DAILY REPORT- 11/11/2017

Reference No: GS#293/DR/2017/ P-114 Rev : 00 Date :11-11-2017


Project Name:CONSTRUCTION OF (G+6+GYM+ROOF) RESIDENTIAL& COMMERCIAL BUILDING
Owner/Client:Mr.AHMED MOHAMMED AHMED FARAJ AL MEHAIRBI, AHMAD SULTAN KHALIFA BELRASHEED ALSUWAIDI
Building Permit :6731189 Plot/Parcel ID:: 673-1189
Engineer:Er. Ajith Contractor:GCC Contracting

Weather Conditions Temperature C Humidity % Wind Speed KM/h


sunny 31

Activities for Today


S.No Activity Description Location Manpower
SLAB REINFORCEMENT FOR POST
1 PART 2&3
TENSION SLAB
2 POST TENSION SLAB CONCRETING PART 1
COMPOUND WALL BLOCK WORK
3 PART 3 (EXTERNAL AREA)
FOR TIE BEAM

Machinery

Machine No Hours Total Machine No Hours Total


Generator 1 Pick Up (--Ton)
(200KVA)
Boom Loader Excavator
Bob cat 1 Mobile Crane (--Ton)
Bulldozer Tower Crane(-- Ton) 1
Skid Steer Loader Roller compactor
Backhoe Loader Showel 1

Manpower/ Main Contractor

Indirect Manpower Direct Manpower


Project Manager 1 QA/QC Engineer Carpenter 68 Labour

Construction Manager Safety Engineer 1 Steel Fixer 112 Driver


Project Engineer 1 Safety Officer 1 A/C Workers Operator
Site Engineer 2 Foreman 7 Plumber Others
Architect Others 4 Electrician 2
Electrical Engineer 1 Helper 10
Mechanical Engineer 1 Mason 11
Total 19 Total 203

Manpower/Subcontractors
Subcontractor 1 Subcontractor 2 Subcontractor 3 Subcontractor 4
GESCO
Electrical Engineer 1 Electrician
Mechanical Engineer 1
Foreman 2
QA-QC-FAT-10-Daily Report
Plumber
Total 4 Total Total Total

Man-hours

Today Previous (Cumulative) Total up to Date

Work Done Yesterday


Location
S.No Activity Description

SLAB REINFORCEMENT FOR POST


1 PART 2&3
TENSION SLAB
COMPOUNDWALL BLOCK WORK FOR
2 PART 3 (EXTERNAL AREA)
TIE BEAM
COMPOUNDWALL TIE BEAM
3 PART 3 (EXTERNAL AREA)
REINFORCEMENT

Work Planned for Tomorrow


Location
S.No Activity Description

SLAB REINFORCEMENT FOR POST


1 PART 2&3
TENSION SLAB
BLOCK WORK FOR COMPOUNDWALL
2 PART 1 (EXTERNAL AREA)
TIE BEAM
COMPOUNDWALL TIE BEAM
3 PART 3 (EXTERNAL AREA)
REINFORCEMENT
4 CURING FOR POST TENSION SLAB PART 1

Comments and Others (if Any)

Contractor's Approval

Name Designation Signature & Stamp


QA/QC Engineer
Project Manager

Engineer's Comments

Engineer : Ajith Signature


Resident Engineer Signature
Received By Contractor Date Signature and Stamp

QA-QC-FAT-10-Daily Report
Note: 1-.Contractor has to submit Daily Report by Maximum 08:30 am
2- Approval shall not relieve Contractor of any of his obligations under the Contract Terms andConditions.

QA-QC-FAT-10-Daily Report