You are on page 1of 8

MAKADWAN NAGDA RATLAM PIPELINE PROJECT(MNRPL)

DAILY PROGRESS REPORT


Project: MNRPL PIPELINE PROJECT Report No 426
Contractor: M/s. Tolani Project Pvt. Ltd. Report Date 11/23/2021
Client: Gujarat Gas Ltd. Progress Date 11/22/2021
PMC: CEIL Weather Sunny
LOA DATE: 31-Aug-2020 Project completion date: 31-Mar-22
Spread - 1 : CH: 0.00Km TO CH.32 Km (From KM 00M01 TO KM 33M04)

S.No. Activity Unit Scope Start Date Prev. Today Cumm. Balance Percentage MANPOWER DETAILS Remarks
Work completion

A Mainline Activity Sl. No. DESCRIPTION NAME QUANTITY


Total main line Pipes Received at
1.0 site(12"NB x 6.4mmThk) RMT 33000.00 12/27/2020 33000.00 0.0 33000.00 0.00 100.00% A Engineer & Staff

Total Casing Pipes Received at sit


1.1 (18"NB x 9.53mmThk) RMT 290.00 2/21/2021 290.00 0.0 290.00 0.00 100.00% 1 Project Manager ON JHA 1
2.0 Route Survey RMT 33000.00 33027.50 0.0 33027.50 -27.50 100.08% 1 RCM G. TRIPATHI 1
3.0 Clearing & Grading RMT 33000.00 12/23/2020 33077.70 0.0 33077.70 -77.70 100.24% 2 Site In charge 0
4.0 Pipeline Stringing RMT 33000.00 12/28/2020 33077.70 0.00 33077.70 -77.70 100.24% 3 Civil Engineer 1
5.0 Pipe Bend 4 QA/ QC Enginner 2
5.1 Pipe Bend(3D) Nos 33 24 0 24 9.00 72.73% 5 Surveyor 1
5.2 Cold Bend Nos 2 3/6/2021 0 0 0 2.00 0.00% 6 Safety Engineer/officer 1
6 Mainline joint Welding Nos 2181 12/28/2020 2188 0 2188 -7.00 100.32% B Sites Workmen
6.1 Tie -In joint Welding Nos 624 1/21/2021 626 0 626 -2.00 100.32% 1 Mechanical Foreman 0
Total Nos of joint Welding Nos 2805 12/28/2020 2811 0 2811 -6.00 100.21% 2 Mechanical Supervisor 1
6.2
Total Mainline Welding Length RMT 33000.00 12/28/2020 33077.70 0.00 33077.70 -77.70 100.24% 3 Civil Supervisor 0
NDT 4 Welder 4
Radiography Taken Nos 2805 12/29/2020 2780 0 2780 25.00 99.11% 5 Fitter 2
Radiography Film Review Nos 2805 1/2/2021 2780 0 2780 25.00 99.11% 6 Grinder 2
Radiography Joint Accepted Nos 1/2/2021 2706 0 2706 7 Rigger 4
Joint Repair Nos 65 0 65 8 Sand Blaster 0
Repair Percentage % 2.34% #DIV/0! 2.34% 9 Insulator 0
7.0 RT Repair Taken Nos 61 0 61 10 Electrician 0
Repair RT Accepted Nos 61 0 61 11 Helper 4
Retake/ Reshoot/ Others Nos 8 0 8 12 Watchman 0
RT/RS/others Taken Nos 8 0 8 13 Civil Labour 0
RT/RS/Accepted Nos 8 0 8 C Driver & Operators
Total RT Accepted Nos 2805 1/2/2021 2772 0 2772 33.00 98.82% 1 BackHoe Loader (JCB) Operator 0
8.0 UT of Weld Joint Nos 212 0 212 2 Excavator/Breaker Operator 0
9.0 Weld Joint CUT OUT Nos 3 0 3 3 Hydra Operator 0
10.0 Production Test of Weld joint Nos 1 0 1
11.0 Field Joint Coating Nos 2805 1/7/2021 2762 0 2762 43.00 98.47% MACHINDERY DETAILS
12.0 Trenching RMT 33000.00 1/15/2021 32555.00 0.00 32555.00 445.00 98.65% A Equipment
13.0 Pipe Lowering RMT 33000.00 1/17/2021 32429.44 0.00 32429.44 570.56 98.27% 1 BackHoe Loader (JCB) 0
14.0 Backfilling RMT 33000.00 1/20/2021 31836.00 25.00 31861.00 1139.00 96.55% 2 EXCAVATOR/ ROCK BREAKER/ Pocklane 0 CH 3.9
B Crossings 3 HYDRA- 14 TON 0

15.1 Pre-Hydro test of Crossing section Nos 8 6 0 6 2.00 75.00% 4 TRACTOR TRAILORS 0

15.2 Post-Hydro test of Crossing section Nos 3 2 0 2 1.00 66.67% 5 DIESEL GENERATORS 0
16.1 Open Cut crossing Nos 11 11 0 11 0.00 100.00% 6 AIR COMPRESSORS: 300-600 CFM 0
SAND BLASTING UNITS WITH
16.2 Open Cut crossing + C.C pipe Nos 10 3/20/2021 10 0 10 0.00 100.00% 7
COMPRESSOR 300 CFM
0
Open Cut crossing + C.C pipe
16.3 (Major Waterways) Nos 0 0 0 0 0.00 8 HDD EQUIPMENT 0
16.4 Open Cut+ Casing Nos 2 2 0 2 0.00 100.00% 9 WELDING M/C 0
HDD + Casing : ROAD
16.5 Nos 5 4/29/2021 1 0 1 4.00 20.00% 10 WATER TANKERS 0
( CH 02,10,11,27,30 )
HDD + Casing : RAILWAYS
16.6 (CH : 3.9, 28 ) Nos 2 1 0 1 1.00 50.00% 11 DE-WATERING PUMP 0
16.7 HDD (without casing) Nos 1 3/8/2021 1 0 1 0.00 100.00% 12 EXTERNAL CLAMP 0
16.8 Crossing Restoration 31 0 0 0 31.00 0.00% QC
C CP Works 1 HOLIDAY DETECTORS 0
17.1 Soil Resistivity Survey RMT 33000.00 33000.00 0.000 33000.00 0.00 100.00% CIVIL/ SURVEY
17.2 TLP Installation Nos 56 56 0 56 0.00 100.00% 1 PLATE COMPACTOR 0
17.3 Pin Brazing Nos 56 27 0 27 29.00 48.21% 2 VIBRATE M/C 0
Zn Anode Installation
17.4 (Type-A,B,C,D) (Each location 2 Nos 16 9 0 9 7.00 56.25% 3 CONCRETE MIXER 0
Nos. of Zn Anode)
Mg Anode Installation
17.5 (Type-A+1,B+1,C+1,D+1, H ) Nos 30 10 0 10 20.00 33.33% 4 CUBE TESTING SET (6Nos. Mould) 0
17.6 Insulation Joints (Type- E) Nos 7 0 0 0 7.00 0.00% 5 Road Roller 0
17.7 Polarization Coupon Nos 3 12 0 12 -9.00 400.00% 0
6 Total Station
( Type A+ PC)
D Final Cleanup & Restoration 7 Theodolite 0
18.1 Mainline Restoration RMT 33000.00 0.00 0.00 0.00 33000.00 0.00%
18.2.1 RoU Boundray Marker Nos 132 0 0 0 132.00 0.00%
18.2.2 Warning Marker Nos 87 0 0 0 87.00 0.00%
18.2.3 Direction Marker Nos 184 0 0 0 184.00 0.00%
18.2.4 Kilometer Marker Nos 32 0 0 0 32.00 0.00%
18.2.5 Total Marker Installation Nos 435 0 0 0 435.00 0.00%
E Mainline Hydrotesting
19.1 Cleaning, Gauging & Pigging RMT 33000.00 0 0 0 33000.00 0.00%
19.2 Mainline Hydro Testing RMT 33000.00 0 0 0 33000.00 0.00%
19.3 De-watering & Swabbing RMT 33000.00 0 0 0 33000.00 0.00%
F Pre-Commissioning
20.1 Drying RMT 33000.00 0 0 0 33000.00 0.00%
20.2 N2 Purging RMT 33000.00 0 0 0 33000.00 0.00%
G Isolation Valve
21.1 Isolation Valve Installation Nos. 10.00 0 0 0 10.00 0.00%
H Valve Chamber
22.1 Valve Chamber Construction Nos. 10.00 0 0 0 10.00 0.00%
I Commissioning
21.0 Gas In Activity RMT 33000.00 0 0 0 33000.00 0.00%
J DRS
21.1 DRS Installation Nos. 3.00 0 0 0 3.00 0.00%
K CNG
22.1 CNG Station Installation Nos. 1.00 0 0 0 1.00 0.00%

Highlights of Project Issues & Concernt by PMC/GGL :

Today's Hindrances

Issues & Concerns by TPPL

FOR TPPL FOR PMC


MAKADWAN NAGDA RATLAM PIPELINE PROJECT(MNRPL)
DAILY PROGRESS REPORT
Project: MNRPL PIPELINE PROJECT Report No 426
Contractor: M/s. Tolani Project Pvt. Ltd. Report Date 11/23/2021
Client: Gujarat Gas Ltd. Progress Date 11/22/2021
PMC: CEIL Weather Sunny
LOA DATE: 31-Aug-2020 Project completion date: 31-Mar-22
Spread - 2 : CH: 33 TO CH 62 (From KM 33M04 TO KM 62M26)
Balance Percentage
S.No. Activity Unit Scope Start Date Prev. Today Cumm. MANPOWER DETAILS Remarks
Work completion

A Mainline Activity Sl. No. DESCRIPTION QUANTITY

1.0 Total main line Pipes Received at RMT 30000.0 12/27/2020 30000.00 0.0 30000.00 0.00 100.00%
site(12"NB x 6.4mmThk) A Engineer & Staff

Total Casing Pipes Received at sit


1.1 RMT 222.0 2/21/2021 222.00 0.0 222.00 0.00 100.00% 1 Project Manager ON JHA 1
(18"NB x 9.53mmThk)
2.0 Route Survey RMT 30000.0 30000.0 0.0 30000.00 0.00 100.00% 2 RCM GC Tripathi 1
3.0 Clearing & Grading RMT 30000.0 12/23/2020 19970.00 200.0 20170.00 9830.00 67.23% 3 Site In charge 0
4.0 Pipeline Stringing RMT 30000.0 12/28/2020 19932.00 216.00 20148.00 9852.00 67.16% 4 Civil Engineer 0
5.0 Pipe Bend 5 QA/ QC Enginner 1
5.1 Pipe Bend(3D) Nos 50.0 2 0 2 48.00 4.00% 6 Surveyor 0
5.2 Cold Bend Nos 10.0 3/6/2021 0 0 0 10.00 0.00% 7 Safety Engineer/officer 1
6 Mainline joint Welding Nos 2000.0 12/28/2020 1144 13 1157 843.00 57.85% B Sites Workmen CH 41 46
6.1 Tie -In joint Welding Nos 500.0 1/21/2021 368 5 373 127.00 74.60% 1 Mechanical Foreman 1 CH 41 56
Total Nos of joint Welding Nos 2500.0 12/28/2020 1516 18 1534 966.00 61.36% 2 Mechanical Supervisor 1
6.2
Total Mainline Welding Length RMT 30000.0 12/28/2020 19822.65 216.75 20039.40 9960.60 66.80% 3 Civil Supervisor 0
NDT 4 Welder 0
Radiography Taken Nos 2500.0 12/29/2020 1393 0 1393 1107.00 55.72% 5 Fitter 0
Radiography Film Review Nos 2500.0 1/2/2021 1393 0 1393 1107.00 55.72% 6 Grinder 0
Radiography Joint Accepted Nos 1/2/2021 1274 0 1274 7 Rigger 0
Joint Repair Nos 102 0 102 8 Sand Blaster 0
Repair Percentage % 7.32% #DIV/0! 7.32% 9 Insulator 0
7.0 RT Repair Taken Nos 77 0 77 10 Electrician 0
Repair RT Accepted Nos 77 0 77 11 Helper
Retake/ Reshoot/ Others Nos 17 0 17 12 Watchman 0
RT/RS/others Taken Nos 13 0 13 13 Civil Labour 0
RT/RS/Accepted Nos 13 0 13 C Driver & Operators

Total RT Accepted Nos 2500.0 1/2/2021 1350 0 1350 1150.00 54.00% 1 BackHoe Loader (JCB) Operator 0
8.0 UT of Weld Joint Nos 150 0 150 2 Excavator/Breaker Operator 0
9.0 Weld Joint CUT OUT Nos 7 0 7 3 Hydra Operator 0
10.0 Production Test of Weld joint Nos 0 0 0
11.0 Field Joint Coating Nos 2500.0 1/7/2021 1102 0 1102 1398.00 44.08% MACHINDERY DETAILS
12.0 Trenching RMT 30000.0 1/15/2021 15569.00 230 15799.00 14201.00 52.66% A Equipment CH 56 59 41
13.0 Pipe Lowering RMT 30000.0 1/17/2021 14799.58 121.39 14920.97 15079.03 49.74% 1 BackHoe Loader (JCB) 0 CH 56 57
14.0 Backfilling RMT 30000.0 1/20/2021 11417.00 150.00 11567.00 18433.00 38.56% 2 EXCAVATOR/ ROCK BREAKER/ Pocklane 0 CH 56 57
B Crossings 3 HYDRA- 14 TON 0

15.1 Pre-Hydro test of Crossing section Nos 5.0 1 0 1 4.00 20.00% 4 TRACTOR TRAILORS 1

15.2 Post-Hydro test of Crossing section Nos 2.0 0 0 0 2.00 0.00% 5 DIESEL GENERATORS 1

16.1 Open Cut crossing Nos 8.0 0 0 0 8.00 0.00% 6 AIR COMPRESSORS: 300-600 CFM 0
SAND BLASTING UNITS WITH
16.2 Open Cut crossing + C.C pipe Nos 19.0 0 0 0 19.00 0.00% 7
COMPRESSOR 300 CFM
0

16.3 Open
Cut crossing + C.C pipe
(Major Waterways) Nos 1.0 0 0 0 1.00 8 HDD EQUIPMENT 0

16.4 Open Cut+ Casing Nos 0.0 0 0 0 0.00 #DIV/0! 9 WELDING M/C 2

16.5 HDD
+ Casing : ROAD
( CH 33,33,34) Nos 3.0 0 0 0 3.00 0.00% 10 WATER TANKERS 0

16.6 HDD + Casing : RAILWAYS Nos 1.0 0 0 0 1.00 0.00% 11 DE-WATERING PUMP 0
(CH : 35 )
16.7 HDD (without casing) Nos 0.0 0 0 0 0.00 #DIV/0! 12 EXTERNAL CLAMP 0
16.8 Crossing Restoration 32.0 0 0 0 32.00 0.00% QC
C CP Works 1 HOLIDAY DETECTORS 0
17.1 Soil Resistivity Survey RMT 30000.0 30000.0 0.000 30000.00 0.00 100.00% CIVIL/ SURVEY
17.2 TLP Installation Nos 40.0 10 1 11 29.00 27.50% 1 PLATE COMPACTOR 0
17.3 Pin Brazing Nos 40.0 0 2 2 38.00 5.00% 2 VIBRATE M/C 0
Zn Anode Installation
17.4 (Type-A,B,C,D) (Each location 2 Nos 16.0 0 0 0 16.00 0.00% 3 CONCRETE MIXER 0 CH 39
Nos. of Zn Anode)

17.5 Mg
Anode Installation
Nos 19.0 0 1 1 18.00 5.26% 4 CUBE TESTING SET (6Nos. Mould) 0 CH 39
(Type-A+1,B+1,C+1,D+1, H )
17.6 Insulation Joints (Type- E) Nos 2.0 0 0 0 2.00 0.00% 5 Road Roller 0

17.7 Polarization
Coupon
Nos 3.0 0 0 0 3.00 0.00% 6 Total Station 0
( Type A+ PC)
D Final Cleanup & Restoration 7 Theodolite 0
18.1 Mainline Restoration RMT 30000.0 0.00 0.00 0.00 30000.00 0.00%
18.2.1 RoU Boundray Marker Nos 120.0 0 0 0 120.00 0.00%
18.2.2 Warning Marker Nos 105.0 0 0 0 105.00 0.00%
18.2.3 Direction Marker Nos 258.0 0 0 0 258.00 0.00%
18.2.4 Kilometer Marker Nos 30.0 0 0 0 30.00 0.00%
18.2.5 Total Marker Installation Nos 513.0 0 0 0 513.00 0.00%
E Mainline Hydrotesting
19.1 Cleaning, Gauging & Pigging RMT 30000.0 0 0 0 30000.00 0.00%
19.2 Mainline Hydro Testing RMT 30000.0 0 0 0 30000.00 0.00%
19.3 De-watering & Swabbing RMT 30000.0 0 0 0 30000.00 0.00%
F Pre-Commissioning
20.1 Drying RMT 30000.0 0 0 0 30000.00 0.00%
20.2 N2 Purging RMT 30000.0 0 0 0 30000.00 0.00%
G Isolation Valve
21.1 Isolation Valve Installation Nos. 7.0 0 0 0 7.00 0.00%
H Valve Chamber
22.1 Valve Chamber Construction Nos. 7.0 0 0 0 7.00 0.00%
I Commissioning
21.0 Gas In Activity RMT 16000.0 0 0 0 16000.00 0.00%
J DRS
21.1 DRS Installation Nos. 2.0 0 0 0 2.00 0.00%
K CNG
22.1 CNG Station Installation Nos. 3.0 0 0 0 3.00 0.00%

Highlights of Project Issues & Concernt by PMC/GGL :

Today's Hindrances
1
Issues & Concerns by TPPL
1

FOR TPPL FOR PMC


MAKADWAN NAGDA RATLAM PIPELINE PROJECT(MNRPL)
DAILY PROGRESS REPORT
Project: MNRPL PIPELINE PROJECT Report No 426
Contractor: M/s. Tolani Project Pvt. Ltd. Report Date 11/23/2021
Client: Gujarat Gas Ltd. Progress Date 11/22/2021
PMC: CEIL Weather Sunny
LOA DATE: 31-Aug-2020 Project completion date: 31-Mar-22
Spread - 3 : CH: 62 TO CH 78 (From KM 62M27 TO KM 78M82)
Balance Percentage
S.No. Activity Unit Scope Start Date Prev. Today Cumm. Work completion
MANPOWER DETAILS Remarks

A Mainline Activity Sl. No. DESCRIPTION QUANTITY


Total main line Pipes Received at
1.0 site(12"NB x 6.4mmThk) RMT 16000.0 12/27/2020 16000.00 0.0 16000.00 0.00 100.00% A Engineer & Staff

Total Casing Pipes Received at sit


1.1 (18"NB x 9.53mmThk) RMT 300.0 2/21/2021 0.00 0.0 0.00 300.00 0.00% 1 Project Manager ON JHA 1

2.0 Route Survey RMT 16000.0 16000.0 0.0 16000.00 0.00 100.00% 1 RCM Rajendra Pandey 1
3.0 Clearing & Grading RMT 16000.0 12/23/2020 16070.00 0.0 16070.00 -70.00 100.44% 2 Site In charge 1
4.0 Pipeline Stringing RMT 16000.0 12/28/2020 16010.16 0.00 16010.16 -10.16 100.06% 3 Civil Engineer 1
5.0 Pipe Bend 4 QA/ QC Enginner 1
5.1 Pipe Bend(3D) Nos 40.0 0 0 0 40.00 0.00% 5 Surveyor 0
5.2 Cold Bend Nos 5.0 3/6/2021 0 0 0 5.00 0.00% 6 Safety Engineer/officer 1
6 Mainline joint Welding Nos 1133.0 12/28/2020 912 0 912 221.00 80.49% B Sites Workmen
6.1 Tie -In joint Welding Nos 200.0 1/21/2021 265 4 269 -69.00 134.50% 1 Mechanical Foreman 1 CH 69 75
Total Nos of joint Welding Nos 1333.0 12/28/2020 1177 4 1181 152.00 88.60% 2 Mechanical Supervisor 5
6.2
Total Mainline Welding Length RMT 16000.0 12/28/2020 15766.78 0.00 15766.78 233.22 98.54% 3 Civil Supervisor 0
NDT 4 Welder 8
Radiography Taken Nos 1333.0 12/29/2020 1171 0 1171 162.00 87.85% 5 Fitter 4
Radiography Film Review Nos 1333.0 1/2/2021 1171 0 1171 162.00 87.85% 6 Grinder 4
Radiography Joint Accepted Nos 1/2/2021 1161 0 1161 7 Rigger 10
Joint Repair Nos 30 0 30 8 Sand Blaster 2
Repair Percentage % 2.56% #DIV/0! 2.56% 9 Insulator 2
7.0 RT Repair Taken Nos 5 0 5 10 Electrician 0
Repair RT Accepted Nos 5 0 5 11 Helper 12
Retake/ Reshoot/ Others Nos 4 0 4 12 Watchman 0
RT/RS/others Taken Nos 0 0 0 13 Civil Labour 0
RT/RS/Accepted Nos 0 0 0 C Driver & Operators

Total RT Accepted Nos 1333.0 1/2/2021 1163 0 1163 170.00 87.25% 1 BackHoe Loader (JCB) Operator 3
8.0 UT of Weld Joint Nos 28 0 28 2 Excavator/Breaker Operator 0
9.0 Weld Joint CUT OUT Nos 0 0 0 3 Hydra Operator 2
10.0 Production Test of Weld joint Nos 0 0 0
11.0 Field Joint Coating Nos 1333.0 1/7/2021 1076 0 1076 257.00 80.72% MACHINDERY DETAILS
12.0 Trenching RMT 16000.0 1/15/2021 12720.00 0.00 12720.00 3280.00 79.50% A Equipment

13.0 Pipe Lowering RMT 16000.0 1/17/2021 12260.44 258.40 12518.84 3481.16 78.24% 1 BackHoe Loader (JCB) 3 CH 75 69

14.0 Backfilling RMT 16000.0 1/20/2021 11540.70 0.00 11540.70 4459.30 72.13% 2 EXCAVATOR/ ROCK BREAKER/ Pocklane 0
B Crossings 3 HYDRA- 14 TON 2

15.1 Pre-Hydro test of Crossing section Nos 2.0 1 0 1 1.00 50.00% 4 TRACTOR TRAILORS 1

15.2 Post-Hydro test of Crossing section Nos 1.0 0 0 0 1.00 0.00% 5 DIESEL GENERATORS 1

16.1 Open Cut crossing Nos 7.0 0 0 0 7.00 0.00% 6 AIR COMPRESSORS: 300-600 CFM 0
SAND BLASTING UNITS WITH
16.2 Open Cut crossing + C.C pipe Nos 7.0 0 0 0 7.00 0.00% 7
COMPRESSOR 300 CFM
0
Open Cut crossing + C.C pipe
16.3 Nos 1.0 0 0 0 1.00 8 HDD EQUIPMENT 0
(Major Waterways)
16.4 Open Cut+ Casing Nos 0.0 0 0 0 0.00 #DIV/0! 9 WELDING M/C 2
HDD + Casing : ROAD
16.5 ( CH 74,76,78,78) Nos 4.0 1 0 1 3.00 25.00% 10 WATER TANKERS 0

16.6 HDD + Casing : RAILWAYS Nos 1.0 0 0 0 1.00 0.00% 11 DE-WATERING PUMP 0
(CH : 78 )
16.7 HDD (without casing) Nos 0.0 0 0 0 0.00 #DIV/0! 12 EXTERNAL CLAMP 1
16.8 Crossing Restoration 20.0 0 0 0 20.00 0.00% QC
C CP Works 1 HOLIDAY DETECTORS 0
17.1 Soil Resistivity Survey RMT 16000.0 16000.0 0.000 16000.00 0.00 100.00% CIVIL/ SURVEY
17.2 TLP Installation Nos 26.0 17 0 17 9.00 65.38% 1 PLATE COMPACTOR 0 CH 66
17.3 Pin Brazing Nos 26.0 2 0 2 24.00 7.69% 2 VIBRATE M/C 0
Zn Anode Installation
17.4 (Type-A,B,C,D) (Each location 2 Nos 5.0 0 0 0 5.00 0.00% 3 CONCRETE MIXER 0
Nos. of Zn Anode)

17.5 Mg Anode Installation Nos 17.0 0 0 0 17.00 0.00% 4 CUBE TESTING SET (6Nos. Mould) 0
(Type-A+1,B+1,C+1,D+1, H )
17.6 Insulation Joints (Type- E) Nos 2.0 0 0 0 2.00 0.00% 5 Road Roller 0

17.7 Polarization Coupon Nos 2.0 0 0 0 2.00 0.00% 6 Total Station 0


( Type A+ PC)
D Final Cleanup & Restoration 7 Theodolite 0
18.1 Mainline Restoration RMT 16000.0 0.00 0.00 0.00 16000.00 0.00%
18.2.1 RoU Boundray Marker Nos 64.0 0 0 0 64.00 0.00%
18.2.2 Warning Marker Nos 72.0 0 0 0 72.00 0.00%
18.2.3 Direction Marker Nos 119.0 0 0 0 119.00 0.00%
18.2.4 Kilometer Marker Nos 16.0 0 0 0 16.00 0.00%
18.2.5 Total Marker Installation Nos 271.0 0 0 0 271.00 0.00%
E Mainline Hydrotesting
19.1 Cleaning, Gauging & Pigging RMT 16000.0 0 0 0 16000.00 0.00%
19.2 Mainline Hydro Testing RMT 16000.0 0 0 0 16000.00 0.00%
19.3 De-watering & Swabbing RMT 16000.0 0 0 0 16000.00 0.00%
F Pre-Commissioning
20.1 Drying RMT 16000.0 0 0 0 16000.00 0.00%
20.2 N2 Purging RMT 16000.0 0 0 0 16000.00 0.00%
G Isolation Valve
21.1 Isolation Valve Installation Nos. 11.0 0 0 0 11.00 0.00%
H Valve Chamber
22.1 Valve Chamber Construction Nos. 11.0 0 0 0 11.00 0.00%
I Commissioning -
21.0 Gas In Activity RMT 30000.0 0 0 0 30000.00 0.00%
J DRS
21.1 DRS Installation Nos. 1.0 0 0 0 1.00 0.00%
K CNG
22.1 CNG Station Installation Nos. 1.0 0 0 0 1.00 0.00%

Highlights of Project Issues & Concernt by PMC/GGL :


1.0

Today's Hindrances
1 0.0
Issues & Concerns by TPPL

FOR TPPL FOR PMC


MAKADWAN NAGDA RATLAM PIPELINE PROJECT(MNRPL)
DAILY PROGRESS REPORT
Project: MNRPL PIPELINE PROJECT Report No 426
Contractor: M/s. Tolani Project Pvt. Ltd. Report Date 11/23/2021
Client: Gujarat Gas Ltd. Progress Date 11/22/2021
PMC: CEIL Weather Sunny
LOA DATE: 31-Aug-2020 Project completion date: 31-Mar-22
Spread - 3 : CH: 00 To CH: 08 (Spur Line)
Balance Percentage
S.No. Activity Unit Scope Prev. Today Cumm. Work completion
MANPOWER DETAILS Remarks

A Mainline Activity Sl. No. DESCRIPTION QUANTITY


Total main line Pipes Received at
1.0 site(12"NB x 6.4mmThk) RMT 5800.0 5800.00 0.0 5800.00 0.00 100.00% A Engineer & Staff

Total Casing Pipes Received at sit


1.1 (18"NB x 9.53mmThk) RMT 0.0 0.00 0.0 0.00 0.00 #DIV/0! 1 Project Manager ON JHA 1

2.0 Route Survey RMT 5800.0 5800.0 0.0 5800.00 0.00 100.00% 1 RCM Rajendra Pandey 1
3.0 Clearing & Grading RMT 5800.0 700.00 200.0 900.00 4900.00 15.52% 2 Site In charge 1
4.0 Pipeline Stringing RMT 5800.0 652.00 192.00 844.00 4956.00 14.55% 3 Civil Engineer 1
5.0 Pipe Bend 4 QA/ QC Enginner 1
5.1 Pipe Bend(3D) Nos 40.0 0 0 0 40.00 0.00% 5 Surveyor 0
5.2 Cold Bend Nos 5.0 0 0 0 5.00 0.00% 6 Safety Engineer/officer 1
6 Mainline joint Welding Nos 483.0 51 12 63 420.00 13.04% B Sites Workmen CH 00 SL
6.1 Tie -In joint Welding Nos 0.0 0 0 0 0.00 #DIV/0! 1 Mechanical Foreman 1
Total Nos of joint Welding Nos 483.0 51 12 63 420.00 13.04% 2 Mechanical Supervisor 2
6.2
Total Mainline Welding Length RMT 5800.0 652.00 192.00 844.00 4956.00 14.55% 3 Civil Supervisor 0
NDT 4 Welder 4
Radiography Taken Nos 483.0 29 29 454.00 6.00% 5 Fitter 2
Radiography Film Review Nos 483.0 29 0 29 454.00 6.00% 6 Grinder 2
Radiography Joint Accepted Nos 28 0 28 7 Rigger 4
Joint Repair Nos 1 0 1 8 Sand Blaster 2
Repair Percentage % 3.45% #DIV/0! 3.45% 9 Insulator 2
7.0 RT Repair Taken Nos 0 0 0 10 Electrician 0
Repair RT Accepted Nos 0 0 0 11 Helper 4
Retake/ Reshoot/ Others Nos 0 0 0 12 Watchman 0
RT/RS/others Taken Nos 0 0 0 13 Civil Labour 0
RT/RS/Accepted Nos 0 0 0 C Driver & Operators

Total RT Accepted Nos 483.0 28 0 28 455.00 5.80% 1 BackHoe Loader (JCB) Operator 3
8.0 UT of Weld Joint Nos 1 0 1 2 Excavator/Breaker Operator 0
9.0 Weld Joint CUT OUT Nos 0 0 0 3 Hydra Operator 2
10.0 Production Test of Weld joint Nos 0 0 0
11.0 Field Joint Coating Nos 483.0 0 28 28 455.00 5.80% MACHINDERY DETAILS CH 00 SL
12.0 Trenching RMT 5800.0 0.00 0.00 0.00 5800.00 0.00% A Equipment

13.0 Pipe Lowering RMT 5800.0 0.00 0.00 0.00 5800.00 0.00% 1 BackHoe Loader (JCB) 3

14.0 Backfilling RMT 5800.0 0.00 0.00 0.00 5800.00 0.00% 2 EXCAVATOR/ ROCK BREAKER/ Pocklane 0
B Crossings 3 HYDRA- 14 TON 2

15.1 Pre-Hydro test of Crossing section Nos 0.0 0 0 0 0.00 #DIV/0! 4 TRACTOR TRAILORS 1

15.2 Post-Hydro test of Crossing section Nos 0.0 0 H #VALUE! #VALUE! #VALUE! 5 DIESEL GENERATORS 1

16.1 Open Cut crossing Nos 0.0 0 0 0 0.00 #DIV/0! 6 AIR COMPRESSORS: 300-600 CFM 0
SAND BLASTING UNITS WITH
16.2 Open Cut crossing + C.C pipe Nos 0.0 0 0 0 0.00 #DIV/0! 7
COMPRESSOR 300 CFM
0
Open Cut crossing + C.C pipe
16.3 Nos 0.0 0 0 0 0.00 8 HDD EQUIPMENT 0
(Major Waterways)
16.4 Open Cut+ Casing Nos 0.0 0 0 0 0.00 #DIV/0! 9 WELDING M/C 2
HDD + Casing : ROAD
16.5 ( CH 74,76,78,78) Nos 0.0 0 0 0 0.00 #DIV/0! 10 WATER TANKERS 0

16.6 HDD + Casing : RAILWAYS Nos 0.0 0 0 0 0.00 #DIV/0! 0


11 DE-WATERING PUMP
(CH : 78 )
16.7 HDD (without casing) Nos 0.0 0 0 0 0.00 #DIV/0! 12 EXTERNAL CLAMP 1
16.8 Crossing Restoration 0.0 0 0 0 0.00 #DIV/0! QC
C CP Works 1 HOLIDAY DETECTORS 0
17.1 Soil Resistivity Survey RMT 5800.0 5800.0 0.000 5800.00 0.00 100.00% CIVIL/ SURVEY
17.2 TLP Installation Nos 0.0 0 0 0 0.00 #DIV/0! 1 PLATE COMPACTOR 0
17.3 Pin Brazing Nos 0.0 0 0 0 0.00 #DIV/0! 2 VIBRATE M/C 0
Zn Anode Installation
17.4 (Type-A,B,C,D) (Each location 2 Nos 0.0 0 0 0 0.00 #DIV/0! 3 CONCRETE MIXER 0
Nos. of Zn Anode)

17.5 Mg Anode Installation Nos 0.0 0 0 0 0.00 #DIV/0! 0


4 CUBE TESTING SET (6Nos. Mould)
(Type-A+1,B+1,C+1,D+1, H )
17.6 Insulation Joints (Type- E) Nos 0.0 0 0 0 0.00 #DIV/0! 5 Road Roller 0

17.7 Polarization Coupon Nos 0.0 0 0 0 0.00 #DIV/0! 0


6 Total Station
( Type A+ PC)
D Final Cleanup & Restoration 7 Theodolite 0
18.1 Mainline Restoration RMT 5800.0 0.00 0.00 0.00 5800.00 0.00%
18.2.1 RoU Boundray Marker Nos 0.0 0 0 0 0.00 #DIV/0!
18.2.2 Warning Marker Nos 0.0 0 0 0 0.00 #DIV/0!
18.2.3 Direction Marker Nos 0.0 0 0 0 0.00 #DIV/0!
18.2.4 Kilometer Marker Nos 0.0 0 0 0 0.00 #DIV/0!
18.2.5 Total Marker Installation Nos 0.0 0 0 0 0.00 #DIV/0!
E Mainline Hydrotesting
19.1 Cleaning, Gauging & Pigging RMT 5800.0 0 0 0 5800.00 0.00%
19.2 Mainline Hydro Testing RMT 5800.0 0 0 0 5800.00 0.00%
19.3 De-watering & Swabbing RMT 5800.0 0 0 0 5800.00 0.00%
F Pre-Commissioning
20.1 Drying RMT 5800.0 0 0 0 5800.00 0.00%
20.2 N2 Purging RMT 5800.0 0 0 0 5800.00 0.00%
G Isolation Valve
21.1 Isolation Valve Installation Nos. 3.0 0 0 0 3.00 0.00%
H Valve Chamber
22.1 Valve Chamber Construction Nos. 3.0 0 0 0 3.00 0.00%
I Commissioning -
21.0 Gas In Activity RMT 5800.0 0 0 0 5800.00 0.00%
J DRS
21.1 DRS Installation Nos. 0.0 0 0 0 0.00 #DIV/0!
K CNG 0.0
22.1 CNG Station Installation Nos. 1.0 0 0 0 1.00 0.00%

Highlights of Project Issues & Concernt by PMC/GGL :


1.0

Today's Hindrances
1 0.0
Issues & Concerns by TPPL

FOR TPPL FOR PMC


MAKADWAN NAGDA RATLAM PIPELINE PROJECT(MNRPL)
DAILY PROGRESS REPORT
Project: MNRPL PIPELINE PROJECT Report No 426
Contractor: M/s. Tolani Project Pvt. Ltd. Report Date 11/23/2021
Client: Gujarat Gas Ltd. Progress Date 11/22/2021
PMC: CEIL Weather Sunny
LOA DATE: 31-Aug-2020 Project completion date: 31-Mar-22
OVERALL : CH: 0.00 TO CH.86 Km

S.No. Activity Unit Scope Start Date Prev. Today Cumm. Balance Percentage MANPOWER DETAILS Remarks
Work completion

A Mainline Activity Sl. No. DESCRIPTION NAME QUANTITY

1.0 Total main line Pipes Received at RMT 84800.00 12/27/2020 84800.0 0.0 84800.0 0.00 100.00%
site(12"NB x 6.4mmThk) A Engineer & Staff

Total Casing Pipes Received at sit


1.1
(18"NB x 9.53mmThk)
RMT 812.00 2/21/2021 512.0 0.0 512.0 300.00 63.05% 1 Project Manager ON JHA 1
2.0 Route Survey RMT 84800.00 84827.5 0.0 84827.5 -27.50 100.03% 1 RCM 3
3.0 Clearing & Grading RMT 84800.00 12/23/2020 69817.7 400.0 70217.7 14582.30 82.80% 2 Site In charge 1
4.0 Pipeline Stringing RMT 84800.00 12/28/2020 69671.9 408.0 70079.9 14720.14 82.64% 3 Civil Engineer 2
5.0 Pipe Bend 0.0 4 QA/ QC Enginner 4
5.1 Pipe Bend(3D) Nos 163.00 26.0 0.0 26.0 137.00 15.95% 5 Surveyor 1
5.2 Cold Bend Nos 22.00 3/6/2021 0.0 0.0 0.0 22.00 0.00% 6 Safety Engineer/officer 3
6 Mainline joint Welding Nos 5797.00 12/28/2020 4295.0 25.0 4320.0 1477.00 74.52% B Sites Workmen
6.1 Tie -In joint Welding Nos 1324.00 1/21/2021 1259.0 9.0 1268.0 56.00 95.77% 1 Mechanical Foreman 2
Total Nos of joint Welding Nos 7121.00 12/28/2020 5555.0 34.0 5589.0 1532.00 78.49% 2 Mechanical Supervisor 7
6.2
Total Mainline Welding Length RMT 84800.00 12/28/2020 69319.1 408.8 69727.9 15072.12 82.23% 3 Civil Supervisor 0
NDT 4 Welder 12
Radiography Taken Nos 7121.00 12/29/2020 5373.0 0.0 5373.0 1748.00 75.45% 5 Fitter 6
Radiography Film Review Nos 7121.00 1/2/2021 5373.0 0.0 5373.0 1748.00 75.45% 6 Grinder 6
Radiography Joint Accepted Nos 0.00 1/2/2021 5169.0 0.0 5169.0 7 Rigger 14
Joint Repair Nos 0.00 198.0 0.0 198.0 8 Sand Blaster 2
Repair Percentage % 0.2 #DIV/0! 0.2 9 Insulator 2
7.0 RT Repair Taken Nos 0.00 143.0 0.0 143.0 10 Electrician 0
Repair RT Accepted Nos 0.00 143.0 0.0 143.0 11 Helper 16
Retake/ Reshoot/ Others Nos 0.00 29.0 0.0 29.0 12 Watchman 0
RT/RS/others Taken Nos 0.00 21.0 0.0 21.0 13 Civil Labour 0
RT/RS/Accepted Nos 0.00 21.0 0.0 21.0 C Driver & Operators
Total RT Accepted Nos 7121.00 1/2/2021 5313.0 0.0 5313.0 1808.00 74.61% 1 BackHoe Loader (JCB) Operator 3
8.0 UT of Weld Joint Nos 0.00 391.0 0.0 391.0 2 Excavator/Breaker Operator 0
9.0 Weld Joint CUT OUT Nos 0.00 10.0 0.0 10.0 3 Hydra Operator 2
10.0 Production Test of Weld joint Nos 0.00 1.0 0.0 1.0
11.0 Field Joint Coating Nos 7121.00 1/7/2021 4940.0 28.0 4968.0 2153.00 69.77% MACHINDERY DETAILS
12.0 Trenching RMT 84800.00 1/15/2021 60844.0 230.0 61074.0 23726.00 72.02% A Equipment
13.0 Pipe Lowering RMT 84800.00 1/17/2021 59489.5 379.8 59869.3 24930.75 70.60% 1 BackHoe Loader (JCB) 3

14.0 Backfilling RMT 84800.00 1/20/2021 54793.7 175.0 54968.7 29831.30 64.82% 2 EXCAVATOR/ ROCK BREAKER/ Pocklane 0

B Crossings 3 HYDRA- 14 TON 2

15.1 Pre-Hydro test of Crossing section Nos 15.00 8.0 0.0 8.0 7.00 53.33% 4 TRACTOR TRAILORS 2

15.2 Post-Hydro test of Crossing section Nos 6.00 2.0 #VALUE! #VALUE! #VALUE! #VALUE! 5 DIESEL GENERATORS 2
16.1 Open Cut crossing Nos 26.00 11.0 0.0 11.0 15.00 42.31% 6 AIR COMPRESSORS: 300-600 CFM 0
SAND BLASTING UNITS WITH
16.2 Open Cut crossing + C.C pipe Nos 36.00 3/20/2021 10.0 0.0 10.0 26.00 27.78% 7
COMPRESSOR 300 CFM
0

16.3 Open Cut crossing + C.C pipe Nos 2.00 0.0 0.0 0.0 2.00 8 HDD EQUIPMENT 0
(Major Waterways)
16.4 Open Cut+ Casing Nos 2.00 2.0 0.0 2.0 0.00 100.00% 9 WELDING M/C 4
HDD + Casing : ROAD
16.5 ( CH 02,10,11,27,30, Nos 12.00 4/29/2021 2.0 0.0 2.0 10.00 16.67% 10 WATER TANKERS 0
33,33,34,74,76,78,78 )

16.6 HDD + Casing : RAILWAYS Nos 4.00 1.0 0.0 1.0 3.00 25.00% 11 DE-WATERING PUMP 0
(CH : 3.9, 28,35,78 )
16.7 HDD (without casing) Nos 1.00 3/8/2021 1.0 0.0 1.0 0.00 100.00% 12 EXTERNAL CLAMP 1
16.8 Crossing Restoration Nos 83.00 0.0 0.0 0.0 83.00 0.00% QC
C CP Works 1 HOLIDAY DETECTORS 0
17.1 Soil Resistivity Survey RMT 84800.00 84800.0 0.0 84800.0 0.00 100.00% CIVIL/ SURVEY
17.2 TLP Installation Nos 122.00 83.0 1.0 84.0 38.00 68.85% 1 PLATE COMPACTOR 0
17.3 Pin Brazing Nos 122.00 29.0 2.0 31.0 91.00 25.41% 2 VIBRATE M/C 0
Zn Anode Installation
17.4 (Type-A,B,C,D) (Each location 2 Nos 37.00 9.0 0.0 9.0 28.00 24.32% 3 CONCRETE MIXER 0
Nos. of Zn Anode)
Mg Anode Installation
17.5 Nos 66.00 10.0 1.0 11.0 55.00 16.67% 4 CUBE TESTING SET (6Nos. Mould) 0
(Type-A+1,B+1,C+1,D+1, H )
17.6 Insulation Joints (Type- E) Nos 11.00 0.0 0.0 0.0 11.00 0.00% 5 Road Roller 0
17.7 Polarization Coupon Nos 8.00 12.0 0.0 12.0 -4.00 150.00% 6 Total Station 0
( Type A+PC)
D Final Cleanup & Restoration 7 Theodolite 0
18.1 Mainline Restoration RMT 84800.00 0.0 0.0 0.0 84800.00 0.00% OVERALL
18.2.1 RoU Boundray Marker Nos 316.00 0.0 0.0 0.0 316.00 0.00% Equipment
18.2.2 Warning Marker Nos 264.00 0.0 0.0 0.0 264.00 0.00% PIPE TRAILORS 0
18.2.3 Direction Marker Nos 561.00 0.0 0.0 0.0 561.00 0.00% PIPE BENDING M/C 1
18.2.4 Kilometer Marker Nos 78.00 0.0 0.0 0.0 78.00 0.00% THRUST BORING M/C 0
18.2.5 Total Marker Installation Nos 1219.00 0.0 0.0 0.0 1219.00 0.00% FILLING PUMP 100 Cu.m /min. 1
E Mainline Hydrotesting HIGH PRESSURE TEST PUMP 0
19.1 Cleaning, Gauging & Pigging RMT 84800.00 0.0 0.0 0.0 84800.00 0.00% DOZING PUMP 0
19.2 Mainline Hydro Testing RMT 84800.00 0.0 0.0 0.0 84800.00 0.00% BEVELING M/C 0
19.3 De-watering & Swabbing RMT 84800.00 0.0 0.0 0.0 84800.00 0.00% QC
F Pre-Commissioning DARK ROOM & ASSOCIATED FACILITIES
1
20.1 Drying RMT 84800.00 0.0 0.0 0.0 84800.00 0.00% RADIOGRAPHY: EXT & INT UNITS 1
20.2 N2 Purging RMT 84800.00 0.0 0.0 0.0 84800.00 0.00% UT M/C 1
G Isolation Valve PIPELINE LOCATORS 1
21.1 Isolation Valve Installation Nos. 31.00 0.0 0.0 0.0 31.00 0.00% HYDRO TESTING EQUIP. 0
H Valve Chamber 0.0 Electrical
22.1 Valve Chamber Construction Nos. 31.00 0.0 0.0 0.0 31.00 0.00% Megger: 1000 Volts 1
I Commissioning Multi Meter 1
21.0 Gas In Activity RMT 84800.00 0.0 0.0 0.0 84800.00 0.00% CLIP-ON Meter 2
J DRS
21.1 DRS Installation Nos. 6.00 0.0 0.0 0.0 6.00 0.00%
K CNG
22.1 CNG Station Installation Nos. 6.00 0.0 0.0 0.0 6.00 0.00%

Highlights of Project Issues & Concernt by PMC/GGL :

Hindrances
1 0.0
Issues & Concerns by TPPL

FOR TPPL FOR PMC


MNRPL Project
Key- Personnel Details
TOTAL
Sl. No. DESCRIPTION NAME (PRESENT 1-Dec 2-Dec 3-Dec 4-Dec 5-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec
DAYS)

OVERALL (0- 86)


A Key- Personnel
ON JHA/AKILESH
1 Project Manager TIWARI 9 1 1 1 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 1 1 1

2 RCM (0-32) G. TRIPATHI 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 RCM (33-62) G. TRIPATHI 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 RCM (63-78) Rajendra Pandey 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

For TPPL For CEIL


MNRPL Project
Manpower Details
TOTAL
Sl. No. DESCRIPTION NAME (PRESENT 1-Dec 2-Dec 3-Dec 4-Dec 5-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec
DAYS)
OVERALL (0- 86)
A Engineer & Staff

1 Project Manager ON JHA 9 1 1 1 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 1 1 1

2 Lead QA/QC Shamsad Ali 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 Lead HSE officer Sanjay Singh 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 Planning engineer Bikash Kr. Singh 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

5 Document Controller Niranjan Tiwari 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6 Material controller/ Store Keeper 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

7 Admin officer Manish Rai 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

B Sites Workmen

1 Fabricator - 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

2 NDT Crew - 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 UT Technician - 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 TCP/PCP Installation Crew - 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

C Driver & Operators

1 Driver LMV - 110 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

2 Trailor Driver - 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 Bending M/c Op. - 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SPREAD-1 ( 0-32)

A Engineer & Staff

1 RCM G. TRIPATHI 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Site In charge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

3 Civil Engineer 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 QA/ QC Enginner 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

5 Surveyor 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6 Safety Engineer/officer 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

B Sites Workmen

1 Mechanical Foreman 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Mechanical Supervisor 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 Civil Supervisor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4 Welder 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

5 Fitter 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6 Grinder 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

7 Rigger 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

8 Sand Blaster 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9 Insulator 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10 Electrician 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11 Helper 132 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6

13 Civil Labour 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

C Driver & Operators

1 BackHoe Loader (JCB) Operator 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Excavator/Breaker Operator 9 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1

3 Hydra Operator 9 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1

SPREAD- 2 (32-62)

A Engineer & Staff

1 RCM GC Tripathi 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Site In charge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

3 Civil Engineer 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 QA/ QC Enginner 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

5 Surveyor 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6 Safety Engineer/officer 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

B Sites Workmen

1 Mechanical Foreman 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

2 Mechanical Supervisor 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 Civil Supervisor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4 Welder 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

5 Fitter 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6 Grinder 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

7 Rigger 88 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

8 Sand Blaster 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9 Insulator 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10 Electrician 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11 Helper 132 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6

12 Watchman 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13 Civil Labour 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

C Driver & Operators

1 BackHoe Loader (JCB) Operator 66 1 1 1 1 1 1 1 1 1 1 1 5 5 5 5 5 5 5 5 5 5 5

2 Excavator/Breaker Operator 22 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2

3 Hydra Operator 55 1 1 1 1 1 1 1 1 1 1 1 4 4 4 4 4 4 4 4 4 4 4

SPREAD- 3 (63-86)

A Engineer & Staff

1 RCM Rajendra Pandey 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Site In charge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

3 Civil Engineer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4 QA/ QC Enginner 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

5 Surveyor 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6 Safety Engineer/officer 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

B Sites Workmen

1 Mechanical Foreman 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Mechanical Supervisor 110 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

3 Civil Supervisor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4 Welder 176 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8

5 Fitter 88 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

6 Grinder 88 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

7 Rigger 220 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10

8 Sand Blaster 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

9 Insulator 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

10 Electrician 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11 Helper 264 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12

12 Watchman 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13 Civil Labour 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

C Driver & Operators

1 BackHoe Loader (JCB) Operator 66 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

2 Excavator/Breaker Operator 44 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

3 Hydra Operator 62 2 2 2 2 2 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4

For TPPL For CEIL


NEXT DAY PLAN

MAKADWAN NAGDA RATLAM PIPE LINE PROJECT (MNRPL)


CLIENT GUJARAT GAS LIMITED (GGL) REPORT NO

PMC CERTIFICATION OF ENGINEERS INTERNATIONAL LIMITED (CEIL) PLAN DATE 11/23/2021

TPIA INTERNATIONAL CERTIFICATION SERVICES (ICS) REPORT DATE 11/22/2021

CONTRACTOR TOLANI PROJETCS PRIVATE LIMITED (TPPL) LOCATION


Sr.
No.
Activity Location TIME Contact Person Contact No Remarks

CH 01 S LINE 09:00- 06:00 SUDISH 9998977133


1 Stringing
CH 47 49 09:00- 06:00 SACHIN 9926030491
CH 01 S LINE 09:00- 06:00 SUDISH 9998977133
2 MAIN LINE
CH 47 49 09:00- 06:00 SACHIN 9926030491
CH 56 59 09:00- 06:00 SOYEB 7310042336
CH 40 42 09:00- 06:00 UMASHANKAR 9340055881
3 TIE IN CH 75 09:00- 06:00 NAUSAD 9560670753
CH 35 09:00- 06:00 DILIP 8853090111
CH 69 09:00- 06:00 RAJAT 8839796827
4 CP WORKS CH 76 09:00- 06:00 SATISH 9029920113
CH 75 09:00- 06:00 NIRAJ 6200916826
5 COATING CH 41 09:00- 06:00 ROHIT 7489419160
CH 56 59 09:00- 06:00 SOYEB 7310042336
CH 00 SL 09:00- 06:00 RAJAN 8651379645
CH 75 09:00- 06:00 NIRAJ 6200916826
6 TRENCHING
CH 56 59 09:00- 06:00 SOYEB 7310042336
CH 40 42 09:00- 06:00 UMASHANKAR 9340055881
CH 00 S LINE 09:00- 06:00 RAJAN 8651379645
CH 69 09:00- 06:00 SUDISH 9998977133 CH 69: MJ57-MJ58, MJ60, MJ62
7 LOWERING
CH 41 09:00- 06:00 ROHIT 7489419160 CH41: MJ01-MJ05

CH 59 10:30 AM SOYEB 7310042336 KM 59: MJ75

CH 69 09:00- 06:00 RAJAN 8651379645


CH 75 09:00- 06:00 NIRAJ 6200916826
8 BACKFILLING CH 3.9 09:00- 06:00 SHYAM SUNDAR 7974622252
CH 41 43 09:00- 06:00 ROHIT 7489419160
CH 57 58 59 09:00- 06:00 JASWANT 800464117
9 PART-B PIPEBOOK CHECK NAGDA OFFICE 09:00- 06:00 SUMIT 9450272652
10 HDD CH 28 09:00- 06:00 DILIP 8853090111 PILOT START

Remarks:
SUBMITTED BY TPPL VERIFIED BY CEIL

SIGNATURE: SIGNATURE:

NAME: BIKASH KUMAR SINGH NAME: MAHENDRA PRATAP SINGH

DATE: 22-12-2021 DATE: 22-12-2021

You might also like