Providing and laying in position cement concrete of specified grade excluding the cost of centering and
shuttering - All work up to plinth level :
Item : PCC
Item Code: 4.1.5 (DAR-2019)
All work up to plinth level: 1:3:6 - Coarse sand, 20mmstone aggregate.. ..
Details of Cost for : 1.00 Cum
Materials:
Assuming shuttering material will be
unsevicea- ble after use of times
Adding for maintenance @ 10% of cost
1005-A Thermo mechanically treated steel Qtl 1.05 0.00 This Co-efficent
bars (for reinforcement) should be
9999 Cover blocks considered for
L.S. 26.00 0.00 with Material
For straightening, cutting, bending,
binding and placing in position-
(Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ lesscement used as per design mix is
payable/recoverable separately).
Item : M-25 (Concrete)
Item Code: 5.33.1
Code Description Unit Quantity Rate Amount Remarks
LABOUR:
0114 Beldar Day 0.186 500.00 93.00
0101 Bhisti Day 0.116 450.00 52.20
0012 Vibrator (Needle type 40mm) Day 0.070 - 0.00
9999 Sundries L.S. 13.000 1.49 19.37
Total: 164.57
Cost for 1.00 Cum 164.57
Rate per One Cum: Rs 164.57
Say = Rs 165.00
Providing and laying in position machine batched and machine mixed design mix M-25/M-30 grade cement concrete for reinforced
cement concrete work, using cementcontent as per approved design mix, including pumping of concrete to site of layingbut
excluding the cost of centering, shuttering, finishing and reinforcement,including admixtures in recommended proportions as per IS:
9103 to accelerate,retard setting of concrete, improve workability without impairing strength anddurability as per direction of
Engineer-in-charge.
All works above plinth level upto floor V level (Above 2.0m)
(Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ lesscement used as per design mix is
payable/recoverable separately).
Item : M-25 (Concrete)
Item Code: 5.33.1
0004 LABOUR:
0009 Labour for pouring, consolidating &
curing
Mason (average) Day 0.145 500.00 72.50
Beldar Day 0.155 500.00 77.50
0155 Bhisti Day 0.090 450.00 40.50
0114 Vibrator (Needle type 40mm) Day 0.07 -
0101 Sundries L.S. 13.00 2.00 26.00
0012 Extra labour for lifting upto floor five
level
9999 0.75 x 1.50 = 1.88
Coolie Day 0.13 500.00 65.00
Total: 281.50
0115 Add water charges @ 1% on 281.50 0.00
281.50
Add C.P & OH @5% on 281.50 0.00
Cost for 1.00 Cum 281.50
Rate per One Cum: Rs 281.50
Say = Rs 282.00