Description of NCR: - CCY install parapet wall not follow the shape
- Parapet wall installation not good curve 02 June 2020
18-May-20
Comments:
A) - Accepted? YES NO
Attach photos on seperate page.
1-Jun-20
Comments:
02-Jun-20 02-Jun-20
NCR
Novotel Holiday Palace KPS
NON-CONFORMANCE REPORT INFORMATION
Project Name Novotel Holiday Palace KPS NCR # NHP-ACT-CCY-NCR-111
Issued Date 2020-03-30 00:00:00 Contractor China Construction Yangtze (Cambodia) Co., Ltd.
Pictures
Attachments Parapet_wall_Installation.pdf
Main recipient CC Chantha Lim, Kosal Chim, Odom Yin, John Morrison,
Dis Seng
CM Comments CCY need to reinstall the block wall by follow the the curve shape as per contract drawing.
NCR issued because:
1- plan not curve as contract drawing
2- elevation not leveling (block wall look like the wave, up and down).
Witnessed by
Pictures
Attachments
CM Comments
Page 1/2
CONSTRUCTION MANAGER CHECKS APPLIED ACTIONS & CLOSES OUT NCR
Page 2/2
Powered by TCPDF (www.tcpdf.org)
NCR
Novotel Holiday Palace KPS
PROPOSED FOR CLOSE NCR FROM CONTRACTOR NCR# NHP-ACT_CCY-111
Propose By Heng Chanvignean/WANG XIAO HUI Date: 2-Jun-20
Action We have rectified the parapet wall according to ACT engineer comment.
Descreptio
n
PHOTO ACTIONS