Code Description Unit Quantity Rate Amount

3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.172 5233.50 900.16
LABOUR
0155 Mason (average) day 0.80 467.00 373.60
0115 Coolie day 0.88 368.00 323.84
0101 Bhisti day 0.99 407.00 402.93
9999 Scaffolding and sundries L.S. 12.61 1.73 21.82
TOTAL 2022.35
Add 1 % Water charges 20.22
TOTAL 2042.57
Add 15 % Contractor's profit and overheads 306.39
Cost of 10.00 sqm 2348.96
Cost of 1.00 sqm 234.89
Say 234.90

13.15 20 mm cement plaster 1:2 (1 cement : 2 stone dust).


Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIAL
Cement mortar 1:2 (1 Cement : 2 stone dust)
3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.224 5233.50 1172.30
LABOUR
0155 Mason (average) day 0.94 467.00 438.98
0115 Coolie day 1.02 368.00 375.36
0101 Bhisti day 1.10 407.00 447.70
9999 Scaffolding and sundries L.S. 12.61 1.73 21.82
TOTAL 2456.16
Add 1 % Water charges 24.56
TOTAL 2480.72
Add 15 % Contractor's profit and overheads 372.11
Cost of 10.00 sqm 2852.83
Cost of 1.00 sqm 285.28
Say 285.30

13.16 6 mm cement plaster of mix :


13.16.1 1:3 (1 cement : 3 fine sand)

Code Description Unit Quantity Rate Amount


Detail of cost for 10 sqm
MATERIAL
Cement mortar 1 : 3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.072 4252.70 306.19
LABOUR
0155 Mason (average) day 0.51 467.00 238.17
0115 Coolie day 0.75 368.00 276.00
0101 Bhisti day 0.92 407.00 374.44
9999 Extra for removing burrs, cleaning with
wire brushes, pock making with pointed
tool etc. complete. L.S. 13.39 1.73 23.16

SUB HEAD : 13- FINISHING 779