You are on page 1of 1

Code Description Unit Quantity Rate Amount

9999 Scaffolding and sundries L.S. 11.70 1.73 20.24


TOTAL 1238.20
Add 1 % Water charges 12.38
TOTAL 1250.58
Add 15 % Contractor's profit and overheads 187.59
Cost of 10.00 sqm 1438.17
Cost of 1.00 sqm 143.81
Say 143.80

13.17 6 mm cement plaster 1:3 (1 cement : 3 fine sand) finished with a floating coat of
neat cement and thick coat of Lime wash on top of walls when dry for bearing
of R.C.C. slabs and beams.

Code Description Unit Quantity Rate Amount


Detail of cost for 10 sqm
MATERIAL
Cement mortar 1 : 3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.072 4252.70 306.19
LABOUR
0155 Mason (average) day 0.51 467.00 238.17
0115 Coolie day 0.75 368.00 276.00
0101 Bhisti day 0.92 407.00 374.44
9999 Extra for removing burrs, cleaning with wire
brushes, pock making with pointed tool etc.
complete. L.S. 13.39 1.73 23.16
9999 Scaffolding and sundries L.S. 11.7 1.73 20.24
0367 Portland Cement (OPC-43 grade) tonne 0.02 5700.00 114.00
2209 Carriage of Cement tonne 0.02 92.24 1.84
0155 Mason (average) day 0.27 467.00 126.09
0115 Coolie day 0.27 368.00 99.36
9999 Scaffolding and sundries L.S. 8.06 1.73 13.94
0776 Satna lime quintal 0.01 370.00 3.70
9999 Indigo gum etc L.S. 2.08 1.73 3.60
9999 Sundries ladder etc. L.S. 0.52 1.73 0.90
0141 White Washer day 0.07 407.00 28.49
0115 Coolie day 0.07 368.00 25.76
9999 Sundries L.S. 2.73 1.73 4.72
TOTAL 1660.60
Add 1 % Water charges 16.61
TOTAL 1677.21
Add 15 % Contractor's profit and overheads 251.58
Cost of 10.00 sqm 1928.79
Cost of 1.00 sqm 192.87
Say 192.85

13.18 Neat cement punning.


Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
0367 Portland Cement (OPC-43 grade) tonne 0.022 5700.00 125.40
2209 Carriage of Cement tonne 0.022 92.24 2.03

SUB HEAD : 13- FINISHING 780