avoid happening damage yield of concrete moment implementation
casting due to with high +- 5000 will experience difficulty among others:

 There will be difficulty trunk from a vibrator that is not could reach until bottom of
the wall.
 There will be risks in the formwork used caused damaged because pressure of the
concrete .
 Will risk to weather / rain moment To do very the resulting stage content concrete
or mixture concrete no unite .
Then do it into 4 stages

a. Casting Stage 1
On casting this Footing, Slab and a little will be done wall use water stop
With illustration below _ this :
Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

Figure 4. Casting Stage 1

b. Casting Stage 2
Stage next casting wall with tall no more from 2 meters to guard concrete so that
maximum when _ casting and results satisfying , with illustration below _ this :

Figure 5. Casting Stage 2

c. Casting Stage 3
Stage next casting wall with tall no more from 2 meters to guard concrete so that
maximum when _ casting and results satisfying , with illustration below _ this :
Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

Figure 6. Casting Stage 3

d. Casting Stage 4
Stage next is Step final casting ie : wall main , slab gutter and work stairs , with
illustration below _ this :

Figure 7. Casting Stage 4


Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022

FINISH 3D APPENDIX
Owner : Pekerjaan Pembangunan Kolam Aerasi MBBR & Contructor :
Clarifier
Contructor No : GKM-QC-PROC-001
Revision No : 00
Issued Date : 29-03-2022