You are on page 1of 18

BASIS AND CONSIDERATION

1 Contractor's profit
2 Overhead expenses
3 VAT
4 Foreman
5 Head mason
6 Mason
7 Skilled labour /Helper
8 Ordinary labour
9 Machine operator
10 Lime
11 Bamboo
12 Bailing-out water
13 Palisading
14 Bamboo driving
15 G.I. wire
16 Sal ballah
17 Nails and gazals etc
18 Wooden plank
19 Garjan size timber
20 60 grade rod
21 Bricks
22 Fine sand
23 1.2 F.M sand
24 2.5 Sylhet sand
25 Cement
26 Form work place & remove
27 Breaking brick chips
28 Bitumenous coating
29 Crushed stone chips
30 Roylty of earth
31 Truck fare: Dhaka city
32 Truckfare: Narayanganj
33 Truck fare: Ctg.
34 Truck fare: other area
35 Scaffolding
36 10 holes machine made ceramic brick
37 9.5" x 4.5" x 2.75" size machine made solid klinker facing bricks
38 9.5" x 4.5" x 2.75" size 10 hole machine made Rock-face/textured
39 klinker facing bricks
40 9.5" x 4.5" x 2.75" size 3 hole machine made reinforced klinker facing bricks
41 200 x 100 x 50 mm machine made hard pressed klinker facing bricks
42 200 x 50 x 50 mm machine made klinker facing strips
43 200 x 62 x 50 mm machine made klinker red strips
44 4'' x 4'' x 4'' design block
45 Colour pigment
46 6.5'' x 4.75'' x 4'' design block
47 6.5" x 6" x 4" design block
48 25 mm thick patent stone (1:2:4) with brick/chips for mosaic work
49 25 mm thick patent stone (1:1.5:3) with stone/chips for mosaic work
50 Mosaic chips: India
51 Mosaic chips: Pakistan
52 White cement
53 Minar stone
54 5 mm glass strip
55 Mosaic machine operator
56 Hire charge of mosaic cutting machine
57 Pumic stone
58 Labour cost of mosaic with glass strip
59 Labour cost of mosaic without glass strip
60 1/2" plaster on walls (1:4)
61 Marble dust / powder
Machine made pre-polished double layer terrazo tiles
62 (Conpac production): 10" x 10" size Silver mixed
63 Machine made pre-polished double layer terrazo tiles
64 (Conpac production): 10" x 10" size White special
65 Machine made pre-polished re-constituted homogeneous natural

aqa BASIS(1-40) - 1
66 marble slab: 13" x 13" size Italian Travertino.
67 Machine charge for cutting tiles
68 20 mm thick marble stone
69 18 mm thick marble stone
70 16 mm thick marble stone
71 12 mm thick marble stone
72 20 mm thick colored/ grey marble stone
73 Marble cutting & shaping machine in/c cutting disc.
74 Marble polishing machine in/c polishing stone
75 White wall tiles of dufferent sizes
76 Coloured wall tiles of different sizes
77 Special design coloured wall tiles
78 White floor tiles of dufferent sizes
79 Coloured floor tiles of different sizes
80 Special design coloured floor tiles
81 GP(Homogeneous) 305 x 305 mm floor tiles
82 GP(Homogeneous) 400 x 400 mm floor tiles
83 GP (Mirror polished) 300 x 300 mm floor tiles
84 GP (Mirror polished) 396 x 396 mm floor tiles
85 GP (Mirror polished) 300 x 600 mm floor tiles
86 GP 305 x 305 mm floor (stair) tiles
87 140 x 140 x 8.5 mm acid proof floor tiles
88 100 x 100 x 8.5 mm acid proof floor tiles
89 Quartz Homogeneous tiles
90 Embossed Homogeneous tiles
91 Special Quality Fibrous floor tiles
92 Water pump for concreting or similar purpose
93 Supplying & fixing Rupban or equivalent sheet and hessian tape (where
necessary) for making water-tight sufficiently
94 12 BWG barbed wire
Welder
Helper to welder
Point welding
Line welding
Scaffolding
Hire charge of paint spray machine

aqa BASIS(1-40) - 2
10.00%
4.50%
15.00%
Tk. 600.00 Each
Tk. 750.00 Each
Tk. 600.00 Each
Tk. 500.00 Each
Tk. 450.00 Each
Tk. 500.00 Each
Tk. 150.00 kg.
Tk. 25.00 rft.
Tk. 1,000.00 day
Tk. 17.08 sft.
Tk. 6.63 rft.
Tk. 80.00 kg.
Tk. 30.00 rft.
Tk. 40.00 kg.
Tk. 360.00 cft.
Tk. 710.00 cft.
Tk. 54,000.00 ton
Tk. 8,500.00 % 0 Nos.
Tk. 1,400.00 % cft.
Tk. 3,000.00 % cft.
Tk. 4,500.00 % cft.
Tk. 420.00 bag
Tk. 15.00 sft.
Tk. 750.00 % cft.
Tk. 150.00 % sft.
Tk. 14,000.00 % cft.
Tk. 250.00 % 0 cft.
Tk. 3,000.00 Trip
Tk. 450.00 Trip
Tk. 700.00 Trip
Tk. 375.00 Trip
Tk. 8.00 sft.
Tk. 7,000.00 % 0 Nos.
Tk. 6,380.00 % 0 Nos.

Tk. 7,670.00 % 0 Nos.


Tk. 7,100.00 % 0 Nos.
Tk. 7,630.00 % 0 Nos.
Tk. 4,973.00 % 0 Nos.
Tk. 12,783.00 % 0 Nos.
Tk. 9,520.00 % 0 Nos.
Tk. 30.00 Ibs.
Tk. 11,970.00 % 0 Nos.
Tk. 15,530.00 % 0 Nos.
Tk. 1,034.41 % sft.
Tk. 1,366.37 % sft.
Tk. 9.33 kg.
Tk. 9.00 kg.
Tk. 16.75 kg.
Tk. 200.00 Each
Tk. 3.00 rft.
Tk. 160.00 Each
Tk. 70.00 day
Tk. 140.00 Each
Tk. 1,482.50 % sft.
Tk. 1,295.00 % sft.
Tk. 6.95 sft.
Tk. 12.00 Per kg.

Tk. 42.79 Per sft.

Tk. 53.24 Per sft.

aqa BASIS(1-40) - 3
Tk. 101.00 Per sft.
Tk. 100.00 % sft.
Tk. 440.00 Per sft.
Tk. 400.00 Per sft.
Tk. 360.00 Per sft.
Tk. 310.00 Per sft.
Tk. 300.00 Per sft.
Tk. 1,025.00 Per day
Tk. 290.00 Per day
Tk. 36.00 Per sft.
Tk. 40.00 Per sft.
Tk. 42.00 Per sft.
Tk. 38.00 Per sft.
Tk. 42.00 Per sft.
Tk. 45.00 Per sft.
Tk. 48.00 Per sft.
Tk. 54.00 Per sft.
Tk. 88.00 Per sft.
Tk. 103.50 Per sft.
Tk. 115.00 Per sft.
Tk. 60.00 Per sft.
Tk. 90.00 Per sft.
Tk. 96.00 Per sft.
Tk. 50.00 Per sft.
Tk. 60.00 Per sft.
Tk. 75.00 Per sft.
Tk. 150.00 Per day

Tk. 1.00 Per sft.


Tk. 3,000.00 Per cwt.
Tk. 700.00 Per day
Tk. 500.00 Per day
Tk. 1.50 Per point
Tk. 2.00 Per inch
Tk. 3.00 Per sft.
Tk. 1.00 Per sft.

aqa BASIS(1-40) - 4
2) Excavation work

Considering 1000 cft. work


1. Mason 0.5 No. @
2. Ordinary labour 10 Nos. @
3. Skilled labour 2.5 Nos. @
4. For lay-out:
i) Head mason 0.25 No. @
ii) Lime for marking 0.5 kg @
5. Tools and plant, sundries etc.

Contra
Overhea

Say,

3) Earth filling
Considering 1000 cft. of work in/c consolidation, dressing and local carriage
c)
Loose earth required in/c 15% shrinkage =
1. Royalty for earth 1150 cft. @
2. Labour for cutting in/c loading & unloading the truck/cart
a) Ordinary labour 7 Nos. @
b) Skilled labour 1 No. @
3. Truck hire charge 7 Trucks @
4. Labour for local carriage, levelling & compacting etc. complete:
a) Ordinary labour 6 Nos. @
b) Skilled labour 1 No. @
5. Sundries, T & P etc.

Contra
Overhea

Say,

4) Sand filling in foundation and plinth with local sand (F.M. 0.80)
Considering 100 cft. of work
1. Sand (F.M. 0.8) considering
30% for compaction 130 cft. @
2. Head mason 1/8 No. @
3. Labour for levelling,
compacting, watering etc. 2/3 No. @
4. Sundries, T & P etc.

Contra
Overhea
Say,

5&7) House floor: brick-chips and sand (F.M. 1.2) (2:1)


Considering 100 cft. of work (loose volume 135 cft)
1. Picked jhama or 1st class
bricks for 90 cft. khoa 765 Nos. @
2. Breaking 19 to 12 mm chips 90 cft. @
3. Sand (F.M. 1.2) 45 cft. @
4. Labour for mixing, spreading, levelling, compacting, watering etc.
(a) Head mason 1/4 No. @
(b) Mason 3/4 No. @
(c) Skilled labour 2 Nos. @
(d) Ordinary labour 2 Nos. @
5. local carriage, T & P, sundries etc.

Contra
Overhea

Say,

6,8, 11&14) C-20 concrete in floor (1:2:4) with brick chips & 100% local sand of F.M. 1.2
Considering 100 cft. of work
1. Bricks for 90 cft chips 765 Nos. @
2. Sand (F.M. 1.2) 45 cft. @
3. Cement 18 bags @
4. Breaking chips in/c screening 90 cft. @
5. Labour for casting:
i) Head mason 0.25 No. @
ii) Mason 0.75 No. @
iii) Skilled labour 2 Nos. @
iv) Ordinary labour 2 Nos. @
6. Curing
7. Mixture machine, pump, local carriage, sundries, T & P etc.

Contra
Overhea

Say,

(9&10) Mass concrete in foundation (1:2:4) with brick chips & 100% local sand of F.M. 1.2
Considering 100 cft. of work
1. Bricks for 90 cft chips 765 Nos. @
2. Sand (F.M. 1.2) 45 cft. @
3. Cement 18 bags @
4. Breaking chips in/c screening 90 cft. @
5. Labour for casting:
i) Head mason 0.25 No. @
ii) Mason 0.75 No. @
iii) Skilled labour 2 Nos. @
iv) Ordinary labour 2 Nos. @
6. Curing
7. Mixture machine, pump, local carriage, sundries, T & P etc.
8. Extra cost of wood for side shutter: for 100 cft
2 x 60'-0" x 4" x 1"= 3.33 cft.
2 x 5'-0" x 4" x 1"= 0.28 cft.
10 x 6" x 2" x 1" = 0.07 cft.
3.68 cft.
Add 5% wastage 0.18 cft.
3.86 cft. @

9. Labour for side shutter


2 x 40'-0" x 6" = 40.00 sft.
2 x 5'-0" x 6" = 5.00 sft.
45.00 sft. @

Contra
Overhea

Say,

12) Brick masonry work (1:4)


Considering 100 cft. of work
1. Bricks 1100 Nos. @

2. Sand (F.M. 1.2) in/c wastage 40 cft. @


3. Cement in/c pointing 6.5 bags @
4. Head mason 1/2 No. @
5. Mason 1.5 Nos. @
6. Skilled labour 1.5 Nos. @
7. Ordinary labour 2 Nos. @
8. Labour for soaking &
cleaning bricks 2 Nos. @
9. Labour for screening &
washing sand 1 No. @
10. Labour for 7 days curing
@ 1/4 labour per day 1.75 Nos. @
11. Scaffolding 25 sft. @
12. Local carriage, storage & sundries etc.

Contra
Overhea
Say,

13) 20 mm cement mortar flooring (1:2:4) with 12 mm brick chips

Considering 100 cft. of work covering 1524 sft. area


1. Bricks @ 8.5 Nos. per cft. chips 765 Nos. @
2. Sand (F.M. 1.2) 22.5 cft. @
3. Sand (F.M. 2.5) 22.5 cft. @
4. Cement 18 bags @
5. Breaking chips in/c screening 90 cft. @
6. Labour for 7 days curing
@ 1/4 labour per day. 1.75 Nos. @
7. Local carriage, sundries, T & P and washing of sand etc.

8. Extra cement for finishing 1/2 bag @


9. Labour cost:
i) Head mason 1/5 No. @
ii) Mason 3/4 No. @
iii) Skilled labour 1 No. @
iv) Ordinary labour 1 No. @
10. Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1" x 3/4" = 0.21 cft.
Add 5% wastage 0.01 cft.
0.22 cft. @
Using 10 times @
11. Labour for shuttering
2 x 4 x 5'-0" x 1" = 3.33 sft. @

Contra
Overhea

(i) Ground floor

Say,
16) 125 mm brick wall with first class bricks (1:4)
Considering 100 sft. work
1. Bricks 480 Nos. @
2. Sand (F.M. 1.2) 17 cft. @
3. Cement 2.6 bags @
4. Head mason 0.1 No. @
5. Mason 3/4 No. @
6. Skilled labour 1/2 No. @
7. Ordinary labour 1/2 No. @
8. Labour for soaking &
cleaning bricks 1 No. @
9. Labour for screening &
washing sand 1/4 No. @
10. Labour for 7 days curing
@ 1/4 No. labour per day 1.75 Nos. @
11. Scaffolding 25 sft. @
12. Local carriage, storage & sundries etc.

Contra
Overhea

considering 2 m height of the wall Say,


17) Barbed wire fencing over brick wall/RCC member with 1.5" x 1.5" x 1/4" M.S. angle
post 1'-0" straight + 1'-0" inclined.
Considering 24'-0" x 3'-6"= 84 sft. of work
A. Barbed wire works:
1) Cost of barbed wire: 12 BWG 2 ply 4 points; @ 950 rft. per cwt.
7 x 24'-0" + 49 x 4'-6"= 388.5 rft.
= 0.41 cwt. @
2) Cost of 18 SWG G.I. wire 1.00 kg @
3) Labour for streching, tightening and binding barbed wire in position
a) Skilled labour 1.50 Nos. @
4) Labour charge for fitting with M.S. angle post
a) Skilled labour 1.00 No. @
5) Local carriage and storage
6) T & P and sundries
B. M.S. Angle works:
1) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 lbs per rft.
4 x (1'-0" + 1'-0" + 1'-0")= 12.00 rft.
Add wastage 5%= 0.60 rft.
= 12.60 rft.
= 29.48 lbs. @
2) Fabrication cost of angles:
i) Welder / fabricator 0.25 No. @
ii) Welder helper 0.25 No. @
iii) Mason for fxing in position 0.25 No. @
iv) Mason helper 0.25 No. @
8) Local carriage and storage

Con
Over

for 60 cm height Say,

18) Supplying, fabrication etc of M.S. rod in RCC works in all floors: 60 grade deformed bar with
minimum fy = 415 Mpa
Considering 1 cwt (50 Kg) of work
A. Cost of materials:
i) M.S. rod: 60 grade 1 cwt. @
ii) G.I. wire 1 kg @
B. Cost of labour
i) Rod binder 0.2 Nos. @
ii) Helper to rod bindr 0.75 Nos. @
iii) Local carriage, T & P etc.

Con
Over

Say,
23) Single brick flat soling road
Considering 100 sft. of work
1. Bricks 300 Nos. @
2. Fine sand 5 cft. @
3. Head mason 1/16 No. @
4. Mason 1/4 No. @
5. Skilled labour 1 No. @
6. Local carriage, sundries, T & P

Con
Over

Say,
Tk. 600.00 each = Tk. 300.00
Tk. 450.00 each = Tk. 4,500.00
Tk. - each = Tk. -

Tk. 750.00 each = Tk. 187.50


Tk. 150.00 Per kg = Tk. 75.00
L.S. = Tk. 270.00
Total = Tk. 5,332.50
Contractor's profit 10.00% = Tk. 533.25
Overhead expenses 4.50% = Tk. 239.96
Tk. 6,105.71
VAT 15.00% = Tk. 915.86
Grand total = Tk. 7,021.57
Rate per cft. = Tk. 7.02
Rate per cum. = Tk. 247.91

Tk. 248 .00 Per cum.

iage

1,150.00 cft.
Tk. 250.00 Per % 0 cft. = Tk. 287.50

Tk. 450.00 each = Tk. 3,150.00


Tk. 500.00 each = Tk. 500.00
Tk. 700.00 Per truck = Tk. 4,900.00

Tk. 450.00 each = Tk. 2,700.00


Tk. 500.00 each = Tk. 500.00
L.S. = Tk. 225.00
Total = Tk. 12,262.50
Contractor's profit 10.00% = Tk. 1,226.25
Overhead expenses 4.50% = Tk. 551.81
Tk. 14,040.56
VAT 15.00% = Tk. 2,106.08
Grand total = Tk. 16,146.64
Rate per cft. = Tk. 16.15
Rate per cum. = Tk. 570.34

Tk. 570 .00 Per cum.

Tk. 1,400.00 Per % cft. = Tk. 1,820.00


Tk. 750.00 each = Tk. 93.75

Tk. 450.00 each = Tk. 300.00


L.S. = Tk. 45.00
Total = Tk. 2,258.75
Contractor's profit 10.00% = Tk. 225.88
Overhead expenses 4.50% = Tk. 101.64
Tk. 2,586.27
VAT 15.00% = Tk. 387.94
Grand total = Tk. 2,974.21
Rate per cft. = Tk. 29.74
Rate per cum. = Tk. 1,050.27

Tk. 1,050 .00 Per cum.

Tk. 8,500.00 Per % 0Nos. = Tk. 6,502.50


Tk. 750.00 Per % cft. = Tk. 675.00
Tk. 3,000.00 Per % cft. = Tk. 1,350.00

Tk. 750.00 each = Tk. 187.50


Tk. 600.00 each = Tk. 450.00
Tk. 500.00 each = Tk. 1,000.00
Tk. 450.00 each = Tk. 900.00
L.S. = Tk. 225.00
Total = Tk. 11,290.00
Contractor's profit 10.00% = Tk. 1,129.00
Overhead expenses 4.50% = Tk. 508.05
Tk. 12,927.05
VAT 15.00% = Tk. 1,939.06
Grand total = Tk. 14,866.11
Rate per cft. = Tk. 148.66
Rate per cum. = Tk. 5,249.93

Tk. 5,250 .00 Per cum

F.M. 1.2

Tk. 8,500.00 Per % 0 Nos. = Tk. 6,502.50


Tk. 3,000.00 Per % cft. = Tk. 1,350.00
Tk. 420.00 Per bag. = Tk. 7,560.00
Tk. 750.00 Per % cft. = Tk. 675.00

Tk. 750.00 each = Tk. 187.50


Tk. 600.00 each = Tk. 450.00
Tk. 500.00 each = Tk. 1,000.00
Tk. 450.00 each = Tk. 900.00
L.S. = Tk. 225.00
L.S. = Tk. 742.50
Total = Tk. 19,592.50
Contractor's profit 10.00% = Tk. 1,959.25
Overhead expenses 4.50% = Tk. 881.66
Tk. 22,433.41
VAT 15.00% = Tk. 3,365.01
Grand total = Tk. 25,798.42
Rate per cft. = Tk. 257.98
Rate per cum. = Tk. 9,110.56

Tk. 9,111 .00 Per cum.

nd of F.M. 1.2

Tk. 8,500.00 Per % 0 Nos. = Tk. 6,502.50


Tk. 3,000.00 Per % cft. = Tk. 1,350.00
Tk. 420.00 Per bag. = Tk. 7,560.00
Tk. 750.00 Per % cft. = Tk. 675.00
Tk. 750.00 each = Tk. 187.50
Tk. 600.00 each = Tk. 450.00
Tk. 500.00 each = Tk. 1,000.00
Tk. 450.00 each = Tk. 900.00
L.S. = Tk. 225.00
L.S. = Tk. 742.50

Tk. 360.00 Per cft.


Using 6 times = Tk. 231.60

Tk. 7.50 Per sft. = Tk. 337.50


Total = Tk. 20,161.60
Contractor's profit 10.00% = Tk. 2,016.16
Overhead expenses 4.50% = Tk. 907.27
Tk. 23,085.03
VAT 15.00% = Tk. 3,462.75
Grand total = Tk. 26,547.78
Rate per cft. = Tk. 265.48
Rate per cum. = Tk. 9,375.43

Tk. 9,375 .00 Per cum.

Tk. 8,500.00 Per % 0 Nos. = Tk. 9,350.00

Tk. 3,000.00 Per % cft. = Tk. 1,200.00


Tk. 420.00 Per bag = Tk. 2,730.00
Tk. 750.00 each = Tk. 375.00
Tk. 600.00 each = Tk. 900.00
Tk. 500.00 each = Tk. 750.00
Tk. 450.00 each = Tk. 900.00

Tk. 450.00 each = Tk. 900.00

Tk. 450.00 each = Tk. 450.00

Tk. 450.00 each = Tk. 787.50


Tk. 8.00 Per sft. = Tk. 200.00
L.S. = Tk. 225.00
Total = Tk. 18,767.50
Contractor's profit 10.00% = Tk. 1,876.75
Overhead expenses 4.50% = Tk. 844.54
Tk. 21,488.79
VAT 15.00% = Tk. 3,223.32
Grand total = Tk. 24,712.11
Rate per cft. = Tk. 247.12
Rate per cum. = Tk. 8,727.04

Tk. 8,727 .00 Per cum

Tk. 8,500.00 Per % 0 Nos. = Tk. 6,502.50


Tk. 3,000.00 Per % cft. = Tk. 675.00
Tk. 4,500.00 Per % cft. = Tk. 1,012.50
Tk. 420.00 Per bag = Tk. 7,560.00
Tk. 750.00 Per % cft. = Tk. 675.00

Tk. 450.00 each = Tk. 787.50


L.S. = Tk. 675.00
Sub-total = Tk. 17,887.50
For 100 sft. of work = Tk. 1,173.72
Tk. 420.00 Per bag = Tk. 210.00

Tk. 750.00 each = Tk. 150.00


Tk. 600.00 each = Tk. 450.00
Tk. 500.00 each = Tk. 500.00
Tk. 450.00 each = Tk. 450.00

Tk. 710.00 Per cft.


Tk. 71.00 Per cft. = Tk. 15.62

Tk. 2.50 Per sft. = Tk. 8.33


Total = Tk. 2,957.67
Contractor's profit 10.00% = Tk. 295.77
Overhead expenses 4.50% = Tk. 133.10
Tk. 3,386.54
VAT 15.00% = Tk. 507.98
Grand total = Tk. 3,894.52
Rate per sft. = Tk. 38.95
Rate per sqm. = Tk. 419.26

Tk. 419 .00 Per sqm.


Tk. 8,500.00 Per % 0 Nos. = Tk. 4,080.00
Tk. 3,000.00 Per % cft. = Tk. 510.00
Tk. 420.00 Per bag = Tk. 1,092.00
Tk. 750.00 each = Tk. 75.00
Tk. 600.00 each = Tk. 480.00
Tk. 500.00 each = Tk. 250.00
Tk. 450.00 each = Tk. 225.00

Tk. 450.00 each = Tk. 450.00

Tk. 450.00 each = Tk. 135.00

Tk. 450.00 each = Tk. 787.50


Tk. 8.00 Per sft. = Tk. 200.00
L.S. = Tk. 225.00
Total = Tk. 8,457.00
Contractor's profit 10.00% = Tk. 845.70
Overhead expenses 4.50% = Tk. 380.57
Tk. 9,683.27
VAT 15.00% = Tk. 1,452.49
Grand total = Tk. 11,135.76
Rate per sft. = Tk. 111.36

Rate per sft. = Tk. 111.36


Rate per sqm. = Tk. 1,198.68

Tk. 2,397 .00 Per m.


Tk. 3,000.00 Per cwt. = Tk. 1,230.00
Tk. 80.00 Per kg. = Tk. 80.00

Tk. 500.00 each = Tk. 750.00

Tk. 500.00 each = Tk. 500.00


L.S. = Tk. 25.00
L.S. = Tk. 25.00

Tk. 36.00 Per lb. = Tk. 1,061.28

Tk. 700.00 each = Tk. 175.00


Tk. 500.00 each = Tk. 125.00
Tk. 600.00 each = Tk. 150.00
Tk. 500.00 each = Tk. 125.00
L.S. = Tk. 100.00
Total = Tk. 4,346.28
Contractor's profit 10.00% = Tk. 434.63
Overhead expenses 4.50% = Tk. 195.58
Tk. 4,976.49
VAT 15.00% = Tk. 746.47
Grand total = Tk. 5,722.96
Rate per sft. = Tk. 68.13
Rate per sqm. = Tk. 733.35

Tk. 440 .00 Per sqm.

Tk. 2,700.00 Per cwt. = Tk. 2,700.00


Tk. 80.00 Per kg. = Tk. 80.00

Tk. 400.00 each = Tk. 80.00


Tk. 350.00 each = Tk. 262.50
L.S. = Tk. 10.00
Total = Tk. 3,132.50
Contractor's profit 10.00% = Tk. 313.25
Overhead expenses 4.50% = Tk. 140.96
Tk. 3,586.71
VAT 15.00% = Tk. 538.01
Grand total = Tk. 4,124.72
Rate per cwt. = Tk. 4,124.72
Rate per ton = Tk. 82,494.40

Tk. 82,494 .00 Per ton


Tk. 8,500.00 Per % 0 Nos. = Tk. 2,550.00
Tk. 1,400.00 Per % cft. = Tk. 70.00
Tk. 750.00 each = Tk. 46.88
Tk. 600.00 each = Tk. 150.00
Tk. 500.00 each = Tk. 500.00
L.S. = Tk. 250.00
Total = Tk. 3,566.88
Contractor's profit 10.00% = Tk. 356.69
Overhead expenses 4.50% = Tk. 160.51
Tk. 4,084.08
VAT 15.00% = Tk. 612.61
Grand total = Tk. 4,696.69
Rate per sft. = Tk. 46.97
Rate per sqm. = Tk. 505.59

Tk. 506 .00 Per sqm.

You might also like