Project Name: B+G+2+R RESIDENTIAL VILLA G15B

DAILY ACTIVITY REPORT


SUBMITTAL REF: REV. DATE
PJJPFG15B/DAR/036 00 22-03-2023

Contractual Completion Date PROGRAM UNDER REVIEW No. of Days Left for Completion days

Weather: Sunny Cloudy Rainy Dusty Humidity: High Medium Low

Temperature: 20 0C Max 28 Min 20

CONTRACTOR'S MANPOWER EQUIPMENT I=Idle R=Repair


Category No. Category No. Type Qty Hours Status
Worked
Project. Mgr. 01 Foreman 1 Backhoe 1
Construction Manager 01 Concreter Wheel Loader
Site Engineers 01 Steel Fixer Tipper
Safety Engineer 01 Carpenter 01 Roller Compactor
Admin Mason Mobile Crane
Tech/Sec Tower Crane
INDIRECT LABOUR Plasterer Transit Mixers
Operator Painter Concrete Pump
Mechanic Unskilled 04 Welding Machine
Electrician Generator
Welder Bar Bending Machine
Drivers Woodcutter
EXCAVATOR (LONG BOOM)
Pick Up trucks
TOTAL Plate compactor

SUBCONTRACTOR'S MANPOWER
Subcontractor Name Elec. Elevator HVAC Mech. Finishes Total
EXCAVATOR OPERATOR
JCB OPERATOR (Ever 1
star machines) MCM
DEWX 1

MATERIALS DELIVERED TO SITE VISITORS TO SITE


Item Unit Qty Name Company
Project Name: B+G+2+R RESIDENTIAL VILLA G15B

CONTRACTOR’S DAILY ACTIVITY REPORT DAR REPORT NO. 36

Project Title: B+G+2+R RESIDENTIAL VILLA G15B Date: 16/02/2023


Project No.: PJJPFG15B

CONSTRUCTION ACTIVITIES (TODAY) LEVEL LOCATION

1. EXCAVATION FOR FINAL LEVELS IN PROGRESS. - -7.19 MT BASEMENT


- -5.77 MT
- - 6.12 MT

2. CLEARING OUT SPACE FOR TEMPORARY CABINS.


3. DEWATERING

CONSTRUCTION ACTIVITIES (TOMORROW)


BASEMENT
1.WILL FINISH ALL EXCAVATION AND WILL START COMPACTION .

Issued by: Received by:


MCM BUILDING CONTRACTING LLC ENGR KHALID NAZKI Date

ALPAGO PROJECT ENGINEER COMMENTS ON QUALITY/PROGRAM/SAFETY:

Name of Consultant Signature Date

Corrections or comments made relative to submittals during this review do not relieve the contractor from compliance with the requirements of the
drawings and specifications. This check is only for review of general conformance with the design concept of the project and general compliance with the
information given in the contract documents. The contractor is responsible for confirming and correlating all quantities and dimensions, selecting
fabrication processes and techniques of construction, coordinating his work with that of other trades and performing his work in safe and satisfactory
manner.