You are on page 1of 4

(Based on DSR 2021, Item No. 19.7.1.

1)

Code Description Qty Unit Rate Amount

Details of cost for 1 manhole

Cement concrete 1:4:8 (1 cement : 4 coarse sand


: 8 graded stone aggregate 40 mm nominal size)
1.51×1.41×0.20 m = 0.426 cum Say 0.43 cum

4.1.8 Rate as per item no 4.1.8 of SH : Concrete Work 0.43 cum 6326.05 2720.20 A

Brick work with bricks of class designation 7.5


in foundation & plinth in cement mortar 1:4 (1
cement : 4 coarse sand)
4.32×0.23×0.35 m = 0.348 cum
Less for pipe 2×3.14x(0.15m)²x0.23m = (-)
0.008 cum
Total = 0.340 cum

6.1.1 Rate as per item no 6.1.1 of SH : Brick Work 0.34 cum 6882.00 2339.88 A

Cement concrete 1:2:4 (1 cement : 2 coarse sand


: 4 graded stone aggregate 20 mm nominal size)
for benching
2×0.90x(0.80/2) x (0.30+0.20)/2 = 0.18 cum
Less for pipe 1×0.90×3.14/4x(0.15m)² = (-) 0.02
cum
= 0.16 cum

Rate as per item no. 4.1.3 of SH : Concrete


4.1.3 0.16 cum 7365.15 1178.42 A
Work
12 mm cement plaster 1:3 (1 cement : 3 coarse
sand) finished with floating coat of neat cement

3.40mx0.05m = 0.17 sqm


2x½x0.80×0.10m = 0.08 sqm
Total= 0.25 sqm

13.9.1 Rate as per item no 13.9.1 of SH : Finishing 0.25 Sqm 386.55 96.64 A

Reinforced cement concrete 1:1.5:3 (1 cement :


1.5 coarse sand : 3 graded stone aggregate 20
mm nominal size)
For slab : 1.36×1.26×0.15m = 0.257 cum
Less for cover 0.61×0.455×0.15m = (-) 0.042
cum
= 0.215 cum Say 0.22 cum

5.3 Rate as per item no 5.3 of SH : RCC Work 0.22 cum 10719.15 2358.21 A

Less labour for not lifting the materilas upto


floor five level

0115 Coolie -0.41 Day 645.00 -264.45

Mild steel reinforcement for slab :


0.22 cum @ 48.06 kg/cum = 10.57 kg

5.22.1 Rate as per item no. 5.22.1 of SH : RCC work 10.57 Kg 88.95 940.20 A

Form work = 0.90×0.80 = 0.72 sqm


Less cover = 0.61×0.455m = (-) 0.278 sqm
= 0.442 sqm Say 0.44 sqm
5.9.3 Rate as per item no 5.9.3 of SH : RCC Work 0.44 Sqm 766.55 337.28 A

LABOUR

Extra labour for making channel :

0123 Mason (brick layer) 1st class 0.06 Day 784.00 47.04

0124 Mason (brick layer) 2nd class 0.06 Day 714.00 42.84

Rectangular shape 600×450 mm precast R.C.C.


7130 1.00 Each 675.00 675.00
manhole cover with frame – L.D. – 2.5

(inside)

9977 Carriage of R.C.C cover with frame 6.76 LS 2.12 14.33

9999 Painting of C.I. cover & frame with coal tar 6.76 LS 2.12 14.33

9999 Sundries 13.52 LS 2.12 28.66

Total 10528.59 W

Add 1 % Water charges on “W-A” 5.58

Total 10534.17 X

Add GST on “X-A” (multiplying factor 0.1405) 79.15

Total 10613.32 Y

Add 15% CPOH on “Y-A” 96.37

Total 10709.69 Z
Add Cess @ 1% on “Z-A” 7.39

Total 10717.08

Add GST Factor by 1.0633 11395.47

Cost for 1 Manhole (say) 11395.