Megha Engineering & Infrastructures Ltd

Adilabad Water Grid(4127)


Project Name /Code : Adilabad Water Grid(4127) Date 2/21/2024
Sub-Contractor Name : M Chandra Mohan Reddy RA Bill No 4
Nature of work : Construction of Internal Roads and Development work at PMC Building in Nirmal Bill Period 01-09-23 to 30-09-23
Work order Reference : MEIL/SRSP - Adilabad Ph2/4127/22-23/1751 DT 01.02.2023
Pan Card No : ALEPM4992L GST NO :36 ALEPM4992L1ZH
Upto Date Bill Deduct Previous Bill This Bill
Sl.No Description of works Units Rate Remarks
Qty Amount Qty Amount Qty Amount
Earth work excavation for structures as per drawing &
Construction of Internal Roads work at PMC Building
1 technical
in Nirmalspecifications
Providing clause 305.1 (CNS)soil
and filling murum/gravely includingfor
settingout,construction
fpundation or above pipes of shoring,bracing
including breakingand disposal
a upto 2km lead and
clodes,spreding as peroftechnical
in layers 10 to 15specifications
cm, 305 cum 103.00 163.64 16854.920 163.64 16854.92 0.000 0.00
MORD/304 MORTH in all soils.
watering,compaction by earth masters to achieve
b density
Cement control of of
concrete notPCC
lessM10(1:3:6)
than 95 percent etc,complete
prop using 40 mm cum 622.00 439.06 273095.320 439.06 273095.32 0.000 0.00
Providing
with lead and laying
upto 50m C.C all
and gradeliftsM20 nominal using
gauge
20mm HBG graded metal including cost and of
HG metal including cost &conveyance all
conveyance
c materials and labour
of all materials charges,
inclusive of labourseigniorage charges using cum 4268.00 149.79 500188.260 76.18 186042.12 73.605 314146.14
concret mixer etc complete.
charges,centering ,laying, vibrating and curing and
d machine mixing charges for RCC Road structure etc., cum 6481.00 171.29 898882.300 97.68 421848.29 73.605 477034.01
complete for
2 Construction of Development work at PMC Building in
Nirmal
Providing and filling murum/gravely (CNS)soil for
e foundation or above including breaking cum 622.0 622.67 387300.740 622.67 387300.74 0.000 0.000
clodes,spreading in layers of 10 to 15 cm,
watering,compaction byTotal
earth masters to achieve 2076321.54 1285141.39 791180.15
2 GST 18% 18% 373737.88 231325.45 142412.43
Grand Total 2450059.42 1516466.84 933592.58
Deductions
3 FSD 5% (Hold) % 5.00% -103816.08 -64257.07 -39559.01
4 TDS 1% % 1.00% -20763.22 -12851.41 -7911.80
Advances & Materials
5 Seigniorage Charge -91155.00 -78568.00 -12587.00
6 Fuel Debit 0.00 0.00 0.00
7 Material Debit Note -540653.11 -540653.11 0.00
8 Advance(Cheque No) 0.00 0.00 0.00
Total Deductions -756387.40 -603709.09 -60057.81
Additions/Releases
9 Relesaes 5% % 5.00% 0.00 0.00 0.00
Net Payable Amount 1693672.01 912757.75 873534.77
Encl:
1 Measurement Sheet,
2 Party Bill Requestion Letter
Upto Date Bill Deduct Previous Bill This Bill
Sl.No Description of works Units Rate Remarks
Qty Amount Qty Amount Qty Amount
Prepaired By Accepted By Site Engineer Accounts AM(Projects)
PMC Building CC Drain at Nirmal
S.No Description of item Nos Length Width Depth Quantity Total quantity Remarks
Cement concrete of PCC M10(1:3:6) prop using 40 mm gauge HG metal
1 including cost &conveyance of all materials and labour charges, seigniorage
charges using concret mixer etc complete.
Parking Area 1 19.5 8.5 0.15 24.86
South side road 1 10.3 5 0.15 7.73
Total Qty 32.59 32.59

Providing and laying C.C grade M20 nominal using 20mm HBG graded metal
including cost and conveyance of all materials inclusive of labour
2
charges,centering ,laying, vibrating and curing and machine mixing charges for
RCC Road structure etc., complete for

Parking Area 1 19.5 8.5 0.15 24.86


South side road 1 10.3 5 0.15 7.73
Total Qty 32.59 32.59

Prepaired By Accepted By
SEINORAGE CHARGES FOR WORK DONE SUB ESTIMATE

Aggregates (Metal) Sand


Total
Sl. Descriptio Grade of Total Total G.O-67,
No. n of Item Concrete Quantity As per G.O-67, As per G.O-67, Differenc dtd:
dtd: Const Qty dtd: e 26/09/2
Cons Qty 26/09/2015 ant 26/09/2015 Amount 015
tant
Amount
Rate Amount Rate Amount

73.61
1 PCC 1:3:6 0.90 66.24 75 4968 0.45 33.12 40 1325 1656 6293
73.61
2 M20 1:1.5:3 0.90 66.25 75 4969 0.45 33.12 40 1325 1656 6294
TOTAL 147.22 9937 2650 3312 12587

Prepaired By Accepted By

Page 4 of 6
PMC Building CC Drain at Nirmal
S.No Description of item Nos Length Width Depth Quantity
Cement concrete of PCC M10(1:3:6) prop using 40 mm gauge HG metal
1 including cost &conveyance of all materials and labour charges, seigniorage
charges using concret mixer etc complete.
fornt side 1 29.6 5 0.15 22.20
left side 1 27 5 0.15 20.25
back side 1 32 5 0.15 24.00
1 4 3.8 0.15 2.28
1 13 2.5 0.15 4.88
Total Qty 73.61

Providing and laying C.C grade M20 nominal using 20mm HBG graded metal
including cost and conveyance of all materials inclusive of labour
2
charges,centering ,laying, vibrating and curing and machine mixing charges for
RCC Road structure etc., complete for

fornt side 1 29.6 5 0.15 22.20


left side 1 27 5 0.15 20.25
back side 1 32 5 0.15 24.00
1 4 3.8 0.15 2.28
1 13 2.5 0.15 4.88

Total Qty 73.61

Prepaired By
Total quantity Remarks

73.61

73.61

Accepted By