67% found this document useful (9 votes)
21K views2 pages

Brickbat Coba Rate Analysis As Per CPWD

This document provides a cost estimate for waterproofing treatment for a 10 square meter area. It includes 6 items: (1) a cement slurry coat, (2) cement mortar with brick bats, (3) a second cement slurry coat, (4) a finishing cement plaster coat, (5) waterproofing compound, and (6) fiber glass reinforcement. The total estimated cost is Rs. 13,984.90 for 10 sqm or Rs. 1,398.50 per sqm. Taxes include a 1% water charge, 14.05% GST, and a 1% cess.

Uploaded by

Deepak Kaushik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
67% found this document useful (9 votes)
21K views2 pages

Brickbat Coba Rate Analysis As Per CPWD

This document provides a cost estimate for waterproofing treatment for a 10 square meter area. It includes 6 items: (1) a cement slurry coat, (2) cement mortar with brick bats, (3) a second cement slurry coat, (4) a finishing cement plaster coat, (5) waterproofing compound, and (6) fiber glass reinforcement. The total estimated cost is Rs. 13,984.90 for 10 sqm or Rs. 1,398.50 per sqm. Taxes include a 1% water charge, 14.05% GST, and a 1% cess.

Uploaded by

Deepak Kaushik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Water Proofing Specification: Details the process and requirements for water proofing treatment, including materials, labor, and execution standards.
  • Item Rate Analysis: Lists rates and quantities for various construction materials and labor involved in water proofing tasks.

Code Description Unit Quantity Rate Amount

9999 Sundries, brushes etc L.S. 23.40 2.00 46.80


TOTAL 3909.29 W
Add 1 % Water charges on "W" 39.09
TOTAL 3948.39 X
Add GST on "X" (multiplying
factor 0.1405) 554.75
TOTAL 4503.14 Y
Add 15% CPOH on "Y" 675.47
TOTAL 5178.61 Z
Add Cess @ 1% on "Z" 51.79
Cost for 10 sqm 5230.39
Cost for 1 sqm 523.04
Say 523.05

22.7 Providing and laying integral cement based water proofing treatment including
preparation of surface as required for treatment of roofs, balconies, terraces
etc consisting of following operations:
(a) Applying a slurry coat of neat cement using 2.75 kg/sqm of cement admixed
with water proofing compound conforming to IS. 2645 and approved by
Engineer-in-charge over the RCC slab including adjoining walls upto 300 mm
height including cleaning the surface before treatment.
(b) Laying brick bats with mortar using broken bricks/brick bats 25 mm to 115
mm size with 50% of cement mortar 1:5 (1 cement : 5 coarse sand) admixed
with water proofing compound conforming to IS : 2645 and approved by
Engineer-in-charge over 20 mm thick layer of cement mortar of mix 1:5 (1
cement :5 coarse sand ) admixed with water proofing compound conforming
to IS : 2645 and approved by Engineer-in-charge to required slope and treating
similarly the adjoining walls upto 300 mm height including rounding of junctions
of walls and slabs.
(c) After two days of proper curing applying a second coat of cement slurry
using 2.75 kg/ sqm of cement admixed with water proofing compound
conforming to IS : 2645 and approved by Engineer-in-charge.
(d) Finishing the surface with 20 mm thick jointless cement mortar of mix 1:4
(1 cement :4 coarse sand) admixed with water proofing compound conforming
to IS : 2645 and approved by Engineer-in-charge including laying glass fibre
cloth of approved quality in top layer of plaster and finally finishing the surface
with trowel with neat cement slurry and making pattern of 300x300 mm square
3 mm deep.
(e) The whole terrace so finished shall be flooded with water for a minimum
period of two weeks for curing and for final test.“All above operations to be
done in order and as directed and specified by the Engineer-in-Charge :
22.7.1 With average thickness of 120 mm and minimum thickness at khurra as 65
mm.
Code Description Unit Quantity Rate Amount

Detail of cost for 10 sqm


i) Cement slury
0367 Portland Cement (OPC-43 grade) tonne 0.0275 4940.00 135.85
ii) Cement mortar 1:5 (1 cement:
5 coarsesand)

SUB HEAD : 22- WATER PROOFING 1814


Code Description Unit Quantity Rate Amount

3.10 Rate as per Item No.3.10 of SH:Mortars cum 0.224 3658.10 819.41
iii) Roof treatment with brick bat and
cement mortar
MATERIAL
0285 Brick Aggregate (Single size) : 63 mm cum 0.94 650.00 611.00
2260 Carriage of Brick aggregate cum 0.94 112.79 106.02
Cement mortar 1:5
3.10 Rate as per Item No.3.10 of SH:Mortars cum 0.50 3658.10 1829.05
LABOUR
0114 Beldar day 1.75 558.00 976.50
0101 Bhisti day 0.28 617.00 172.76
0123 Mason (brick layer) 1st class day 0.05 738.00 36.90
0124 Mason (brick layer) 2nd class day 0.05 679.00 33.95
0128 Mate day 0.04 617.00 24.68
Extra labour for ramming
0114 Beldar day 0.25 558.00 139.50
9999 Sundries L.S. 13.65 2.00 27.30
iv) Cement slury
0367 Portland Cement (OPC-43 grade) tonne 0.0275 4940.00 135.85
0114 Beldar day 0.20 558.00 111.60
v) 20 mm cement plaster 1:4
(1 cement : 4 coarse sand)
13.6.1 Rate as per item no 13.6.1 of
SH : Finishing sqm 10.00 379.70 3797.00 A
vi) Water proofing compound
vi) Water proofing compound
27.50+27.50+69.40+124.00 =
248.40 kg @
1 kg per bag of cement
1213 Water proofing materials kilogram 5.00 35.00 175.00
Extra for making chequers for 10 sqm
7233 Fibre glass tissue reinforcement
Type II Grade I sqm 10.50 82.00 861.00
0124 Mason (brick layer) 2nd class day 0.36 679.00 244.44
0114 Beldar day 0.36 558.00 200.88
9999 Chequer plate L.S. 13.65 2.00 27.30
Add labour for laying 20 mm bed mortar
0124 Mason (brick layer) 2nd class day 0.54 679.00 366.66
0114 Beldar day 0.54 558.00 301.32
0101 Bhisti day 0.45 617.00 277.65
TOTAL 11411.63 W
Add 1 % Water charges on "W-A" 76.15
TOTAL 11487.77 X
Add GST on "X-A" (multiplying
factor 0.1405) 1080.55
TOTAL 12568.33 Y
Add 15% CPOH on "Y-A" 1315.70
TOTAL 13884.03 Z
Add Cess @ 1% on "Z-A" 100.87
Cost for 10 sqm 13984.90
Cost for one sqm 1398.49
Say 1398.50

SUB HEAD : 22- WATER PROOFING 1815