Rate Analysis based on DAR

Providing and laying in position cement concrete of specified grade excluding the cost of centering and
shuttering - All work up to plinth level :
Item : PCC
Item Code: 4.1.5 (DAR-2019)
All work up to plinth level: 1:3:6 - Coarse sand, 20mmstone aggregate.. ..
Details of Cost for : 1.00 Cum

Code Description Unit Quantity Rate Amount Remarks


LABOUR:
0155 Mason Day 0.015 500.00 7.50
0114 Beldar Day 0.021 450.00 9.45
0101 Bhishti Day 0.038 350.00 13.30
0002 Mixer Day 0.07 - 0.00
0012 Vibrator Day 0.07 - 0.00
9999 Sundries L.S. 13.52 1.49 20.14
Total: 50.39
Cost for 1.00 Cum 50.39
Rate per One Cum: Rs 50.39
Say = Rs 50.00
Rate Analysis based on DAR
Centering and shuttering including strutting, propping etc. and removal of form work for :
Item : Shuttering & Centering
Item Code: 4.3.1 (DAR-2019)
Foundations, footings, bases for columns
Details of Cost for : 10.80 Sqm

Code Description Unit Quantity Rate Amount Remarks

Details of cost for footing size


2.7m x 2.7m x l.00m
Contact area = 10.8 sqm.
MATERIAL:
Assuming shuttering material will
become unserviceable after use of 40
times
Adding for maintenance @ 10% of cost

Taking salvage value after full use of


material @ 25% of cost
7319 Wall form panel 1250x500mm each 0.34 1,050.00 357.00
Qty taken for cost of using once =
16x0.85/40 = 0.34
9999 Assembly nuts & bolts L.S. 22.10 1.49 32.93
LABOUR: Deduction of Material (Total Sum) =
0116 Fitter Grade-I Day 0.82 550.00 451.00
0114 Beldar Day 1.50 450.00 675.00
9999 Shuttering oil L.S. 52.00 1.49
9999 Sundries L.S. 26.00 1.49
Total: 1515.93
Cost for 10.80 Sqm 1515.93
Rate per One Sqm: Rs 140.36
Say = Rs 140.00
Rate Analysis based on DAR
Retaining walls, return walls, walls (any thickness) including attached pilasters,buttresses, plinth and string
courses fillets, kerbs and steps etc.
Item : Shuttering & Centering
Item Code: 4.3.2
Details of Cost for : 15.80 Sqm

Code Description Unit Quantity Rate Amount Remarks

Details for 7.9m long and 1.00m high


wall
Area of contact 2x7.9x1.0 = 15.8 sqm.

Materials:
Assuming shuttering material will be
unsevicea- ble after use of times
Adding for maintenance @ 10% of cost

Taking salvage value after full use of


material @ 25% of cost
7319 Wall form Panel (1.25x0.5) 2x3x2x2 = each 0.51 1050.00 535.50
24 Nos
Qty taken for cost of using once =
24x0.85/40 =0.51
9999 Nut & Bolts L.S. 27.62 1.49 41.15
LABOUR: Deduction of Material (Total Sum) =
0116 Fitter Grade-I Day 1.84 550.00 1012.00
0114 Beldar Day 6.00 450.00 2700.00
9999 Shuttering oil L.S. 78.00 1.49
9999 Sundries L.S. 52.00 1.49
Total: 4288.65
Cost for 15.80 Sqm 4288.65
Rate per One Sqm: Rs 271.43
Say = Rs 271.00
Rate Analysis based on DAR
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all
complete upto plinth level.
Item : Steel
Item Code: 5.22.6
Thermo-Mechanically Treated bars.
Details of Cost for : 100.00 Kg

Code Description Unit Quantity Rate Amount Remarks

Qty of TMT bars : 1.00 q


add 5% wastage : 0.05q
Total : 1.05q

1005-A Thermo mechanically treated steel Qtl 1.05 0.00 This Co-efficent
bars (for reinforcement) should be
9999 Cover blocks considered for
L.S. 26.00 0.00 with Material
For straightening, cutting, bending,
binding and placing in position-

0102 Blaks smith I Class Day 0.23 600.00 138.00


0114 Beldar Day 0.92 350.00 322.00
9999 Sundries L.S. 26.91 1.49 40.10
Total: 500.10
Cost for 100.00 Kg 500.10
Rate per One Kg: Rs 5.00
Say = Rs 5.00
Rate Analysis based on DAR
Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced
cement concrete work, using cementcontent as per approved design mix, including pumping of concrete to site of layingbut
excluding the cost of centering, shuttering, finishing and reinforcement,including admixtures in recommended proportions as per IS:
9103 to accelerate,retard setting of concrete, improve workability without impairing strength anddurability as per direction of
Engineer-in-charge.
Upto Plinth Level

(Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ lesscement used as per design mix is
payable/recoverable separately).
Item : M-25 (Concrete)
Item Code: 5.33.1
Code Description Unit Quantity Rate Amount Remarks

LABOUR:
0114 Beldar Day 0.186 500.00 93.00
0101 Bhisti Day 0.116 450.00 52.20
0012 Vibrator (Needle type 40mm) Day 0.070 - 0.00
9999 Sundries L.S. 13.000 1.49 19.37
Total: 164.57
Cost for 1.00 Cum 164.57
Rate per One Cum: Rs 164.57
Say = Rs 165.00
Providing and laying in position machine batched and machine mixed design mix M-25/M-30 grade cement concrete for reinforced
cement concrete work, using cementcontent as per approved design mix, including pumping of concrete to site of layingbut
excluding the cost of centering, shuttering, finishing and reinforcement,including admixtures in recommended proportions as per IS:
9103 to accelerate,retard setting of concrete, improve workability without impairing strength anddurability as per direction of
Engineer-in-charge.
All works above plinth level upto floor V level (Above 2.0m)

(Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ lesscement used as per design mix is
payable/recoverable separately).
Item : M-25 (Concrete)
Item Code: 5.33.1
0004 LABOUR:
0009 Labour for pouring, consolidating &
curing
Mason (average) Day 0.145 500.00 72.50
Beldar Day 0.155 500.00 77.50
0155 Bhisti Day 0.090 450.00 40.50
0114 Vibrator (Needle type 40mm) Day 0.07 -
0101 Sundries L.S. 13.00 2.00 26.00
0012 Extra labour for lifting upto floor five
level
9999 0.75 x 1.50 = 1.88
Coolie Day 0.13 500.00 65.00
Total: 281.50
0115 Add water charges @ 1% on 281.50 0.00
281.50
Add C.P & OH @5% on 281.50 0.00
Cost for 1.00 Cum 281.50
Rate per One Cum: Rs 281.50
Say = Rs 282.00