You are on page 1of 8

POKHARA METROPOLITAN CITY OFFICE

NEW ROAD, POKHARA


Detail Measurement and Abstract of Cost
Name of project :- Sera Bridge Maintenance F/Y :- 080/081
Site :- PMC-25 Date:- 2080-05-12
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks

Earthwork in excavation in all tpes


1.00
of soil by mechanical means.
45.20 1.00 3.00 0.20 27.12
27.12 cum 79.38 2152.79
Earthwork in excavation in all types
2.00 of soil for foundation by mechanical
means
gabion foundation 97.00 2.00 1.50 0.75 218.25 cum 119.07 25987.03

Supply and placing and erection with


3.00 binding, lacing and bracing of Machine
made and mechanically selvedged
double twisted hexagonal mesh
products(Meccaferri product) wire Mesh
Net. All complete work
2*1*1 97.00 1067.00 sqm 325.44 347244.48

Providing and filling stone.boulder in


4.00 gabion boxes/ matress etc. Including
dressing, Bedding, bonding all complete
as per Drawing and Technical
Specifications.
2*1*1 97.00 194.00 cum 3795.73 736371.62
Total 1,111,755.92
contengecies @ 3% 33,352.68
Grand total 1,145,108.60

Prepared By:
Checked By:
Ast. Sub-Er.Pratikshya Aryal Recommended By: Approved By:
Er.Prabhat Baral
POKHARA METROPOLITAN CITY OFFICE
NEW ROAD, POKHARA
Detail Estimate and Abstract of Cost
Name of project :- जनहित आमासमुह भवन मर्मत तथा व्यवस्थापन। F/Y :- 080/081
Site :- PMC-27 Date:- 2080-07-14
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks

Brick masonry works including


materials
collection, preparation of mortar
1.00
with 30m
transportation. Chimney Bhatta
Bricks in c/s mortar 1:6
1.00 29.06 0.23 2.70 18.05
deductions
Main door -1.00 1.07 0.23 2.29 -0.56
Door -1.00 0.90 0.23 2.13 -0.44
Window -6.00 1.68 0.23 1.68 -3.89
13.16 cum 16587.12 218286.50
12.5mm th. Cement plaster works in
2.00
Wall & floor in 1:6 C/S motar
2.00 29.06 2.70 156.92
column
deductions
Main door -1.00 1.07 2.29 -2.45
Door -1.00 0.90 2.13 -1.92
152.55 cum 377.48 57584.57

3.00
Plain cement concrete works in
foundation
including material collection & 30m lead
(Building Works) M20
2.00 29.06 0.23 0.075 1.00
-1.00 0.90 0.23 0.075 -0.02
-1.00 1.07 0.23 0.075 -0.02
0.960 sqm 16463.37 15804.84

Reinforcement bar for RCC works


4.00 including
cutting, binding, bending & placing as
per
drawing with 30m lead
10 mm dia bar 4.00 29.06 0.62 72.07 Kg 140.73 10142.41
Salwood frame with wood size
5.00
100*75mm
Main door 1.00 6.71 0.075 0.10 0.05
Door 1.00 5.12 0.075 0.10 0.0384
0.0884 Cum 312073.35 27587.28
Total 329,405.60
contengecies @ 3% 9,882.17
Grand total 339,287.77

Prepared By: Sub-Er.


Checked By:
Naresh Sah Approved By:
Er.Prabhat Baral
पोखरा महानगरपालिका
नगरपालिकाको कायार्लय
न्यूरोड, कास्की
गण्डकी प्रदेश, नेपाल
कार्य सम्पन्न प्रतिवेदन

कार्य स्थान – ,PMC - 25 Estimate भन्दा बढी वा घटी– less


Name of project :- जनहित आमासमुह भवन मर्मत तथा व्यवस्थापन। ईस्टमेट रकम 310872.87 घटी वा बढीको प्रतिशत – 98.33%
लागेको खर्च रकम 18669723 कार्य सम्पन्न गर्ने माघ्यमः
सि.न. विवरण ईस्टमेट अनुसार खुद लागेको खर्च फरक पर्न आएको कै फियत
परिमाण दर रकम परिमाण दर रकम परिमाण प्रतिशत रकम

Brick masonry works including materials


collection, preparation of mortar with 30m
transportation. Chimney Bhatta Bricks in c/s mortar
1 1:6 13.16 16587.12 218286.4992 27.12 16587.12 449842.6944 13.96 106.08% 231556.1952

12.5mm th. Cement plaster works in Wall & floor in


2 1:6 C/S motar 152.55 377.48 57584.574 218.25 377.48 82385.01 65.70 43.07% 24800.436

Plain cement concrete works in foundation


including material collection & 30m lead
3 (Building Works) M20 0.96 16463.37 15804.8352 1067.00 16463.37 17566415.79 1066.04 111045.83% 17550610.955

Reinforcement bar for RCC works including


cutting, binding, bending & placing as per
4 drawing with 30m lead 72.07 140.73 10142.4111 194.00 140.73 27301.62 121.93 169.18% 17159.2089
Sub Total 301818.32 18,125,945.11 17824126.79
contingency @ 3% 9054.55 543,778.35
Grand Total 310872.87 18,669,723.46 18358850.59 less

तयार पर्नेको सही चेक गर्नेको सही स्वीकृ त गर्नेको सही


Project :- Jalbinaayek Chautara Marmat

POKHARA METROPOLITAN CITY


Office of Municipal Executive
MEASUREMENT BOOK
Gandaki Province , kaski

Issued To:
Site Incharge:

Site Name: Jalbinaayek Chautara Marmat


PMC 03

Issuing Officer :

Date of first entry:


Date of last entry: 2077-12-01

Certified that this books contains 2 Page of pre - numbered measurement sheets.

Engineer Executive officer


INDEX OF MEASUREMENTS ENTERED

Pages Measured By Checked By Remarks


Name of work Done By
From To Name signature & date Name Signature & date

Jalbinaayek Chautara Bikram


1 2 User's Commettee
Marmats Timilsina
POKHARA METROPOLITAN CITY OFFICE
NEW ROAD, POKHARA
Measurment Book
Name of project :-Jalbinaayek Chautara Marmat F/Y :- 077/078
Site :- PMC-03 Date:- 25/11/2077
Kharcha Shirshak 31157
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks
A Construction Works
Dismentalling of cement mortar
1 masonary with deposition upto 10 mtr.
Lead works
1.00 5.80 3.40 0.100 1.97
5.80 1.97 Cum 1558.20 3069.65
2 Excavation of ordinary soft soil
1.00 4.70 5.70 0.150 4.02
0.50 5.70 3.30 0.150 1.41
1.00 11.80 0.30 0.150 0.53
4.70 5.96 Cum 605.64 3609.61
3 Boulder Soling and Levelling works
1.00 5.80 5.70 0.15 4.96
0.50 5.70 3.30 0.15 1.41
1.00 11.80 0.30 0.15 0.53
-3.14 0.55 0.55 0.15 -0.14
-3.14 0.60 0.60 0.15 -0.17
-3.14 0.85 0.85 0.15 -0.34
6.59 Sqm 3502.50 23081.47
4 Pcc works 1:2:4 works
1.00 5.80 5.70 0.075 2.48
0.50 5.70 3.30 0.075 0.71
1.00 11.80 0.40 0.075 0.35
-3.14 0.55 0.55 0.075 -0.07
-3.14 0.60 0.60 0.075 -0.08
-3.14 0.85 0.85 0.075 -0.17
3.39 Sqm 12129.36 41118.53
Stone Paving and Clidding Works 1:4
5
mortar
1.00 5.80 6.00 34.80
0.50 5.70 3.30 9.41

Prepared By: Checked By: Recommended By:


Approved By:
POKHARA METROPOLITAN CITY OFFICE
NEW ROAD, POKHARA
Measurment Book
Name of project :-Jalbinaayek Chautara Marmat F/Y :- 077/078
Site :- PMC-03 Date:- 25/11/2077
Kharcha Shirshak 31157
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks
1.00 12.50 0.40 5.00
1.00 3.45 0.80 2.76
1.00 3.45 0.85 2.93
1.00 1.15 0.85 0.98
1.00 4.10 0.90 3.69
1.00 1.10 0.85 0.94
1.00 1.10 0.65 0.72
-3.14 0.55 0.55 -0.95
-3.14 0.60 0.60 -1.13
-3.14 0.85 0.85 -2.27
56.88 Sqm 1851.99 105341.19

Iron Works 1" Square Pipe 11/2"


6 Square Pipe & 20*3 patti of Raling and 1.00 97.25 102.25 Kg 152.25 15567.56
Chair
Total 191,788.01
contengecies @ 3% 5,968.22
Grand total 197,756.23

Prepared By: Checked By: Recommended By:


Approved By: